HomeMy WebLinkAbout18 - Design Report - RSVP Event Center - Stormwater DESIGNP T
STORMWATER MANAGEMENT
RSVP EVENT CENTS
Prepared for:
Folkvord Investments, LLC
10778 Highway 287
Three Forks, MT 59752
Prepared by:
C IS[Engineering and Surveying, Inc.
1091 Stoneridge Drive, Bozeman, MT 59718
(406) 587-1115
Project Number: 180620
November 2018
INTRODUCTION
The proposed RSVP Event Center is an addition to the existing RSVP Motel located on Lot IA,
Block 2, Violett Addition to Bozeman. This lot is a 1.625-acre parcel located in Section 12,
Township 2 South,Range 5 East of P.M.M., Gallatin County, City of Bozeman.A combination of
site grading, curb and gutter,piping, and underground retention chambers will be used to manage
stormwater runoff on the site. Supporting stormwater calculations are attached to this report. A
Drainage Area Map is included in Appendix A. Calculations for each individual drainage area
(total area,weighted C factor, and time of concentration) are included in Appendix B.
UNDERGROUND RETENTION CHAMBER DESIGN
All underground retention chambers have been sized according to City of Bozeman Design
Standards. Retention facilities are sized to capture the entire volume of the 10-year 2-hour storm
event. Calculations used for sizing each pond can be found in Appendix C.
EXISTING SUBDIVISION STORMWATER SYSTEM
The existing Tom's Flooring site currently sends runoff from 9,767 square feet of hardscape,which
results in 626 cubic feet of runoff during the 10-year, 2-hour event. This new RSVP Event Center
proposes to reduce the amount of runoff being discharged into the existing subdivision stormwater
system by 126 cubic feet due to the majority of the site runoff being handled with the underground
infiltration chambers. The existing stormwater infrastructure will handle runoff from Drainage
Area #2, totaling 0.18 acres. The new volume of water being discharged into the existing
stormwater infrastructure is 500 cubic feet.Because this is less than the current site discharges into
the existing infrastructure, there is adequate capacity to handle the runoff from this development.
Supporting calculations can be found in Appendix C.
PROPOSED UNDERGROUND INFILTRATION CHAMBERS
The proposed underground infiltration chambers are located underneath the pavement. They
receive runoff from Drainage Area 1, totaling 0.32 acres. The required volume of the chambers
was calculated to be 887 cubic feet.The proposed volume of the underground infiltration chambers
is 893 cubic feet,which is adequate to handle the additional runoff from this development. Sizing
calculations for these chambers can be found in Appendix C.
APPENDIX A
DRAINAGE AREA MAP
DRANVAGE A MAP
RSVP EVENT CENTER
1I
EXISTING BUILDING
I _
/ ! PROPOSED
✓ UNDERGROUND
t _ - INFlLiRA-noN
VI CHAMBERS 1
>
1:5,07 SF r V 75,
�❑ � HDARDSCAPE
` , 1,091 SF
ix"
i I
EXISTING^;SiDEWAU( _
r E
t
-777
W. SHORT STREET DSCAPE
1,391 SF
N
Scale In Feet
30 0 30
9 0 9
Scale In Meters
Engineering and Surveying Inc.
1091 9mnomdge 0nv •Bozeman,M159718
Phone(406)587411 S•Fax(406)587-9768
mm.chengineers.com•infoVchengi-vm.com Sheet 1 of it
(/16Q$2Q
APPENDIX B
DRAINAGE AREA CALCULATIONS
DRAINAGE AREA #1
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2) C "Area
Hardscape 0.95 13857 13164
Landscape 0.20 0 0
Total 13857 13164
A =Area(acres) 0.3181
C=Weighted C Factor 0.95
2. Calculate Tc(Time to Concentration)
Tc Overland Flow
Tc= 1.87 (1.1-CC)D'12/S'/3
------------------------------
;Storm
S= Slope of Basin (%) 2.00% ;Return (yrs) Cf
C = Rational Method Runoff Coefficient 0.35 i2 to 10 1
Cf= Frequency Adjustment Factor 1.1 11 to 25 1.1
D= Length of Basin (ft) 100 ,26 to 50 1.2
:51 to 100 1.25
Tc Overland Flow(minutes) 10.6
Tc Gutter Flow
Tc= L/V/60
V= (1.486/n)R2i3 S112
n = Mannings Coefficient 0.013
R= Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb)
S= slope (%) 1.20%
L= length of gutter(ft) 0
V= mean velocity(ft/s) 3.28
Tc Gutter Flow(minutes) = 0.0
Tc Total= 10.6 (5 minute minimum)
APPENDIX C
RETENTION FACILITIES DESIGN
DRAINAGE AREA #2
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft 2) C *Area
Hardscape 0.95 7807 7416
Landscape 0.20 0 0
Total 7807 7416
A =Area(acres) 0.1792
C=Weighted C Factor 0.95
2. Calculate Tc(Time to Concentration)
Tc Overland Flow
Tc= 1.87 (1.1-CC)D'/2/S1i3
------------------------------
;Storm
S = Slope of Basin (%) 2.00% ;Return (yrs) Cf
C= Rational Method Runoff Coefficient 0.35 ;2 to 10 1
Cf= Frequency Adjustment Factor 1.1 :11 to 25 1.1
D = Length of Basin (ft) 30 126 to 50 1.2
151 to 100 1.25
Tc Overland Flow(minutes) 5.8
Tc Gutter Flow
Tc= W/60
V= (1.486/n)R213 S112
n = Mannings Coefficient 0.013
R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb)
S = slope (%) 1.20%
L= length of gutter(ft) 80
V= mean velocity (ft/s) 3.28
Tc Gutter Flow(minutes) = 0.4
Tc Total= 6.2 (5 minute minimum)
UNDERGROUND INFILTRATION CHAMBERS
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area (ft2) C *Area
Hardscape 0.95 13857 13164
Landscape 0.20 0 0
Total 13857 13164
C=Weighted C Factor 0.95
2. Calculate Additional Required Volume
Q = CIA
V=72000
C =Weighted C Factor 0.95
1 = intensity(in/hr) 0.41 (10 yr, 2hr storm)
A=Area (acres) 0.32
Q = runoff(cfs) 0.12
V= REQUIRED VOL(ft) 887
EXISTING STORMWATER INFRASTRUCTURE
REQUIRED VOLUME
1. Calculate Area and Weighted C Factor
Contributing Area C Area ft2) C *Area
Hardscape 0.95 7807 7416
Landscape 0.20 0 0
Total 7807 7416
C=Weighted C Factor 0.95
2. Calculate Additional Required Volume
Q = CIA
V=72000
C =Weighted C Factor 0.95
1 = intensity (in/hr) 0.41 (10 yr, 2hr storm)
A=Area (acres) 0.18
Q = runoff(cfs) 0.07
V= REQUIRED VOL(ft) 500
INSPECTION AND MAINTENANCE FOR
STORMWATER MANAGEMENT FACILITIES
The Property Owners Association shall be responsible for the maintenance of the stormwater
drainage facilities within RSVP Motel Event Center development.
Storm Water Facilities:
I. Drainage swales slope toward retention and detention ponds to collect storm water
runoff and channel it to the retention or detention pond.
2. Retention Ponds collect storm water runoff and store the water until it evaporates and/or
infiltrates into the ground.
3. Detention ponds collect storm water runoff while allowing some water to drain to
another location.
4. Culverts are pipes which channel storm water from ditches or swales under roads.
5. Pipe Networks convey storm water to different discharge locations underground.
6. Inlets are facilities where storm water runoff enters a pipe network. Inlets include storm
water manholes and drains.
7. Catch Basins are sumps typically located directly below storm water inlets and allow
sediment to settle before storm water enters the pipe network.
8. Outlets are points where storm water exits a pipe network.
9. Dtywells are underground storm water collection facilities that collect and temporarily
store runoff from roof tops and landscaped areas before allowing storm water to infiltrate
into the ground.
Post Construction Inspection:
1. Observe drain time in retention ponds for a storm event after completion of the facility to
confirm that the desired drain time has been obtained. If excessively slow infiltration
rates are observed then excavate a minimum 5 ft by 5 ft drain to native gravels(or native
well-draining material)and backfill with well-draining material (pit-run).
2. Observe that drywells, catch basins, and outlet structures are clear of any material or
obstructions in the drainage slots. Inspect these structures to insure proper drainage
following a storm event. Immediately identify and remove objects responsible for
clogging if not draining properly.
Semi-Annual Inspection:
I. Check retention ponds and dry wells three days following a storm event exceeding 1/4
inch of precipitation. Failure for water to percolate within this time period indicates
clogging or poor-draining soils. Clear any clogs and replace any poor-draining soils with
well-draining gravely soils.
2. Check for grass clippings, litter, and debris in drainage swales, catch basins, dry wells,
culverts and retention ponds. Flush and/or vacuum drywells or storm water pipes if
excessive material is observed in the facilities.
Standard Maintenance:
1. Remove sediment and oil/grease from retention ponds and detention
2. Inspect and remove debris from drainage swales, catch basins,dry wells, and retention
ponds.Use a vacuum truck to clean catch basins and dry wells.
3. Monitor health of vegetation and revegetate as necessary to maintain full vegetative
cover.
4. Inspect for the following issues:differential accumulation of sediment,drain time,signs of
petroleum hydrocarbon contamination (odors, oil sheen in pond water), standing water,
trash and debris.
Sediment accumulation:
In most cases,sediment from a retention pond does not contain toxins at levels posing a hazardous
concern. However, sediments should be tested for toxicants in compliance with current disposal
requirements and if land uses in the drainage area include commercial or industrial zones, or if
visual or olfactory indications of pollution are noticed. Sediments containing high levels of
pollutants should be disposed of in accordance with applicable regulations and the potential
sources of contamination should be investigated and contamination practices terminated.
m t3 ® e o o a e B
EEN
Underground stormwater detention and infiltration systems must Maintenance
be inspected and maintained at regular intervals for purposes of CMP detention systems should be cleaned when an inspection reveals
performance and longevity. accumulated Sediment or trash is clogging the discharge orifice.
Inspection Accumulated sediment and trash can typically be evacuated through
Inspection is the key to effective maintenance of CMP detention the manhole over the outlet orifice. If maintenance is not performed
systems and is easily performed. Contech recommends ongoing, as recommended, sediment and trash may accumulate in front of the
quarterly inspections. The rate at which the system collects pollutants outlet orifice. Manhole covers should be securely seated following
will depend more on site specific activities rather than the size or cleaning activities. Contech suggests that all systems be designed with
configuration of the System. an access/inspection manhole situated at or near the inlet and the
outlet orifice. Should it be necessary to get inside the system to perform
Inspections should be performed more often in equipment washdown maintenance activities, all appropriate precautions regarding confined
areas, in climates where sanding and/or salting operations take space entry and OSHA regulations should be followed.
place, and in other various instances in which one would expect
higher accumulations of sediment or abrasive/corrosive conditions. A Systems are to be rinsed, including above the spring line, annually
record of each inspection is to be maintained for the life of the system. soon after"the spring thaw, and after any additional use of salting
agents, as part of the maintenance program for all systems where
salting agents may accumulate inside the pipe.
Maintaining an underground detention or infiltration system is easiest
when there is no flow entering the System. For this reason, it is a good
idea to schedule the cleanout during dry weather.
The foregoing inspection and maintenance efforts help ensure
underground pipe systems used for stormwater storage continue to
function as intended by identifying recommended regular inspection
and maintenance practices. Inspection and maintenance related
to the structural integrity of the pipe or the soundness of pipe joint
connections is beyond the scope of this guide.
i NOR
d
b "
°v
}y3
1
NOTHING IN THIS CATALOG SHOULD BE CONSTRUED AS A WARRANTY APPLICATIONS t/�r
SUGGESTED HEREIN ARE DESCRIBED ONLY TO HELP READERS MAKE THEIR OWN EVALUATIONS ���®► o ,.
AND DECISIONS,AND ARE NEITHER GUARANTEES NOR WARRANTIES OF SUITABILITY FOR ANY CMP DETENTION SYSTEMS
APPLICATION.CONTECH MAKES NO WARRANTY WHATSOEVER,EXPRESS OR IMPLIED,RELATED
TO THE APPLICATIONS,MATERIALS,COATINGS,OR PRODUCTS DISCUSSED HEREIN,All IMPLIED
WARRANTIES OF MERCHANTABILITY AND ALL IMPLIED WARRANTIES OF FITNESS FOR ANY
PARTICULAR PURPOSE ARE DISCIAIMED BY CONTECH"SEE CONTECIS CONDITIONS OF SALE
(AVAILABLE AT WWW CONTECHES.COM/COS)FOR MORE INFORMATION ENGINEERED SOLUTIONS
2017 Contech Engineered Solutions IIC
CMP MAINTENANCE GUIDE 2/17 PDF All rights reserved.Printed in USA.
WB-19 TRUCK TURNING ANALYSIS
M
� 11Z
ps} t Ld2
M
VEHICLE G
WHEEL PATH
SHORT STREET
W6-19 INTERSTATE
SEMITRAILER VEHICLE OVERRAN
I�
N
Scale In Feet
40 0 40
12 0 12
Scale In Mete"
&-
Engireerting and Surveying Inc.
1091 5craxwilW @rises•Bazcarnn,MT 59718
Ph—(4061587-1115•Feu(4061587-9768
tn¢v h-g -s-ecan•aSa .can Sweet 11 Or 1
y180620