Loading...
HomeMy WebLinkAbout15 - Design Report - Traditions Ph 3 Oak Street Improvements - Stormwater STORMWATER MANAGEMEV)F pC it j� FF- DESIGN REPORT : ur :LOPME.N J . TRADITIONS SUBDIVISION PHASE 3 OAK STREET IMPROVEMENTS Prepared for: Rosa Construction, Inc. 125 Central Avenue, Bozeman, MT 59718 Prepared by: C&H Engineering and Surveying, Inc. 1091 Stoneridge Drive, Bozeman, MT 59718 (406) 587-1115 Project Number: 14170.1 AUGUST 2015 INTRODUCTION Oak Street improvements are proposed during construction of Traditions Subdivision Phase 3 and will connect West Oak Street from Boulder Creek Subdivision to Twin Lakes Avenue at the boundary of Flanders Creek Subdivision. The 7.89-acre Lot R1, with frontage along Oak Street, is situated in the Northeast Quarter of the Southeast Quarter of Section 4, Township 2 South, Range 5 East of P.M.M., City of Bozeman, Gallatin County, Montana. Lot Rl is a restricted use lot and zoned R4. This report considers the management of stormwater with Lot R1 in its current undeveloped state but also provides adequate detention to accommodate the anticipated buildout of the lot in sizing overflow structures and detention pond volume. A future subdivision or site plan will address stormwater management on the developed Lot R1 in more detail and additional stormwater management will be implemented if found to be necessary. C&H Engineering developed spreadsheets were used for all calculations in this report including pipe outlet capacities, gutter flow depth and detention pond sizing. Each drainage area, composite "C" value, total acreage and storm peak runoff was calculated using a C&H Engineering developed Excel spreadsheet. Data was taken from the Flanders Creek Stormwater Report and revisions dated June 2005 to model the existing storm sewer facilities in order to interface the existing system with the proposed. All excel spreadsheet printouts and other sources can be found at the end of this report. STORMWATER MANAGEMENT Design of the stormwater facilities for this project was based on the City of Bozeman Design Standards and Specifications Policy, March 2004 including Addendums 1 through 5. The future site plan for Lot R1 was incorporated into the detention pond volume as described in the detention pond section of this report. For the purposes of determining the volume for Pond 1 the Lot R1 area was assumed to have a future runoff coefficient of 0.7. In the future site plan excess runoff, which cannot be detained in Pond 1, will be retained on site or an additional detention pond will need to be designed. Pond 1 is currently shown at its maximum size on Figure D1 found at the end of this report. The inlet at the corner of Twin Lakes Avenue and Oak Street (Inlet FC-14) is proposed to be removed during Oak Street improvements. FC-14 currently is piped to a temporary retention pond located in the Oak Street right of way;this structure will be removed and Design Report-Page 2 of 5 the contributing drainage area will be graded to drain from the current location of FC-1.4 to proposed Storm Inlet IA. There is a small section of Oak Street on the far west of the proposed street (Oak West) which accounts for 4,263 square feet of Oak Street (C=0.82). This small area will be temporarily drained to Pond 1 until completion of Boulder Creek Subdivision. A temporary swale is shown on the construction plans for management of this runoff. DRAINAGE AREA 1 Drainage Area 1 consists of a portion of Oak Street to the north of Lot R1 and a portion of Twin Lakes Avenue east of Lot R1, as shown on Figure D1. Drainage Area 1 will contribute runoff to Pond 1 via Storm Inlet IA located on the south side of Oak Street at the low point in the street profile. This inlet will be piped to a proposed 48-inch manhole (Storm Inlet 2A) via a 15-inch PVC storm sewer pipe under the curb in Oak Street. From Storm Inlet 2A a 15-inch PVC pipe will connect with a new 60-inch manhole (SDMH 1) proposed to be installed at the existing 30-inch RCP pipe draining from east to west along the south side of Oak Street in the existing 15 foot stormwater easement. The existing 30-inch RCP pipe is an outlet pipe currently used for the 19,000 cubic foot existing detention pond that was installed with Flanders Creek Subdivision (existing pond). A 30-inch PVC pipe will be installed downstream from SDMH 1. This pipe will be the inlet pipe for a new detention pond (Pond 1) proposed to detain runoff from Drainage Area 1. A composite "C" runoff coefficient was calculated for Drainage Area 1 along with the post-development time of concentration. The proposed 15-inch,30-inch and 36-inch storm sewer pipes discussed above all have adequate capacity as calculated on the storm sewer pipe capacity spreadsheets. Additionally all existing and proposed gutter capacities were checked to verify adequate freeboard while flowing at the COB maximum gutter flow depth of 0.15 feet below the top of curb. As can be seen in the attached spreadsheets all gutters have adequate capacity. STORMWATER DETENTION AT POND 1 Pond 1 is proposed in the designated open space area along the west side of Lot RI. This pond will retain and release runoff from Drainage Area 1 and it has been oversized for future use following buildout of the Lot R1 site. The exact drainage area contribution to this pond from Lot R1 will be determined in the future site plan. Design water depth for the detention pond Design Report- Page 3 of 5 calculations was limited to 1.5 feet, which is the maximum allowed pond water depth in the COB stormwater design standards without safety fencing. Drainage area 1 has a total area of 1.14 acres and a composite "C"runoff coefficient of 0.82. The pre-developed runoff rate was calculated to be 0.17 ft3/sec. (See end of the report for detailed calculations). The storage volume was computed by increasing the storm duration and computing the runoff volume minus the release volume. The release rate is equal to the pre-developed runoff rate. The maximum storage required occurs at a storm duration of 85 minutes and is equal to 1,579 cubic feet. Detention Pond #1 has a volume of 10,623 cubic feet as shown on the construction drawings. This volume accounts for the area of Lot RI (7.89 acres) with a C coefficient of 0.7, the 1.14 acres from Drainage Area 1 plus the small contribution from Oak West. As shown on the spreadsheet entitled Detention Pond#1 (Oak Street, Twin Lakes and Lot R1 included) found at the end of this report the required volume of Pond 1 is 10,299 cubic feet. Therefore the pond as shown on Figure D1 will be sized to have ample volume to detain the required runoff from Oak Street, Twin Lakes Avenue, and from the completed Lot RL OUTLET STRUCTURE AND PIPING—POND 1 AND EXISTING POND An outlet structure and piping will be installed in the north end of Detention Pond#1. The outlet structure will be sized per the City of Bozeman Design Standards and will be adjusted to a weir width of 5.6 inches. Discharge to Baxter Ditch will be limited to 2.88 ft3/sec. which includes 2.71 ft3/sec., the pre-development runoff release rate of the existing pond's 5.3-inch weir, plus the pre-development runoff release rate of 0.17 ft3/sec. from Drainage Area 1. An adjustable outlet weir will be used in the outlet structure at Pond 1 in order to increase the overflow rate in the future if additional detention volume is required during development of the future site plan design. The weir notch will have a maximum width of 8-inches which will handle the pre-development runoff from Lot R1, Drainage Area 1 and the current release rate of the outlet weir on the existing pond. The outlet pipe for the new pond will be sized as a 36-inch PVC pipe with a 0.54% slope (maximum capacity = 52.72 ft3/sec.). The outlet pipe has been oversized to handle overflow drainage from Drainage Area 1, Lot R1 and the existing pond. The capacity of this pipe exceeds the required design flow rate of 35.41 ft3/sec., which includes the existing outlet structure's overflow rate, Q25 of 20.29 ft3/sec. (Flander's Creek Stormwater Design Report and revisions Design Report-Page 4 of 5 dated June 2005), plus 15.12 ft3/sec. which is the total amount of overflow from Drainage Area 1 and the anticipated maximum overflow contribution from Lot R1. The detention pond outlet pipe therefore will provide sufficient overflow capacity from the proposed detention pond to the Baxter Ditch outfall in a major storm event for the current design and the weir width can be easily adjusted to handle additional flows from Lot R1 as required. Design Report-Page 5 of 5 '_ ^-- r-� . DETENTION POND #1 (Twin Lakes and Oak Street Only) REQUIRED VOLUME 2. Calculate Area and Weighted C Factor(Post-Development) Contributing Area C Area (ft 2) C *Area ROW 0.82 49504 40593 OS/Park 0.2 0 0 Lot R1 0.7 0 0 Laurel Parkway 0.81 0 0 Durston ROW 0.68 0 0 Total 49504 40593 A =Area(acres) 1.1365 C= Weighted C Factor 0.82'I 3. Calculate Tc (Pre-Development) Tc Overland Flow Tc= 1.87(1.1-CCf)D1/2/S1/3 (Storm I S =Slope of Basin (%) 1 Return (yrs) Cf C = Rational Method Runoff Coefficient 0.2 12 to 10 11 Cf= Frequency Adjustment Factor 1.1 111 to 25 1.1 D = Length of Basin (ft) 886 :26 to 50 1.21 I51 to 100 1.251 -----------------------------+ Tc(Pre-Development) (minutes) 49 4. Calculate Rainfall Intensity(Duration =Pre-Development Tc) i =0.64x o.s5 (10-yr Storm, Fig. 1-3, COB Design Standards) x= storm duration (hrs) 0.82'i(Tc Pre-Development) i=rainfall intensity(in./hr.) 0.73' 5. Calculate Runoff Rate(Pre-Development) Q=CiA C = Rational Method Runoff Coefficient 0.2 (open land) i = rainfall intensity(in./hr.) 0.73 (calculated above) A=Area (acres) 1.14 (calculated above) Q=Runoff Rate (Pre-Development) (cfs) 0.17' 6. Calculate Required Pond Volume Total Area (acres) = 1.14+acres Weighted C = 0.82' Discharge Rate (cfs)= 0.17 cfs(Equal to Pre-Development Runoff Rate) Duration(min) Duration(hrs) Intensity Qm(cfs) Runoff Release Required 3 (in/hr) Volume Volume Storage (ft) ) 78 1.30 0.54 0.50 2354 777 1577 79 1.32 .0,54 0.50 2364 787 1577 80 1.33 0.53 0.49 2375 797 1578' 81 1.35 0.53 ' 0.49 2385 807 1578': 82 1.37 0.52 0.49 2395 817 1579 83 1.38 0.52 0.48 2405 827 1579' 84 1.40 0.51 0.48 2415 836 1579' 85 1.42 0,51 0.48 2425 846 1579 86 1.43 0.51 0.47 2435 856 1579 87 1.45 0.50 0.47 2445 866 1579' 88 1.47 0,50 0.46 2455 876 ' 1579'; 89 1.48 0.50 0.46 2465 886 1579'i 90 1.50 0.49 0.46 2474 896 1578 91 1.52 0.49 0.45 2484 906 1578 92 1.53 0.48 0.45 2494 916 1577 OUTLET STRUCTURE SLOT Q=CLH 312 QExIsTINc POND = Discharge(cfs) 2.71 QPOND 1 = Discharge (cfs) 0.17 QTOTAL AT POND 1 WEIR= Discharge (cfs) 2.88! C =Weir Coefficient 3.33;(per COB Design Standards) H = Head (ft) 1.5 L= Horizontal Length (ft) 0.47 L =Slot Width (inches) 5.6 DETENTION POND #1 (Oak Street, Twin Lakes and Lot R1 included) REQUIRED VOLUME 2. Calculate Area and Weighted C Factor(Post-Development) Contributing Area C Area (ft 2) C *Area ROW 0.82 53767 44089 OS/Park 0.2 0 0 Lot R1 0.7 343838 240687 Laurel Parkway 0.81 0 0 Durston ROW 0.68 0 0 Total 397605 284776 A =Area (acres) 9.1278 C= Weighted C Factor 0.72 3. Calculate Tc (Pre-Development) Tc Overland Flow Tc= 1.87(1.1-CCf)D1/2/Sv3 (Storm I S =Slope of Basin (%) 1 ;Return (yrs) Cf C = Rational Method Runoff Coefficient 0.2 ;2 to 10 1; Cf= Frequency Adjustment Factor 1.1 111 to 25 1.1 D = Length of Basin (ft) 886! :26 to 50 1.2i 151 to 100 1.251 Tc(Pre-Development) (minutes) 49 4. Calculate Rainfall Intensity(Duration =Pre-Development Tc) i = 0.64x'-"(10-yr Storm, Fig. 1-3, COB Design Standards) x=storm duration (hrs) 0.82i;(Tc Pre-Development) i=rainfall intensity(in.1hr.) 0.73 5. Calculate Runoff Rate(Pre-Development) Q =CiA C = Rational Method Runoff Coefficient 0.2;(open land) i= rainfall intensity(in./hr.) 0.73'(calculated above) A=Area (acres) 9.13;(calculated above) Q=Runoff Rate (Pre-Development)(cfs) 1:33 6. Calculate Required Pond Volume Total Area (acres) = 9.13 acres Weighted C = 0.72: Discharge Rate(cfs)= 1.33 cfs (Equal to Pre-Development Runoff Rate) Duration min} Duration(hrs} Intensity QI�(cfs) Runoff Release Required (in/hr) Volume Volume Storage (ft3) 58 097 0.65 4.28 14885 4639 10246 59 0.98 0.65 4.23 14974 4719 10255` 60 1.00 0.64 4,18 15063 4799 10264+ 61 1.02 0.63 4.14 15150 4879 10271' 62 1.03 0.63' 4.10 15236 4959 10277 63 1.05 0.62 4.05 15322 5039 10283: 64 1.07 0.61 4.01 15407 6119 ' 10288 65 1.08 0.61 3.97 15490 5199 10292 66 1.10 0.60 3.93 15573 5279 + 10295 67 1.12 0.60 3.89 15656 5359 10297' 68 1.13 0.59 3.86 15737 5439 10298 69 1.15 0.58 3.82 15818 5519 10299 70 1.17 0.58 3.79 15897 5599 10299 71 1.18 0.57 3.75 15977 5679 10298 72 1.20 0.57 3.72 16055 5759 1 10296' 73 1.22 0.56 3.68 16133 5839 10294 74 1.23 0.56 3.65 16210 5919 10291 75 1.25 0.55 3.62 " 16286 5999 10287' 76 1.27 0.55 3.59 16362 6079 10283' OUTLET STRUCTURE SLOT Q=CLH 312 QEXISTING POND= Discharge(cfs) 2.71 QPOND 1 = Discharge (cfs) 1.33' QTOTAL AT POND 1 WEIR= Discharge (cfs) 4.04 C =Weir Coefficient 3.33 (per COB Design Standards) H = Head (ft) 1:5 L= Horizontal Length (ft) 0.66 L =Slot Width(inches) 7.9 DETENTION POND #1 (Temp. Drainage from Oak West) REQUIRED VOLUME 2. Calculate Area and Weighted C Factor(Post-Development) Contributing Area C Area (ft 2) C *Area ROW 0.82 4263 3496 OS/Park 0.2 ! 0 0" Lot R1 0.7 0 0 Laurel Parkway 0.81 0 0 Durston ROW 0.68 0 0 Total 4263 3496 A =Area(acres) 0.0979 C= Weighted C Factor 0.82 3. Calculate T, (Pre-Development) Tc Overland Flow Tc= 1.87 (1.1-CCf)D1/2/Sv3 (Storm 1 S =Slope of Basin (%) 1 :Return (yrs) Cf C = Rational Method Runoff Coefficient 0.2 12 to 10 1 Cf= Frequency Adjustment Factor 1.1 ill to 25 1.1 D = Length of Basin (ft) 886' :26 to 50 1.21 151 to 100 1.251 ----------------------------- Tc(Pre-Development) (minutes) 49' 4. Calculate Rainfall Intensity(Duration =Pre-Development Tc) i =0.64x-'-"(10-yr Storm, Fig. 1-3, COB Design Standards) x= storm duration (hrs) 0.82 (Tc Pre-Development) i=rainfall intensity(in./hr.) 0.73 5. Calculate Runoff Rate(Pre-Development) Q =CiA C = Rational Method Runoff Coefficient 02 (open land) i = rainfall intensity(in./hr.) 0.73 (calculated above) A=Area (acres) 10.10'(calculated above) Q=Runoff Rate (Pre-Development)(cfs) 0.01 6. Calculate Required Pond Volume Total Area (acres)= 0.10 acres Weighted C = 0.82 Discharge Rate (cfs)= 0.01 cfs (Equal to Pre-Development Runoff Rate) Duration(min) Duration(hrs) Intensity Q,�(cfs) Runoff Release Required (in/hr) Volume Volume Storage (ft3) 70 1.17 0.58 0.05 195 60 135 71 1.18 0.57 ; 0.05 196 61 ! 135' 72 1.20 0.57 0.05 197 62 135 73 1.22 0.56 0.05 198 63 135 74 1.23 0.56 ', 0.04 199 63 136 75 1.25 0.55 0.04 200 64 136! 76 1.27 0.55 0.04 201 65 136 77 1.28 0.54 0.04 202 66 136 78 1.30 0.54 A4 203 67 136' 79 1.32 0.54 0.04 204 68 " 1361i 80 1.33 0.53 0.04 204 69 136 81 1.35 0.53 0.04 205 69 136 82 1.37 0.52 0.04 206 70 136' 83 1.38 0.512 0.04 207 71 136' 84 1.40 0.51 0.04 208 72 136 85 1.42 0.51 0.04 209 ( 73 136 86 1.43 0.51 0.04 210 74 136 87 1.45 0.50 0.04 211 75 136 88 1.47 0.50 0.04 211 75 136! 89 1.48 0.50 0.04 212 76 136 90 1.50 0.49 0.04 213 77 136' 91 1.52 0.49 0.04 214 78 136 92 1.53 0.48 0.04 215 79 136' 93 1.55 0.48 0.04 216 80 136 94 1.57 0.48 0.04 216 81 136': 95 1.58 0.47 0.04 217 81 136 96 1.60 0.47 0.04 218 82 136 97 1.62 0.47 0.04 219 83 136 98 1.63 0.47 0.04 220 84 135 DRAINAGE AREA OAK WEST Contributing Area C Area (ft 2) C * Area Composite ROW ROW 0.81957 4263 349 ((0.95*43)+(0.2*17))/60 OS/Park 0.2 0 0.$195652 Lots 0.35 0 , 0 Total 4263 ;3493 $l C =Weighted C Factor A =Area(acres) 0:I0 Required Gutter/Pipe Capacity (25-yr Storm) Tc Overland Flow Tc = 1.87 (1.1-CC)D1/2/S1/3 Storm S = Slope of Basin (%) 0.5 Return Cf C =Rational Method Runoff Coefficient 035 2 to 10 1 Cf=Frequency Adjustment Factor 1,1 11 to 25 1.1 D =Length of Basin (ft) 15 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes) Tc Gutter Flow Tc =L/V/60 V = (1.486/n)R211 S v2 n =Mannings Coefficient'0 0)3 R= Hydraulic Radius A/P (ft) �< 0 73 (0.15'below top of curb) S = slope (ft/ft) 0.005 L=length of gutter(ft) 88 V = mean velocity (ft/s) Tc Gutter Flow (minutes) _ ,3;69 Tc Total (Overland+Gutter) Q = CIA C =Weighted C Factor (calculated above) I = 0.78 Tc°_64(in/hr) Drainage Area#OAK WEST A = area(acres) � Qrequired (CfS) Provided Gutter Capacity (flowing at 0.15' below top of curb) Q = (1.486/n)AR"'S"' n =Mannings Coefficient 0f113' A = area (ft'`) 4 P =wetted perimeter(ft) 93' R=Hydraulic Radius A/P(ft) 0 _ S = slope (ft/ft) 0.005 Qprovided (CfS) GUTTER HAS ADEQUATE CAPACITY Drainage Area#OAK WEST DRAINAGE AREA TWIN LAKES WEST Contributing Area C Area (ft'-) C * Area Composite ROW ROW 0.81957 24594 2015 ((0.95*43)+(0.2*l7))/60 OS/Park 0.2 0 �0; 0.8195652 Lot RI 0.7 0 , 0 Total 24594 ;:'201564' C=Weighted C Factor :`,0. A=Area (acres) (J, 6� Required Gutter/Pipe Capacity (25-yr Storm) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 0.5 Return Ce C =Rational Method Runoff Coefficient {};35' 2 to 10 1 Cf=Frequency Adjustment Factor :1 11 to 25 1.1 D = Length of Basin (ft) 15 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes) _ 6n52 Tc Gutter Flow Tc =L/V/60 V= (1.486/n)R2/1 S 1 is n=Mannings Coefficient 0 013: R= Hydraulic Radius A/P(ft) 0 1 '(015' below top of curb) .. .............:. S = slope (ft/ft) 0.010 L= length of gutter(ft) 670 V = mean velocity (ft/s) Tc Gutter Flow (minutes) = :72T Tc Total (Overland+ Gutter) Q= CIA C=Weighted C Factor 0 82=(calculated above) I=0.78 Tc 0'64(in/hr) 2 4 Drainage Area#TWIN LAKES WEST A = area(acres) =0;56 Qrequired (Cfs) Provided Gutter Capacity (flowing at 0.15' below top of curb) Q= (1.486/n)AR2/1S1/2 n =Mannings Coefficient :,�' 0;�13 A = area (ft2) 14 P = wetted perimeter(ft) R = Hydraulic Radius A/P (ft) t7: 3' S = slope (ft/ft) 0.01 Qprovided (Cfs) _ = GUTTER HAS ADEQUATE CAPACITY Drainage Area#TWIN LAKES WEST DRAINAGE AREA 1 (TWIN LAKES WEST AND OAK STREET) Contributing Area C Area(ft 2) C * Area Composite ROW ROW 0.81957 45504 37293 ((0.95*43)+(0.2*17))/60 OS/Park 0.2 0 °Q, 0.8195652 Lot RI 0.7 0 (? Total5504 , 3729 :5 C =Weighted C Factor 82' A =Area (acres) a104 Required Gutter/Pipe Capacity (25-_yr Storm) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/51/3 Storm S = Slope of Basin (%) 0.5 Return Cr C =Rational Method Runoff Coefficient 0.,35 2 to 10 1 Cf=Frequency Adjustment Factor 11 to 25 1.1 D =Length of Basin (ft) 15 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes) -52: Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2i3 S 1/2 n=Mannings Coefficient (JGl3 R=Hydraulic Radius A/P (ft) 0 1'3'(0.15' below top of curb) S = slope (ft/ft) 0.005 L=length of gutter(ft) 968 V = mean velocity (ft/s) Tc Gutter Flow (minutes) Tc Total (Overland +Gutter) Q = CIA C =Weighted C Factor 0 82 (calculated above) 0 I= 0.78 Tc '64(in/hr) A = area (acres) 04= Qrequired (CfS) _ 1: r Provided Gutter Capacity (flowing at 0.15' below top of curb) Q= (1.486/n)AR2/1S1/2 n =Mannings Coefficient 0.013` A area (ft) 1,24: P= wetted perimeter(ft) :23 R = Hydraulic Radius A/P (ft) 013 S = slope (ft/ft) 0.01 Qprovided (CfS) GUTTER HAS ADEQUATE CAPACITY DRAINAGE AREA LOT RI Contributing Area C Area(fe) C * Area Composite ROW ROW 0.81957 0 Q ((0.95*43)+(0.2*17))/60 OS/Park 0.2 0 �`: <0 0.8195652 Lot R1 0.7 346141 42299 Total 346:141 242299 C =Weighted C Factor A =Area (acres) � ;75 Required Gutter/Pipe Capacity (25-yr Storm) Tc Overland Flow Tc = 1.87 (1.1-CCr)D1/2/S1/3 Storm S = Slope of Basin (%) 0.5 Return Ce C =Rational Method Runoff Coefficient :0,35 2 to 10 1 Cf=Frequency Adjustment Factor l;'1 11 to 25 1.1 D =Length of Basin (ft) 15 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes) Tc Gutter Flow Tc =L/V/60 V = (1.486/n)R2r3 S vz n =Mannings Coefficient R= Hydraulic Radius AlP(ft) 013�(0.15'below top of curb) S = slope (ft/ft) 0.010 L=length of gutter(ft) 670 V = mean velocity (ft/s) .00; Tc Gutter Flow (minutes) Tc Total (Overland +Gutter) Q=CIA C=Weighted C Factor 0 7<,0 (calculated above) I=0.78 Tc 0�64(in/hr) Drainage Area#LOT R1 A = area (acres) - 79 Qrequired (cfs) = 1344 Provided Gutter Capacity (flowing at 0.15' below top of curb) Q = (1.486/n)AR113S Ill n =Mannings Coefficient A = area (ft') 124 P= wetted perimeter(ft) 2 � R=Hydraulic Radius AT (ft) S = slope (ft/ft) 0.01 Qprovided (cfs) = 3.72' CAPACITY PROBLEM Drainage Area#LOT R1 R"' =0.2623 ft S = 0.0060 ft/ft S 112=0.0775 ft/ft Q= (1.486/0.013)(1.24)(0.2623)(0.0775)=2.88 cfs. 2.81 cfs < 2.86 cfs — Gutter capacity is adequate DRAINAGE AREA#2 Drainage Area#2 consists of a total of 490,865 ft'-, with 79,295 ft'-of that being right of way, 263,990 ft2 of park land, and 147,580 ft2 of medium density lots. Drainage area#2 will be divided into four subareas, three for each area that contributes to a catch basin that will be utilized, plus the portion of the park that will drain into the detention pond. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to the catch basin. The time of concentration for sub-area#24 is calculated below: Time of Concentration Overland flow(115 ft @ 1.00%, C=0.35) = 14.3 min. Gutter flow(830 ft @ 1.00% avg. slope on Rosa Way) V= (1.486/n)R2i3S1i2 (n=0.013,A=1.24 ft, P=9.23, R2/3=0.2623, S1/2=0.1000) V= 3.00ft/s T= 830 ft/3.00 ft/s/60s/min =4.6 min Total Time of Concentration = 18.9 minutes (0.32 hours) For a 25-year storm event Its =0.78X-.64= 0.78(0.32)--64= 1.62 in/hr Q25 Lots =CIA =0.35(1.62 in/hr)(1.7553 acres) = 1.00 cfs Q25 r/w =CIA = 0.70(1.62 in/hr)(0.6123 acres) =0.69 cfs Q25 Total = (1.00+0.69) = 1.69 cfs =Total flow rate entering catch basin#4 The time of concentration for sub-area#2-2 is calculated below: Time of Concentration Overland flow(110 ft @ 1.00%, C=0.35) = 14.0 min. Gutter flow(830 ft @ 1.0% avg. slope on Rosa Way) V= (1.486/n)R2/1S1/1 (n=0.013, A=1.24 ft, P=9.23, Rv3=0.2623, S"2=0.1000) V= 3.00 ft/s T= 830 ft/3.00 ft/s/60s/min =4.6 min Total Time of Concentration = 18.6 minutes(0.31 hours) For a 25-year storm event Its = 0.78X-.64=0.78(0.31)--64= 1.65 in/hr Q25 Lots =CIA = 0.35(1.65 in/hr)(1.656 acres) =0.96 cfs Q25 r/w = CIA =0.70(1.65 in/hr)(0.9431 acres) = 1.09 cfs Q25 Total = (0.96+1.09) = 2.05 cfs =Total flow rate entering catch basin#5 The time of concentration for sub-area#2-3 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) = 3.2 min. Gutter flow(150 ft @ 0.60% avg. slope on Annie Street) V= (1.486/n)R2/3S1/2 (n=0.013, A=1.24 ft, P=9.23, R'-/3=0.2623, S 112=0.07746) V= 2.32 ft/s T= 150 ft/2.32 ft/s/60s/min = 1.1 min Total Time of Concentration =4.3 minutes (0.09 hours) For a 25-year storm event I25 = 0.78X-.64= 0.78(0.07)-.64=4.21 in/hr Q25 r/w =CIA = 0.70(4.21 in/hr)(0.2649 acres) =0.78 cfs Q25 Total= 0.78 cfs=Total flow rate entering catch basin#6 Q25 Total for Storm Sewer#2 = (1.69+2.05+0.78)=4.52 cfs DRAINAGE AREA#3 Drainage Area#3 consists of a total of 421,020 ft2, with 85,620 ft2 of that being right of way, 151,785 ft2 of park land, and 183,615 ft2 of medium density lots. Drainage area#3 will be divided into three subareas, one for each catch basin that will be utilized. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to the catch basin. The time of concentration for sub-area#3-1 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) = 3.2 min. Gutter flow(115 ft @ 0.60% avg. slope on Sherwood Way) V= (1.486/n)R2/35112 (n=0.013, A=1.24 ft, P=9.23, R213=0.2623, S 112=0.07746) V= 2.32 ft/s T= 115 ft/2.32 ft/s/60s/min =0.8 min Total Time of Concentration =4.0 minutes(0.07 hours) For a 25-year storm event I25 =0.78X-.fi4=0.78(0.07)-.64=4.30 in/hr Q25 r/w =CIA =0.70(4.30 in/hr)(0.1625 acres) = 0.49 cfs Q25 Total =0.49 cfs =Total flow rate entering catch basin#7 & 8 Q25 Total for Storm Sewer#3 =0.49 cfs The time of concentration for sub-area#3-2 is calculated below: Time of Concentration Overland flow(I15 ft @ 1.0%, C=0.35) = 14.3 min. Gutter flow(320 ft @ 1.10% avg. slope on Rosa Way) V= (1.486/n)R2i3S1i2 (n=0.013, A=1.24 ft, P=9.23, R213=0.2623, 5112=0.1049) V= 3.14 ft/s T= 320 ft/3.14 ft/s/60s/min = 1.7 min Gutter flow(200 ft @ 0.60% avg. slope on Sherwood Way) V= (1.486/n)R2/3S1/2 (n=0.013,A=1.24 ft, P=9.23,R2/3=0.2623, S1/2=0.0775) V= 2.32 ft/s T= 200 ft/2.32 ft/s/60s/min = 1.4 min Total Time of Concentration = 17.4 minutes (0.29 hours) For a 25-year storm event I25 =0.78X-.64=0.78(0.29)--64= 1.72 in/hr Q25 Lots = CIA =0.35(1.72 in/hr)(0.7118 acres) =0.43 cfs Q25 r/w = CIA =0.70(1.72 in/hr)(0.7375 acres) =0.89 cfs Q25 Total = (0.43+0.89) = 1.32 cfs=Total flow rate entering catch basin#9 The time of concentration for sub-area#3-3 is calculated below: Time of Concentration Overland flow(145 ft @ 1.0%, C=0.35) = 16.1 min. Gutter flow(620 ft @ 0.80% avg. slope on Parkview Avenue) V= (1.486/n)R2/3S112 (n=0.013, A=1.24 ft, P=9.23, R"3=0.2623, S'/2=0.0894) V= 2.68 ft/s T= 620 ft/2.68 ft/s/60s/min = 3.9 min Gutter flow(270 ft @ 0.60% avg. slope on Parkview Avenue) V= (1.486/n)R2i3S112 (n=0.013, A=1.24 ft, P=9.23, R2i3=0.2623, S112=0.0775) V=2.32 ft/s T= 270 ft/2.32 ft/s/60s/min = 1.9 min Total Time of Concentration =21.9 minutes (0.37 hours) For a 25-year storm event 125 = 0.78X-�64= 0.78(0.37)".64= 1.47 in/hr Q25 Lots =CIA = 0.35(1.47 in/hr)(3.5035 acres) = 1.80 cfs Q25 r/w =CIA= 0.70(1.47 in/hr)(1.0655 acres) = 1.10 cfs Q25 Total = (1.80+1.10) =2.90 cfs =Total flow rate entering catch basin#10 Q25 Total for Storm Sewer#3 = (1.32+2.90) =4.22 cfs DRAINAGE AREA#4 Drainage Area#4 consists of a total of 474,050 ft2, with 143,825 ft2 of that being right of way, 40,660 ft'- of park land, and 289,565 ft2 of high density lots. Drainage area#4 will be divided into three subareas, one for each catch basin that will be utilized. The time of concentration for each sub-area needs to be calculated to determine the intensity of storm that will contribute to the catch basin. The time of concentration for sub-area#4-1 is calculated below: Time of Concentration Overland flow(13.5 ft @ 2.0%, C=0.46) = 3.2 min. Gutter flow(625 ft @ 1.20% avg. slope on Rosa Way) V= (1.486/n)R2/3S'/2 (n=0.013, A=1.24 ft, P=9.23, R213=0.2623, S'12=0.1095) V= 3.28 ft/s T= 625 ft/3.28 ft/s/60s/min = 3.2 min Total Time of Concentration = 6.4 minutes(0.11 hours) For a 25-year storm event 125 = 0.78X-.64=0.78(0.11),64 = 3.20 in/hr Q25 r/w = CIA =0.70(3.20 in/hr)(0.5342 acres) = 1.20 cfs Q25 Total = 1.20 cfs =Total flow rate entering catch basin#11 The time of concentration for sub-area#4-2 is calculated below: Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.8 min. Gutter flow(262.5 ft @ 0.60% avg. slope on A Street) V= (1.486/n)R2/3S'/2 (n=0.013,A=1.24 ft, P=9.23, R'-/3=0.2623, S'/'-=0.0775) V= 2.32 ft/s T= 262.5 ft/2.32 ft/s/60s/min = 1.89 min Total Time of Concentration = 15.7 minutes (0.26 hours) For a 25-year storm event 125 = 0.78X-.64=0.78(0.26)-.64 = 1.85 in/hr Q25 Lots = CIA =0.60(1.85 in/hr)(1.4415 acres) = 1.60 cfs Q25 r/w = CIA =0.70(1.85 in/hr)(0.47 acres) = 0.61 cfs Q25 Total = (1.60 +0.61) = 2.21 cfs =Total flow rate entering catch basin#15 Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.8 min. Gutter flow(262.5 ft @ 0.60% avg. slope on A Street) V= (1.486/n)R2/3S112 (n=0.013, A=1.24 ft, P=9.23, R'-/3=0.2623, S'/2=0.0775) V= 2.32 ft/s T=262.5 ft/2.32 ft/s/60s/min = 1.89 min Total Time of Concentration = 15.7 minutes (0.26 hours) For a 25-year storm event 125 =0.78X-.64=0.78(0.26)-.64 = 1.85 in/hr Q25 Lots = CIA=0.60(1.85 in/hr)(1.2609 acres) = 1.40 cfs Q25 r/w = CIA =0.70(1.85 in/hr)(0.47 acres)= 0.61 cfs Q25 Total = (1.40 + 0.61) =2.01 cfs =Total flow rate entering catch basin#12 Q25 Total for Storm Manhole#2= (2.21 + 2.01) =4.22 cfs The time of concentration for sub-area#4-3 is calculated below: Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.9 min. Gutter flow(300 ft @ 1.20% avg. slope on Rosa Way) V= (1.486/n)R"'S'/2 (n=0.013, A=1.24 ft, P=9.23, RZis=0.2623, S'12=0.1095) V= 3.28 ft/s T= 300 ft/3.28 ft/s/60s/min = 1.5 min Total Time of Concentration = 15.4 minutes (0.26 hours) For a 25-year storm event 125 =0.78X-.64= 0.78(0.26)-.64= 1.85 in/hr Q25 Lots =CIA= 0.60(1.85 in/hr)(1.9050 acres)=2.11 cfs Q25 r/w =CIA =0.70(1.85 in/hr)(0.6319 acres) = 0.82 cfs Q25 Total = (2.11+0.82) = 2.93 cfs =Total flow rate entering catch basin#13 The time of concentration for sub-area#44 is calculated below: Time of Concentration Overland flow(280 ft @ 1.0%, C=0.60) = 13.9 min. Gutter flow(300 ft @ 1.60% avg. slope on Rosa Way) V= (1.486/n)R2/3S1/2 (n=0.013,A=1.24 ft, P=9.23, R'-/3=0.2623, S'12=0.1265) V= 3.79 ft/s T= 300 ft/3.79 ft/s/60s/min = 1.3 min Total Time of Concentration = 15.2 minutes (0.25 hours) For a 25-year storm event 125 = 0.78X-.64=0.78(0.25)-.64 = 1.89 in/hr Q25 Lots =CIA = 0.60(1.89 in/hr)(1.7423 acres) = 198 cfs Q25 r/w =CIA =0.70(1.89 in/hr)(0.8160 acres) = 1.08 cfs Q25 Total= (1.98+1.08) = 3.06 cfs =Total flow rate entering catch basin#14 Q25 Total for Storm Sewer#4= (1.20+4.42+2.93+3.06) = 11.61 cfs Drainage Area#1 15" PVC from Catch Basin #1 to Catch Basin#2 This pipe carries the storm water from drainage sub-area#1-1. As previously calculated we should anticipate a flowrate of 1.02 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.40 feet with a velocity of 3.00 ft/sec. 15" PVC from Catch Basin#2 to Catch Basin#3 This pipe carries the storm water from drainage sub-areas 1-1 & 1-2. As previously calculated we should anticipate a flowrate of(1.02 + 2.81) = 3.83 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.88 feet with a velocity of 4.17 ft/sec. 15" PVC from Catch Basin#3 to Pond #1 This pipe carries the storm water from drainage sub-areas 1-1, 1-2 & 1-3. As previously calculated we should anticipate a flowrate of(1.02+ 2.81+0.93) =4.76 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 1.08 feet with a velocity of 4.22 ft/sec. Detention Pond#1 The total area served by Detention Pond#1 is 6.11 acres with a weighted C-factor of 0.464 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow (acceptable release rate) is 1.07 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.07 cfs. The required storage for Detention Pond#1 is 3,215 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#1 will be 2.09 inches in width. These calculations are included with the calculations for sizing the pond. Drainage Area#2 15" PVC from Catch Basin#4 to Catch Basin#5 This pipe carries the storm water from drainage sub-area 2-1. As previously calculated we should anticipate a flowrate of 1.69 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.53 feet with a velocity of 3.44 ft/sec. 15" PVC from Catch Basin#6 to Catch Basin#5 This pipe carries the storm water from drainage sub-area 2-3. As previously calculated we should anticipate a flowrate of 0.78 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.75% slope. The 15-inch pipe will flow at a depth of 0.32 feet with a velocity of 3.21 ft/sec. 15" PVC from Catch Basin#5 to Storm MH#1 to Detention Pond#2 This pipe carries the storm water from drainage sub-area 2-1, 2-2, & 2-3. As previously calculated we should anticipate a flowrate of(1.69+0.78+2.05) =4.52 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 1.01 feet with a velocity of 4.24 ft/sec. Detention Pond#2 The total area served by Detention Pond#2 is 11.270 acres with a weighted C-factor of 0.326 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow (acceptable release rate) is 1.801 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.801 cfs. The required storage for Detention Pond#2 is 3,610 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#2 will be 3.53 inches in width. These calculations are included with the calculations for sizing the pond. Drainage Area#3 15" PVC from Catch Basin#7-8 to Pond#3 This pipe carries the storm water from drainage sub-area 3-1. As previously calculated we should anticipate a flowrate of 0.49 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 1.00% slope. The 15-inch pipe will flow at a depth of 0.23 feet with a velocity of 3.10 ft/sec. Detention Pond#3 The total area served by Detention Pond#3 is 2.23 acres with a weighted C-factor of 0.367 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow (acceptable release rate) is 0.367 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 0.367 cfs. The required storage for Detention Pond#3 is 525 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#3 will be .72 inches in width. These calculations are included with the calculations for sizing the pond. 15" PVC from Catch Basin#10 to Catch Basin#9 This pipe carries the storm water from drainage sub-area 3-3. As previously calculated we should anticipate a flowrate of 2.90 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.72 feet with a velocity of 3.94 ft/sec. 15" PVC from Catch Basin#9 to Pond#4 This pipe carries the storm water from drainage sub-area 3-2 & 3-3. As previously calculated we should anticipate a flowrate of(2.90+1.32) =4.22 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.95 feet with a velocity of 4.22 ft/sec. Detention Pond #4 The total area served by Detention Pond#4 is 7.440 acres with a weighted C-factor of 0.3.96 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow (acceptable release rate) is 1.11 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.11 cfs. The required storage for Detention Pond#4 is 3,340 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#4 will be 2.18 inches in width. These calculations are included with the calculations for sizing the pond. Drainage Area#4 15" PVC from Catch Basin#14 to Catch Basin#13 This pipe carries the storm water from drainage sub-area 4-4. As previously calculated we should anticipate a flowrate of 3.06 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.75 feet with a velocity of 3.99 ft/sec. 15" PVC from Catch Basin#12 to Storm MH#2 This pipe carries the storm water from drainage sub-area 4-2. As previously calculated we should anticipate a flowrate of 2.21 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.61 feet with a velocity of 3.69 ft/sec. 15" PVC from Catch Basin#15 to Storm MH#2 This pipe carries the storm water from drainage sub-area 4-2. As previously calculated we should anticipate a flowrate of 2.01 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 0.58 feet with a velocity of 3.60 ft/sec. 15" PVC from Storm MH#2 to Catch Basin#13 This pipe carries the storm water from drainage sub-area 4-2. As previously calculated we should anticipate a flowrate of 4.22 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.50% slope. The 15-inch pipe will flow at a depth of 1.39 feet with a velocity of 4.23 ft/sec. 18" PVC from Catch Basin#13 to Catch Basin #11 This pipe carries the storm water from drainage sub-area 4-2, 4-3, &4-4. As previously calculated we should anticipate a flowrate of(4.22+2.93+3.06) = 10.21 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 18" PVC pipe at 1.00% slope. The 18-inch pipe will flow at a depth of 1.20 feet with a velocity of 6.77 ft/sec. 18" PVC from Catch Basin#11 to Detention Pond #5 This pipe carries the storm water from drainage sub-area 4-1, 4-2, 4-3, &4-4. As previously calculated we should anticipate a flowrate of(1.20+4.22+2.93+3.06) = 11.41 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 18" PVC pipe at 1.50% slope. The 18-inch pipe will flow at a depth of 1.10 feet with a velocity of 8.22 ft/sec. Detention Pond#5 The total area served by Detention Pond#5 is 10.88 acres with a weighted C-factor of 0.596 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow (acceptable release rate) is 1.61 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 1.61 cfs. The required storage for Detention Pond#5 is 9,200 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#5 will be 3.16 inches in width. These calculations are included with the calculations for sizing the pond. LFwt l of i . , i - i: -J _... ; cy m; ,.:,o. :;b," -,b,. 'b'-. -.b',;. gip„ 'ao°_ ,b.o; �,;` .•g_a » Wit'" - ,.,&� , �y r � r- w t 0.40e`00 c r 6 Ti I * ++ wl'.. ON ubs10004 _Vt 101 ♦ ¢ Im'vIo �'m�co�.o a'm;'cylo�w a�IoI (..� ¢ 'mLLI`w Bt 101 {..... d r *�X 'r a� t•... FRS o Io�olo o�o'o `0 0 0`.o�J)o. ,_�' r Ot lol bs000's �a1101 J94 "- az1' B 101 3 t 1101 o j o 0 J a _ - I 85 1 `.,\.•r V41 l .g"Lpl� 8Z-01 oZ 01 ;' i i Y=` V4 1 ,3Z 101- _ J J �0 r ' �. S "101 00 8 1 ' t r-or mi t3soa1R�'-" & 1 Of 101oil w � 1 m'l ✓ �,,w,rr�" 4,, '-SC E -1 day r �C mC C Y t � _�-..._ rz00'i -- _ - t '� �G� ��� � � �g �,, r,"r wp a� _ . _ �.. ^ y __ ~off }f-ST �3[ �� � �.. - ao � � — K %' J o 0Z��1 t ' a m l o,, "`^./ - '� co —X^% X�X % xzx`X x _x S---FN UAW ti 3Z< < g o o w 3daiae000M— o I oZ �0`IR ¶II ( UWi a? n 4CDo I ro� IIln DRAINAGE PLAN �+ scup:V-zoo z Scale In Feet 200 0 200 w ak yfnpa 60 0 60 Scale In Meters 4770 June 22, 2006 City of Bozeman Engineering Dept. Attn: Sue Stodola,P.E. 20 E. Olive Street P.O. Box 1230 Bozeman, MT 59771-1230 RE: Flanders Creek Subdivision, Storm Water Design Report Revisions (05189) Dear Sue, Please find the enclosed revisions for the storm water design report for the above referenced project. These revisions are in response to a letter from you dated February 8, 2006. A brief narrative of the revisions and additional information requested are as follows: 1. Upon further review of the drainage calculations, inconsistencies were found in the calculations for the overland flow distance and time of concentration. By correcting the runoff coefficient "C" and the overland flow distance, the gutter capacity was found to be below the maximum allowed. Therefore additional outlets are not needed. Calculations are included to show this. 2. a. The 24" PVC from Catch Basin #9 to Detention Pond #3 was installed as a 24" diameter pipe, which is larger than the previously approved size, but more than adequate to handle the storm water load. b. The 15" PVC from Catch Basin #10 to Detention Pond #3 is now consistent at a 0.5% slope on both the design report and the plans, with calculations included. C. Calculations are included for the 15" PVC pipe running from Catch Basin #10 to Detention Pond#3 at a 6.01% slope which matches the plans. 3. Detention Pond #1 is now labeled as 2000cf on plan Sheet C1.0 to match the design report. The weir that was installed in the outlet control structure was 18" H x 1.95" W. The correct weir for this outlet control structure is 18"H x 1.29"W. The plan sheet is now correctly labeled to match the design report. The weir dimensions will be corrected to the size indicated. 4. The calculations for Detention Pond #2 which is now a Retention Pond are included. Sheet C 1.0 is still labeled Retention Pond. 5. The weir for Detention Pond#3 was installed at 18" H x 9.77" W. In the design report, the height dimension was called out as 12", not 18". The correct width for an 18" weir is 5.31". This is now correctly labeled in the plans, with the calculations attached. A new weir will be ordered and installed in the outlet structure. 6. Sheets C1.0, C4.10 and C4.11 are now labeled with a 30" sewer instead of 36" sewer. The storm easement was adjusted to accommodate the 30" storm sewer line. 7. On sheet C1.0 the legend now includes proposed Storm Sewer Main and proposed Storm Sewer Manhole. The drawing is also to scale. 8. On sheet C4.11 it is now clearly labeled as a 60" diameter Storm Sewer Manhole. This summarizes the extent of the modifications from the previous plan and design report submittal. If any other changes occur, we will notify you immediately. Please review this material for your approval and contact us if any additional information is needed. Sincerely, Jon Jupka,E.I. Enc. GAc&h\05\05189\0ffice\05189 Stodola storm revisions 061906.wpd Storm Sewer revisions: The following calculations are included for the revisions to the outlet pipe from Pond #3 to Baxter Ditch. The time of concentration for sub-area#3-1 is calculated below: Time of Concentration Overland flow(140 ft @ 1.0%, C=0.35) = 15.82 min. Gutter flow(580 ft @ 1.10% avg. slope on Cottonwood Road) V= (1.486/n)R213SI/I (n=0.013,A=1.24 ft, P=9.23, R2/3=0.2623, S"2=0.1049) V= 3.14 ft/s T= 580 ft/3.14 ft/s/60s/min = 3.1 min Gutter flow(260 ft @ 0.60% avg. slope on Sherwood Way) V= (1.486/n)R21351/2 (n=0.013, A=1.24 ft, P=9.23, R'-/3=0.2623, S1/'-=0.0775) V= 2.32 ft/s T= 260 ft/2.32 ft/s/60s/min = 1.9 min Total Time of Concentration = 20.82 minutes(0.347 hours) For a 25-year storm event Its = 0.78X--64= 0.78(0.347)-.64 = 1.53 in/hr Q25 Medium Density Lots =CIA =0.35(1.53 in/hr)(3.4023 acres) = 1.83 cfs Q25 r/w =CIA= 0.70(1.53 in/hr)(1.6478 acres) = 1.76 cfs Q25 Total = (1.83+1.76) = 3.59 cfs =Total flow rate entering catch basin#6 The time of concentration for sub-area#3-2 is calculated below: Time of Concentration Overland flow(135 ft @ 1.0%, C=0.35) = 15.36 min. Gutter flow(585 ft @ 0.85% avg. slope on Flanders Creek Avenue) V= (1.486/n)R21IS112 (n=0.013, A=1.24 ft, P=9.23, RZi3=0.2623, S1i2=0.0922) V= 2.76 ft/s T= 585 ft/2.76 ft/s/60s/min =3.5 min Gutter flow(245 ft @ 0.60% avg. slope on Sherwood Way) V= (1.486/n)R2/3S1i2 (n=0.013, A=1.24 ft, P=9.23, R2/3=0.2623, S1i2=0.0775) V= 2.32 ft/s T= 245 ft/2.32 ft/s/60s/min = 1.8 min Total Time of Concentration = 20.84 minutes (0.347 hours) For a 25-year storm event 125 =0.78X-.64=0.78(0.347)-.64 = 1.53 in/hr Q25 Medium Density Lots = CIA=0.35(1.53 in/hr)(3.2849 acres) = 1.76 cfs Q25 r/w =CIA =0.70(1.53 in/hr)(1.2770 acres) = 1.37 cfs Q25 Total = (1.76+1.37) = 3.13 cfs =Total flow rate entering catch basin#7 The time of concentration for sub-area#3-3 is calculated below: Time of Concentration Overland Flow (140 ft @ 1.0%, C=0.60) = 9.7 min. Gutter Flow (143.5 ft @ 0.75% avg. slope on Twin Lakes Drive) V= (1.486/n)RZi3Sii2 (n=0.013, A=1.24 ft, P=9.23, R213=0.2623, S"2=0.08660) V= 2.60 ft/s T= 143.5 ft/2.60 ft/s/60 s/min =0.92 min. Total Time of Concentration = 10.62 minutes (0.177 hours) For a 25-year storm event Its = 0.78X-.64= 0.78(0.177)-.64= 2.36 in/hr Q25 High Density Lots = CIA =0.60(2.36 in/hr)(0.8744 acres) = 1.24 cfs Q25 r/w = CIA =0.70(2.36 in/hr)(0.20 acres)= 0.33 cfs Q25 Total= (1.24+0.33) = 1.57 cfs =Total flow rate entering catch basin#8 Time of Concentration Overland Flow (140 ft @ 1.0%, C=0.60) = 9.7 min. Gutter Flow (218.42 ft @ 0.75% avg. slope on Twin Lakes Drive) V= (1.486/n)R2/3S1/2 (n=0.013, A=1.24 ft, P=9.23, R2/3=0.2623, 5112=0.08660) V= 2.60 ft/s T= 218.42 ft/2.60 ft/s/60 s/min = 1.40 min. Total Time of Concentration = 11.1 minutes (0.185 hours) For a 25-year storm event Its =0.78X-.64= 0.78(0.185),64 =2.30 in/hr Q25 High Density Lots =CIA =0.60(2.30 in/hr)(1.1937 acres) = 1.65 cfs Q25 r/w =CIA=0.70(2.30 in/hr)(0.30 acres) = 0.48 cfs Q25 Total = (1.65 +0.48) = 2.13 cfs =Total flow rate entering catch basin#9 The capacity of the curb and gutter, at a 0.75% slope, with a depth of water 0.15'below the top of curb is calculated as follows: Q=(1.486/n)AR2/35112 n = 0.013 for Concrete A= 1.24 ft'- P=9.23 ft R =A/P= 1.24/9.23 =0.1343 ft R213 =0.2623 ft S =0.0075 ft/ft S112=0.08660 ft/ft Q= (1.486/0.013)(1.24)(0.2623)(0.08660)= 3.21 cfs. 1.57 cfs < 2.13 cfs < 3.21 cfs - Gutter capacity is adequate Q25 Total for Storm Sewer#3 = (3.58+3.13+1.57+2.13) =10.41 cfs The time of concentration for sub-area#34 is calculated below: Time of Concentration Overland flow(140 ft @ 1.0%,C=0.60) =9.7 min. Gutter flow(340 ft @ 0.75% avg. slope on Twin Lakes Drive) V= (1.486/n)R2/3S1/2 (n=0.013,A=1.24 ft, P=9.23, R2/3=0.2623, 5112=0.08660) V= 2.60 ft/s T= 340 ft/3.67 ft/s/60s/min =2.2 min Gutter flow(260 ft @ 0.87% avg. slope on A Street) V= (1.486/n)R2/3S1J2 (n=0.013, A=1.24 ft, P=9.23, R213=0.2623, 51/2=0.0933) V= 2.78 ft/s T=260 ft/2.78 ft/s/60s/min = 1.6 min Gutter flow(350 ft @ 1.5% avg. slope on Parkview Avenue) V= (1.486/n)R213S1/2 (n=0.013, A=1.24 ft, P=9.23, RZ/3=0.2623, S1/2=0.1225) V= 3.67 ft/s T= 350 ft/3.28 ft/s/60s/min = 1.6 min Total Time of Concentration = 15.1 minutes (0.25 hours) For a 25-year storm event Its =0.78X-.64= 0.78(0.25)-.64= 1.89 in/hr Q25 High Density Lots =CIA =0.60(1.89 in/hr)(2.008 acres) = 2.27 cfs Q25 r/w =CIA=0.70(1.89 in/hr)(1.5327 acres) = 2.03 cfs Q25 Total = (2.27+2.03) =4.30 cfs =Flow rate entering catch basin#10 Time of Concentration (Oak Street) Gutter flow(600 ft @ 0.5% avg. slope on Oak Street) V= (1.486/n)Rv3S1/2 (n=0.013, A=1.24 ft, P=9.23, R2-/1=0.2623, S1/2=0.07071) V=2.63 ft/s T= 600 ft/2.63 ft/s/60s/min =4.72 min Total Time of Concentration =4.72 minutes (0.079 hours) For a 25-year storm event I25 = 0.78X-.64=0.78(0.079)".64= 3.95 in/hr Q25 r/w =CIA =0.70(3.95 in/hr)(0.8276 acres) = 2.29 cfs Q25 Total = 2.29 cfs = Flow rate entering catch basin#10 Q25 Total for Storm Sewer#4=4.30 cfs+ 2.29 cfs = 6.59 cfs The capacity of the curb and gutter, at a 1.5% slope for Parkview Avenue, with a depth of water 0.15'below the top of curb is calculated as follows: Q=(1.486/n)AR2/3S1/2 n =0.013 for Concrete A= 1.24 ft'- P= 9.23 ft R= A/P= 1.24/9.23 =0.1343 ft R2/1 =0.2623 ft S = 0.015 ft/ft S1/2=0.1225 ft/ft Q = (1.486/0.013)(1.24)(0.2623)(0.1225)=4.55 cfs. 4.31 cfs < 4.55 cfs - Gutter capacity on Parkview Avenue is adequate The capacity of the curb and gutter, at a 0.5% slope for Oak Street, with a depth of water 0.15' below the top of curb is calculated as follows: Q= (1.486/n)AR213S1/2 n =0.013 for Concrete A= 1.24 ft2 P= 9.23 ft R=A/P = 1.24/9.23 =0.1343 ft R2/2 =0.2623 ft S =0.015 ft/ft S 112 =0.07071 ft/ft Q= (1.486/0.013)(1.24)(0.2623)(0.07071)= 2.63 cfs. 2.29 cfs < 2.63 cfs - Gutter capacity on Oak Street is adequate The time of concentration for sub-area#3-5 is calculated below: Time of Concentration Gutter flow(615 ft @ 1.1% avg. slope on Cottonwood Road) V= (1.486/n)R2/3Su2 (n=0.013, A=1.24 ft, P=9.23, R213=0.2623, 512=0.1049) V= 3.14 ft/s T= 615 ft/3.14 ft/s/60s/min = 3.3 min Total Time of Concentration = 3.3 minutes (0.06 hours) For a 25-year storm event I25 =0.78X--64= 0.78(0.06)`64 =4.721 in/hr Q25 r/w =CIA =0.70(4.721 in/hr)(0.9936 acres) = 3.28 cfs Q25 Total for Storm Sewer#5 = 3.28 cfs =Flow rate entering catch basin#11 The capacity of the curb and gutter, at a 1.1% average slope for Cottonwood Road, with a depth of water 0.15'below the top of curb is calculated as follows: Q= (1.486/n)AR2r3Sii2 n=0.013 for Concrete A= 1.24 ft2 P= 9.23 ft R= A/P= 1.24/9.23 =0.1343 ft R2/3 =0.2623 ft S = 0.011 ft/ft SI/2 = 0.10488 ft/ft Q= (1.486/0.013)(1.24)(0.2623)(0.10488)= 3.89 cfs. 3.28 cfs < 3.89 cfs - Gutter capacity on Cottonwood Road is adequate 24" PVC from Catch Basin#9 to Detention Pond#3 This pipe carries the storm water from drainage sub-areas 3-1 & 3-2 &3-3. As previously calculated we should anticipate a flowrate of(3.58 + 3.13 + 1.57 + 2.13) = 10.41 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 24" PVC pipe at 1.85% slope. The 24-inch pipe will flow at a depth of 1.18 feet with a velocity of 5.42 ft/sec. 15" PVC from Catch Basin#10 to Detention Pond#3 This pipe carries the storm water from drainage sub-area 3-4. As previously calculated we should anticipate a flowrate of 6.59 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 0.5% slope. The 15-inch pipe will flow at a depth of 1.02 feet with a velocity of 6.13 ft/sec. 15" PVC from Catch Basin#11 to Detention Pond#3 This pipe carries the storm water from drainage sub-area 3-5. As previously calculated we should anticipate a flowrate of 3.28 cfs from a 25-year storm event. Calculations are enclosed in the Appendix for a 15" PVC pipe at 6.01% slope. The 15-inch pipe will flow at a depth of 0.39 feet with a velocity of 10.18 ft/sec. Detention Pond#3 The total area served by Detention Pond#2 is 20.593 acres with a weighted C-factor of 0.524 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow (acceptable release rate) is 2.71 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 2.71 cfs. The required storage for Detention Pond#3 is 15,175 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#3 will be 5.32 inches in width. These calculations are included with the calculations for sizing the pond. The discharge pipe from Pond#3 to Baxter Ditch will be designed to handle a flow rate of 20.29 cfs. The discharge pipe will be 30" RCP at a slope of 0.22%. Calculations are attached for this section of pipe. Detention Pond#1 The total area served by Detention Pond#1 is 3.62 acres with a weighted C-factor of 0.483 after development. The storage basin can have a release rate equal to the pre-development flow. The calculations for the pre-development time of concentration and flows are included in the Appendix. The pre-development flow (acceptable release rate) is 0.658 cfs. Calculations are also enclosed in the Appendix for sizing the detention pond by varying the storm duration and holding the release rate at 0.658 cfs. The required storage for Detention Pond#1 is 2,000 cubic feet. The weir must also be sized to insure the discharge never exceeds the allowable release rate. The weir in the discharge structure for Detention Pond#1 will be 1.29 inches in width. These calculations are included with the calculations for sizing the pond.