13 - Traffic Impact Study - Boulder Creek_Westbrook
traffic Traffic Impact Study services Boulder Creek/Westbrook Residential Development Bozeman, Montana Prepared For: Four Corners Construction, I.I.C. 125 Central Avenue Bozeman, MT 571 November, 2013 130 South l-iowle stroet Helena, Montana 59,601 406-450-1443 Boulder Creek/Westbrook Traffic Impact Study Bozeman,Montana Table of Contents A. Executive Summary................................... ...................... ...........................I B. Project Description........................................................................................I C. Existing Conditions........................ ............................... ............ ......... ....I AdjacentRoadways ..............................................................................2 TrafficCounts........................................................................................3 Levelof Service.......... ............................................. ............................3 D. Proposed Development.......................................... ............ ......................4 E. Trip Generation and Assignment.............. ................. ...............................4 F. Trip Distribution ..........................................................................................7 G. Traffic Impacts Outside of the Development.,.............................................7 H. Impact Summary& Recommendations......................................................8 List of Figures Figure I — Proposed Development Site......... ................... ................................ 2 Figure 2— Proposed Boulder Creek Development..................................................5 Figure 3— Proposed Westbrook Development...................................... .................6 Figure 4— Trip Distribution.................---..............................................................7 List of Tables Table I — 2013 Level of Service Summary.........................................A...... .............3 Table 2— Trip Generation Rates.............. .................................................. ........7 Table 3— Level of Service Summary With Development........................................8 Boulder Creek/Westbrook Traffic Impact Study Bozeman,Montana Boulder Cre / r i i 1 DevelopmentI Impact Bozeman, Montana A. EXECUTIVE SUMMARY As proposed, the Boulder Creels and Westbrook developments will not create any new roadway capacity problems along Durston Road. The intersection of Durston Road and Cottonwood Road is currently operating at a poor LOS in the PM peak-hour and the traffic from these developments will add to this problem. It is recommended that a left-turn be installed at this intersection for westbound traffic and that the intersection be converted to four-way STOP control. Alternatively this intersection could be improved by the installation of a modern roundabout. All other nearby intersections will continue to function at acceptable levels of service and no other additional improvements will be required along Durston Road to serve the proposed developments. B. PROJECT DESCRIPTION This document studies the possible effect on the surrounding road system from two proposed residential developments located north of Durston Road between Laurel Parkway and Rosa Way in Bozeman, Montana. The document also identifies any traffic mitigation efforts that the development may require. The site is located north of Durston Road '/4 mile west of Cottonwood Road. The property would be developed to include up to 233 new residential units. Based on the City of Bozeman Subdivision Regulations, the developers must study all effected intersections within '/z mile of the proposed development which includes the intersections of Durston Road with Laurel Parkway, Rosa Way, Cottonwood Road, and Flanders Mill Road. Although this development will include the construction of a portion of Oak Street,the section of road will not connect to the existing sections of Oak Street to east and will not provide access to the development site until additional properties in this area are developed to the east. A traffic impact study was prepared for this project in 2007 which was then called Laurel Glen Phases 3 & 4. The 2007 traffic study, which anticipated the construction of 270 residential units on the property, recommended the construction of a designated left-turn lane along Durston Road at Cottonwood Road, and that four-way STOP controls be installed at the intersections of Durston Road with Ferguson Road (completed) and Cottonwood Road. C. EXISTING CONDITIONS The proposed development properly currently consists of a 70-acre parcel of undeveloped land located north of Durston Road between Laurel Parkway and Rosa Way. The site is located Abelin Traffic.Services 1 November 2013 Boulder Creek/Westbrook Traffic Impact Studio Bozeman,Montana between the Laurel Glen Phase 2 Subdivision and the Traditions Subdivision. The topography in this area is flat. See Figure 1 for a location map of the proposed development. Fi ure 1- Proposed Development Site A,'' ks t f I. Adjacent Roadways Durston Road is a two-way east/west minor arterial route that provides access to the residential areas to the west of Bozeman. In recent year much of the road has been reconstructed to accommodate development in this area. Currently the road has a three-lane cross-section with a paved width of 46-feet east of Cottonwood Road and two-lanes paved at 31 feet west of Cottonwood Road. Durston Road also has designated bike lanes. All cross- street between Laurel Parkway and Flanders Mill Road are controlled by STOP signs. The roadway has a posted speed limit of 35 MPH and currently carries 8,600 Vehicles Per Day (VPD). Laurel Parkway is a north/road that was constructed to serve the different phases of the Laurel Glen development. This roadway was constructed with a wide median, turn lanes, and roundabouts at some intersection to provide capacity for future development and future road connections. The roadway has a posted speed limit of 25 MPH and currently carries 2,800 Vehicles Per Day (VPD). Cottonwood Road is a principal arterial north/south route that provides access to the residential developments to the north and Huffine lane to the south. The road has a two-lane cross-section with a paved width of 28-feet near Durston Road. The road has a posted speed limit of 25 MPH north of Durston Road and 40 MPH south of Durston Road. Cottonwood Road currently carries 550 VPD north of Durston Road. . Abelin Traffic Services 2 November 2013 Boulder CreeldWestbrook Traffic Impact Study Bozeman, Montana Flanders Mill Road in a north/south two-lane road which provides access north to Baxter Lane. The road currently has a paved width of 27 feet and a posted speed limit of 40 MPH. Flanders Mill Road currently carries 2,500 VPD north of Durston Road. Traffic Counts In July 2013 Abelin Traffic Services (ATS) collected turning movement count data at intersections along Durston Road as requested by the City of Bozeman. These counts included the intersections of Durston Road with Laurel Parkway, Rose Way, Cottonwood Road, and Flanders Mill Road. ATS also collected 24-hour ADT data on Laurel Parkway, Flanders Mill, and Durston Road. The raw traffic data is included in Appendix A of this report. Level of Service Using the data collected for this project, ATS conducted a Level of Service (LOS) analysis at area intersections. This evaluation was conducted in accordance with the procedures outlined in the Transportation Research Board's Highway Capacity Manual (HCM) - Special Report 209 and the Highway Capacity Software (HCS) version 5.3. Intersections are graded from A to F representing the average delay that a vehicle entering an intersection can expect. Typically, a LOS of C or better is considered acceptable for peak-hour conditions. Table 1 —2013 Level of Service Summary AM Peak Hour PM Peak Hour Intersection Delay Sec. LOS Delay Sec. LOS Durston Road & Laurel 14.4 B 13.3 B Parkewa Durston Road & Rosa 12.6 B 13.8 B Way Durston Road & 11.9/15.3 B/C 56.2/23.4 F/C Cottonwood Road* Durston Road & 11.3 B 16.8 C Flanders Mill Road *North bound/Southbound LOS and Delay Table 1 shows the existing 2013 LOS for the AM and PM peak hours without the traffic from the proposed developments. The LOS calculations are included in Appendix C. Table 1 shows that most of the existing intersections along Durston Road are currently operating within acceptable limits. However, the intersection of Cottonwood Road and Durston Road is currently experiencing excessive evening peak-hour delay. This issue Abelin Traffic Services 3 November 2013 Boulder CreeklWestbrook Traffic Impact Stugy Bozeman,Montana will need to be addressed regardless of any additional development within this area. If this intersection were converted to a four-way STOP controlled intersection it would function at LOS C with 16.8 seconds of delay in the PM peak-hour. If an additional left- turn lane were added to this intersection for westbound traffic, the overall intersection delay would drop to 14.0 seconds. D. PROPOSED DEVELOPMENT The development currently under consideration for this site includes 70 acres of land located north of Durston Road which would be developed into two residential subdivisions. The Westbrook Subdivision would be located just north of Durston Road and the Boulder Creek Subdivision would be located just north of Annie Street. The Westbrook Subdivision would include 118 single-family residential units. A total of 115 single-family residential units are proposed in the Boulder Creek Subdivision for a total of 233 new residential units. It should be noted that this is a significant decrease for the 270 residential units previously proposed for this property. The developments would each have designated parks and sidewalks throughout the properties. Access to the development sites would be provided through a variety of new connections onto Laurel Parkway, Rosa way, and North Cottonwood Road. Presently these three streets would be the only access points from the developments to Durston Road and the City of Bozeman. As this area continues to develop in the future it is likely that additional road connections will be provided to the north and east. The Westbrook and Boulder Creek development are shown in Figures 2 & 3. E. TRIP GENERATION AND ASSIGNMENT ATS performed a trip generation analysis to determine the anticipated future traffic volumes from the proposed development using the trip generation rates contained in Trip Generation (Institute of Transportation Engineers, Seventh. Edition). These rates are the national standard and are based on the most current information available to planners. A vehicle "trip" is defined as any trip that either begins or ends at the development site. ATS determined that the critical traffic impacts on the intersections and roadways would occur during the weekday morning and evening peak hours. According to the ITE trip generation rates, at full build-out the developments would produce 175 AM peak hour trips, 235 PM peak hour trips, and 2,230 daily trips. See Table 2 for detailed trip generation information. Abelin Traffic Services 4 November 2013 Boulder Creek/Westbrook Traffic Impact Study Bozeman,Montana Figure 2 a Proposed Boulder Creek Development 014 all F1iC{tI IS Z!(Al I(1e71i. � r 4 ift e q� 1 ? s4 bi s! irk s3 �S� ; sS r 5 )I:IM ................... ri ?Ic l j Q, _aP�Y ew as -A" f t A^ - �.pr °$ f7 W5n 5ti liy c�itu Ofi OZ v�Y ` jam/ =_ ✓ .t �J w ! ' r h11 { zi t I as i iN°`I.AHI�I.AS u I'I J Ia:l��I iUISII�Te3 i5 N!I oEEa cry § gri $� a § "o3i 3$ ^§` e'S =t Abelin Traffic Services 5 November 2013 Boulder Creek/Westbrook Traffic Impact Study Bozeman,Montana Figure 3 - Proposed Westbrook Development d _ �t7�-,t�it7tt..i'.'z ^tUtFS�$irS F , rxCO rL n•. at t I (mod ...__..::: ._:.:::_ aneuc ncrxna � .° agw�: ppggg gg�kvlR T AyC V 7:H . oEE•;' �xsaa� r4 4, a i Abelin Traffic Services 6 November 2013 Boulder Creek/Westbrook Traffic Impact Study Bozeman,Montana Table 2 - Trip Generation Rates AM Peak Total AM PM Peak Total PM Hour Trip Peak Hour Trip Peak Weekday Total Ends per Hour Trip Ends per Hour Trip Trip Ends Weekday Land Use Units Unit Ends Unit Ends per Unit Trip Ends Boulder Creek Single-Family 115 0.75 86 1.01 116 9.57 1,101 Westbrook Single-Family 118 0.75 89 1.01 119 9.57 1,129 Total 2331 175 235 2,230 F. TRIP DISTRIBUTION The traffic distribution and assignment for the proposed subdivisions was based upon the existing ADT volumes along the adjacent roadways and the peak-hour turning volumes. Based on field observations, half of the traffic from the development site will use Durston Road to reach areas to the east in Bozeman. The rest of the traffic will use Cottonwood Road, Flanders Mill Road, and Durston Road to reach other destinations. Traffic is expected to distribute onto the surrounding road network as shown on Figure 4. Figure 4—Trip Distribution 5% 0 0 Proposed Development Site a� v c 5% Durston Road t, 50% ca 0 v 0 0 3 c 0 0 40% V G. TRAFFIC IMPACTS OUTSIDE OF THE DEVELOPMENT Using the trip generation and trip distribution numbers, ATS determined the future Level of Service for the area intersections. The anticipated intersection LOS with the Westbrook and Boulder Creek Subdivisions is shown in Table 3. These calculations are based on the projected model volumes included in Appendix B of this report. Abelin Traffic Services 7 November 2013 Boulder CreeklWestbrook Traffic Impact Study Bozeman,Montana Table 3 indicates that the construction of the Boulder Creek and Westbrook Subdivisions will not cause any additional roadway capacity problems at locations along Durston Road. The intersection of Cottonwood Road and Durston Road is currently operating at a poor LOS and the Bounder Creek/Westbrook developments will contribute to the need for improvements at this location. There are several options for improving the capacity and LOS at the intersection of Durston Road and Cottonwood Road. If the intersection were modified to a four-way STOP controlled intersection with its current lane configuration the LOS would improve to D with 29.3 seconds of peak-hour delay. If an additional left-turn lane were added for westbound traffic with the four- way STOP control, the overall intersection delay would improve to 19.3 seconds (LOS C) and the intersection would have considerable reserve capacity. With the current road layouts in this intersection, a left-turn lane could be created by widening only the west leg of Durston Road and re-striping the intersection. Alternatively, the capacity related issues at this intersection could be addressed by constructing a modern roundabout at this location. There is sufficiently area to construct a roundabout in this intersection and this type of traffic control is becoming common in this part of Bozeman. If constructed, a roundabout would operate at LOS B with 11.5 seconds of delay and would provide sufficient capacity for this intersection well into the future. Table 3-Level of Service Summary With the Boulder Creek/Westbrook Developments AM Peak Hour PM Peak Hour Intersection Delay Sec.) LOS Delay (Sec.) LOS Durston Road & Laurel 15.1 B 14.1 B Parkewa Durston Road & Rosa 14.0 B 15.2 C Way Durston Road & 14.6/25.6 B/D 204.8/45.9 HE Cottonwood Road* Durston Road & 12.0 B 19.6 C Flanders Mill Road *North bound/Southbound LOS and Delay H. IMPACT SUMMARY & RECOMMENDATIONS As proposed, the Boulder Creek and Westbrook developments will not create any new roadway capacity problems along Durston Road. The intersection of Durston Road and Cottonwood Road. is currently operating at a poor LOS in the PM peak-hour and the traffic from these developments will add to this problem. It is recommended that a left-turn be installed at this intersection for westbound traffic and that the intersection be converted to four-way STOP Abclin Traffic Services 8 November 2013 Boulder CreeklWestbrook Traffic Inc act Study Bozeman,Montana control. Alternatively this intersection could be improved by the installation of a modern roundabout. All other nearby intersections will continue to function at acceptable levels of service and no other additional improvements will be required along Durston Road to serve the proposed developments. Abelin Traffic Services 9 November 2013 APPENDIX A Traffic Data AbelinTraffic services 130 S. Howie Street Helena, MT 59601 Abelin Traffic Services File Name durstandcottonwood 130 S. Howie Street Site Code 00000000 Helena, MT 59601 Start Date 7/23/2013 Page No 1 Groups Printed-Bank 2 FLANDERS DURSTON FLANDERS DURSTON Southbound — WestbOUnd Northbound ] EastboundLtarlTire Right Left Pds Right hu Left Right Thru= jEeds Right ThrU L eftTl Int.Total aU j_# : - - oT 07:30 AM 13 0 8 0 5 36 0 0 0 0 0 0 0 52 9 0 123 07:45 AM 18 0 9 0 4 25 0 0 0 i 0 0 0 0 103 8 0 167 Total 31 0 17 0 9 61 0 0 0 0 0 0 0 155 17 0 290 08:'0 AM 8 0 6 0 4 28 0 0 0 0 0 64 10 0 120 08:15 AM 11 0 10 0 4 35 0 0 0 0 0 0 0 50 8 0 Its 08:30 AM 8 0 6 0 4 28 0 0 0 0 0 0 0 53 3 0 102 08:45 AM 7 0 7 0 10 31 0 0 0 0 0 0 0 51 11 0 117 Total 34 0 29 0 22 122 0 0 0 0 0 0 0 218 32 0 457 BREAK*** 04:15 PM 14 0 6 0 14 62 0 0 0 0 0 0 0 40 12 0 148 04:30 PM 10 0 6 0 7 49 0 0 0 0 0 0 0 58 12 0 142 04:45 PM 12 0 5 0 8 53 0--0 0 0 0 47 1 5 0 140 Total 36 0 17 0 29 164 0 0 0 0 0 0 0 145 39 0 430 05:00 PM 19 0 10 0 11 so 0 0 1 0 0 1 0 67 13 0 210 05:15 PM 18 0 12 0 16 102 0 0 0 0 0 0 0 36 12 0 196 05:30 PM 17 0 14 0 11 90 0 0 0 0 0 0 0 51 14 0 197 Grand Total 155 0 99 0 98 619 0 0 0 1 0 0 0 672 127 0 1770 Apprch% 61 0 39 0 13.7 86.3 0 0 0 0 0 0 0 84.1 15.9 0 Total% 8.8 0 5.6 0 5.5 35 0 0 0 0 0 0 0 38 T2 0 AbelinTraffic services 130 S. Howie Street Helena, MT 59601 Abelin Traffic Services File Name d u rsta nd cottonwood 130 S. Howie Street Site Code 00000000 Helena, MT 59601 Start Date 7/23/2013 Page No I --.--------Groups Printed- nshifted COTTONWOOD DURSTON COTTONWOOD DURSTON — Southbound Westbound Northbound Eastbound L—Stail Time-- i91t] Thru f Lett Peds RightRLgItj Thj Left Prds Right �Th- Left �11� Int.'Total 07:30 AM 4 3 6 0 0 28 14 0 13 1 9 0 11 49 1 1 140 07745 AM 2 0 3 0--1 26 26 0 14 1 1 0 30 81 0 0 185 Total 6 3 9 0 1 54 40 0 27 2 10 0 41 130 1 1 325 08:00 AM 1 2 it 0 0 0 18 0 3 0 15 48 1 1 142 08:15 AM 0 1 3 0 2 32 19 0 23 2 7 0 14 44 0 0 147 08:30 AM 1 3 1 0 0 29 17 0 12 1 2 0 7 49 0 0 122 08:45 AM 0 1 3 0 2 _____-__0 38 18 19 0 3 0 16 46 2--- 0 .148 Total 2 7 It 0 4 28 22 127 76 0 f 72 3 N 15 0 52 187 3 0 559 BREAK*** 04:15 PM I I 1 0 2 64 15 0 28 2 11 0 15 37 0 0 177 04:30 PM 2 1 3 0 1 54 12 0 29 6 10 0 10 59 1 0 188 04:45 PM -0— 2 2 0 2 51 19 0 37 2 10 0 6 56 0 0 187 Total 3 4 6 —0 5 169 46 0 94 10 31 0 31 152 1 0 —552 05:00 PM 0 2 3 0 2 76 27 0 34 4 15 0 19 59 2 0 243 05:15 PM 0 0 1 0 9 98 32 0 31 3 20 0 8 38 2 0 242 05:30 PM 0 0 6 0 6 78 32 0 43 5 23 0 13 52 0 0 258 Grand Total 11 16 36 0 27 602 253 0 301 27 114 0 164 618 9 1 2179 Apprch% 17.5 25A 57.1 0 3,1 68.3 28.7 0 68.1 6.1 25.8 0 20.7 78 LI 01 'total% 0.5 0.7 1.7 0 L2 27,6 11.6 0 13.8 L2 5.2 0 7.5 28.4 0.4 0 AbelinTraffic Services 130 S. Howie Street Helena, MT 59601 Abelin Traffic Services File Name durstandrosa 130 S. Howie Street Site Code 00000000 Helena, IVIT 59601 Start Date 7/22/2013 Page No I Groups Printed-Unshifted ROSA DURSTON ROSA DURSTON Southbound Westbound Northbound Eastbound rTLWI --i.gh rhru --UFI P�ds t:=F.tl t4.11 Tilne Right Left Pews hru Left �P Right W ds -K E fL :jh:m__ _�e= _1 07:30 AM 1 0 2 0 0 28 0 0 0 0 0 0 0 56 0 0 87 07:45 AM 2 0 4 0 1 59 0 0 0 0 0 0 0 109 0 0 175 Total 3 0 6 0 1 97 0 0 0 0 -6—6 —0 165 0-0 262 08t AM 1 0 2 0 0 21 0 0 1 0 0 0 0 69 1 0 101 08 5 AM 1 0 3 0 0 26 0 0 0 0 0 0 0 69 1 0 100 08:30 AM 1 0 2 0 0 37 0 0 0 0 0 0 0 52 0 0 92 08745 AM 1 0.------2 0 0---23-___ 0 _ 0 0 0 0 0 0 64 0 0 90 Total 4 0 9 0 0 114 0 0 0 0 0 0 0 254 2 0 383 BREAK*** 04:30 PM 0 0 1 1 63 0 0 0 0 0 0 47 3 0 0 0�__q_ 0 0 0 1 0 51 0 0 24 04AS PM 1-- 0 0 2 400 ---L-- 70 ---- 0 0 Total 0 0 3 0 2 133 0 0 0 0 0 0 0 98 3 0 239 05�00 PM 0 0 1 0 2 56 0 0 0 0 0 0 0 so 0 0 109 05 15 PM 0 0 0 0 1 85 0 0 0 0 0 0 0 52 0 0 138 05:30 PM 1 0 4 0 4 106 0 0 0 0 0 0 0 71 1 0 187 05:45 PM 0 0 1 0 1 74 0 0 0 0 0 0 0 62 0 0 138 Total 1 0 6 0 8 321 0 0 0 0 0 0 0 235 1 0 572 Grand Total 8 0 24 0 11 655 0 0 0 0 0 0 0 752 6 0 1456 A pprch-1. 25 0 75 0 1.7 98.3 0 0 0 0 0 0 0 99.2 0.8 0 Tota I% 0.5 0 L6 0 0.8 45 0 0 0 0 0 0 0 5 t.6 0.4 0 Abelin TrafficServices 130 S. Howie Street Helena, IVIT 59601 Abelin Traffic Services File Name : durstandrosa 130 S. Howie Street Site Code : 00000000 Helena, MT 59601 Start Date : 7/22/2013 Page No : 1 Groups Printed-Batik I— LAUREL DURSTON LAUREL DURSTON Soutlibound Westbound Northbound Eastbound Right Left Int.Total RightnTLL—l---f-IL Peds lt lled�s Right'[ t Nds 07:30 AM 0 0 10 0 2 27 0 0 0 0 0 0 0 55 1 0 95 07:45 AM ------5 0 43 0 8 53 0 0 0 0 0 0 0 190 0 0 299 Total 5 0 53 0 10 80 0 0 0 0 0 0 0 245 1 0 394 08�00 AM 3 0 24 0 6 23 0 0 0 0 0 0 0 69 1 0 126 08 5 A 1 0 21 0 7 20 0 0 0 0 0 0 0 70 0 0 119 08:30 AM 1 0 13 0 3 35 0 0 0 0 0 0 0 51 1 0 104 08A5 AM 1 0 16 0 24 0 0 0 0 0 0 0 64 0 0 105 T 5otal 6 0 74 0 16 102 0 0 0 0 0 0 0 254 2 0 4-4 BREAK*** 04:30 PM 2 0 13 0 14 49 0 0 48 2 0 121 04:45 T o PMtal 3 1 8 0 31 0 20 50 0 0 48 3 0 140 __0 I O 0 1 0 0 Al� 0 0 0—0 1 1 34 99 0 0 0 0 0 0 0 96 5 01 268 05:00 PM 2 0 6 0 11 45 0 0 0 0 0 0 0 47 3 0 114 05:15 PM 0 0 12 0 15 70 0 0 0 0 0 0 0 47 5 0 149 05:30 PM 4 0 11 0 20 87 0 0 0 0 0 0 0 69 3 0 194 05:45 PM 1 0 __12 0 26 48 0 0 0 0 0 0 4 0. 149 _ Total 0 7 0 41 0 72 250 0 0 0 0 0 0 221 15 0 606 GrandTotal 21 0 199 0 � 132 531 0 0 0 0 0 0 0 816 23 1 1722 Apprch% 9.5 0 90.5 0 19.9 80,1 0 0 0 0 0 0 0 97.3 2.7 0 Total% 1.2 0 11.6 0 T7 30.8 0 0 0 0 0 0 0 47.4 1.3 0 Station ID : DURST Last Connected Device Type : Unic-L Info Line I ATS Version Number: 1.41 Info Line 2 UNICORN#1 Serial Number: GPS Lat/Lon Number of Lanes : 1 D13 File : DURST.DB Posted Speed Limit: Lanell.Configu' ration # Dir. Information Volume Mode Volume Sensors Divide By2 Comment 1 ALL Normal Axle Yes Lane#1 Basic Volume Data From: 111:00-08/06/2013 To: 08:59-08/09/2013 Date DW 0000 0100 0200 0300 0400 0500 0600 0700 0800 0900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 Total 080613 T 544 667 597 543 570 708 885 621 399 360 257 124 88 6363 080713 W 34 11 18 7 15 72 227 554 595 509 485 502 613 542 549 595 649 881 618 390 317 269 157 80 8689 080813 T 38 11 7 7 18 84 232 515 598 529 536 511 631 635 607 552 694 905 606 423 298 212 153 90 8892 080913 F 50 27 20 14 25 65 205 464 870 Month Total 122 49 45 28 56 221 664 1533 1193 1038 1021 1557 1911 1774 1699 1717 2051 2671 1845 1212 975 738 434 258 24814 Percent: 0% 0% 0% 0% 0% 1-/. 31% 6% 5% 4% 4% 6% 8% 7% 7% 7% 8% 11% 7% 5% 4% 3% 2% 1% ADT: 41 16 15 9 19 74 221 511 597 519 511 519 637 591 566 572 684 890 615 404 325 246 145 86 8813 ----------- Sun Mon Tue Wed Thu Fri Sat Total Percent DW Totals: 0 0 6363 8689 8892 870 0 Weekday(Mon-Fri): 24814 100% #Days: 0.0 0.0 0.5 1,13 1.0 0.3 0.0 ADT: 8631 ADT: 0 0 11747 8689 8892 2610 0 Weekend(Sat-Sun): 0 0% Percent: 0% 0% 26% 35% 36% 4% 0% ADT: 0 Centurion Basic Volume Report Printed.,06121113 Page 1 Station ID : GTN D N Last Connected Device Type : Unic-L Info Line 1 : ATS Version Number: 1.41 Info Line 2 : UNICORN#3 Serial Number: 91888 GPS Lat/Lon : Number of Lanes : 1 DB File : CTNWD N.DB Posted Speed Limit : - lane#1 'Dortf gur do # Dir. Information Volume Mode Volume Sensors Divide By 2 Comment 1.-�- ALL Normal Axle T^� Yes --�LL----- -- - Lane##1 Basic Volume Data From: 10:00-08/0612013 To: 08:59 -08/09/2013 Date DW 0000 0100 0200 0300 0400 0500 0600 0700 0800 0900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 Total 080613 T 29 34 38 44 40 32 52 56 36 33 24 17 15 5 455 080713 W 3 2 0 0 3 6 9 26 14 23 24 42 43 29 28 37 32 52 55 19 28 8 19 5 507 080813 T 2 6 0 0 4 12 12 25 23 21 26 30 33 37 43 42 38 44 49 32 24 16 7 2 528 080913 F 5 6 2 1 7 6 8 23 58 Month Total 10 14 2 1 14 24 29 74 37 44 79 106 114 110 111 111 122 162 140 84 76 41 41 12 1548 Percent: 1% 1% 0% 0% 1% 2% 2% 5% 2% 3% 5% 7% 7% 7% 7% 7% 8% 10% 9% 5% 5% 3% 3% 1% ADT: 3 5 1 0 5 8 10 25 19 22 26 35 38 37 37 37 41 51 47 28 25 14 14 4 532 Sun Mon Tue Wed Thu Fri Sat _ Total Percent DW Totals: 0 0 455 507 528 58 0 Weekday(Mon-Fri): 1548 100% #Days: 0,0 0.0 0.6 1.0 1.0 0.3 0.0 ADT: 531 ADT: 0 0 780 507 528 174 0 Weekend(Sat-Sun): 0 0% Percent: 0% 0% 29% 33% 34% 4% 0% ADT: 0 centurion Basic Volume Report Printed 08121113 Page 1 APPENDIX B Traffic Model Boulder Creek/Westbrook Traffic Model Bozeman,MT Existing 2013 AM Peak Hour Laurel Parkway Rosa Way Cottonwood Flanders MITI Peak 15-Min x 4 8 4J it 4 20 1L 32 8 4 IL 4 0 .9 4- 104 72 4) 16 172 4- 212 16 44 4- 236 12 14 8" 104 36 14 4- 140 Durston 4 ,J• 0 .1 4 .$ 4 32 .1 264 436 -0 324 4 392 -41 120 ` 56 PM Peak Hour Laurel Parkway Rosa Way Cottonwood Flanders Mill Peak 15-MIn x 4 0 4J 24 16 4J 1L 80 4 4J , 16 0 4® 312 68 40 44 44 4- 348 16 1 d' 424 24 4117 128 56 4m 408 Durston 12 4 J 8 J +1 172 56 240 -4 284 —1, 208 -4 t 20 324 52 `4 tO 92 Boulder Creek/Westbrook Traffic Model Bozeman,MT MODEL AM Peak Hour Laurel Parkway Rosa Way Cottonwood Flanders Mill IN 44 OUT 132 601% 20% 20% 79 26 26 9 269 13 5 4) IL 7 3 48 8 40 11 2 0 1 21 4® 3 24 14 4- 7 15 40 24 to 4m 22 Durston 2 1 .t 45 4 73 7 1 -4 21 34 13 66 11 PM Peak Hour Laurel Parkway Rosa Way Cottonwood Flanders Mill IN 150 OUT 85 60°10 20*A 20% 5190 17 30 17 30 pP 1L 45 3 $, 24 2 4) IL 27 26 4- 38 8 14 2 15 4- 24 51 26 C 83 Lo 4- 75 Durston 6 3 .$ 29 4j 13 47 5 3 m4 14 ®4 22 -' t 45 42 -4 7 '4 QF Boulder Creek/Westbrook Traffic Model Bozeman,MT With Development AM Peak Hour Laurel Parkway Rosa Way Cottonwood Flanders Mill 8 40 IL 17 25 4) L 39 11 4) IL 12 40 1 4— 115 74 4) IL i6 193 94 4® 215 40 4- 243 52 t* r 104 36 1p 4® 162 Durston 6 .A 1 .9 4 .? 8 39 265 457 358 - f 17 458 -41 131 "0 56 PM Peak Hour Laurel Parkway Rosa Way Cottonwood 0 4j 69 19 4) 1L 104 6 40 IL 43 26 .1 350 76 40 'L 44 58 350 31 04 4m 448 50 � 128 56 4- 483 Durston i8 7 t 8 1 55 61 243 298 -4 230 65 366 ®F 59 $ r* 92 APPENDIX C LOS Calculations Two-Way Stop Control Page 1 of 1 TWO-WAY STOP CONTROL SUMMARY General Information Site Information Analyst RLA Intersection Durston&Laurel Agency/Co. Abelin Traffic Jurisdiction Date Performed 811212013 Analysis Year 2013 Analysis Time Period AM Peak Hour Proiect Description Boulder/Westbrook East/West Street: Durston Road North/South Street: Laurel Parkwa Intersection Orientation: East-West Study Period hrs : 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L T R plume veh/h 4 264 212 32 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 4 264 veh/h 0 0 212 32 Percent Hea Vehicles 0 -- -- 0 _ Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LT TR U stream Si nal 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume veh/h 172 20 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 0 0 0 172 0 20 veh/h Percent Heavy Vehicles 0 0 0 0 0 0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 JR Lanes 0 0 0 1 0 Conti uration LE Delay,Queue Len th,and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration LT L R (veh/h) 4 172 20 C (m) (veh/h) 1334 532 816 lc 0.00 0.32 0.02 5%queue length 0.01 1.39 0.08 Control Delay(s/veh) 7.7 15.0 1 9.5 LOS A B A [Approach Delay(s/veh) -- -- 14.4 pproach LOS I -- -- B Copyright®2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12/2013 8:58 AM file:///C:/Users/Bob%2OAbelin/AppData/Local/Temp/u2l<4450.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information Analyst RLA Intersection Durston&Laurel Agency/Co. Abelin Traffic Jurisdiction Date Performed 811212013 Analysis Year 2013 Analysis Time Period PM Peak Hour Project Description BoulderlWestbrook EastA/Vest Street: Durston Road North/South Street: Laurel Parkway Intersection Orientation: East-West IStud y Period (hrs): 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 —3 4 5 6 T R L T R Volume(veh/hJ_ 12 240 348 80 Peak-Hour Factor, PHF 1.00 1.00 1.00 —100 1.00 1.00 Hourly Flow Rate, HFR 12 240 0 0 348 80 (veh/h) I I Percent Heavy Vehicles 0 -- 0 -- Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 —0 Configuration LT TR U stream Si nal 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume(veh/h 44_ 16 Peak-Hour Factor, PHF 1.00 1.00 TOO 1.00 1.00 1.00 Hourly Flow Rate, HFIR 0 0 0 44 0 16 veh/h� -- Percent Heavy Vehicles 0 0 0 0 0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 -0 0 1 0 1 Configuration L R Delay,Queue Length, and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1— 4 7 8 9 10 11 12 Lane Configuration LT L R v(veh/h) 12 44 16 C (m)(veh/h) 1142 431 665 Vic 0.01 0.10 0.02 95% queue length 0.03 0.34 0.07 Control Delay(s/veh) 8.2 14.3 10.5 LOS A B B [Approach Delay(s/veh) 13.3 rp p:r:oa:c:h:L:O:S' B Copyright(D 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12/2013 8:58AM file:///C:/Usei-s/Bob%2OAbeiiii/AppData/Local/Teiiip/u2kBF2D.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information RLA Intersection — Durston &Rosa Wa . Agency/Co. Abelin Traffic Jurisdiction Date Performed 811212013 Analysis Year 2013 Analysis Time Period TM—Peak Hour Project Description Boulder/Westbrook_ East/West Street: Durston Road outh Street: Rosa Wa Intersection Orientation: East-West ---[S—tudy Period (hrs): 0.25 Vehicle Volumes and Adjustments Ma'or Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L f- R Volume(veh/h) 2 436 236 4 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 —100 TOO Hourly Flow Rate, HFR 2 436 0 0 236 4 (veh/h) I I Percent Heavy Vehicles 1 0. Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LT TR Upstream Signal 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume(veh/h) 16 8 Peak-Hour Factor, PHF —7-00 - 1.00 1.00 1,00 1.00 1.00 Hourly Flow Rate, HFR 0 0 0 16 0 8 (veh/h) I Percent HeaMY2!hicles 0 0 . L0 0 0 0 Percent Grade 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 0 0 0 0 0 Configuration LR Delay,Queue Len2th,and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 8 9 10 11 12 Lane Configuration LT LR 0 v(veh/h) 2 24 C (m) (veh/h) 1339 500 v/C 0.00 0.05 95%queue length 0,00 0.15 Control Delay(s/veh) 77 12.6 LOS A B Approach Delay(s/veh) 12.6 Approach LOS B Copyright 0 2010 University of Florida,All Rights Reserved HCS+Tm Version 5.6 Generated: 11/12/2013 8:58AM file:///C:/Users/Bob%20Abeiiii/AppData/Local/Temp/Li2kI ID2.trnp 11/12/2013 'Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information Analyst RLA Intersection Agency/Co. Abefin Traffic Jurisdiction Date Performed 811212013 Analysis Time Period PM Peak Hour.___ Project Description BoulderlWestbrook East/West Street: Durston Road lNorth/South Street: Rosa WaZ Intersection Orientation: East-West IStud y Period (hrs): 0.25 Vehicle Volumes and-Adjustments Major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L T R plume veh/h 4 284 424 16 Peak-Hour Factor, PHF 1.00 1.00 1.00 M 1.00 1.00 1.00 Hourly Flow Rate, HFR 4 284 0 0 424 16 (veh/h� Percent Heavy Vehicles 0 -- A -- 0 Media2iKE— Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LT TR ga§tream Si2al 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume(veh/h) 16 4 Peak-Hour Factor, PHF TOO TOO TOO 1.00 1.00 1.00 Hourly Flow Rate, HFR 0 0 0 16 1 0 4 (veh/h) I I Percent Heavy—Vehicles 0 0 0 0 —f-0 0 Percent Grade 0 0 Flared ApproachN N Storage 0 0 RT Channelized a 0 Lanes 0 0 0 0 0 0 Configuration LR Delay,Queue Lenqth,and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration LT LR v(veh/h) 4 20 C(m)(veh/h) 1131 427 V/C a.00 0.05 95%queue length 0.01 0.15 Control Delay(s/veh) 8.2 ---13.8 LOS A 1 8 Approach Delay(s eh) 13.8 Kpproach LOS B Copyright(D 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/1212013 8:59AM filc:///C:/Users/Bob%20Abelin/AppData/Local/Temp/ti2k6C43.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information ite Infarmation AnaLst IRLA Intersection urston&Cottonwood Abefin Traffic Jurisdiction Date Performed 811212013 Analysis Year 2013 Analysis Time Period PM Peak Hour Project Description Boulder/Westbrook East/West Street: Durston Road INorth/South Street: Cottonwood Road Intersection Orientation: East-West IStud y Period-(hrs): 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L T R Volume(veh/h) 8 208 52 128 312 24 Peak-Hour Factor, PHF —7-00 — TOO 1.00 1,00 1.00 1.00 Hourly Flow Rate, HFR 8 206 52 128 312 24 (veh/h) I I I Percent Heavy Vehicles 0 1 0 1 -- Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LTR LTR gpLtream Si nal 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R plume veh/h 172 —2-0— 92 24 _4 4 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 172 20 92 24 4 4 (veh/h) L Percent Heamy2hicles 0 0 0 0 0 0 Percent Grade 0 0 - Flared Approach N N Storage 0 0 RT ChannelizWd 0 0 Lanes 0 1 0 0 —1 0 Configuration LTR LTR Delay,Queue Length,and Level of Service Approach Eastbound Westbound Northbound Southbound F Movement 1 4 7 9 10 11 12 Lane Configuration LTR LTR LTR LTR v(veh/h) 8 128 284 32 C (m) (veh/h) 1235 1316 331 228 V/C 0.01 0.10 0.86 0.14 95%queue length 0.02 0.32 7,79 0.48 Control Delay(s/veh) 7.9 8.7 56.2 23.4 LOS A A F C I Approach Delay(s/veh) 56.2 23.4 Approach LOS I -- F C Copyright 0 2010 University of Florida,All Rights Reserved HCS+Tm Version 5.6 Generated: 11/12/2013 8:56AM file:///C:/Users/Bob%20Abeiiii/AppData/f,ocal/Temp/u2klOE8.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information Analyst RLA Intersection Durston&Cottonwood Abelin Traffic Jurisdiction Date Performed 811212013 Analysis Year 2013 Analysis Time Period AM Peak Hour Project Description BoulderlWestbrook East/West Street: Durston Road outh Street: Cottonwood Road Intersection Orientation: East-West -IStud y Period (hrs): 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L T R Volume (veh/h) 4 324 120 104 104 4 Peak-Hour Factor, PHF 1.00 1.00 TOO 1.00 1.00 1,00 Hourly Flow Rate, HFR 4 324 120 104 104 4 (veh/h) Percent Heavy Vehicles Median Type Undivided RT Channeliz;d 0 0 Lanes 0 1 0 0 1 0 22nf,auration LTR LTR U stream Si nal Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume(veh/h)_ 4 4 56 12 4 8 Peak-Hour Factor, PHF 1.00 1.00 1,00 -100 TOO 1.00 Hourly Flow Rate, HFR 4 4 56 12 4 8 (veh/h) Percent Heavy Vehicl�es 0 0 0 0 T0T_0 Percent Grad (%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 1 0 0 1 0 lConfiguration LTR LTR Bela ,Queue Length,and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration LTR LTR LTR LTR v(veh/h) 4 104 64 24 C (m)(veh/h) 1495 1127 588 _74 Vic 0.00 0.09 0A 1 0.06 9 _5%queue length 0.01 0.30 0.36 0.20 Control Delay(s/veh) 7.4 8.5 11.9 15.3 LOS A A B C Approach Delay(s/veh)j 11.9 15.3 Approach LOS B C Copyright Q 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12/2013 8:53AM file:///C:/Uset-s/Bob%20Abelin/AppData/Local/"Femp/u2k77EF.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information Analyst RLA Intersection urston&Randers Abefin Traffic Jurisdiction Date Performed 811212013 Analysis Year gi 20FIS31 Analysis Time Period AM Peak Hour Project Descri tion Boulder/Westbrook East/West Street: Durston Road lNorth/South Street: Flanders Mill Intersection Orientation: East-West Study Period his . 0.25 Vehi .le Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 3 4 5 -6 L T R L T R 32 392 140 16 Peak-Hour Factor, PHF 1.00 1.00 —7-05 , 1,00 1.00 --T-oo Hourly Flow Rate, HFR 32 392 0 0 140 16 (veh/h) Percent Heavxythicles 0 0 Median Type Undivided RT Channelized 0 0 Lanes 1 1 0 0 1 0 Configuration L T TR Upstream Sign_al 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L. T R L T R Volume(vehl!�_— — 361M 72 Peak-Hour Factor, PHF 1.00 1,00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR (veh/h) 0 1 0 0 36 0 72 Percent Heavty2hicles 0 0 0 0 0 Percent Grade(%) 0 0 Flared Approach — N EN Storage 0 0 RT Channelized — 0 0 Lanes 0 0 0 0 0 0 Configuration LR Delay,Queue Len th and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 7—T—8 —9 10 11 12 Lane Configuration L LR v(veh/h) 32 108 C(m)(veh/h) 1436 680 V/C 0.02 0.16 95%queue length 0.07 0,56 Control Delay(s/veh) 7.6 11.3 LOS A Approach Delay(s/veh) 11.3 Approach LOS B Copyright 02010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12/2013 8,57AM l'ile:///C:/Users/Bob%20Abetin/AppData/Local/Temp/u2k6D4D.tmp 11/12/2013 7wn-VVov ��n Cou(n)� /— '— -, P > ) Page lof ) TWO-WAY STOP CONTROL SUMMARY General Information Site Infarm a at 16 ion Agency/Co. Abelin Traffic Jurisdiction Date Performed 811212013 Analysis Year 2013 Analysis Time Period PM Peak Hour East/West Street: Durston Road INorth/South Street: Flanders Mill Vehicle Volumes and Adjustments Major Street Eastbound Westbound Percent HeavyLVvehicles Median Type Undivided Minor Street Northbound Southbound Hourly Flow Rate, HFR Flared Approach N Delay,Queue Length, nd Levelof Service Approach Eastbound Westbound Northbound- Southbound Lane Configuration L LR Approach Delay(s/veh) 16.8 � / nopynght@ 2mounwnmx �rwnm�/mmomone�wn oco�u vemmnn� oa���o `1nu�om ummw � —, - � `-^ fiic/7/C in/& ]n�o |i/l2/2�|� � --'- --� --- -- ,,--------- --'r--''--' ' . � Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information RLA Intersection Durston&Laurel Abelin Traffic Jurisdiction Date Performed —8/12I2013 �nal sis Time Period AM Peak Hour Project Description Boulder/Westbrook East/West Street: Durston Road North/South Street: Laurel Parkwav Intersection Orientation: East-West IStud y Period KqEs�. 0.25.-. Vehicle Volumes and Ad'ustments major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L Volume(veh/h) 6 265 Peak-Hour Factor, PHF 1.00 1 1.00 1.05-- Hourly Flow Rate, HFR [1265 0 0 215 39 (veh/h) Percent Heaay�tcles 0 0 Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Confiouration LT TR Upstream Si 7a—1 0 0 Minor Street Northbound SouthbOUnd Movement 7 8 9 10 11 12 L T R L T R Volume (veh/h 193 25 Peak-Hour Factor, PHF —7-00 1,00 1.00 1.00 1.00 1,00 Hourly Flow Rate, HFR 0 0 0 193 0 25 Percent Heav)Ly2!2i!2!n-- o ------ 0 0 0 �01 Percent Grade(%) 0 0 Flared Approach —N N Storage 0 0 RT Channelized 0 0 Lanes 0 0 1 0 1 Configuration L I R Delay,Queue Lenqth,and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration LT L R v(veh/h) 6 193 25 C(m) (veh/h) 1323 524 810 is ------- 0.00 --0.37 0.03 95%queue length 0.01 1.68 0.10 Control Delay(s/veh) 7.7 158 9.6 LOS A C A rpproach Delay(s/veh) 15.1 pproach LOS C Copyright(D 2010 University of Florida,All Rights Reserved HCS+Tm Version 5.6 Generated: 11/1212013 9:17AM file:///C:/Users/Bob%20Abelin/AppData/Local/Tei-np/u2kA30C.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOIC CONTROL SUMMARY General Information Site Information Analyst RLA Intersection Durston&Laurel enc lCo. belin Traffic Jurisdiction Date Performed 811212013 nal sis Year With Develo ment Analysis Time Period PM Peak Hour Project Description BoulderlWestbrook East/West Street: Durston Road North/South Street: Laurel Parkway Intersection Orientation: East-West IStudy Period hrs : 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L T R olume veh/h 18 243 350 104 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 18 243 0 0 350 104 vehlh Percent Heav Vehicles 0 -- -- 0L -- -- Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LT TR Upstream Signal 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume veh/h 58 19 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 0 0 0 58 0 19 veh/h Percent Hea Vehicles 0 0 0 0 0 0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 0 0 1 0 1 Configuration L R Delay,Queue Length,and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 7 8 9 1 Q 11 12 Lane Configuration LT L R (veh/h) 18 58 19 (m) (veh/h) 1117 412 653 /c 0.02 1 0.14 0.03 5%queue length 0,05 0.49 1 E10. Control Delay(s/veh) 8.3 15.2 LOS A C Approach Delay(s/veh) -- -- 14.1 pproach LOS — -- B Copyright©2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12/2013 9:17 AM file:///C:/Users/Bob%2OAbelin/AppData/Local/Temp/u2kEE8F.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site—Information Analyst, RLA Intersection Durston&Rosa yny— Agency/Co. Abefin Traffic Jurisdiction Date Performed -�IIV2 0 73 Analysis Year With DeveLoement Analysis Time Period AM Peak Hour Project Description Boulder/Westbrook EastNVest Street: Durston Road INorth/South Street: Rosa Wev- Intersection Orientation: East-West IStud y Period (hrs): 0.25 chide Volumesand Adjustments Major Street Eastbound Westbound Movement 1 2— 3 4 --5 6 L T R L T R Volume(vehU_ 2 457 243 12 —— o— Too 1.00 Peak-Hour Factor, PHF 1.00 1.00 Too To Hourly Flow Rate, HFR 2 457 0 0 243 12 (veh/h) Percent Heavy Vehicles — 0 -- Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Confi uration LT TR Upstream Sign Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume(veh/h) 40 11 Peak-Hour Factor, PHF ---773-5 1.00 Too 1.00 1,00 1.00 Hourly Flow Rate, HFR 0 0 0 40 0 11 (veh1h) Percent Heavy_yehicles 0 0 -0 0 0-...- -0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 0 0 0 0 0 Configuration LR ela ,Queue Length,and Level of Service Approach Eastbound Westbound Northbound ---Southbound Movement.----- 1 4 7 8 9 10 11 12 Lane Configuration LT LR v(veh/h) F— 51 C(m)(veh/h) 1322 450 v/C 0.00 0,11 95%queue length 0.00 0.38 Control Delay(s/veh) T7 14.0 LOS A B jApproach Delay s/veh) 14.0 KpProach LOS B Copyright 0 2010 University of Florida,All Rights Reserved HCS+TM Version 5,6 Generated: 11/1212013 9:17AM file:///C:/Users/Bob`/`2OAbelin/AppData/Local/Temp/u2k49DB.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information Analyst RLA Intersection Durston&Rosa Wav Agency/Co. Abefin Traffic Jurisdiction Date Performed 811212013 Analysis Year With DeveloPment Analysis Time Period PM Peak Hour Project Description Boulder/Westbrook r E s �ast/West Street: Durston Road INorth/South Street: Rosa WaX Intersection Intoersection Orientation: East-West IStud y Period (hrs): 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L T R Volume veh/h) 7 298 - 448 43 Peak-Hour Factor, PHF 1,00 1.00 1.00 1.00 TOO 1.00 Hourly Flow Rate, HFR 7 298 0 0 448 43 (veh/h) I I I Percent HeavLEEhicles 0 -- -- 0 Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LT TR Upstream Signal -0 6 Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R Volume(veh/h- 31 6 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 0 0 0 31 0 6 Percent Heavy Vehicles 0 0 0 0 0 0 Percent Grade 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 0 0 0 0 0 Configuration LR Delay,Queue Length,and Level of Service Approach Eastbound Westbound Northbound Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration LT LR v(veh/h) 7 37 C (m)(veh/h) 1083 389 V/C 0.01 0.10 95%queue length 0.02 0.31 Control Delay(sIveh) 8.3 15.2 LOS A C Approach Delay(s/veh) 15.2 Approach LOS C Copyright@ 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12/2013 9:18AM file:///C:/Users/Bob%20Abelin/AppData/Local/'reinp/u2kA279.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information RLA Intersection Durston&Cottonwood Abefin Traffic Jurisdiction Date Performed 811212013 Analysis Year With DeveLoement Analysis Time Period AM Peak Hour Project Descri tion Boulder/Westbrook East/West Street: Durston RoadCottonwood Road Intersection Orientation: East-West Study Period (hrs): 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement 1 2 3 —4 —5 6 L T R L T R 4 358 131 104 115 17 Peak-Hour Factor, PHF 1.00 1.00 1.00 —100 —100 1.00 Hourly Flow Rate, HFR 4 358 131 104 115 17 Percent Heav Vehicles 0 Median Type Undivided RT Channelized —0 0 Lanes 0 1 0 0 1 0 Configuration LTR LTR gRs!ream SiEal -- 0 —0 — Minor Street Northbound Southbound Movement 7 8 9 10 11 12 L T R L T R 8— 17 5-6 52 40 8 Peak-Hour Factor, PHF 1.00 1,00 1.00 1.00 1,00 1.00 Hourly Flow Rate, HPT-- 8 17 56 52 40 8 �Y� -- Percent Hieavy Ve'hicles �Jov 0 0 —0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 1 0 —0— 1 Configuration LTR LTR De,lay,Queue Length,-and Level of Service Approach — Eastbound Westbound Northbound Southbound g Movement 4 —1--9 —10 11 — - T7 12 Lane Configuration LTR LTR LTR LTR v(veh/h) 4 104 81 100 C(m) (veh/h) 1466 1085 457 273 v/C 0.00 0.10 0.18 0.37 95%queue length 0.01— 0.32 0,64.- 1.61 Control Delay(s/veh) 7.5 8.7 14.6 25.6 LOS A A B D JApproach Delay(s/veh), 14.6 25.6 pproach LOS —I--- B D Copyright Q 2010 University of Florida,All Rights Reserved HCS+Tm Version 5.6 Generated: 11/1212013 9:15 AM file:///C:/Users/Bob%2OAbelin/AppData/Local/Temp/Li2kI 938.trnp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information 22bLs�..RLA Intersection Ourston& Cottonwood �2ena/co. Abelin Traffic Jurisdiction Date Performed 811212013 Analysis Year With Development Analysis Time Period PM Peak Hour Project Description Boulder/Westbrook EastAA/est Street: Durston Road NorthJSouth Street: Cottonwood�Road Intersection Orientation: East-West Stud Period(hrs): 0.25 Vehicle Volumes and Adjustments ----—----Major Street Eastbound Westbound Movement 1 2 3 —4 5 6 L T R L T R Volume veh/h)_ 1,00 J 8 230 59 128 350 69 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR '9c) (veh/h) 8 1 230 59 1 128 350 69 Percent Heavy Vehicles 0 �0 Median Type Undivided RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LTR LTR Upstream Si nal 0 0 Minor Street Northbound Southbound Movement 7 8 9 10 11 1-2 L T R L T R V 1-6-5— 790— 26 1 olume(veh/!� 65 Peak-Hour Factor, PHF 1.00 TOO TOO 1.00 1.00 1.00 Hourly Flow Rate, HFR 165 65 92 50 26 1 (veh/h) I— Percent Heavy Vehicles 0 -0—A 0 0 0 —0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 1 0 0 1 0 Configuration LTR LTR Delay,Queue Length,and Level of Service Approach Eastbound Westbound Northbound— Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration LTR LTR LTR LTR v(veh/h) 8 128 342 77 C(m) (veh/h) 1151 1284 260 162 v/C 0.01 0.10 1.32 0,48 95%queue length 0.02 0.33 17,56 2,24 Control Delay(s/veh) 8.1 8.1 204.8 45.9 LOS A A F E pproach Delay(s/veh) 204.8 45.9 pproach LOS F E Copyright@ 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 1111212013 9:15AM ftle:///C:/Users/Bob�/�20Abelin/AppData/Local/`I'emp/u2k6A37.tinp 11/12/2013 Two-Way Stop Control Page I of 1 TWO-WAY STOP CONTROL SUMMARY General Information Site Information nal st RLA Intersection Durston&Flanders Agency/Co. Abelin Traffic urisdiction Date Performed 811212013 nal sis Year With Develo went Ej Analysis Time Period AM Peak Hour Project Description BoulderlWestbrook East/West Street: Durston Road North/South Street: Flanders Mill Intersection Orientation: East-West IStudy Period hrs : 0.25 Vehicle Volumes and Adjustments Major Street Eastbound Westbound Movement W39458 3 4 5 6 R L T R Volume veh/h 162 16 Peak-Hour Factor, PHF1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 0 0 162 16 veh/hPercent Heav Vehicles -- 0 Median Type Undivided RT Channelized 0 0 Lanes 1 1 0 0 1 0 Configuration L T TR Upstream Si nal 0 0 Minor Street Northbound Southbound Movement 7 M 9 10 11 12 L R L T R Volume veh/h 36 74 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR 0 0 veh/h 0 36 0 74 Percent Hea Vehicles 0 0 0 0 0 0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 0 0 0 0 0 Configuration f I I LR Delay,Queue Length,and Level of Service pproach Eastbound Westbound Northbound Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration L LR (veh/h) 39 110 C(m) (veh/h) 1410 627 lc 0.03 0.18 5%queue length 0.09 0.63 Control Delay(s/veh) 7.6 12.0 LOS A B Approach Delay(s/veh) -- -- 12.0 pproach LOS -- -- B Copyright(9 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12I2013 9:16 AM file:///C:/Users/Bob%2OAbelin/AppData/Local/Temp/u2kC88F.tmp 11/12/2013 Two-Way Stop Control Page I of I TWO-WAY STOP CONTROL SUMMARY General Information Site Information Analyst RLA Intersection Durston&Flanders Abefin Traffic Jurisdiction Date Performed 811212013 Analysis Time Period AM Peak Hour Project Description BoulderlWestbrook East/West Street: Durston Road -INorth/South Street: Flanders Mill Intersection Orientation: East-West IStud y Period (hrs): 0.25 Vehicle Volumes and Adjustment- Major Street Eastbound Westbound Movement 1 2 3 4 5 6 L T R L T R Volume(vehL_ 61 366 483 44 Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00 Hourly Flow Rate, HFR I (veh/h) 61 366 0 0 483 44 Percent Hea Vehicles —0 0 Median Type Undivided RT Channelized 0 0 Lanes 1 1 0 0 _1 _0 Configuration--l— L 7— TR F_ Upstream Signal 0 0 Minor Street— --Northbound Southbound Movement 7 ;];8; 9 10 11 12 L T R L T R Volume(veh/!�_ 56 76 Peak-Hour Factor, PHF 1,00 1.00 1,00 1.00 1.00 Hourly Flow Rate, HFR 0 0 0 56 0 76 (veh/h) Percent Heavy Vehicles D 0 0 0 0 0 Percent Grade(%) 0 0 Flared Approach N N Storage 0 0 RT Channelized 0 0 Lanes 0 0 0 0 0 0 Configuration I I LR Delay,Queue Length,and Level of Service Approach Eastbound " Westbound Northbound Southbound Movement 1 4 7 8 9 10 11 12 Lane Configuration L LR v(veh/h) 61 132 C(m) (veh/h) 1050 377 v/C 0.06'___ 0.35 95%queue length 0.18 _ 1.54 Control Delay(s/veh) &6 19.6 LOS A C kpproach Delay(s/veh) 19.6 Approach LOS C Copyright Q 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11112/2013 9:16AM file:///C:/Users/Bob%2OAbelin/AppData/Local/1'einp/Lt2k3FI8.tmp 11/12/2013 All-Way Stop Control Page I of I ALL-WAY STOP CONTROL ANALYSIS General Information Site Information 22!�� IRLA Intersection Cottontvod&Dursfon Aqencv/Co. befin Traffic urisdiction Date Performed 811212013 Analysis Time Period IPM Peak Hour Project ID Boulder/Westbrook [East/West Street: Durston Road jNorth/South Street: Cottonwood Road r/.Thplume Adjustments and Site Characteristics roach Eastbound Westbound ovement L T R L -----------T------- R l lume(veh/h) 8 230 59 128 69 um Left rus Left Lane ripproach Northbound Southbound govement L T R L- T-----T---R Volume(veh/h) 185 65 92 50 2 %Thrus Left Lane ---------- Eastbound Westbound Northbound Southbound Ll L2 Ll L2 Ll L2 Ll L2 - -TR Configuration L TR L TR 7 L TR PHF IM im -73-3 --Uo-o 1.00 Flow Rate(veh1h) 297_ 128 419 342 80 0/.Heavy Vehicles 0 0 0 0 0 No.Lanes Geometry Group 4a 5 2 2 Duration,T 0.25 Saturation Headway Adjustment WorkshWe-t Prop.Left-Turns 0.0 1.0 0.0 0.5 0.6 Prop.Right-Turns 0.2 0.0 0.2 0.3 0.1 Prop.Heavy Vehicle Q.0 0.0 0.0 0.0 0.0 hLT-adj 0.2 0.2 0.5 0.5 0.2 32 0. hRT-adj -0.6 -0.6 -0.7 -0.7 -0.6 -0.6 -0.6 -0,6 1 hHV-adj 1.7 1.7 1.7 1.7 1.7 Taadj,computed -0.-1 -0.-5 -0.1 -0.1 0.1 h rD-eparture Headway and Service Time j._ 3,20 Y_20 7771 hd,initial value(s) 3,20 20 0.37 -j._30 3.20 0.07 x,initial 0.26 0.11-_7�0_4 6.41 76.41- 7.38 hd,final value(s) 6.34 - xfinal value 0.52 --T2-5 0.75 0.61 0.16 , Move-up time,rn(s) 2.0 2.3 2.0 2.0 i Is ervice Time,I.(s) 4.3 4.7 4.1 4.4 5.4 Fgapacity and Level of Service Eastbound Westbound Northbound Southbound Ll L2 Ll L2 L 1 L2 L I L2 7 5 Capacity(veh/h) 534 378 �49 31 330 -8_6 _T1._8 Delay(s/veh) 16.10 12.07 25.59 78 3 LOS C B D C B Approach:Delay(s/veh) 16.10 22.42 18.86 11.83 LOS C C C B Intersection Delay(s1veh) 19.31 Intersection LOS C Copyright C 2010 University of Florida,All Rights Reserved HCS+TM Version 5.6 Generated: 11/12/2013 9:18AM file:///C:/Users/Bob%2OAbelin/AppData/Local/Telnp/Li2k997.tmp 11/12/2013 Formatted Report �� `\ `-- ) Page lo[ 1 ROUNDABOUTREPORT General Information Site Information Agency or Co, Abelin Traffic ElVV Street Name Durston Road Date Performed 811212013 N/S Street Name Time Period PM Peak Hour Analysis Year With Development Peak Hour Factor IM -Project ID BoulderlWestbrook Project Description: Volume Adjustment and Site Characteristics Right-Turn Bypass None None None None Critical and Follow-Up Headway Adjustment Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass Follow-Up Headway(sec) 3.1858 3.1858 13,1858 3.1858 3.1858 3.1858 3.1858 3.1858 3.1858 3 E3 3.1858 Flow Computations Entry Volume v( 547 342 =T-80 Capacity and v1c Ratios Left Right Bypass Left Right Bypass Left Right Bypass Left I Right Bypass Capacity(c),veh/h 889 841 815 E554 Delay and Level of Service Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass Intersection Delay,s/veh 11.48 Copyright 0 2013 University of Florida,All Rights Reserved FICS 201OTM 6.50 Roundabouts Generated: 11/12/2013 9:19AM '---\ / ` ) � � -_�