Loading...
HomeMy WebLinkAbout20- Change Order 2 - Montana Civil Contractors Inc. - Durston Road from Flanders Mill Road to Fowler AvenueDATE OF ISSUANCE CHANGE ORDER EFFECTIVE DATE lM OWNER: City of Bozeman CONTRACTOR Montana Civil Contractors Inc. Contract: Durston Road from Flanders Mill Road to Fowler Avenue dated July 2 2019 Project: Durston Road from Flanders Mill to Fowler OWNER's Contract No. ENGINEER: RPA ENGINEER's Contract No. 14510.001 You are directed to make the following changes in the Contract Documents: • Add a Field Adjustable Wattage Selector (FAWS) retrofit kit to the LED lamps that are currently in stock at the Contractors storage facility,,.The FAWS will be added to all 33 lamps to meet the lighting standards in the cnirent draft revision of the City of Bozeman Standard Specificationsfor Lighting Materials and Installation, dated January 2020. This Change Order also includes one house shield for the luminaire in the northeast corner of Durston Road and Ferguson Avenue, near a townhouse. The additional cost for the FAWS and house shield is $7,455.00. Reason for Change Order: • To meet current City of Bozeman lighting standards that were approved after the design of this lighting system. Attachments: (List documents supporting change) CHANGE IN CONTRACT PRICE: Original Contract Price _$ 3,561,215.00 Net Increase (Decrease) from previous Change Orders No. 1 $22,323.55 Contract Price prior to this Change Order: $3,583,538.55 Net increase (decrease) of this Change Order: $7,455.00 Contract Price with all approved Change Orders: $3,590,993.55 CHANGE IN CONTRACT TIMES: Original Contract Times: Substantial Completion: 180 calendar days Ready for final payment: (days or dates Net change from previous Change Orders No. 1 Substantial Completion: 7 calendar days Ready for final payment: (days) Contract Times prior to this Change Order: Substantial Completion: 187 calendar days Ready for final payment: (days or dates Net increase (decrease) this Change Order: Substantial Completion: n/a Ready for final payment: (days) Contract Times with all approved Change Orders: Substantial Completion: 187 calendar days Ready for final payment: (days or dates) CHANGE ORDER FORM Page 1 of 3 Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set forth herein and unless expressly stated otherwise in the Change Ordcr. And further, that the price agreed-upon herein represents the full cost and value for the subject work performed and the materials supplied under the terms of the contract and that the work quantities and value were properly determined and are correct. CONTRACT (Autho'rized Signature) Date' RECOMMENDED BY: APPROVED BY: Z_�2�JZp �-�— �. P TDte e 2.0 (ENGINEER - Signature) Date OWNER (Authorized Signa rc) CHANGE ORDER FORM Page 2 of 3 CHANGE ORDER INSTRUCTIONS A. GENERAL INFORMATION This document was developed to provide a uniform format for handling contract changes that affect Contract Price or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a subsequent Change Order if they affect Price or Times. Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes. If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed. For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a Field Order should be used. B. COMPLETING THE CHANGE ORDER FORM Engineer normally initiates the form, including a description of the changes involved and attachments based upon documents and proposals submitted by Contractor, or requests from Owner, or both. Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval, depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated agreement for a previously performed change. After approval by one contracting party, all copies should be sent to the other party for approval. Engineer should make distribution of executed copies after approval by both parties. If a change only applies to price or to times, cross out the part of the tabulation that does not apply. CHANGE ORDER FORM Page 3 of 3 Montana Civil Contractors tic. P.O. Box 1019, Belgrade, MT59714 imv.montanacivil.com T.- 406-388-1740 F.- 406-388-5105 Work Change Directive #7 — Field Adjustable Wattage Selector Project: Durston Road, Flanders Mill to Fowler Ave Date: March 27, 2020 Dear Staci, Below are the costs associated with the work to be done as described below to install field adjustable wattage selectors and shielding along the roundabout at Durston and Ferguson. 1. Procure and install field adjustable wattage selectors to 33ea lighting fixtures. 2. Procure and install shielding to lea fixture. *Price does not include any work from the original project specified work already contracted with MCC Below is the estimated manhours and eauivment needed to car v ntit the work riPccrihnri Description Subtotal Montana Lines — Subcontractor $7,100.00 Markup — 5% $355.00 Total Cost $7,455.00 Price does not include unforeseen time & materials above and beyond line items 1 and 2. Sincerely, Owen Strods Montana Civil Contractors