HomeMy WebLinkAboutWater Impact Fee Report IFAC 10.29.20 WATER IMPACT FEE FUND FINANCIAL SUMMARY Financial Summary Current YearFY21 FY22 FY23 FY24 FY25 FY26 UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 1,423,506$ (830,980)$ (911,174)$ (225,624)$ 459,316$ 1,558,299$ ‐$ Plus: Impact Fee Revenues Dedicated to CIP 1,965,831$ 2,024,806$ 2,085,550$ 2,148,117$ 2,212,560$ 2,278,937$ ‐$ Plus: Loan for Well Field WIF32 7,500,000$ Plus: Loan for Sourdough Transmission Main, PH 2 WIF40 4,320,000$ Less: Carryover FY20Capital Projects (6,979,026)$ Less: Debt payments (WIF03 WIF 32, and WIF40) (600,000)$ (600,000)$ (1,113,177)$ (1,113,577)$ (1,113,577)$ Less: Scheduled CIP Project Costs (1,561,291)$ (1,505,000)$ (8,300,000)$ (350,000)$ ‐$ ‐ (42,500,000)$ Projected Year‐End Cash Dedicated to CIP (830,980)$ (911,174)$ (225,624)$ 459,316$ 1,558,299$ 2,723,659$ Assumptions Made for Revenue Estimates Current YearFY21 FY22 FY23 FY24 FY25 FY26Estimated Annual Water Impact Fee Revenues 1,965,831$ 1,965,831$ 2,024,806$ 2,085,550$ 2,148,117$ 2,212,560$ Estimated Annual Increase 0.0% 3% 3% 3% 3% 3%Total Estimated Revenues 1,965,831$ 2,024,806$ 2,085,550$ 2,148,117$ 2,212,560$ 2,278,937$ Current Revenues Dedicated to CIP % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to Water Capacity Expansion CIP 0.0%0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%Total Estimated Revenues Dedicated to CIP 1,965,831$ 2,024,806$ 2,085,550$ 2,148,117$ 2,212,560$ 2,278,937$ ProjectedProjectedCURRENT$(1,505,000)$(8,300,000)$(350,000)$‐‐$(42,500,000)FY21 FY22 FY23 FY24 FY25 FY26 UNSCHEDULEDWATER IMPACT FEE PROJECTS
WATER IMPACT FEE FUND PROJECT SUMMARY Project # Project Name FY2022 FY2023 FY2024 FY2025 FY2026 UnscheduledWIF28 5126 WEST SOURDOUGH RESERVOIR 1 ‐ SITING 350,000 ‐ ‐ ‐ ‐ ‐ WIF32 GROUNDWATER WELL FIELD AND TRANSMISSION CONSTRUCTION‐ 7,500,000 ‐ ‐ ‐ ‐ WIF37 SOURDOUGH CANYON NATURAL STORAGE ‐ PLANNING & DESIGN ‐ ‐ 150,000 ‐ ‐ ‐ WIF40SOURDOUGH TRANSMISSION PH2 1,000,000 ‐ ‐ ‐ WIF51SOURDOUGH CANYON NATURAL STORAGE ‐ ‐ ‐ ‐ ‐ 10,000,000 WIF52WATER MAIN COTTONWOOD ROAD BETWEEN OAK TO BAXTER ‐ 400,000 ‐ ‐ ‐ ‐ WIF54PRV OVERSIZING‐ NELSON MDW 155,000 ‐ ‐ ‐ ‐ WIF55BILLINGS CLINIC WATER MAIN ‐ 200,000 ‐ ‐ ‐ WIF56BLACKWOOD GROVES WATER MAIN ‐ 200,000 ‐ ‐ ‐ WIF57NW CROSSING WATER MAIN ‐ ‐ 200,000 ‐ ‐ WIF59WESTERN TRANSMISSION MAIN ‐ ‐ 24,000,000 WIF60W SOURDOUGH RESERVOIR ‐ ‐ ‐ ‐ ‐ 8,500,000 Fiscal Year totals 1,505,000 8,300,000 350,000 ‐ ‐ 42,500,000 Project # Project Name FY2022 FY2023 FY2024 FY2025 UnscheduledWIF28 5126 WEST SOURDOUGH RESERVOIR 1 ‐ SITING 350,000 ‐ ‐ ‐ ‐ WIF32 GROUNDWATER WELL FIELD AND TRANSMISSION CONSTRUCTION7,500,000 ‐ ‐ ‐ ‐ WIF37 SOURDOUGH CANYON NATURAL STORAGE ‐ PLANNING & DESIGN ‐ ‐ 150,000 ‐ ‐ WIF51SOURDOUGH CANYON NATURAL STORAGE ‐ ‐ ‐ ‐ 10,000,000 WIF52WATER MAIN COTTONWOOD ROAD BETWEEN OAK TO BAXTER ‐ 400,000 ‐ ‐ ‐ Fiscal Year totals 7,850,000 400,000 150,000 ‐ 10,000,000 Current CIP RequestsCurrent CIP Requests
WATER IMPACT FEE FUND DETAIL BACKGROUND This enterprise fund revenue source is impact fees. Revenue estimates for Water Impact Fees have been updated with the 5‐year average collection amount, detailed on the following page. Revenues have grown on average by 6 % per year, over the past 5 years. For the CIP, we have used the 5‐year Average collection, plus 3% growth each year from FY21 to FY25. $1,663,000.00 $2,262,000.00 $1,885,123.00 $2,757,565.00 $2,042,324.00 $2,061,504.00 2,201,703.20 $‐ $500,000.00 $1,000,000.00 $1,500,000.00 $2,000,000.00 $2,500,000.00 $3,000,000.002015 2016 2017 2018 2019 2020 AverageFY16‐20Water Impact Fee Revenues
CAPITAL PLAN SUMMARY WIF32 Groundwater Well Field and Transmission Construction ‐ Water right permitting and mitigation plan; purchase of mitigation water rights; construction of aquifer recharge or other mitigation infrastructure; acquisition of land for well field site; construction of wells, power, power backup, instrumentation and controls, SCADA, control building and site improvements; and transmission main construction to tie ground water supply into the existing system. This is critical for meeting long‐range water supply needs and enhancing overall water supply resiliency and redundancy. It enhances connectivity by providing a redundant water supply source in the event of Sourdough WTP outage. The project highlighted above aids in our efforts towards the Strategic Plan 6.1 a Watershed Management. A significant amount of borrowing has been incurred for Projects WIF03, and WIF 40 and more will be incurred with WIF32. Because of the uncertainty of the revenue stream, the Water Utility will need to borrow via revenue bonds and be reimbursed by the Water Impact Fee Fund. There may be rate‐requirements to support this borrowing which were included as part of our more recent Water rate study. The estimated borrowing is outlined in the table below: Debt‐ Description Project # FY2022 FY2023 FY2024 FY2025 FY2026Loan Debt Service ‐ WTP 5.3MG Water Storage Reservoir (WIF03)WIF14 600,000 600,000 600,000 600,000 600,000 Debt Service for Borrowing ‐ Transmission Main (WIF40)WIF45 513,177 513,577 513,577 600,000 600,000 1,113,177 1,113,577 1,113,577 Estimated Debt Schedule
Project NameYear Description Amount Total Project #5126 WEST SOURDOUGH RESERVOIR 1 ‐ SITING 350,000 DESCRIPTION: ‐ SITING STUDY AND LAND ACQUISITION FOR 5MG GROUND ‐ STORAGE RESERVOIR TO SERVE 5126 PRESSURE ZONE ‐ FROM WEST TRANSMISSION MAIN. THE WEST ‐ SOURDOUGH RESERVOIR WILL BE THE NEXT NECESSARY ‐ RESERVOIR FOR THE CITY TO CONTINUE TO PROVIDE ‐ ADEQUATE POTABLE WATER AND FIRE FLOW. PROPER ‐ SITING OF THIS RESERVOIR WILL PROVIDE REDUNDANT ‐ SUPPLY TO SOURDOUGH AND HILLTOP RESERVOIRS. IT ‐ WILL INCREASE WATER STORAGE CAPACITY BY 5MG, AND ‐ WILL PROVIDE GREATER EFFICIENCY IN PROVIDING ‐ POTABLE WATER AND FIRE FLOWS TO THE CITY'S WESTERN ‐ AREAS. BETTER ABILITY TO TAKE SOURDOUGH OR HILLTOP ‐ RESERVOIRS OFFLINE AND STILL PROVIDE SUFFICIENT ‐ STORAGE. OTHER AFFECTED PROJECTS INCLUDE ‐ GROUNDWATER PLANNING, ENGINEERING AND ‐ CONSTRUCTION WEST TRANSMISSION MAIN STUDY, ‐ DESIGN, CONSTRUCTION; RESERVOIR DESIGN, ‐ CONSTRUCTION PROJECTS. ‐ ALTERNATIVES CONSIDERED: ‐ WAIT UNTIL THE NEED FOR THE RESERVOIR IS MORE ‐ IMMINENT ‐ ADVANTAGES OF APPROVAL: ‐ PROCUREMENT OF LAND WHILE IT IS AVAILABLE, AND ‐ LESS EXPENSIVE ‐ ADD OPERATING COSTS: ‐ UNKNOWN AND WOULD BE ACCOUNTED FOR IN THE WATER ‐ FUND. ‐ 5126 WEST SOURDOUGH RESERVOIR 1 ‐ SITING 2022350,000 WIF28
Project NameYear Description Amount Total Project #GROUNDWATER WELL FIELD AND TRANSMISSION CONSTRUCTI 7,500,000 DESCRIPTION: ‐ WATER RIGHT PERMITTING AND MITIGATION PLAN; ‐ PURCHASE OF MITIGATION WATER RIGHTS; CONSTRUCTION ‐ OF AQUIFER RECHARGE OR OTHER MITIGATION ‐ INFRASTRUCTURE; ACQUISITION OF LAND FOR WELL FIELD ‐ SITE; CONSTRUCTION OF WELLS, POWER, POWER BACKUP, ‐ INSTRUMENTATION AND CONTROLS, SCADA, CONTROL ‐ BUILDING AND SITE IMPROVEMENTS; AND TRANSMISSION ‐ MAIN CONSTRUCTION TO TIE GW SUPPLY INTO THE ‐ EXISTING SYSTEM. THIS IS ABSOLUTELY CRITICAL FOR ‐ MEETING LONG‐RANGE WATER SUPPLY NEEDS AND ‐ ENHANCING OVERALL WATER SUPPLY RESILIENCY AND ‐ REDUNDANCY. IT ENHANCES CONNECTIVITY BY PROVIDING ‐ A REDUNDANT WATER SUPPLY SOURCE IN THE EVENT OF ‐ SOURDOUGH WTP OUTAGE. ‐ ALTERNATIVES CONSIDERED: ‐ STATUS QUO OPERATION ‐ ADVANTAGES OF APPROVAL: ‐ IMPROVE WATER DISTRIBUTION OPERATIONS THROUGH ‐ INCREASED UNDERSTANDING OF SYSTEM OPERATING ‐ CHARACTERISTICS. IMPROVE RESPONSIVENESS TO ‐ DYNAMIC OPERATING CONDITIONS. FACILITATE ‐ IMPROVED ACCESS TO EXISTING SITES NOW REQUIRING ‐ CONFINED SPACE ENTRY PROCEDURES. STANDARDIZE ‐ AND IMPROVE SURGE CONTROL FEATURES THROUGHOUT ‐ SYSTEM. ‐ ADD OPERATING COSTS: ‐ DEBT SERVICE (IF ANY) TO CONSTRUCT, POWER COSTS, ‐ SCADA MAINTENANCE, VAULT MAINTENANCE, INSTRUMENT ‐ MAINTENANCE, PROGRAMMING LIBRARIES ‐ GROUNDWATER WELL FIELD AND TRANSMISSION CONSTRUCTION20237,500,000 WIF32
Project NameYear Description Amount Total Project #SOURDOUGH CANYON NATURAL STORAGE ‐ PLANNING & DESIGN 150,000 DESCRIPTION: ‐ ALTERNATIVES PLANNING AND DESIGN FOR SOURDOUGH ‐ NATURAL STORAGE ENHANCEMENT PROJECT. THIS PROJECT ‐ WILL INCREASE RESILIENCY OF SOURDOUGH WATERSHED TO ‐ DROUGHT IMPACTS AND PROVIDES AUGMENTED WATER ‐ SUPPLY, PROTECTS EXISTING MUNICIPAL WATER RIGHTS, ‐ AND IT AUGMENTS WATER SUPPLY CAPACITY OF ‐ SOURDOUGH WATERSHED. THIS IMPACTS THE CITY'S LONG‐ ‐ TERM WATER RIGHTS AND HELPS CLOSE THE APPROACHING ‐ WATER SUPPLY GAP. THIS PROJECT COULD HAVE ‐ POTENTIAL FEMA INVOLVEMENT FOR FLOOD CONTROL. ‐ OTHER AFFECTED PROJECTS INCLUDE FINAL SIZING OF ‐ WEST TRANSMISSION MAIN. IT WILL ALSO INFORM LONG‐ ‐ TERM GROUNDWATER NEEDS. ‐ ALTERNATIVES CONSIDERED: ‐ POSTPONE ‐ ADVANTAGES OF APPROVAL: ‐ IMPLEMENTS IWRP, AUGMENTS SOURDOUGH WATER ‐ SUPPLY CAPACITY, AND INCREASES RESILIENCY OF ‐ SOURDOUGH WATER SUPPLY BY PROVIDING 'STORAGE' ‐ TO REDUCE THE SUSCEPTIBILITY OF DROUGHT IMPACTS ‐ ADD OPERATING COSTS: ‐ UNKNOWN ‐ SOURDOUGH CANYON NATURAL STORAGE ‐ PLANNING & DESIGN2024150,000 WIF37 (FY24)
Project NameYear Description Amount Total Project #SOURDOUGH TRANSMISSION MAIN PH 2 1,000,000 DESCRIPTION: ‐ THE PROJECT CONSISTS OF CONSTRUCTING APPROXIMATELY ‐ 8,000 FEET OF 30‐INCH DIP TRANSMISSION MAIN, WHICH ‐ WILL START AT THE END OF THE PHASE I CONNECTION ‐ POINT AND GO TO THE SOURDOUGH PLANT. THIS PROJECT ‐ IS CRITICAL TO OVERCOME VULNERABILITIES PRESENTED ‐ BY THE AGING AND UNKNOWN CONDITION OF THE EXISTING ‐ TRANSMISSION MAIN BETWEEN THE CITY'S WTP AND ‐ SOURDOUGH TANK, AND WILL PROVIDE ADDITIONAL ‐ CAPACITY FROM THE WTP TO THE SOURDOUGH RESERVOIR. ‐ THIS PROJECT WILL MITIGATE THE RISK OF NOT HAVING ‐ ADEQUATE POTABLE WATER AND FIRE FLOW SUPPLIES TO ‐ THE CITY IN THE EVENT OF A FAILURE TO THE EXISTING ‐ BAR‐WRAPPED 30" MAIN. THIS PROJECT'S COST AND ‐ ADMINISTRATION COULD BE IMPROVED IF COMBINED WITH ‐ THE NEW 3,000 FEET OF 48" BYPASS PIPE. ‐ ALTERNATIVES CONSIDERED: ‐ CONDUCT A CONDITION ASSESSMENT OF THE EXISTING 30" ‐ CONCRETE PIPE AND REPAIR/REHABILIATE AS NECESSARY. ‐ ADVANTAGES OF APPROVAL: ‐ THE CONDITION OF THE EXISTING TRANSMISSION MAIN ‐ FROM THE WTP TO THE SOURDOUGH RESERVOIR IS ‐ CURRENTLY UNKNOWN. APPROVAL OF THIS PROJECT WILL ‐ PROVIDE REDUNDANCY FOR THIS MAIN, AND MITIGATE ‐ THE RISK AND CONSEQUENCE OF ITS FAILURE. ‐ ADDITIONAL OPERATING COSTS: ‐ MAINTENANCE COSTS WHICH WOULD BE ACCOUNTED FOR IN ‐ THE WATER FUND. ‐ SOURDOUGH TRANSMISSION PH2 20221,000,000 WIF40
Project NameYear Description Amount Total Project #SOURDOUGH CANYON NATURAL STORAGE 10,000,000 DESCRIPTION: ‐ ALTERNATIVES PLANNING & DESIGN FOR SOURDOUGH ‐ STORAGE ENHANCEMENT PROJECT. THIS PROJECT WILL ‐ INCREASE RESILIENCY OF SOURDOUGH WATERSHED TO ‐ DROUGHT IMPACTS & PROVIDES AUGMENTED WATER SUPPLY, ‐ PROTECTS EXISTING MUNICIPAL WATER RIGHTS, AND IT ‐ AUGMENTS WATER SUPPLY CAPACITY OF SOURDOUGH ‐ WATERSHED. THIS IMPACTS THE CITY'S LONG‐TERM WATER ‐ RIGHTS & HELPS CLOSE THE APPROACHING WATER SUPPLY ‐ GAP. THIS PROJECT COULD HAVE POTENTIAL FEMA ‐ INVOLVEMENT FOR FLOOD CONTROL. ‐ ALTERNATIVES CONSIDERED: ‐ POSTPONE ‐ ADDITIONAL OPERATING COSTS: ‐ UNKNOWN ‐ WATER MAIN COTTONWOOD ROAD BETWEEN OAK TO BAXTER 400,000 DESCRIPTION: ‐ 16‐INCH WATER MAIN TO BE CONSTRUCTED IN COTTONWOOD ‐ ROAD BETWEEN OAK AND BAXTER TO MATCH OUR STREET ‐