HomeMy WebLinkAbout07-13-20 City Commission Packet Materials - C5. CO1 w Martel Construction for Anderson Pavilion Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Jon Henderson, Strategic Services Director SUBJECT: Change Order #1 for the Repair of the Anderson Pavilion at Bogert
Park MEETING DATE: July 13, 2020 MEETING TYPE Consent
RECOMMENDATION: Approve Change Order #1 for the Repair of the Anderson Pavilion at Bogert Park.
BACKGROUND:
On July 15th, 2019 the City Commission directed staff to proceed with repair of the Anderson Pavilion at Bogert Park (formerly known as the Bogert Pavilion) following a partial roof collapse that occurred on March 17th, 2019. Martel Construction was selected through a competitive RFQ / RFP process and awarded a Construction Contract for General Contractor / Construction
Manager services on November 4th, 2019. Further analysis has presented a need for additional
measures to support uneven loads that were not addressed in the initial structural calculations. Change Order #1 provides for an additional metal plate at the steel/wood interface of each beam end to mitigate instantaneous load reversal and shoring needs. This design change will ensure
long-term safety and longevity of the facility.
The project schedule will be adjusted by a total of three days, resulting in significant completion by September 23, 2020.
UNRESOLVED ISSUES:
None. FISCAL EFFECTS: Costs for this work total $16,745 and will be allocated from contingency funds within the
existing Guaranteed Maximum Price amount of $696,714.
ALTERNATIVES: As suggested by the City Commission.
Report Compiled on: 07/01/20
Attachments:
40
Change Order #1
41
Page 1 of 2 N:\0417\083 - Bogert Roof\06 Construction\CO (Change Orders)\Change Order #1\25 COB Change Order Form - Bogert CO#1.doc
CHANGE ORDER No. 1
DATE OF ISSUANCE 6/24/20 EFFECTIVE DATE 6/24/20
OWNER City of Bozeman CONTRACTOR Martel Construction Contract: Bogert Pavilion - GMP Amendment 2 Project: Bogert Pavilion Renovation OWNER's Contract No. 181901 ENGINEER Morrison Maierle ENGINEER's Contract No. April 1st, 2019 You are directed to make the following changes in the Contract Documents: Description: Changes to the shoring connection and connection of the steel beam to GLB per ESI #1 (attached)
Reason for Change Order: Update to connections per ESI #1, the additional cost for the connections is being
requested the contingency be used to cover the additional items.
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price $ 696,714
Original Contract Times: Substantial Completion: 9/9/20 Ready for final payment: 9/9/20
(days or dates)
Net Increase (Decrease) from previous Change
Orders No. to :
$ 0
Net change from previous Change Orders No. to No. : N/A Substantial Completion: Ready for final payment: (days)
Contract Price prior to this Change Order: $ 696,714
Contract Times prior to this Change Order: Substantial Completion: 9/9/20 Ready for final payment: 9/9/20 (days or dates)
Net increase (decrease) of this Change Order: $ 16,745 (to be used from Contingency)
Net increase (decrease) this Change Order: Substantial Completion: 5 Ready for final payment: 5 (days)
Contract Price with all approved Change Orders: $ 696,714
Contract Times with all approved Change Orders: Substantial Completion: 9/14/20 Ready for final payment:9/14/20 (days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein represents the full cost and value for the subject work performed and the materials supplied under the terms of the contract and that the work quantities and value were properly determined and are correct.
CONTRACTOR (Authorized Signature) Date 6/24/20 RECOMMENDED BY: APPROVED BY:
42
Page 2 of 2 N:\0417\083 - Bogert Roof\06 Construction\CO (Change Orders)\Change Order #1\25 COB Change Order Form - Bogert CO#1.doc
6/24/20 (ENGINEER - Signature) Date OWNER (Authorized Signature) Date CHANGE ORDER INSTRUCTIONS A. GENERAL INFORMATION
This document was developed to provide a uniform format for handling contract changes that affect Contract Price
or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a
subsequent Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice
of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes.
If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a
Field Order should be used.
B. COMPLETING THE CHANGE ORDER FORM
Engineer normally initiates the form, including a description of the changes involved and attachments based upon
documents and proposals submitted by Contractor, or requests from Owner, or both.
Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval,
depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated
agreement for a previously performed change. After approval by one contracting party, all copies should be sent to
the other party for approval. Engineer should make distribution of executed copies after approval by both parties.
If a change only applies to price or to times, cross out the part of the tabulation that does not apply.
43
06.24.20
City of Bozeman
Bozeman, Montana 59715
ATTN: Jon Henderson
Martel COR # 01
PROJECT:Bogert Pavilion Repairs
SUBJECT:Reinforcing and Shoring
REFERENCE:ESI #1
Dear Jon:
We propose to provide all labor, materials, and equipment required to
perform the above mentioned work. Our lump sum quotation is based
on our interpretation of the instructions and scope of work
identified by the Proposal Request(s). If we have misinterpreted this information in any
way (omissions, etc.) please advise us prior to processing this quotation into a
formal Change Order. Other wise, our interpretation shall stand as correct.
We have not been directed to proceed with the work.
At this time, we are hereby requesting 3 calendar days for a time extension
Please note this proposal is valid until 6/24/20. Approval beyond that date may result in additional costs or delays.
Our proposal is based on receipt of a signed Change Order within (25) calendar days.
We are requesting an Adjustment to the Project lump sum for the amount of:16,745.00$
If you have any questions, please call me at (406) 600-4057
Sincerely,
MARTEL CONSTRUCTION, INC.
John Kalmon
Enclosure(s)
CC.File
44
ENGINEER’S SUPPLEMENTAL INSTRUCTION ESI #1
Date: June 21, 2020 Job Number: 0417.083
Project: Bogert Park Pavilion Renovation Issued To: Martel Construction
Regarding: Connection of the steel beam saddle to the existing interior and exterior GLB per detail 2/S300 to include additional bolts and side plate reinforcing to resist a reversal in the forces seen by the beams due to an unbalance snow condition if the snow slides off one side. The reinforcing will resist the load reversal until compression forces can help resist the load reversal. Information: Provide (10) additional 1” dia. ASTM A307 through bolts in 2 rows of (5) with the first row starting 3” below the top of the GLB, and the second row starting 4”. Space the bolts at 3” O.C. The minimum saddle required for the new bolts shall be ¼” thick, by 1’-8” long and 12” deep each side of beam and
welded to the original saddle. The below shoring detail is acceptable, as an alternative.
Attachments: None
Issued By: Morrison Maierle Inc By: Jay Fischer Date: 06-21-20 End of Engineer’s Supplemental Instructions
45
Martel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - CO#1 Shoring & Reinforcement R46/24/2020 10:05 AMGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal Amount01-0000GENERAL REQUIREMENTS101-0150Project Management2Project Manager20.00hr996--9963 Project Management99699601-6120Equipment Rental4Shoring post, jack, cable, tensioners1.00ea--1,840-1,8405 Equipment Rental1,8401,84001-7010Layout6Layout1.00hr421-5-477 Layout421547 GENERAL REQUIREMENTS1,03811,84052,88302-0000EXISTING CONDITIONS802-2200Selective Demolition9Shore Typical Glulam Beams for Splices(18.00)ea*(4,860)---(4,860)10Shore Beams at Warming Area(2.00)ea*(540)---(540)11Cut Back Roofing / Sheathing - 64" Strip917.00sf320----32012Remove Wood I Joists20.00ea838----83813 Selective Demolition1,159(5,400)(4,241) EXISTING CONDITIONS1,159(5,400)(4,241)05-0000STEEL1405-1200Structural Steel15Shoring saddle & splice plates20.00ea4193,792-4,21116Reinforcement saddle & splice plates20.00ea41903,7920-4,21117Shoring connector - labor0.00ea0000-018Shoring connector - material4.00ea813-81319Weld splice plates20.00ea1,6670-0-1,66720 Structural Steel2,5058,39710,902 STEEL2,5058,39710,90206-0000WOOD & PLASTICS2106-0600Wood Materials22Drill bits1.00ls--100-10023 Wood Materials10010006-0900Hardware & Fasteners24Bolts, nuts, washers - A307400.00est-3,600---3,60025 Hardware & Fasteners3,6003,60006-1160Roof Framing26Salvage existing second joist - mat0.00bf00---027New second joist - mat0.00bf00---028Install second joist - labor450.00bf755---75529 Roof Framing75575506-1650Wood Panel Sheathing305/8" Plywood Roof Sheathing - Roof Edge Splice - 64" Width617.00sf924543---1,46731 Wood Panel Sheathing9245431,467 WOOD & PLASTICS1,6784,1431005,92146
Martel ConstructionSpreadsheet ReportPage 2ABogert Pavilion Renovation - CO#1 Shoring & Reinforcement R46/24/2020 10:05 AMEstimate TotalsDescriptionAmountTotalsRateLabor6,380Material(1,257)Subcontract10,237Equipment105Other15,46515,465General Liability Insurance1490.890%Gross Receipts Tax1671.000%Builders Risk300.180%Bond1370.820%Construction Fee7975.000%Construction Contingency1,28016,745Total16,745This is the combined amount from OwnersContingency and Contractors Contingency47
Martel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - CO#1.1 Reinforcement Only R46/24/2020 10:07 AMGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal Amount01-0000GENERAL REQUIREMENTS101-0150Project Management2Project Manager10.00hr498--4983 Project Management49849801-6120Equipment Rental4Shoring post, jack, cable, tensioners0.00ea--00-0501-7010Layout6Layout0.50hr210-3-247 Layout210324 GENERAL REQUIREMENTS5190352202-0000EXISTING CONDITIONS802-2200Selective Demolition9Shore Typical Glulam Beams for Splices0.00ea*0---010Shore Beams at Warming Area0.00ea*0---011Cut Back Roofing / Sheathing - 64" Strip917.00sf320----32012Remove Wood I Joists20.00ea838----83813 Selective Demolition1,1591,159 EXISTING CONDITIONS1,1591,15905-0000STEEL1405-1200Structural Steel15Shoring saddle & splice plates0.00ea0000-016Reinforcement saddle & splice plates20.00ea41905,2400-5,65917Shoring connector - labor0.00ea0000-018Shoring connector - material0.00ea0000-019Weld splice plates20.00ea1,6670-0-1,66720 Structural Steel2,0865,2407,326 STEEL2,0865,2407,32606-0000WOOD & PLASTICS2106-0600Wood Materials22Drill bits1.00ls-0-50-5023 Wood Materials505006-0900Hardware & Fasteners24Bolts, nuts, washers - A307320.00est-2,880---2,88025 Hardware & Fasteners2,8802,88006-1160Roof Framing26Salvage existing second joist - mat0.00bf00---027New second joist - mat0.00bf00---028Install second joist - labor450.00bf7560---75629 Roof Framing75675606-1650Wood Panel Sheathing305/8" Plywood Roof Sheathing - Roof Edge Splice - 64" Width617.00sf924543---1,46731 Wood Panel Sheathing9245431,467 WOOD & PLASTICS1,6803,423505,15348
Martel ConstructionSpreadsheet ReportPage 2ABogert Pavilion Renovation - CO#1.1 Reinforcement Only R46/24/2020 10:07 AMEstimate TotalsDescriptionAmountTotalsRateLabor5,443Material3,423Subcontract5,240Equipment53Other14,15914,159General Liability Insurance1360.890%Gross Receipts Tax1531.000%Builders Risk280.180%Bond1260.820%Construction Fee7305.000%Construction Contingency1,17315,332Total15,332This amount is fromOwners Contingency49
Martel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - CO#1.2 Shoring Only R46/24/2020 10:09 AMGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal Amount01-0000GENERAL REQUIREMENTS101-0150Project Management2Project Manager10.00hr498--4983 Project Management49849801-6120Equipment Rental4Shoring post, jack, cable, tensioners1.00ea--1,840-1,8405 Equipment Rental1,8401,84001-7010Layout6Layout0.50hr210-3-247 Layout210324 GENERAL REQUIREMENTS51901,84032,36202-0000EXISTING CONDITIONS802-2200Selective Demolition9Shore Typical Glulam Beams for Splices(18.00)ea*(4,860)---(4,860)10Shore Beams at Warming Area(2.00)ea*(540)---(540)11Cut Back Roofing / Sheathing - 64" Strip0.00sf0----012Remove Wood I Joists0.00ea0----013 Selective Demolition(5,400)(5,400) EXISTING CONDITIONS(5,400)(5,400)05-0000STEEL1405-1200Structural Steel15Shoring saddle & splice plates4.00ea841,517-1,60116Reinforcement saddle & splice plates0.00ea0000-017Shoring connector - labor0.00ea0000-018Shoring connector - material4.00ea813-81319Weld splice plates0.00ea00-0-020 Structural Steel842,3302,414 STEEL842,3302,41406-0000WOOD & PLASTICS2106-0600Wood Materials22Drill bits1.00ls--50-5023Plug beam holes400.00ea559600--1,15924 Wood Materials559600501,20906-0900Hardware & Fasteners25Bolts, nuts, washers - A30780.00est-720---72026 Hardware & Fasteners72072006-1160Roof Framing27Salvage existing second joist - mat0.00bf00---028New second joist - mat0.00bf00---029Install second joist - labor0.00bf00---03006-1650Wood Panel Sheathing315/8" Plywood Roof Sheathing - Roof Edge Splice - 64" Width0.00sf00---032 WOOD & PLASTICS5591,320501,92950
Martel ConstructionSpreadsheet ReportPage 2ABogert Pavilion Renovation - CO#1.2 Shoring Only R46/24/2020 10:09 AMEstimate TotalsDescriptionAmountTotalsRateLabor1,161Material(4,080)Subcontract4,170Equipment53Other1,3041,304General Liability Insurance130.890%Gross Receipts Tax141.000%Builders Risk30.180%Bond120.820%Construction Fee675.000%Construction Contingency1091,413Total1,413This amount is fromContractors Contingency51
ID Task NameDuration Start Finish Predecessors12PRE-CONSTRUCTION PHASE172 daysFri 10/11/19Fri 6/12/203City of Bozeman Approval Process6 daysFri 10/11/19Fri 10/18/194Execute Contract between COB and GCCM6 daysFri 10/11/19Fri 10/18/1956Building Permit Process32 daysThu 4/30/20Fri 6/12/207Application & Submittal of Building Permit32 daysThu 4/30/20Fri 6/12/208Submission of Building Permit3 daysThu 4/30/20Mon 5/4/20259Building Permit Review Process15 daysTue 5/5/20Mon 5/25/20810Building Department Review Letter1 dayTue 5/26/20Tue 5/26/20911Building Department Corrections - Documented & Submitted5 daysWed 5/27/20Tue 6/2/201012Final Plan Approval Letter3 daysWed 6/3/20Fri 6/5/201113Building Permit Issuance5 daysMon 6/8/20Fri 6/12/20121415DESIGN PHASE103 daysMon 10/21/19Tue 3/17/2016Design Development Phase38 daysMon 10/21/19Fri 12/13/191790% Construction / Permit Documents Phase Drawings25 daysMon 10/21/19Fri 11/22/1941890% CD Budget10 daysMon 11/25/19Tue 12/10/191719Owner Approval of 90% CD's & Budget3 daysWed 12/11/19Fri 12/13/191820Construction Documents Phase65 daysMon 12/16/19Tue 3/17/2021Construction Documents Phase Drawings55 daysMon 12/16/19Tue 3/3/201922GC/CM update project budget 7 daysWed 3/4/20Thu 3/12/202123Approval of CD's and Budget For Procurement3 daysFri 3/13/20Tue 3/17/20222425CONSTRUCTION PROCUREMENT PHASE31 daysWed 3/18/20Wed 4/29/2026GC/CM Bidding Prep5 daysWed 3/18/20Tue 3/24/202327SUB / Supplier BIDDING OF PROJECT18 daysWed 3/25/20Fri 4/17/202628Proposals Due0 daysFri 4/17/20Fri 4/17/202729Prepare Final Estimate5 daysMon 4/20/20Fri 4/24/202830Amendment No. 2 Award - FINAL GMP FOR PROJECT3 daysMon 4/27/20Wed 4/29/20293132CONSTRUCTION PHASE104.5 daysThu 4/30/20Wed 9/23/20COB Building DepartmentCOB Building DepartmentMorrison & MaierleCOB Building DepartmentCOB Building DepartmentMEBMEBMEBMEBMJuneJulyAugustSeptemberOctoberTaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneProgressDeadlineProject ScheduleBogert Pavilion6/22/20 - CO#1Martel Construction, Inc.Page 1Bogert Pavilion10.11.201952
ID Task NameDuration Start Finish Predecessors33SUBMITTALS40 daysThu 4/30/20Wed 6/24/2034Procurement of Lead Time Items40 daysThu 4/30/20Wed 6/24/203035Joist Hangers0 daysMon 6/22/20Mon 6/22/2036Joists0 daysMon 6/22/20Mon 6/22/2037GL Beam0 daysMon 6/22/20Mon 6/22/2038Steel Beams0 daysFri 6/26/20Fri 6/26/203940NOTICE TO PROCEED16 daysThu 4/30/20Thu 5/21/2041Contract Insurance Certificates to Owner3 daysThu 4/30/20Mon 5/4/203042Contract Bonds to Owner3 daysTue 5/5/20Thu 5/7/204143Notice to Proceed Submittals by GCCM5 daysFri 5/8/20Thu 5/14/204244Owner Requirements for NTP (Testing, Builders Risk, Contracts)5 daysFri 5/15/20Thu 5/21/20434546PRE-CONSTRUCTION MEETING0 daysThu 5/28/20Thu 5/28/2047Pre-Con Meeting0 daysThu 5/28/20Thu 5/28/2044FS+5 days4849MOBILIZATION9 daysThu 6/18/20Tue 6/30/2050Construction Staging and Laydown Area & Security Fencing4 daysThu 6/25/20Tue 6/30/203351Temp Facilities - Trailers, Dumpsters, Porta Potties etc.4 daysThu 6/25/20Tue 6/30/203352Brad + 1 labor0 daysThu 6/18/20Thu 6/18/2053Add 2 carpenters0 daysMon 6/22/20Mon 6/22/205455CONSTRUCTION - BUILDING REPAIRS60.5 daysMon 6/22/20Mon 9/14/2056Building Shell47 daysMon 6/22/20Tue 8/25/2057Steel Erection - 10 beams / 20 ends40 daysWed 7/1/20Tue 8/25/2013,4958Install temp beam shoring8 wksWed 7/1/20Tue 8/25/2059Demo beam ends8 wksWed 7/1/20Tue 8/25/2060Install new anchor bolts8 wksWed 7/1/20Tue 8/25/2061Erect new steel beam ends8 wksWed 7/1/20Tue 8/25/2062Install miscellaneous iron and bracing8 wksWed 7/1/20Tue 8/25/2063Carpentry Work21.5 daysMon 6/22/20Tue 7/21/2064Install GLB arch2.4 wksMon 6/22/20Tue 7/7/205365Install joists & sheathing at new roof area1.5 wksWed 7/8/20Fri 7/17/2064Martel6/226/226/226/26MartelMartel6/186/22Steel Erection ContractorSteel Erection ContractorSteel Erection ContractorSteel Erection ContractorSteel Erection ContractorFraming ContractorFraming ContractorMEBMEBMEBMEBMJuneJulyAugustSeptemberOctoberTaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneProgressDeadlineProject ScheduleBogert Pavilion6/22/20 - CO#1Martel Construction, Inc.Page 2Bogert Pavilion10.11.201953
ID Task NameDuration Start Finish Predecessors66Repair bathroom roof2 daysFri 7/17/20Tue 7/21/206567Roofing15 daysTue 7/21/20Tue 8/11/2068Install New Roofing Systems Flashing & Trim3 wksTue 7/21/20Tue 8/11/206369Plumbing15 daysTue 7/21/20Tue 8/11/2070Re-connect Fire Sprinkler Lines and Repair as required2 wksTue 7/21/20Tue 8/4/206371Flush, test, and clean piping and fixtures1 wkTue 8/4/20Tue 8/11/207072Electrical20 daysTue 7/21/20Tue 8/18/2073Electrical Conduit Repairs2 wksTue 7/21/20Tue 8/4/206374Install new LED fixtures1 wkTue 8/4/20Tue 8/11/207375Install new main panel on pedestal 1 wkTue 8/11/20Tue 8/18/207476Paint 12.5 daysFri 8/21/20Tue 9/8/2077Paint roof understructure & bathroom exterior2.5 wksFri 8/21/20Tue 9/8/2057FS-3 days,7578Final Clean-up4 daysTue 9/8/20Mon 9/14/2079Remove debris from building and do final clean-up4 daysTue 9/8/20Mon 9/14/2071,7680Request Substantial completion date0 daysMon 9/14/20Mon 9/14/20798182SUBSTANTIAL COMPLETION & OCCUPANCY31 daysTue 8/11/20Wed 9/23/2083Substantial Completion - Project Milestone0 daysMon 9/14/20Mon 9/14/208084AHJ Requirements11 daysTue 8/11/20Wed 8/26/2085Perform local building agency inspection1 dayTue 8/18/20Wed 8/19/207586Perform Fire Marshal's inspection1 dayTue 8/11/20Wed 8/12/207187Complete task list items from all inspections5 daysWed 8/19/20Wed 8/26/2085,8688Obtain certificate of occupancy - AHJ0 daysWed 8/26/20Wed 8/26/208789Owner / Architect Requirements20 daysWed 8/26/20Wed 9/23/2090Request Engineer's Inspection0 daysWed 8/26/20Wed 8/26/208891Engineers's Inspection2 daysWed 8/26/20Fri 8/28/209092Complete punch list items from Engineer's Inspection5 daysFri 8/28/20Fri 9/4/209193Engineer confirm punch list1 dayFri 9/4/20Mon 9/7/209294Issue final completion documents including warranties1 dayMon 9/7/20Tue 9/8/209395Issue final request for payment1 dayMon 9/14/20Tue 9/15/2080,9496Contractor Prepared Punch List Process - to Subs7 daysMon 9/14/20Wed 9/23/208097Owner Occupancy0 daysMon 9/14/20Mon 9/14/2098Owner Occupancy0 daysMon 9/14/20Mon 9/14/2088,79Roofing ContractorFS ContractorFS ContractorElectric ContractorElectric ContractorPainting ContractorG.C. Labor Crew9/149/14AHJFire MarshalAll Trades8/268/26Morrison & MaierleMartelMorrison & MaierleMartelMartelMartel9/149/14MEBMEBMEBMEBMJuneJulyAugustSeptemberOctoberTaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneProgressDeadlineProject ScheduleBogert Pavilion6/22/20 - CO#1Martel Construction, Inc.Page 3Bogert Pavilion10.11.201954
CONFIDENTIAL
Price Quotation
June 22, 2020
MARTEL CONSTRUCTION, INC.
1203 S CHURCH AVE
BOZEMAN, MT 59715-5801
Phone: 406-600-4057
Fax:
ATTN: John Kalmon
25387
BZMT1564
07/22/2020
06/24/2020Account #:
Quote #:Expiration Date:
Due Date:
Job #:PO #:
Extended PriceQuantityDescriptionCustomer Part #Part #Price/C
14485 $2,632.08$658.0200400HCS 1-8 x 11 P8
1"-8 x 11" Grade 8 Plain Finish Hex Cap Screw
36419 $212.00$53.00004001"-8 FHN P 8
1"-8 Plain Finish Grade 8 Finished Hex Nut
33852 $272.64$34.0800800USS THRU-HARD 1" P
1" x 2.500" OD Thru-Hardened Plain Finish Steel USS General Purpose Flat Washer
$3,116.72USD Subtotal:
$100.00Shipping & Handling:
$3,216.72USD Total:
*Shipping & Handling charges are subject to change.
FASTENAL
8235 Huffine Lane
Bozeman, MT 59718
Phone: (406)582-8119
Fax: (406)582-8142
E-mail: MTBOZ@stores.fastenal.com
Thank you,
Page 1 of 1 QUOTE REPORTFASTENAL COMPANY 55
56
Quote number: Q200615-6
Prepared for:Prepared by:
John Kalmon
Martel Construction
1203 S Church Ave
Bozeman, MT 59715
Phone: 406-600-4057
Chuck Gardenhire
112 Commercial Dr
Bozeman, MT 59715
Created date:
Expiration date:
06/15/2020
07/15/2020
20 Ea. Shoring Saddles including 4 ea. 3/4-10 Grade 8 Studs per unit.
Note; 16 ea. 8.750" Wide, 4 ea. 5.125" Wide
Notes:
Quantity Unit Price Extended PriceNameItemMaterialGaugeWidthLength
Shoring Saddle(2)40 $54.908 $2,196.311MS A36 HR
0.250 in.
.25028.50 20.00
Shoring Saddle(1)16 $21.383 $342.132MS A36 HR
0.250 in.
.25010.00 20.00
Shoring Saddle(3)4 $17.558 $70.233MS A36 HR
0.250 in.
.2506.50 20.00
Weld & Assm.20 $105.177 $2,103.5440.00 0.00
Secondary operations:
3/4-10 All-Thrd.
Weld & Assm.
Total:$4,712.22
6/19/2020 Page 1 of 1www.JMetalWorks.com
57
Quote number: Q200618-7
Prepared for:Prepared by:
John Kalmon
Martel Construction
1203 S Church Ave
Bozeman, MT 59715
Phone: 406-600-4057
Chuck Gardenhire
112 Commercial Dr
Bozeman, MT 59715
Created date:
Expiration date:
06/18/2020
07/18/2020
4 Ea. Shoring Base Plt. Assm.Notes:
Quantity Unit Price Extended PriceNameItemMaterialGaugeWidthLength
Shoring Base Plt
Assm(1)
4 $21.836 $87.341MS A36 HR
0.500 in.
.50010.63 4.00
Shoring Base Plt
Assm(2)
4 $24.289 $97.162MS A36 HR
0.250 in.
.25012.00 12.00
Shoring Base Plt
Assm(3)
4 $39.385 $157.543MS A36 HR
0.500 in.
.50012.00 12.00
6.00" Sch 40 Pipe 4 $15.600 $62.4040.00 0.00
Weld & Assm.4 $102.375 $409.5050.00 0.00
Secondary operations:
Saw
Weld & Assm.
Total:$813.94
6/18/2020 Page 1 of 1www.JMetalWorks.com
58
Quote number: Q200618-6
Prepared for:Prepared by:
John Kalmon,
Martel Construction
1203 S Church Ave
Bozeman, MT 59715
Phone: 406-600-4057
Chuck Gardenhire
112 Commercial Dr
Bozeman, MT 59715
Created date:
Expiration date:
06/18/2020
07/18/2020
20 sets Splice Plt. & Joist Saddle
Note: We may have to use a USP416 Brkt. the other are out 6 days on Delv.
Notes:
Quantity Unit Price Extended PriceNameItemMaterialGaugeWidthLength
Splice Plts 40 $18.321 $732.831MS A36 HR
0.250 in.
.2506.00 28.50
Simpson HUC416 Face
Mnt Hanger
40 $53.463 $2,138.5020.00 0.00
Secondary operations:
Weld & Assm.
Total:$2,871.33
6/19/2020 Page 1 of 1www.JMetalWorks.com
59
60