HomeMy WebLinkAboutF. Blvds Darlinton presentation 9.9.20Boulevards Apartments and
Darlinton Manor Preservation
The Boulevards
6 West Babcock
41 units (39 subsidized S8MR)
3 studio, 36 one bedroom, 2 two bedroom
Darlinton Manor
606 North 5th
100 units (85 subsidized PBS8)
32 Studio, 68 one bedroom
•Both buildings are elderly/disabled designated
•Very low, often fixed incomes
•Boulevards: 41 units (39 with current subsidy)
•Darlinton: 100 units (85 with current subsidy)
•Acquisition rehab process would add 17 subsidized units
•Subsidies ensure that residents pay 30% of income toward rent
Current Residents
Where does preservation fit in?
Darlinton/Blvds
Arrowleaf/Perennial
Willow Springs
Warming Center
About 38% of Bozeman’s low-income renters earn below 30% of AMI
Bozeman Housing Needs
Scope of work -Boulevards
•Electrical rewiring/systems upgrades
•Sprinkler system install
•New elevator
•Windows
•Roof
•Accessibility upgrades
•Units
•Appliances •Cabinets•Flooring•Fixtures
Scope of work -Darlinton
•Windows
•Roof
•Accessibility upgrades
•Units
•Appliances
•Cabinets
•Flooring
•Fixtures
Budget
Uses
Acquisition 12,500,000
Rehabilitation 7,484,750
Furnishings 245,217
Contingency 741,000
Relocation 775,500
Architect and Engineering 381,000
Construction Financing Fees and Interest 2,186,511
Permanent Financing Costs 318,177
Legal 130,000
Reserves 760,776
LIHTC Syndication Costs 462,679
Permitting 61,304
Developer Fee 3,478,213
TOTAL USES 29,525,127
Construction Sources
Construction Loan 21,000,000
LIHTC Equity 1,845,233
Developer Note 2,568,948
Housing Trust Fund 1,000,000
City of Bozeman 500,000
Deferred Developer Fee 2,610,946
TOTAL CONSTRUCTION SOURCES 29,525,127
Permanent Sources
Permanent Loan 16,277,508
LIHTC Equity 7,380,932
Developer Note 2,568,948
Housing Trust Fund 1,000,000
City of Bozeman 500,000
Rehab NOI 571,852
Deferred Developer Fee 1,225,887
TOTAL PERMANENT SOURCES 29,525,127
Milestone Date
Acquire Boulevards Jul-19
Extend Boulevards subsidy contract Oct-19
Acquire Interest in Darlinton Jul-20
Submit Tax Credit and Bond Applications Aug-20
HTF, City Funds, Risk Share Loan
Submit Application for HTF Sep-20
Submit Application for City Funds Aug-20
Request to MBOH for Risk Share Loans Sep-20
Order Third Party Reports June - August 2020
Design and Engineering June - August 2020
Scope Finalization Aug-20
Plan Check Submission Sep-20
Permit Nov-20
Select Contractor Sep-20
Finalize Schedule of Values Oct-20
Finalize Construction Contract Oct-20
Finance and Legal
Select Investor and Lender Aug-20
Due Diligence/Underwriting Aug-Oct 2020
LIHTC Partnership, Loan, Bond and HUD docs complete Oct-20
HUD Process
Submit Applications for MUTM and RAD Aug-20
Complete HUD Legal Review Sep-20
Receive HUD Approval Oct-20
Close on the Financing and LIHTC Nov-Dec-20
Issue Notice to Proceed Dec-20
Construction Mobilization Dec-20
Begin Unit Renovations/Relocation Jan-21
Construction Completion Mar-22
Blvd/Darlinton Schedule
Schedule