HomeMy WebLinkAboutIV - Project Team Applications Fees 05-05-2020May 2020
PRELIMINARY PUD: Arrowleaf Park & Perennial Park
Section IV: Project Team, Applications & Fees - Pg. 1
Section IV
Project Team
Owner Christian Center First Assembly of God of Bozeman, Inc.
921 West Mendenhall Street
Bozeman, MT 59715
p: 406-587-9283
Applicant GMD Development, LLC
520 Pike Street
Seattle, WA 98101
p: 206.745.6464
CONSULTANT TEAM
Architect & Planner Intrinsik Architecture, Inc.
(Attn: Peter Andrews)
111 N. Tracy Avenue
Bozeman, MT 59715
p: 406.582.8988
Civil Engineer TD&H Engineering
234 E Babcock St. #3
Bozeman, MT 59715
p: 406.586.0277
Landscape Arch. Design 5
37 East Main St.
Bozeman, MT 59715
p: 406.587.4873
May 2020
PRELIMINARY PUD: Arrowleaf Park & Perennial Park
Section IV: Project Team, Applications & Fees - Pg. 2
Application Forms & Fee Calculation
All required City forms for the Arrowleaf Park & Perennial Park Preliminary PUD
have been included in this submittal. The fee calculations are outlined below. The
Preliminary PUD application is submitted concurrently with the Site Plans, and the
expected fee reflects this assumption.
Submitted concurrently with this application are the Subdivision Exemption, and the required
PLS and N1 forms (with the associated adjoining property owners information). The Site Plan
Checklist (SP1) is addressed in detail in Section III.
COMPONENT FEE QUANTITY TOTAL
PUD-P $1,761 1 $ 1,761.00
Dwelling Units $95 232 $ 22,040.00
Non-Res. Space (Up to 30,000 sq. ft.) $530 / 1,000 sf 30,000 sf $ 15,900.00
Non-Res. Space (> 30,000 sq. ft.) $250 / 1,000 sf 7,538 sf $ 1,884.50
Subdivision Exemption $200 1 $ 200.00
TOTAL $ 41,785.50