HomeMy WebLinkAbout20- Guaranteed Maximum Price Amendment - Langlas & Associates, Inc. - Bozeman Public Safety Center GUARANTEED MAXIMUM PRICE (GMP) AMENDMENT
TO AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
Pursuant to Articles 4, 5, and 6 of the Preconstruction Services Conditions Agreement between
Owner and Construction Manager this GMP Amendment dated the 22nd day of July, 2020,
between City of Bozeman ("Owner") and Langlas &Associates, Inc. ("Contractor") for the
Bozeman Public Safety Center, hereby authorizes the entire Work for the project as described in
the complete set of Construction Documents prepared by ThinkOne and AndersonMasonDale
Architects, outlined below.
The Contract Sum is guaranteed by the Construction Manager not to exceed Thirty Six Million
Four Hundred Thirty Six Thousand Four Hundred Eighty Five Dollars and Zero Cents
($36,436,485.00). This amount may only be altered by Amendment or Change Order executed by
the parties in accordance with the Contract Documents.
See attached Exhibit 1 for an itemized statement of the Guaranteed Maximum Price organized by
trade categories, allowances, alternates, contingency, the Construction Manager's Fee, and other
items that comprise the Guaranteed Maximum Price and information on which it is based.
The Guaranteed Maximum Price is based on the following plans, specifications and addenda:
Volume 1 Plans, Issue for Bid, dated June 4, 2020, totaling 108 sheets
Volume 2 Plans, Issue for Bid, dated June 4, 2020, totaling 191 sheets
Volume 3 Plans, Issue for Bid, dated June 4, 2020, totaling 155 sheets
Volume 1 Project Manual, Issue for Bid, dated June 4, 2020, totaling 938 pages
Volume 2 Project Manual, Issue for Bid, dated June 4, 2020, totaling 938 pages
Volume 3 Project Manual, Issue for Bid, dated June 4, 2020, totaling 740 pages
Addendum No. 1, dated July 1, 2020, totaling 537 pages
Addendum No. 2, dated July 2, 2020, totaling 67 pages
Addendum No. 3, dated July 7, 2020, totaling 84 pages
The anticipated date of Substantial Completion established by this Amendment is April 8, 2022.
OWNER: CONTRACTOR:
City of Bozeman Langlas & Associates, Inc.
121 N. Rouse Ave. 1019 E. Main St. Suite 101
Bozeman, MT 59715 Bozeman, MT 59715
By: By:
b1filklich, City Manager Steve T. Langlas, Presi e t
GMP Amendment—Bozeman Public Safety Center
Page 1
July 22,2020
Bozeman Public Safety Center
Guaranteed Maximum Price
GENERAL CON"III ACTO ItS
Exhibit No.1
Bid
Package
No. Description Value Comments
1A Construction Cleaning,Housekeeping and Protection of Finishes $215,000
3A Concrete Footings,Foundations and Slabs on Grade $2,215,000
Add for concrete fill at duct bank, excluded by BP 26A $32,618
3B Polished Concrete Finishing $59,732
3C Foundation Dampproofing and Waterproofing $17,359
4A Masonry $2,568,000
5A Structural Steel,Metal Deck and Miscellaneous Steel Supply $1,825,645
Deduct elevator pit ladders provided by BP 14A ($1,425)
5B Steel Erection $986,265
Deduct installation of Parapet ladders provided by BP 6A ($675)
6A Metal Stud Framing,Exterior Sheathing and Moisture Barrier $3,626,300
6B Casework and Interior Finish Carpentry $432,702
7A Interior Building Insulation $116,416
7B Metal Panel Siding,Soffit,Fascia&Trim and Sheet Metal Flashing $345,760
7C Roofing $708,600 Coping is 22 gage. All metal is 2 coat pre-finished
paint with 35 year finish warranty. Exlcudes FM
testing on metal roof.
7E Exterior Insulation Board and Fluid-Applied Membrane Air Barrier $367,076
Credit Henry VP-160,bid by subcontractor,but not required ($21g082)
Add high-temp self-adhered underlayment at exterior sills $3,056
8B Aluminum Framed Storefront,Automatic Entrances&Int.Glazing $756,230
9A Drywall Hang,Tape and Finish $754,185
9B Painting and Staining $504,873
Add penetrating masonry sealer per spec 07 19 00,Bid Scope Item 4 $51,755
Add Polyurea joint fitter at sealed concrete floors $5,500
9D Flooring(Tile,Wood,Resilient,Carpet and Base) $515,266
9E Specialty Floor Coatings(Resinous Flooring,Epoxy Coating,Traffic Coati $8,500
10A Building and Site Specialties $518,000
10B Interior and Exterior Building Signage $76,276
12A Roller Window Shades $79,284 Includes standard switching. Additive cost options
avaiable for controls once City determines
preferences.Attic stock per spec not included,and
not recommended for this project due to varied sizes
and product is readily available.
14A Elevators $401,270 Ceilings are standard suspended with powder coat
frame with LED downlights. (baked enamel not
available).Guide rail support for Elevator#3 is under
evaluation at the time of GMP. Nominal cost to be
added once known.
21A Fire Protection Systems $297,800
22A Plumbing(Domestic Plumbing and Hydronic HVAC) $3,315,643
23A HVAC(Dry Side) $1,716,678
26A Electrical $2,677,352
27A Low Voltage Communications and Data Cabling $269,549
27B Audiovisual Systems $616,954
28A Access Control and Video Surveillance $302,236 Owner shall provide recording servers per
specifications(drawings conflict and indicate S.C.shall
provide).
Subtotal of All Bid Packages $26,177,698
Page 1 of 2
Contract
PREVIOUSLY AWARED BID PACKAGES(EWAs 1-4) Amount Comments
02A Demolition of Existing Structures $224,971
02B Asbestos Abatement $46,950
02C Demolition and New Construction of Building Utility Services $103,826
31B Sitework $1,896,167
31B Rammed Engineered Aggregate Piers $84,000
32A Landscaping and Irrigation $398,407
32B Permanent Fencing and Gates $221,107
GC/CM SCOPES OF WORK
01 General Conditions $1,790,403
02 Site Maintenance and SWPPP $83,850
Security Camera/Timelapse Service $17,890 Based on two camera locations.
ALLOWANCES
1B Final Clean $138,205
011 Winter Conditions $250,000
01F Construction Fence $30,822
02D Construction Survey and Staking $40,000
07D Caulking and Sealants $108,000
08A Doors,Frames and Finish Hardware $470,000
08C Overhead Doors and Bi-folding Rapid Response Doors $310,000
08D Window Film $10,000
09C Acoustic Tile Ceilings and Acoustic Wall Panels $450,000
12B Stainless Steel Countertops and Wall Paneling $20,000
13A Pre-Engineered Metal Building(Facilities Garage)Supply and Erection $100,000
PROJECT SUBTOTAL $32,972,296
GC/CM Insurance @ 0.625% $206,077
GC/CM Fee @ 3.2% $1,061,708
Payment and Performance Bond @ 1% $342,401
PROJECT TOTAL $34,582,482
CONTRACTOR'S CONTINGENCY at 2.5% $864,562
PROJECT TOTAL WITH CONTINGENCY $35,447,044
ALTERNATE SUMMARY TOTAL
PROJECT TOTAL(without Contingency) $34,582,482
Alternate 1 $354,690
Alternate 2 $235,864
Alternate 3 $89,520
Alternate 4-Not including PEMB,see Allowance Item 13A $78,919
Alternate 5 $3,671
Alternate 6 $57,001
Alternate 7 $26,220
Alternate 8 $87,959
Alternate 9 $31,465
PROJECT TOTAL WITH ACCEPTED ALTERNATES $35,547,790
CONTRACTOR'S CONTINGENCY at 2.5% $888,695
PROJECT TOTAL WITH ALTERNATES AND CONTINGENCY $36,436,485