HomeMy WebLinkAboutCity Commission Meeting 5.18.2020 C7 Amendment Constr. Contract, Anderson Pavilion at Bogert Park Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Jon Henderson, Strategic Services Director SUBJECT: Setting the Guaranteed Maximum Price for Repair of the Anderson Pavilion at Bogert Park MEETING DATE: May 18, 2020 MEETING TYPE Consent RECOMMENDATION: Ratify the Interim City Manager’s signature on an Amendment to the Construction Contract for the Anderson Pavilion at Bogert Park Setting the Guaranteed Maximum Price. BACKGROUND: On July 15th, 2019 the City Commission directed staff to proceed with repair of the Anderson Pavilion at Bogert Park (formerly known as the Bogert Pavilion) following a partial roof collapse that occurred on March 17th, 2019. Martel Construction was selected through a competitive RFQ / RFP process and awarded a Construction Contract for General Contractor / Construction Manager services on November 4th, 2019. The contract relies on a Guaranteed Maximum Price (GMP) to ensure total costs fit within the allowable budget. Formal bids for the project were received on April 17th, 2020 following an extensive design process intended to provide the highest level of safety and longevity, in addition to construction standards needed to comply with current building codes. This Amendment sets the Guaranteed Maximum Price (GMP) for the construction phase of the project not exceed $696,714. The Base Bid of $440,704 comprises all general requirements and existing conditions, including electrical work and minor site improvements (among other related services). Alternate #1 includes full replacement of the roof membrane for $202,378, necessary to maintain the integrity of the overall roof system among all areas of the repair. Alternate #3 includes LED lighting upgrades for $13,310 to replace aging and inefficient fixtures. Other work includes $10,352 for pre- construction services and $29,970 for winter stabilization efforts including the installation of a support system to prevent further collapse. The attached amendment has been reviewed by the Legal Department and signed by the City Manager to expedite long-lead material orders without negatively impacting the project schedule. Substantial completion is anticipated by September 18th, 2020. Efforts will be made to minimize disruption in the adjacent park area, while the Pavilion remains closed to the public. 85 UNRESOLVED ISSUES: None. FISCAL EFFECTS: On June 24th, 2019 the City Commission allocated $200,000 to the project as part of Resolution No. 5048 adopting a final budget for FY20. An additional $209,507 was allocated on September 9th, 2019 as part of Resolution No. 5068 setting mill levies for FY20. On October 21st, 2019 the City Commission accepted a donation of $350,000 in exchange for naming rights (“The Anderson Pavilion at Bogert Park”), bringing the total budget to $759,507. $51,626 has been spent to date for structural assessments, security fencing, and other expenses related to the initial response. Negotiations with MMIA are ongoing as part of an insurance claim to determine the appropriate reimbursement for damage related to the collapse. Any remaining balance upon project completion will go back to the General Fund. ALTERNATIVES: As suggested by the City Commission. Report Compiled on: 05/08/20 Attachments: Guaranteed Maximum Price Proposal Guaranteed Maximum Price Amendment 86 Bogert Pavilion Repairs Bozeman, Montana GMP April 24, 2020 87 TABLE OF CONTENTS Section One Executive Summary Section Two Notes and Assumptions Concerning the GMP Section Three Schedule Section Four GMP Spreadsheet Section Five Document List 88 SECTION ONE Executive Summary Task Outline Martel Construction Inc. was selected by the City of Bozeman to repair the Bogert Pavilion roof damage. After bids were received, a GMP (Guaranteed Maximum Price) was assembled for the project. This GMP includes all the work shown on the contract documents. The attached GMP Summary is taken from the drawings and other information provided by the Design Team. Project Description The project consists of repairs and upgrades for the Bogert Pavilion located in Bogert Park. The scope of the work is defined by the project plans, specifications and addenda used to determine the Guaranteed Maximum Cost. Briefly Described as: a. Approximate Square Footage: ~30,000 gross square feet. b. Location: Bogert Park, 325 S Church Ave, Bozeman, MT c. Occupancy: Assembly Group A-5 GMP - Summary of Cost Pre-Construction Services $10,352 Early Work Amendment #1 $29,970 Construction Services Amendment #2 Base Bid $440,704 Alternate #1 – Complete Reroof $202,378 Alternate #2 – New LED Lighting $13,310 Total GMP $696,714 89 SECTION TWO Notes and Assumptions Concerning the Budget General This Presentation and the Notes and Assumptions Concerning the Proposals and are prepared for the purpose of providing information to the City of Bozeman to guide their decisions on the proposed work. Pricing – The Current pricing is based on the information from Martel Construction and from public bidding results. Total estimated value includes the following costs: · Performance and Payment Bond · General Liability Insurance · GC/CM Fee per Contract · Gross Receipts Tax · Builders Risk Insurance · Alternates as depicted in the attachment · Construction Contingency We are not carrying costs in our construction estimate for: · Plan Review Fees, Building Permits or Impact Fees · Escalation · Third Party Testing & Inspections and Special Inspections · Commissioning · Northwest Energy Costs · Other Utility Company Costs · Hazardous Material Abatement of any kind. · Moving Expenses of Owner Items General Conditions for the project are based on a project duration totaling 10 weeks without shutdown. If the project schedule is altered and the phasing of construction is different than estimated, the duration of the General Conditions will be changed to reflect the alternations. 90 SECTION THREE Project Schedule · See attached 91 ID Task NameDuration Start FinishPredecessorsSuccessorsResource Names12PRE-CONSTRUCTION PHASE172 daysFri 10/11/19Fri 6/12/203City of Bozeman Approval Process6 daysFri 10/11/19Fri 10/18/194Execute Contract between COB and GCCM6 daysFri 10/11/19Fri 10/18/1917COB / Martel56Building Permit Process32 daysThu 4/30/20Fri 6/12/207Application & Submittal of Building Permit32 daysThu 4/30/20Fri 6/12/208Submission of Building Permit3 daysThu 4/30/20Mon 5/4/20259Morrison & Maierle9Building Permit Review Process15 daysTue 5/5/20Mon 5/25/20810COB Building Department10Building Department Review Letter1 dayTue 5/26/20Tue 5/26/20911COB Building Department11Building Department Corrections - Documented & Submitted5 daysWed 5/27/20Tue 6/2/201012Morrison & Maierle12Final Plan Approval Letter3 daysWed 6/3/20Fri 6/5/201113COB Building Department13Building Permit Issuance5 daysMon 6/8/20Fri 6/12/201252COB Building Department1415DESIGN PHASE103 daysMon 10/21/19Tue 3/17/2016Design Development Phase38 daysMon 10/21/19Fri 12/13/191790% Construction / Permit Documents Phase Drawings25 daysMon 10/21/19Fri 11/22/19418Morrison & Maierle1890% CD Budget10 daysMon 11/25/19Tue 12/10/191719Martel19Owner Approval of 90% CD's & Budget3 daysWed 12/11/19Fri 12/13/191821COB20Construction Documents Phase65 daysMon 12/16/19Tue 3/17/2021Construction Documents Phase Drawings55 daysMon 12/16/19Tue 3/3/201922Morrison & Maierle22GC/CM update project budget 7 daysWed 3/4/20Thu 3/12/202123Martel23Approval of CD's and Budget For Procurement3 daysFri 3/13/20Tue 3/17/202226COB2425CONSTRUCTION PROCUREMENT PHASE31 daysWed 3/18/20Wed 4/29/20826GC/CM Bidding Prep5 daysWed 3/18/20Tue 3/24/202327Martel27SUB / Supplier BIDDING OF PROJECT18 daysWed 3/25/20Fri 4/17/202628Martel28Proposals Due0 daysFri 4/17/20Fri 4/17/202729Martel29Prepare Final Estimate5 daysMon 4/20/20Fri 4/24/202830Martel30Amendment No. 2 Award - FINAL GMP FOR PROJECT3 daysMon 4/27/20Wed 4/29/202934,37COB / Martel3132CONSTRUCTION PHASE102 daysThu 4/30/20Fri 9/18/2033SUBMITTALS40 daysThu 4/30/20Wed 6/24/2046,4734Procurement of Lead Time Items40 daysThu 4/30/20Wed 6/24/2030Martel3536NOTICE TO PROCEED16 daysThu 4/30/20Thu 5/21/2037Contract Insurance Certificates to Owner3 daysThu 4/30/20Mon 5/4/203038Martel38Contract Bonds to Owner3 daysTue 5/5/20Thu 5/7/203739Martel39Notice to Proceed Submittals by GCCM5 daysFri 5/8/20Thu 5/14/203840Martel40Owner Requirements for NTP (Testing, Builders Risk, Contracts)5 daysFri 5/15/20Thu 5/21/203943FS+5 daysMartel4142PRE-CONSTRUCTION MEETING0 daysThu 5/28/20Thu 5/28/2043Pre-Con Meeting0 daysThu 5/28/20Thu 5/28/2040FS+5 daysMartel4445MOBILIZATION4 daysThu 6/25/20Tue 6/30/205246Construction Staging and Laydown Area & Security Fencing4 daysThu 6/25/20Tue 6/30/2033MartelCOB / MartelMorrison & MaierleCOB Building DepartmentCOB Building DepartmentMorrison & MaierleCOB Building DepartmentCOB Building DepartmentMorrison & MaierleMartelCOBMorrison & MaierleMartelCOBMartelMartel4/17MartelCOB / MartelMartelMartelMartelMartelMartel5/285/28MartelSONDJFMAMJJASONDHalf 1, 2020Half 2, 2020Half 1, 2021TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneProgressDeadlineProject ScheduleBogert Pavilion4/1/20Martel Construction, Inc.Page 1Bogert Pavilion10.11.201992 ID Task NameDuration Start FinishPredecessorsSuccessorsResource Names47Temp Facilities - Trailers, Dumpsters, Porta Potties etc.4 daysThu 6/25/20Tue 6/30/203358Martel4849CONSTRUCTION - BUILDING REPAIRS51 daysWed 7/1/20Wed 9/9/2050Building Shell32.5 daysWed 7/1/20Fri 8/14/2051Steel Erection - 10 beams / 20 ends32.5 daysWed 7/1/20Fri 8/14/2052Install temp beam shoring1 wkWed 7/1/20Tue 7/7/2013,4553Steel Erection Contractor53Demo beam ends1 wkWed 7/8/20Tue 7/14/205254Steel Erection Contractor54Install new anchor bolts1 wkWed 7/15/20Tue 7/21/205355Steel Erection Contractor55Erect new steel beam ends2 wksWed 7/22/20Tue 8/4/205456Steel Erection Contractor56Install miscellaneous iron and bracing1.5 wksWed 8/5/20Fri 8/14/2055Steel Erection Contractor57Carpentry Work14.5 daysWed 7/1/20Tue 7/21/2062,64,6758Install GLB arch1 wkWed 7/1/20Tue 7/7/204759Framing Contractor59Install joists & sheathing at new roof area1.5 wksWed 7/8/20Fri 7/17/205860Framing Contractor60Repair bathroom roof2 daysFri 7/17/20Tue 7/21/205961Roofing15 daysTue 7/21/20Tue 8/11/2062Install New Roofing Systems Flashing & Trim3 wksTue 7/21/20Tue 8/11/2057Roofing Contractor63Plumbing15 daysTue 7/21/20Tue 8/11/2064Re-connect Fire Sprinkler Lines and Repair as required2 wksTue 7/21/20Tue 8/4/205765FS Contractor65Flush, test, and clean piping and fixtures1 wkTue 8/4/20Tue 8/11/206473,80FS Contractor66Electrical20 daysTue 7/21/20Tue 8/18/2067Electrical Conduit Repairs2 wksTue 7/21/20Tue 8/4/205768Electric Contractor68Install new LED fixtures1 wkTue 8/4/20Tue 8/11/20676969Install new main panel on pedestal 1 wkTue 8/11/20Tue 8/18/206871,79Electric Contractor70Paint 12.5 daysTue 8/18/20Thu 9/3/207371Paint roof understructure & bathroom exterior2.5 wksTue 8/18/20Thu 9/3/2069Painting Contractor72Final Clean-up4 daysFri 9/4/20Wed 9/9/2073Remove debris from building and do final clean-up4 daysFri 9/4/20Wed 9/9/2065,7074,92G.C. Labor Crew74Request Substantial completion date0 daysWed 9/9/20Wed 9/9/207377,84G.C. Superintendent7576SUBSTANTIAL COMPLETION & OCCUPANCY28.5 daysTue 8/11/20Fri 9/18/2077Substantial Completion - Project Milestone0 daysWed 9/9/20Wed 9/9/207478AHJ Requirements11 daysTue 8/11/20Wed 8/26/2079Perform local building agency inspection1 dayTue 8/18/20Wed 8/19/206981AHJ80Perform Fire Marshal's inspection1 dayTue 8/11/20Wed 8/12/206581Fire Marshal81Complete task list items from all inspections5 daysWed 8/19/20Wed 8/26/2079,8082All Trades82Obtain certificate of occupancy - AHJ0 daysWed 8/26/20Wed 8/26/208185,92Martel83Owner / Architect Requirements17.5 daysWed 8/26/20Fri 9/18/2084Contractor Prepared Punch List Process - to Subs7 daysThu 9/10/20Fri 9/18/2074Martel85Request Engineer's Inspection0 daysWed 8/26/20Wed 8/26/208286Martel86Engineers's Inspection2 daysWed 8/26/20Fri 8/28/208587Morrison & Maierle87Complete punch list items from Engineer's Inspection5 daysFri 8/28/20Fri 9/4/208688Martel88Engineer confirm punch list1 dayFri 9/4/20Mon 9/7/208789Morrison & Maierle89Issue final completion documents including warranties1 dayMon 9/7/20Tue 9/8/208890Martel90Issue final request for payment1 dayTue 9/8/20Wed 9/9/2089Martel91Owner Occupancy0 daysWed 9/9/20Wed 9/9/2092Owner Occupancy0 daysWed 9/9/20Wed 9/9/2082,73COBMartelSteel Erection ContractorSteel Erection ContractorSteel Erection ContractorSteel Erection ContractorSteel Erection ContractorFraming ContractorFraming ContractorRoofing ContractorFS ContractorFS ContractorElectric ContractorElectric ContractorPainting ContractorG.C. Labor Crew9/99/9AHJFire MarshalAll Trades8/26Martel8/26Morrison & MaierleMartelMorrison & MaierleMartelMartel9/99/9SONDJFMAMJJASONDHalf 1, 2020Half 2, 2020Half 1, 2021TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneProgressDeadlineProject ScheduleBogert Pavilion4/1/20Martel Construction, Inc.Page 2Bogert Pavilion10.11.201993 SECTION FOUR GMP Spread Sheet · See attached 94 Description Rate Base Bid Alternate #1 Alternate #2 Total Estimated Cost of the Work 378,983.00$ 174,035.00$ 11,446.00$ 564,464.00$ General Liability Insurance 0.89% 3,652.00$ 1,677.00$ 110.00$ 5,439.00$ Gross Receipts Tax 1.00% 4,104.00$ 1,885.00$ 124.00$ 6,113.00$ Builders Risk 0.18% 739.00$ 339.00$ 22.00$ 1,100.00$ Bond 0.82% 3,365.00$ 1,545.00$ 102.00$ 5,012.00$ Construction Fee 5.00% 19,542.00$ 8,974.00$ 590.00$ 29,106.00$ 410,385.00$ 188,455.00$ 12,394.00$ 611,234.00$ Construction Contingency 8.00% 30,319.00$ 13,923.00$ 916.00$ 45,158.00$ 440,704.00$ 202,378.00$ 13,310.00$ 656,392.00$ Grand Total Bogert Pavilion Renovation Amendment #2 Summary Martel Construction, Inc. 4.23.2020 Total 95 Description Base Bid Alternate #1 Alternate #2 Total Amendment #2 - 12.18.2019 SD 477,005.00$ 186,429.00$ N/A 663,434.00$ Amendment #2 - 3.16.2020 CD 464,740.16$ 185,293.00$ 37,875.00$ 687,908.16$ Amendment #2 - 4.23.2020 CD 440,704.00$ 202,378.00$ 13,310.00$ 656,392.00$ Bogert Pavilion Renovation Amendment #2 Budget History Martel Construction, Inc. 4.24.2020 96 Martel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - 4.24.2020 Base4/24/2020 10:09 AMLocationGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal AmountBase101-0000GENERAL REQUIREMENTS201-3150Temporary Toilet3Temporary Toilet10.00wk----5005004 Temporary Toilet50050001-7050Cleanup5Current Cleanup10.00wk2,096--200-2,2966 Cleanup2,0962002,29601-7080Trash & Rubbish Handling7Rental Dumpster w/ County Dump Fee10.00wk-2,400-2,500-4,9008 Trash & Rubbish Handling2,4002,5004,900 GENERAL REQUIREMENTS2,0962,4002,7005007,69602-0000EXISTING CONDITIONS902-2200Selective Demolition10Shore Typical Glulam Beams for Splices18.00ea6,0364,860---10,89611Shore Beams at Warming Area2.00ea1,006540---1,54612Cut Back Roofing / Sheathing - 36" Strip1,179.00sf412----41213Remove Glulam Beam Sections19.00ea1,991---1,99114Cut Existing Anchor Bolts Flush w/ Pier80.00ea168----16815Remove Wood I Joists16.00ea503----5031632' Scissor Lifts - 1 Each1.00wk*--600-60017Shoring Design1.00ls*-5,000*-5,00018 Selective Demolition10,1165,4005,00060021,11602-2250Site Demolition19Sawcut Concrete Slabs & Sidewalks45.00lf**675*-67520Remove Concrete Slabs & Sidewalks98.00sf514213-*-72721Compressor, Jackhammer, Fuel Mobilization1.00day845-140-22922 Site Demolition5972186751401,630 EXISTING CONDITIONS10,7145,6185,67574022,74703-0000CONCRETE2303-1560Dowels24Drill & Epoxy Rebar Dowels - Slab Patch31.00ea21162---27325 Dowels2116227303-1730Prepare Slab-on-Grade26Prepare Slab on Grade - Slab Patch98.00sf41--*-4127 Prepare Slab-on-Grade414103-2050Rebar Accessories28Supply Rebar Supports - Slab Patch98.00sf-5---529 Rebar Accessories5503-2100Concrete Reinforcing30Rebar - #4 @ 12" OC - Slab Patch0.08ton87104---19131 Concrete Reinforcing8710419103-3050Place Concrete Slabs32Place SOG 6" Thick - Slab Patch1.82cy76255-**33133 Place Concrete Slabs7625533103-3510Grout Base Plates34Grout Base Plates20.00ea1,677500---2,17735 Grout Base Plates1,6775002,17703-5060Broom Finish Slabs36Broom Finish Slabs - Slab Patch98.00sf--392--39237 Broom Finish Slabs39239203-5290Curing Compound38Curing Compound - Slab Patch98.00sf105---1539 Curing Compound10515 CONCRETE2,1029303923,42505-0000STEEL4005-0500Division 5 Materials41Welder, Fuel, Misc. Welding Supplies &Electrodes2.00wk*75*50030087542Mobilize & Demobilize Forklift2.00trip8410***9443Mobilize & Demobilize Scissor Lifts2.00trip16810*80*25844Mobilize & Demobilize Misc. Small Tools2.00trip84****844510K Forklift w/ Fuel5.00wk*375*4,750*5,12546Small Tools5.00wk***375*3754732' Scissor Lifts - 2 Each5.00wk***6,000*6,00048Layout - Steel Erection Scope Only10.00hr54450***59449 Division 5 Materials87952011,70530013,40405-1200Structural Steel5097 Martel ConstructionSpreadsheet ReportPage 2Bogert Pavilion Renovation - 4.24.2020 Base4/24/2020 10:09 AMLocationGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal Amount05-1200Structural SteelW21x55 Corten Steel Beam Stubs w/Baseplates, Washers, Web Stiffners & Buckets20.00ea17,402*-*-17,402511/4" x 7" Corten Steel Beam Strapping820.00lf8,918*-*-8,918521" Cross Braces32.00ea1,740*-*-1,74053Clevis Ends at Cross Braces32.00ea**-*-054Clevis Pins at Cross Braces32.00ea**-*-055Turnbuckles at Cross Braces16.00ea**-*-0563/8" Corten Connection Plates at Cross Braces32.00ea**-*-0571/4" x 6" x 8" Corten Steel Strap Splices16.00ea870*-*-870584 x 6 Continuous Tube Steel at Roof Edge442.00lf3,005*-*-3,00559Field Weld Beam Strapping / Splice Plates56.00weld3,045-**-3,04560Field Weld 4 x 6 Tube Steel to W21x55 BeamSplices20.00ea1,088-**-1,08861Supply Structural Steel, Lag Screws atStrapping, Through Bolts at Glulams, EpoxyAnchors1.00est*99,290**-99,29062 Structural Steel36,06899,290135,358 STEEL36,94799,81011,705300148,76206-0000WOOD & PLASTICS6306-0600Wood Materials64Layout - Rough Carpentry Scope Only6.00hr25230---2826510K Forklift w/ Fuel3.00wk-225-2,850-3,07566Small Tools3.00wk-*-225-2256732' Scissor Lifts - 2 Each3.00wk-*-3,600-3,60068 Wood Materials2522556,6757,18206-0900Hardware & Fasteners691/2" x 4-1/2" Lag Screws at Steel Strapping1,648.00ea-*---0703/4" x 10" Through Bolts at Typical Beam Saddles256.00ea-*---0713/4" x 6" Through Bolts at End Bay Beam Saddles64.00ea-*---072Nails, Screws, Bolts etc. - Rough CarpentryScope1.00est-750---750733/4" x 10" Epoxy Anchors80.00ea4,350*---4,35074IUS3.56/16 Face Mount Hangers - RebuildDemolished Area84.00ea293*---29375 Hardware & Fasteners4,6447505,39406-1000Rough Carpentry76Misc. Repairs to Existing Warming Hut1.00est671300---97177 Rough Carpentry67130097106-1190Backing & Blocking782 x 4 Backing at Roof Edge - Treated - By Roofer442.00lf**--792 x 4 Backing at Roof Edge End Bays - Radiused -Treated - By Roofer224.00lf**--8006-1650Wood Panel Sheathing815/8" Plywood Roof Sheathing - Roof EdgeSplice - 48" Width1,764.00sf2,6411,184---3,825825/8" Plywood Roof Sheathing - RebuildDemolished Area2,600.00sf2,2711,745---4,01583 Wood Panel Sheathing4,9122,9287,84006-1740Wood I-Joists8425' LPI56 Wood I Joists - Rebuild DemolishedArea42.00ea1,409*---1,409852x4 Web Stiffeners - Rebuild Demolished Area168.00ea352*---35286 Wood I-Joists1,7611,76106-1800GluLam Construction87New 8-3/4" x 28-1/2" Arched Glulam Beam -Rebuild Demolished Area - Install Only1.00ea1,341*---1,34188Supply Glulam Beam1.00est*24,495---24,49589Glulam Beam Hoisting - Use Forklift*est**---090 GluLam Construction1,34124,49525,836 WOOD & PLASTICS13,58028,7286,67548,98307-0000THERMAL & MOISTURE PROT.9107-5300Membrane Roofing92Patch Roofing - Roof Edge Splice983.00sf--*--093Patch Roofing - Rebuild Damaged Area2,850.00sf--*--094Add for 15 Year Warranty1.00ls--*--095Add Fall Protection Anchors10.00ea4192,200*--2,61996Membrane Roofing - Base Bid1.00ls--50,446--50,4469798 Martel ConstructionSpreadsheet ReportPage 3Bogert Pavilion Renovation - 4.24.2020 Base4/24/2020 10:09 AMLocationGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal Amount Membrane Roofing4192,20050,44653,06507-7200Roof Accessories98Reinstall Roof Vents2.00ea16810---17899 Roof Accessories16810178 THERMAL & MOISTURE PROT.5872,21050,44653,24309-0000FINISHES10009-9100Paint Finishes101Painting - Roof Edge Splice983.00sf--*--0102Painting - Rebuild Demolished Area2,850.00sf--*--0103Painting - Add to Paint Entire Roof23,585.00sf--*--0104Painting - Warming Hut1.00est--*--0105Painting Subcontract1.00ls--30,100--30,100106 Paint Finishes30,10030,100 FINISHES30,10030,10021-0000FIRE SUPPRESSION10721-1100Fire Protection Piping108Replace Fire Sprinkler Pipe that was DamagedDue to Roof Failure1.00ls--11,132--11,132109 Fire Protection Piping11,13211,132 FIRE SUPPRESSION11,13211,13226-0000ELECTRICAL11026-0500Electrical111Reinstall Light Fixtures at Collapsed Bays w/ NewWire & Conduits2.00est--*--0112New Freestanding Electrical Panel1.00est--*--0113Reinstall Light Fixtures at Collapsed Bays w/ NewWire & Conduits(2.00)est--*--0114Electrical Base Bid1.00ls--9,753--9,753115 Electrical9,7539,753 ELECTRICAL9,7539,75332-0000SITE IMPROVEMENTS11632-9000Landscaping117Repair Landscaping1.00all--2,500--2,500118 Landscaping2,5002,500 SITE IMPROVEMENTS2,5002,500Base66,025139,697109,99821,820800338,340Base -GC11901-0000GENERAL REQUIREMENTS12001-0110Supervision121Superintendent - Full Time 6/22-9/410.00wk23,380795-1,625-25,800122 Supervision23,3807951,62525,80001-0150Project Management123Project Mgmt. - On Site10.00wk5,845199-406-6,450124 Project Management5,8451994066,45001-2050Temporary Telephone125Temporary Phone10.00wk----500500126 Temporary Telephone50050001-2100Temporary Electric127Temporary Electric Service - BY OWNER0.00mo----*012801-2400Temporary Water Service129Temporary Water Service - BY OWNER0.00mo----*013001-3200Barricades & Enclosures131Temporary Fence Changes1.00ls**3,800--3,800132 Barricades & Enclosures3,8003,80001-6000Mobilize133Mobilize & Demobilize Office Trailer2.00trip33511-260-606134 Mobilize3351126060601-6400Construction Equipment135Office Trailer + Temporary Power Connection2.50mo--5001,000-1,500136 Construction Equipment5001,0001,50001-7540Allowances137Raken Daily Reporting App10.00wk----100100138Submittal Exchange per Spec1.00ls----1,8871,887139 Allowances1,9871,98701-8150Construction Permits140Building Permit - By Owner*ls----*0141 GENERAL REQUIREMENTS29,5601,0054,3003,2912,48740,64399 Martel ConstructionSpreadsheet ReportPage 4Bogert Pavilion Renovation - 4.24.2020 Base4/24/2020 10:09 AMLocationGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal AmountBase - GC2.00mo29,5601,0054,3003,2912,48740,643Estimate TotalsMartel ConstructionSpreadsheet ReportPage 4Bogert Pavilion Renovation - 4.24.2020 Base4/24/2020 10:09 AMDescriptionAmountTotalsLabor95,586Material140,701Subcontract114,298Equipment25,111Other3,287378,983378,983General Liability Insurance3,652Gross Receipts Tax4,104Builders Risk739Bond3,365Construction Fee19,542Construction Contingency31,402410,385Total410,385100 Martel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - 4.24.2020 Alternate #14/24/2020 10:13 AMLocationGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal AmountAlternate#1107-0000THERMAL & MOISTURE PROT.207-5300Membrane Roofing3Add for Complete Re-Roof1.00ls--174,035--174,0354 Membrane Roofing174,035174,035 THERMAL & MOISTURE PROT.174,035174,035Alternate #1174,035174,035Estimate TotalsMartel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - 4.24.2020 Alternate #14/24/2020 10:13 AMDescriptionAmountTotalsLaborMaterialSubcontract174,035EquipmentOther174,035174,035General Liability Insurance1,677Gross Receipts Tax1,885Builders Risk339Bond1,545Construction Fee8,974Construction Contingency14,420188,455Total188,455101 Martel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - 4.24.2020 Alternate #24/24/2020 10:14 AMLocationGroupPhaseDescriptionTakeoff QuantityLabor AmountMaterial AmountSub AmountEquip AmountOther AmountTotal AmountAlternate#2126-0000ELECTRICAL226-0500Electrical3Replace Existing Fixtures w/ New LED Fixtures- ALT218.00est--11,446--11,4464 Electrical11,44611,446 ELECTRICAL11,44611,446Alternate #211,44611,446Estimate TotalsMartel ConstructionSpreadsheet ReportPage 1Bogert Pavilion Renovation - 4.24.2020 Alternate #24/24/2020 10:14 AMDescriptionAmountTotalsLaborMaterialSubcontract11,446EquipmentOther11,44611,446General Liability Insurance110Gross Receipts Tax124Builders Risk22Bond102Construction Fee590Construction Contingency94812,394Total12,394102 SECTION FIVE Document List The Following Documents were used to prepare the GMP. · 100% CD Drawing Set 3/3/20 - Morrison Maierle o See Attached Cover Sheet · 100% Project Manual March 2020 - Morrison Maierle o See attached Table of Contents · Project Addendums o Addendum #1 – 3/20/20 o Addendum #2 – 4/3/20 o Addendum #3 – 4/16/20 103 LIBBY KALISPELL POLSON HAVRE GREAT FALLS GLASGOW MILES CITY BILLINGS LEWISTOWN HARLOWTON LIVINGSTON WHITE SULPHUR SPRINGS BOZEMAN DILLON ANACONDA HELENADEER LODGE MISSOULA HAMILTON engineers surveyors planners scientists Morrison Maierle 2880 Technology Blvd W, Bozeman, MT 59718 Phone: 406.587.0721 www.m-m.net QUALITY ASSURANCE PROJECT MANAGER OFFICE QUALITY ASSURANCE COORDINATOR PEER REVIEWER Q.A. APPROVAL DATE Q.A. PROJECT NUMBER PROJECT LOCATION PROJECT LOCATION SET NO. MORRISON-MAIERLE PROJECT NO. 0417.083 APPROVED BY: JAY FISCHER, PE PROJECT MANAGER LOCATION MAP NOT TO SCALE VICINITY MAP NOT TO SCALE PREPARED BY: CONSTRUCTION DRAWINGS FOR BOGERT PARK PAVILION RENOVATION CITY OF BOZEMAN BOZEMAN, MONTANA 3/3/2020 CONSTRUCTION DRAWINGS 3/3/20 ©This document was prepared by Morrison-Maierle, Inc. and may contain confidential or privileged information. Morrison-Maierle, Inc. retains all common law, statutory, and reserved rights including the copyright thereto. Unauthorized use of this document or changes are strictly prohibited and may be unlawful. VERIFY COLOR! THIS SHEET IS INTENDED TO BE IN COLOR. RED, GREEN AND BLUE WILL BE VISIBLE IF REPRODUCED CORRECTLY. SHEET LIST DRAWING NUMBER SHEET NAME SHEET NUMBER CURRENT REVISION REVISION DATE S001 GENERAL STRUCTURAL NOTES S100 ROOF FRAMING PLAN S300 FRAMING DETAILS S200 PAVILION SECTION FP100 FIRE PROTECTION PLAN E100 ELECTRICAL PLAN E001 ELECTRICAL NOTES & DETAILS 0 COVER 104 CITY OF BOZEMAN MARCH 2020 BOGERT PARK PAVILION RENOVATION PROJECT MANUAL TABLE OF CONTENTS CONSULTANT REPRESENTATIVES DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS GC/CM PROCUREMENT REQUIREMENTS 00 11 16 - INVITATION TO BID ADDENDUM #1 00 11 20 - INSTRUCTIONS TO BIDDERS ADDENDUM #1 00 11 30 - BID PACKAGE DESCRIPTIONS & SCHEDULE ADDENDUM #1 00 11 50 - BID FORM ADDENDUM #1 AIA A312 - PERFORMANCE AND PAYMENT BOND ADDENDUM #1 AIA A 401 - STANDARD FORM OF AGRMT BTWN CONTRACTOR SUBCONTR. ADDENDUM #1 SUPPLEMENTAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION. ADDENDUM #1 CITY OF BOZEMAN DOCUMENTS GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION – GC/CM – LATEST ED. MONTANA PREVAILING WAGE RATES FOR BUILDING CONST. SERVICES – LATEST ED. NON-COLLUSION AFFIDAVIT NON-DISCRIMINATION MISCELLANEOUS CITY OF BOZEMAN FORMS NOTICE OF AWARD NOTICE TO PROCEED ORDER TO CONTRACTOR TO SUSPEND WORK ORDER TO CONTRACTOR TO RESUME WORK CERTIFICATE OF SUBSTANTIAL COMPLETION CONTRACTORS CERTIFICATE AND RELEASE SUBCONTRACTOR RELEASE SURETY’S CONSENT TO FINAL PAYMENT DIVISION 1 - GENERAL REQUIREMENTS 01 00 60 - CONTRACTOR BONDS & CERTIFICATES OF INSURANCE 01 10 00 - SUMMARY 01 23 00 - ALTERNATES 01 25 00 - SUBSTITUTION PROCEDURES CSI 13.1A CSI SUBSTITUTION REQUEST 01 26 00 - CONTRACT MODIFICATION PROCEDURES 01 29 00 - PAYMENT PROCEDURES 01 31 00 - PROJECT MANAGEMENT AND COORDINATION 01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION 01 32 33 - PHOTOGRAPHIC DOCUMENTATION 01 33 00 - SUBMITTAL PROCEDURES AIA C106 DIGITAL DATA LICENSING AGREEMENT CSI 12.1A SUBMITTAL TRANSMITTAL 01 40 00 - QUALITY REQUIREMENTS 105 CITY OF BOZEMAN MARCH 2020 BOGERT PARK PAVILION RENOVATION 01 42 00 - REFERENCES 01 50 00 - TEMPORARY FACILITIES AND CONTROLS 01 60 00 - PRODUCT REQUIREMENTS 01 73 00 - EXECUTION 01 74 1 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 77 00 - CLOSEOUT PROCEDURES - CITY OF BOZEMAN CLOSEOUT REQUIREMENTS CSI 14.1A PUNCH LIST FORM 01 78 23 - OPERATION AND MAINTENANCE DATA 01 78 39 - PROJECT RECORD DOCUMENTS 01 79 00 - DEMONSTRATION AND TRAINING DIVISION 05 – METALS 05 12 00 - STRUCTURAL STEEL FRAMING DIVISION 6 – WOOD, PLASTICS, AND COMPOSITES 06 18 00 – GLUED LAMINATED CONSTRUCTION DIVISION 7 – THERMAL AND MOISTER PROTECTION 07 53 23 – ROOFING 07 72 00 – ROOF ACCESSORIES DIVISION 9 - FINISHES 09 91 13 – EXTERIOR PAINTING DIVISION 21 – FIRE SUPPRESSION 21 13 16 – DRY PIPE SPRINKLER SYSTEM. DIVISION 26 – ELECTRICAL 26 00 10 – GENERAL ELECTRICAL REQUIREMENTS 26 05 05 – SELECTIVE DEMOLITION OF ELECTRICAL SYSTEMS 26 05 19 – LOW – VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 26 05 26 – GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 05 29 – HANGERS AND SUPPORT FOR ELECTRICAL SYSTEMS 26 05 33 – RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 48.16 – SEISMIC CONTROL FOR ELECTRICAL SYSTEMS 26 05 53 – IDENTIFICATION FOR ELECTRICAL SYSTEM 26 27 26 – WIRING DEVICES 26 51 10 – LED LIGHTING. 106 GUARANTEED MAXIMUM PRICE AMENDMENT (GMP) NO. 2 TO AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER Pursuant to Article 4.5 of the Preconstruction Services Conditions Agreement between Owner and Construction Manager this amendment dated the 29th day of April, 2020, between City of Bozeman (“Owner”) and Martel Construction, Inc. (“Contractor”) for the Bogert Pavilion Project, hereby establishes a Guaranteed Maximum Price and Contract Time for the portion of the Project as set forth below: GUARANTEED MAXIMUM PRICE FOR BOGERT PAVILION REPAIRS The Construction Manager’s Guaranteed Maximum Price (GMP) for the Work, including the Cost of the Work and the Construction Manager’s Fee is as follows: Base Bid General Requirements $7,696 Existing Conditions $22,747 Concrete $3,425 Steel $148,762 Wood & Plastics $48,983 Thermal & Moisture Protection $53,243 Finishes $30,100 Fire Suppression $11,132 Electrical $9,753 Site Improvements $2,500 Base Bid Subtotal $338,340 General Requirements $40,643 General Liability Insurance $3,652 Gross Receipts Tax $4,104 Builders Risk $739 Bond $3,365 Construction Fee $19,542 Construction Contingency $30,319 Base Bid Total $440,704 Alternate #1 Thermal & Moisture Protection $174,035 Alternate #1 Subtotal $174,035 DocuSign Envelope ID: 6D0C2A8B-2B1C-4F9A-B315-0D649C9B6A36 107 General Liability Insurance $1,677 Gross Receipts Tax $1,885 Builders Risk $339 Bond $1,545 Construction Fee $8,974 Construction Contingency $13,923 Alternate #1 Total $202,378 Alternate #2 Electrical $11,446 Alternate #2 Subtotal $11,446 General Liability Insurance $110 Gross Receipts Tax $124 Builders Risk $22 Bond $102 Construction Fee $590 Construction Contingency $916 Alternate #2 Total $13,310 Pre-Construction Services Total $10,352 Early Work Amendment #1 Total $29,970 TOTAL GUARANTEED MAXIMUM PRICE $696,714 CONTRACT TIME The date of Substantial Completion for the Work outlined above is: September 18th, 2020 OWNER: CONTRACTOR: City of Bozeman Martel Construction, Inc. 121 N. Rouse Ave. 1203 S. Church Ave. Bozeman, MT 59715 Bozeman, MT 59715 By:__________________________ By: __________________________ Dennis M. Taylor, Interim City Manager Jason Martel, Executive Vice President DocuSign Envelope ID: 6D0C2A8B-2B1C-4F9A-B315-0D649C9B6A36 108