HomeMy WebLinkAbout07-27-20 City Commission Packet Materials - A1. Gauranteed Maximum Price for Bozeman Public Safety Center
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Chuck Winn, Assistant City Manager SUBJECT: Approve Guaranteed Maximum Price (GMP) Amendment for Construction of the Bozeman Public Safety Center.
MEETING DATE: July 27, 2020 AGENDA ITEM TYPE: Action RECOMMENDATION: Authorize the City Manager to sign GMP Amendment to Contract
for Construction with Langlas and Associates for construction of the Bozeman Public Safety Center. RECOMMENDED MOTION: After listening to the presentation by staff and considering public
comment, I move to authorize the City Manager to sign the Guaranteed Maximum Price
amendment with all alternates to the Contract for Construction with Langlas and Associates for the construction of the Bozeman Public Safety Center. BACKGROUND: On August 5, 2019, the City Commission approved the Contract for a General
Contractor/Construction Manager for the Bozeman Public Safety Center (BPSC). That contract
authorized preconstruction and construction services for the project including work necessary to develop a guaranteed maximum price (GMP) for construction. Staff has spent the last year designing the project and refining a budget based on changing market conditions, commodity and supply pricing, and cost of labor. Through this work and a competitive bidding process in
accordance with Montana law, Langlas has determined a GMP for construction. The GMP
represents the maximum price the City will pay to complete the BPSC as described in the contract documents and includes all the alternate components which were separated from the base project due to budget concerns. These include:
Alternate #1 Patrol vehicle canopies within the secured parking area
Alternate #2 Fire vehicle canopies adjacent to fire station Alternate #3 Snow melt systems around key overhead doors and entry points Alternate #4 Small storage building for site maintenance equipment Alternate #5 Argon fill glazing for energy efficiency
Alternate #6 Roller shades for solar protection and energy efficiency
Alternate #7 Solar Tubes – energy efficiency Alternate #8 Solar photovoltaic system (solar panels) energy efficiency Alternate #9 Ultraviolet disinfectant for heating, ventilation and air conditioning systems
It is important to note the project may cost less to build than the number represented in the GMP,
in fact, it is reasonable to believe the actual costs will be less. The City will realize all cost savings in the project including unspent contingency monies.
The total guaranteed maximum price for completion of the work described in the complete set of
construction documents, including the nine alternate work items, is $36,436,485.00 which is equivalent to $389.59 a square foot – well within the range of our initial estimates.
Construction is anticipated to be completed in April of 2022.
UNRESOLVED ISSUES: None.
ALTERNATIVES: None identified
FISCAL EFFECTS: The cost of the GMP is included within the overall project budget and will
be paid from bonds sold after the voters approved this project in November 2018. The amount is appropriated in this year’s budget.
Attachments:
BPSC Guaranteed Maximum Price Amendment
Report compiled on: July 22.2020
GMP Amendment – Bozeman Public Safety Center
Page 1
GUARANTEED MAXIMUM PRICE (GMP) AMENDMENT
TO AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
Pursuant to Articles 4, 5, and 6 of the Preconstruction Services Conditions Agreement between
Owner and Construction Manager this GMP Amendment dated the 22nd day of July, 2020,
between City of Bozeman (“Owner”) and Langlas & Associates, Inc. (“Contractor”) for the
Bozeman Public Safety Center, hereby authorizes the entire Work for the project as described in
the complete set of Construction Documents prepared by ThinkOne and AndersonMasonDale
Architects, outlined below.
The Contract Sum is guaranteed by the Construction Manager not to exceed Thirty Six Million
Four Hundred Thirty Six Thousand Four Hundred Eighty Five Dollars and Zero Cents
($36,436,485.00). This amount may only be altered by Amendment or Change Order executed by
the parties in accordance with the Contract Documents.
See attached Exhibit 1 for an itemized statement of the Guaranteed Maximum Price organized by
trade categories, allowances, alternates, contingency, the Construction Manager’s Fee, and other
items that comprise the Guaranteed Maximum Price and information on which it is based.
The Guaranteed Maximum Price is based on the following plans, specifications and addenda:
Volume 1 Plans, Issue for Bid, dated June 4, 2020, totaling 108 sheets
Volume 2 Plans, Issue for Bid, dated June 4, 2020, totaling 191 sheets
Volume 3 Plans, Issue for Bid, dated June 4, 2020, totaling 155 sheets
Volume 1 Project Manual, Issue for Bid, dated June 4, 2020, totaling 938 pages
Volume 2 Project Manual, Issue for Bid, dated June 4, 2020, totaling 938 pages
Volume 3 Project Manual, Issue for Bid, dated June 4, 2020, totaling 740 pages
Addendum No. 1, dated July 1, 2020, totaling 537 pages
Addendum No. 2, dated July 2, 2020, totaling 67 pages
Addendum No. 3, dated July 7, 2020, totaling 84 pages
The anticipated date of Substantial Completion established by this Amendment is April 8, 2022.
OWNER: CONTRACTOR:
City of Bozeman Langlas & Associates, Inc.
121 N. Rouse Ave. 1019 E. Main St. Suite 101
Bozeman, MT 59715 Bozeman, MT 59715
By:_________________________________
Jeff Mihelich, City Manager
July 22, 2020
Bozeman Public Safety Center
Guaranteed Maximum Price
Exhibit No. 1
Bid
Package
No. Description Value Comments
1A Construction Cleaning, Housekeeping and Protection of Finishes $215,000
3A Concrete Footings, Foundations and Slabs on Grade $2,215,000
Add for concrete fill at duct bank, excluded by BP 26A $32,618
3B Polished Concrete Finishing $59,732
3C Foundation Dampproofing and Waterproofing $17,359
4A Masonry $2,568,000
5A Structural Steel, Metal Deck and Miscellaneous Steel Supply $1,825,645
Deduct elevator pit ladders provided by BP 14A ($1,425)
5B Steel Erection $986,265
Deduct installation of Parapet ladders provided by BP 6A ($675)
6A Metal Stud Framing, Exterior Sheathing and Moisture Barrier $3,626,300
6B Casework and Interior Finish Carpentry $432,702
7A Interior Building Insulation $116,416
7B Metal Panel Siding, Soffit, Fascia & Trim and Sheet Metal Flashing $345,760
7C Roofing $708,600 Coping is 22 gage. All metal is 2 coat pre-finished
paint with 35 year finish warranty. Exlcudes FM
testing on metal roof.
7E Exterior Insulation Board and Fluid-Applied Membrane Air Barrier $367,076
Credit Henry VP-160, bid by subcontractor, but not required ($210,082)
Add high-temp self-adhered underlayment at exterior sills $3,056
8B Aluminum Framed Storefront, Automatic Entrances & Int. Glazing $756,230
9A Drywall Hang, Tape and Finish $754,185
9B Painting and Staining $504,873
Add penetrating masonry sealer per spec 07 19 00, Bid Scope Item 4 $51,755
Add Polyurea joint filler at sealed concrete floors $8,500
9D Flooring (Tile, Wood, Resilient, Carpet and Base)$515,266
9E Specialty Floor Coatings (Resinous Flooring, Epoxy Coating, Traffic Coatings)$8,500
10A Building and Site Specialties $518,000
10B Interior and Exterior Building Signage $76,276
12A Roller Window Shades $79,284 Includes standard switching. Additive cost options
avaiable for controls once City determines
preferences. Attic stock per spec not included, and
not recommended for this project due to varied sizes
and product is readily available.
14A Elevators $401,270 Ceilings are standard suspended with powder coat
frame with LED downlights. (baked enamel not
available). Guide rail support for Elevator #3 is under
evaluation at the time of GMP. Nominal cost to be
added once known.
21A Fire Protection Systems $297,800
22A Plumbing (Domestic Plumbing and Hydronic HVAC)$3,315,643
23A HVAC (Dry Side)$1,716,678
26A Electrical $2,677,352
27A Low Voltage Communications and Data Cabling $269,549
27B Audiovisual Systems $616,954
28A Access Control and Video Surveillance $302,236 Owner shall provide recording servers per
specifications (drawings conflict and indicate S.C. shall
provide).
Subtotal of All Bid Packages $26,177,698
Page 1 of 2
PREVIOUSLY AWARED BID PACKAGES (EWAs 1-4)
Contract
Amount Comments
02A Demolition of Existing Structures $224,971
02B Asbestos Abatement $46,950
02C Demolition and New Construction of Building Utility Services $103,826
31B Sitework $1,896,167
31B Rammed Engineered Aggregate Piers $84,000
32A Landscaping and Irrigation $398,407
32B Permanent Fencing and Gates $221,107
GC/CM SCOPES OF WORK
01 General Conditions $1,790,403
02 Site Maintenance and SWPPP $83,850
Security Camera / Timelapse Service $17,890 Based on two camera locations.
ALLOWANCES
1B Final Clean $138,205
01I Winter Conditions $250,000
01F Construction Fence $30,822
02D Construction Survey and Staking $40,000
07D Caulking and Sealants $108,000
08A Doors, Frames and Finish Hardware $470,000
08C Overhead Doors and Bi-folding Rapid Response Doors $310,000
08D Window Film $10,000
09C Acoustic Tile Ceilings and Acoustic Wall Panels $450,000
12B Stainless Steel Countertops and Wall Paneling $20,000
13A Pre-Engineered Metal Building (Facilities Garage) Supply and Erection $100,000
PROJECT SUBTOTAL $32,972,296
0.00625 GC/CM Insurance @ 0.625%$206,077
0.03200 GC/CM Fee @ 3.2%$1,061,708
0.01000 Payment and Performance Bond @ 1% $342,401
PROJECT TOTAL $34,582,482
0.02500 CONTRACTOR'S CONTINGENCY at 2.5% $864,562
PROJECT TOTAL WITH CONTINGENCY $35,447,044
ALTERNATE SUMMARY TOTAL
PROJECT TOTAL (without Contingency)$34,582,482
Alternate 1 $354,690
Alternate 2 $235,864
Alternate 3 $89,520
Alternate 4 - Not including PEMB, see Allowance Item 13A $78,919
Alternate 5 $3,671
Alternate 6 $57,001
Alternate 7 $26,220
Alternate 8 $87,959
Alternate 9 $31,465
PROJECT TOTAL WITH ACCEPTED ALTERNATES $35,547,790
0.02500 CONTRACTOR'S CONTINGENCY at 2.5% $888,695
PROJECT TOTAL WITH ALTERNATES AND CONTINGENCY $36,436,485
Page 2 of 2