HomeMy WebLinkAbout20213 20216 DRC Comments-RESPONSES_FinalPage 1 of 6
FROM: DEVELOPMENT REVIEW COMMITTEE
RE: BILLINGS CLINIC MASTER SITE PLAN AND SITE PLAN
APPLICATIONS #20213 & 20216
DATE: AUGUST 12, 2020
Project Location: Lot 2-A1, Minor Subdivision 221F, Township 1 South, Range 5 East, PMM, City
of Bozeman, Gallatin County, Montana.
Project Description: Master Site Plan for the Billings Clinic Bozeman Campus. Site Plan is for Phase
I which contains an Ambulatory Center on 13 acres. The property is zoned B-2 and is 58 acres.
These comments pertain to both the MSP & SP.
Recommendation: The DRC review finds that the project does not comply with the requirements
of the Bozeman Municipal Code and is deeming the application inadequate for further review .
Code corrections must be satisfied prior to continued review. All references are to the Bozeman
Municipal Code (BMC). However, as the comments are minor, the project will move forward to
notice and an ADR review.
Administrative Design Review Team: Due to events of COVID-19, all advisory boards have been
canceled. An ADR team made up of city staff will review this project and provide a summary memo
based on the review. This will be scheduled upon adequacy.
Section 2 – RECOMMENDED CONDITIONS OF APPROVAL
Please note that these conditions are in addition to any required code provisions identified in this
report. These conditions are specific to the development.
1. The applicant is advised that unmet code provisions, or code provisions that are not
specifically listed as conditions of approval, does not, in any way, create a waiver or other
relaxation of the lawful requirements of the Bozeman Municipal Code or state law.
Section 3 – REQUIRED CODE CORRECTIONS
Planning Division, Sarah Rosenberg, srosenberg@bozeman.net, 582-2297
Master Site Plan
· Identify the hierarchy of the streets. Although mixed and gateway block frontage is
identified, other block frontages should be identified as follows:
o Private drives – internal roadway
o Trail – park and trail block frontage
Responses:
The park and trail block frontages have been added to the plan (legend) for the required
trails indicated in the PROST Master Plan.
Page 2 of 6
For the private drives, as per our discussion, we have designated these as mixed-use
block frontages in the legend. If all the requirements of Mixed-Use block frontages
cannot be met then departures may be requested with the future PUD.
· Identify the pink dashed line on the master site plan.
Response: This is to identify the Phase One area. We have added this to the legend
· Include what the neighborhood center would consist of, how it would be maintained,
and ownership. It is assumed that this park will be a private park that is maintained and
owned by the property owner. Per BMC 38.410.020.A.3, a neighborhood center needs
to have 100% frontage. The larger of the two meets this standard, however, the smaller
one does not. Since the larger neighborhood center appears to meet the 1 acre
requirement, it is not necessary to have an additional neighborhood center. The smaller
area can be designated open space.
Response: We have identified the neighborhood center as intended as park or civic space
and removed this designation from the smaller open space area. We have also added a
note confirming the maintenance of the neighborhood center by the Owner.
· Shared use path and trees need to be on property and not on MDT right-of-way.
Response: Revised.
· The class II trails in the development should be concrete not soft path as it is seen more
as a circulation pathway over a recreational pathway. However, any of the path that is in
the watercourse setback should be gravel fines.
· Response: Revised.
· BMC 38.520.050.D. The local streets are defined as internal roadways which require
street trees and sidewalks. Many of these internal roadways don’t need an additional
trail adjacent to it as there would be a sidewalk required.
Response: Agreed, these redundant trails have been removed.
· The DRC recommends extending the trails as seen below:
Response: These connections have been added.
Page 3 of 6
Phase One Site Plan
· There are two departure requests that have a fee of $284 each.
o Parking lot along public street along Westlake Road – The DRC is in support of.
o Entrance to ambulatory center on East Valley Center – The DRC is in support of
this departure.
Response: These two departures have been granted for this project and Billings Clinic is
coordinating payment this week with Nate
· BMC 38.520.040.C.3. The crosswalks that cross the parking lots must contain
contrasting material and/or patterns.
Response: We have added concrete crosswalks in these areas.
· The DRC recommends an additional connection from the parking lot on the north end of
the property to the trail along East Valley Center.
Response: This connection has been added.
· BMC 38.530.050.E. The entrance on the north façade of the building needs more
articulation. Consider making it a double door with a more prominent canopy (similar to
the urgent care entrance).
Response: This entrance is a staff entrance and we have intentionally downplayed its
presence so as not to be confused with a main entry for public/visitors. This is to support
the important and comprehensive way finding strategies necessary to enhance patient
experience and reduce confusion for visitors. (Significant research lead by the center for
health design points at the importance of appropriate way finding solutions that
enhance patient experience.) However, to help to address this comment, we have
enlarged the canopy (making it more prominent) but intend to not enlarge the door
itself. The site/landscape features provide at this entry help to enhance the patient
Page 4 of 6
experience and better articulate this entry point. See additional building elevations with
landscaping illustrated.
· BMC 38.530.070. The following elevations have blank walls:
o ACC Building: West elevation, north elevation
o ASC-1 Building: North elevation,
Response: Based on the code, this can be addressed with architectural features and/or
landscaping. We have made changes to the locations and heights of planting materials
in front of these blank wall areas and have shared building elevations that also include
the planned landscaping to better illustrate this screening. Where landscaping cannot be
used to adequately screen these areas we have also made changes to the building and
screen wall designs. Please see revised elevation that shows the landscape / screening
features provided in accordance with section.
· BMC 38.550.050.C.2. The parking lot on the west side requires additional screening as it
is adjacent to a residential use. Screening needs to be maintained at a height of four to
six feet. Additional trees or taller shrubs should be provided. There must be one canopy
or non-canopy tree for each 50 lineal feet.
Response: There is an existing Cotoneaster hedge located along this entire property line
providing a solid visual buffer at 6’-8’ in height. Billings Clinic has been working in
cooperation with the adjacent landowner to protect this hedge in place. We have also
provided a continuous shrub buffer with taller species adjacent to the parking lot. We
have retained an open area between these two buffers to accommodate the utility
easement in this area while still providing significant visual screening.
· BMC 38.550.050.E. Two small ornamental trees can take place of a large canopy tree.
Each street frontage does not meet the required amount of trees.
Response: Trees have been added to meet this requirement
· BMC 38.570.040.B. Building entrances must average 5.0 maintained footcandles. Most
of the entrances exceed this.
Response: Quantities and/or output have been reduced
· The ACS floor plans were not provided with this submission.
Response: Floor plans are now provided.
· Recommend providing more renderings of the ASC building from different angles.
Response: Additional views included
Engineering Division; Griffin Nielsen, gnielsen@bozeman.net
· See attached comments
Parks Department; Addi Jadin, ajadin@bozeman.net , 406-582-2908
· The Trout Meadows Park to the south is discussing a potential master plan update and is
discussing the concept at the Thursday, August 14 RPAB meeting. Ensure communication
with the Parks Department on trails system and connectivity through the area.
Response: BHA attended the RPAB meeting. We believe our plans will support the future
ideas for this park and would like to remain engaged through the park master plan update.
Page 5 of 6
Northwestern Energy; Thomas Stewart, thomas.stewart@northwesternenergy.com
· An application needs to be submitted with the calculated electric and gas loads. Plans
show one location for a transformer for the proposed ASC Building and proposed ACC
Building. Once the NWE engineer receives the calculated electric loads and requested
service size they will determine if the service need is within the limits of one
transformer.
Response: The applications and corresponding load information was previously
submitted to Northwestern Energy.
· Gas services are not shown on the plans. Will gas be omitted from this design?
· Response: The gas service is now shown on the revised drawings.
· If the transformer is to be installed within the enclosed structure separation
requirements need to be met. The front of the transformer will need a minimum
working distance of 10-feet in the front where the transformer doors are located. If this
is not possible then a gate should be provided in the fence in front of the access door to
the transformer to allow a 10-foot unobstructed working area. A minimum of 2-feet on
all other sides are allowed as long as the wall material is non-combustible otherwise 10-
foot clearance is required. Since the building is a large building a 3-phase transformer
will need to be installed and therefore a crane will most likely be needed to install and
remove if need be for maintenance for the transformer, the area shall be clear above
the equipment. The NWE engineer will help to determine the needed parameters for
the enclosure.
Response: Acknowledged.
· A 10-foot wide easement will need to be shown on the plat for the underground electric
utility from the pole location to the transformer pad and around the transformer
location.
Response: Acknowledged. Utility easements will be provided as necessary.
· If Street A and all the parking lots are to be completed during this phase I would
recommend getting power or at least stubbing conduit to the future building location.
This would eliminate digging up landscaping, sidewalks or asphalt when the power is
needed.
Response: Acknowldeged .
· If a service application has not been submitted at this time it is my recommendation
that they submit one to NWE as soon as possible to get the process started. Then the
NWE engineer can help assess the plans for best location for new installation of electric
and gas services.
Response: The application was previously submitted and we received a response from
Northwestern Energy.
· As the phases are designed submit an application well in advance to Northwestern
Energy and the NWE engineer will work with the applicant to help assist in getting gas
mains and electric primary extension designs to proposed building locations and stubs
for future phases.
Response: Acknowledged.
Page 6 of 6
· Any new gas mains and electric primary underground or overhead extensions will
require a 10-foot easement or bigger to be shown on the plats.
Response: Acknowledged. Utility easements will be provide as necessary.
Future Impact Fees - Please note that future building permit applications will require payment of
the required transportation, water, sewer and fire impact fees according to the City of Bozeman
adopted impact fee schedule in place at the time of building permit issuance. If you desire an
estimate of the required impact fees according to current rates please contact the Department of
Community Development and/or visit.
Response: Acknowledged
Note: During preparation of the staff report, additional conditions of approval may be
recommended based on comments and recommendations provided by other applicable review
agencies involved with the review of the project.