HomeMy WebLinkAbout20- Change Order G-2 - AE2S - Pear Street Booster Station Rehabilitation 4 n www.ae2s.com December 17, 2019 Bob Murray— Engineering Division City of Bozeman 20 East Olive St#202 Bozeman, MT 59715 bmurray@bozeman.net RE: Bozeman Pear Street Booster Station Rehabilitation Recommendation to Approve Change Order G-2 Dear Mr. Murray: AE2S recommends the approval of the enclosed Change Order G-2 on to the General Construction Contract for Pear Street Booster Station Rehabilitation project. The following information is included in this recommendation letter for your and the Commission's review: Summary of Scope Changes, and the General Construction Contract Summary. Summary of Scope Change: • Change Order Request No. 2 — FRP Wall Panel Improvements • Cost Increase: $25,620.00 • Contract Time: +14 Days • During the early construction phase,Western Municipal suggested and provided a quote for removing the existing drywall finish and replacing with insulated FRP paneling.The poor condition of the existing walls was noted during the design but value-engineered out of the Bidding Documents to save on project budget. The Contractor noted this work is best to complete while the process piping and existing electrical is "gutted" from the facility and wanted to give the City this option while the opportunity was present. AE2S and the City agreed with the contractor's approach and decided to move forward with the proposed improvements. The change order covers the following work: removal of the existing drywall panels, insulation, and framework; and installation of new wall framing, support header, rigid foam insulation, dry-wall, and FRP panels per construction the detail sketch provided in WCD No. 2. The improvement provides the following benefits: cleaner finished work environment, easier cleaning and maintenance with water resistant finishes, and sturdier support headers for hanging electrical panels. The estimated labor included in the PCO price was generally in line with the labor and time AE2S observed and recorded on-site, and the Contractor has provided the invoice for the materials estimated. Advanced Engineering and Environmental Services, Inc. 1288 North 14th Avenue,Unit 103 • Bozeman, MT 59715 • 406-219-2633 4t\; • Extension of Contract Time • Cost Change: $0.00 • Contract Time: +9 Days • A total of 9 calendar days are added as a result of the following change of conditions: i. Discrepancy between the record drawing, project drawings, and the field condition of the existing supply line located in the northwest corner of the building. ii. Alignment issues depicted on the existing pump discharge lines. iii. Orientation difficulties on the surge anticipation line due to existing bolt patterns. • The change of conditions listed above are legitimate changes AE2S observed on site. AE2S will reflect the changes in the record drawings as best as reasonably possible. • Modification in Process Piping: • Cost Decrease: ($581.12) • As mentioned in the extension of contract time section, WMC had to utilize an additional reducer in We of a new 12" valve. As a result of this field modification the new 12" valve was not installed.WMC offered a cost deduct for the difference in cost between the fitting and the valve. • Stop Work Order: • No Cost Change • WMC will shut down construction activities for the Christmas Holiday and requested a Stop Work Order to suspend contract days between December 23,2019 and January 5, 2020. During this time, no work will be performed in the field by either WMC or AE2S and the contract days will be suspended to allow Substantial Completion to be achieved after the holiday break. General Construction Contract Summary: • Change in Contract Price: o Original Contract Price:............................................................................$521,060.00 o Cost Increase from Change Order G-1: +$11,637.52 o Cost Increase from Change Order G-2: (this CO) + $25,038.88 o Current Contract Price:.............................................................................$557,736.40 o NET Percent Increase/ (Decrease) by Change Order:.............................7.04 % https://ae2s.shorepoint.com/sites/PearSt.BoosterStation/Shared Documents/General/Phase 060-Construction/raskO-Construction Phose/[2]Change Orders/CO G2 FRP Wall Panels/Pear St G2coverletter.docx • Change in Contract Times: o Time adjustments: 23 Days added to Time for Substantial Completion 23 Days added to Time for Final Completion o Time for Substantial Completion: ...............................................january 9, 2019 o Time for Final Completion: .....................................................February 12, 2020 ** We greatly appreciate the opportunity to provide professional engineering services to the City of Bozeman and look forward to a successful start-up and close-out of the Pear Street Booster Station Rehabilitation project. Should you have any questions or concerns, please do not hesitate to contact me at your convenience. Sincerely, Brian Viall, E Project Mana er Encl: Change Order G-2 for the General Construction Contract. Work Change Directive No. 2. PCO 5 Letter dated December 11, 2019. *Substantial Completion Date including Stop Work Order between December 23,2019 and January 5,2020 **Final Completion Date including Stop Work Order between December 23,2019 and January 5,2020 https://aels.sharepoint.com/sites/PearSt.BoosterStation/Shored Documents/General/Phase 060-Construction/Task 03-Construction Phose/(11 Chonge Orders/CO_G2_FRP Wall Panels/Pear St G2 cover lettecdou Change Order No. G-2 Date of Issuance: December 16,2019 Effective Date: Project: Pear Street Booster Station Owner: Rehabilitation City of Bozeman,MT Contract:General Construction Date of Contract: June 7,2019 Contractor:Western Municipal Construction,Inc. Engineees Project No.: P05097-2017-016 The Contract Documents are modified as follows upon execution of this Change Order: Description of Change: Provide submittals,equipment,and materials for the following: Item Description Cost Adjustment 1 FRP Wall Panel Improvement $25,620.00 2 Extension of Contract Time $0.00 3 Modification in Process Piping ($581.12) 4 Stop Work Order:December 23,2019 through January 5,2020. $0.00 Total Net Change-CO G-2 $25,038.88 Attachments: •Proposed Change Order No.2 from WMC,Inc dated October 11,2019 •Work Change Directive No.2 dated October 31,2019 •PCO 5 letter dated December 11,2019 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: ;Original Contract Times: ❑ Working days 16 Calendar days ;Substantial completion(days ordate): November 26,2019 $ $521,060.00 .Ready for final payment(days ordate): December 30,2019 [Increase][De ase]from previously approved = Change Orders '.[Increase][I3esrease] from previously approved Change Orders No. N/A to No. NIA: 'No. N/A to No. N/A !Substantial completion(days): 7 $ $11,637.52 lReady for final payment(days): 7 [ Contract with[Increasey[DeGFeasc}from previously approved Change Orders !Contract Times prior to this Change Order: ;Substantial completion(days or date): December 3,2019 $ $532,697.52 1Ready for final payment(days or date): January 6,2020 Increase f this Change Order ;[Increase][Des:ea6e]Time of this Change Order: [ Substantial completion(days or date): 23 $ $25,038.88 ;Ready for final payment(days or date): 23 [ Contract Price incorporating this Change Order: ;Contract Times with all approved Change Orders: ;Substantial completion(days or date): January 9,2020* $ $557,736.40 ;Ready for final payment(days ordate): February12,2020** RECOMMEN ED: ACC PT D: ACCEPTED: By: By By: Engineer(Autho a Signature) Bu er(A thorized Signa ure) Seller(Au drized Si ature) Date: Date: L/ Date: C �X Approved by Funding Agency(if applicable): Date: CJCDC No.C-941(2002 Edition) Page 1 of 1 Prepared by the Engineers'Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute. *Substantial Completion Date including Stop Work Order between December 23,2019 and January 5,2020. **Final Completion Date including Stop Work Order between December 23,2019 and January 5,2020. .,�� •' L,� ..< E,iCI�C CNGInCCPS X1111 COIL PVT DOCI!II'.t115 CO),1MITIrt Work Change Directive No. 2 j Date of Issuance: 10/31/2019 Effective Date: 10/31/2019 Owner: City of Bozeman, Montana Owner's Contract No.: Contractor:Western Municipal Construction, Inc Contractor's Project No.: Engineer:AE2S, Inc. Engineer's Project No.: P05097-2017-016 i Project: Pear Street Booster Station Rehabilitation Contract Name: General Construction Contractor is directed to proceed promptly with the following change(s): Description: Remove the old interior dry-wall and any existing furring and replace them with insulated FRP panels. © The hand sketch attached summarizes the engineer's understanding of the contractor's proposed construction. Final detail to be included in Record Drawings. Attachments:[List documents supporting change] Proposed Change Order PCO No 2: See WMC,Inc.PCO Dated October 11,2019. Purpose for Work Change Directive: Directive to proceed promptly with the Work described herein, prior to agreeing to changes on Contract Price and Contract Time,is issued due to:[check one or both of the following] ❑Non-agreement on pricing of proposed change. ® Necessity to proceed for schedule or other Project reasons. Estimated Change in Contract Price and Contract Times(non-binding,preliminary): Contract Price $ 25,620.00 Increase Contract Time 14 days Increase Basis of estimated change in Contract Price: ❑ Lump Sum ❑ Unit Price ® Cost of the Work ❑ Other ECOMMENDED: AUTHORIZED BY: By: By: By: Enginee 4thorized Signature) Owner(Authorized ignature) Contractor(Authorized Signature) Title: Project Manager Title: iqb L ., Title: Date: 10/31/2019 Date: t 31 Date: Approved by Funding Agency(if applicable) By: Date: Title: Pear Street Booster Station 00 63 49- 1 February 2019 Bozeman, Montana Work Change Directive Form �I Advanced Engineering and Environmental Services, Inc. W\ Sh o 1 '6 t �1 c�c� G 1- �012$Ito — - —�-�-- � ----� ---- []ale ^ _ Class --t—. 11-- rr —- --• Page-- S-_o( Assignment W1131� W �� LC 1 v L No. Z ---- -- -- — - ------ L_�,� bcas e,r St�ti�i d�� Wa-� [— )ii g t. a . s«PRoRI- to" I{EAUE� W�H SPAcF FVVNL'1 AI nf,i(', qW-Vt_ )--I WE, 11�' ok . sma rvrA)ty W-CEuTrk TO AeftWbArF STAt\1lbARO WA-VTA / 0 lb VON TNS" ITo N/ 1 -- -OP(ttlAi 1 1ANC °K FrP L17"E� PANEL _ —_ A pC�HO(Z Z,xyr i l I wifk ANCFi-s2 8OLTS DR1U.44 CM U WAO 2"Y 4" TgEAZEO LU m aEf? WALE t►f RANG, A 18 o k . l�i;4V1ll� 1c I�EhbE!� Z" ?,T-GTp F0AM 1NS(A1 Arzp-N Bowl) TG suppo — aEC17 '41 / PAfVELs, CWTINATE FLAUA-WO , V31 FLFCTiZe-AL. C Ac'Ttsim K/ALL M` t�R tsx. 7 " a. c F"JFE), z" Pl Kl o FOAM X"sUt472 _— I�a. 51'l�t.ihRp 'DQ�IWALL FP- L1=NeP- PANEL mmae2s.com Western Municipal Construction, Inc. 10/16/2019 17:10 ICH-1904-ICO2 Pear Booster Station-CO2 FRP Page: 1 i Bid Summary Totals Report ! ! Standard Markup Instructions Previous Run Summary: 10/16/2019 5:07 PM Cost Basis Markup% Markup Spread: 10/16/2019 5:07 PM Labor: 9,426 15.00 1,414 Summary run on Takeoff Quan and Adjusted to Bid Quan. Burden: 5,978 15.00 897 Perm Mati: 4,267 15.00 640 Standard Spreads Const Matl: 983 15.00 147 Indirect Spread: Total less Sub ! Sub: 0 5.00 0 Markup Spread: Markup% i ! Eq.Op.Exp: 268 15.00 40 Addon/Bond Spread: Total r Co.Equip: 268 15.00 40 Rented Eq.: 0 15.00 0 Totals as of Last Spread Indirect/O: 600 15.00 90 Cost: Markup: Total: Misc2: 0 15.00 0 Direct: 21,106 3,166 24,272 Misc3: 0 15.00 0 Indirect: 683 102 785 Overrides: 0 0 Addons: 256 0 256 Total: 21,790 15.00 3,268 Bond: 307 307 i SubTotal: 22,352 3,268 25,620 i Selected Bond Table: A Pass Through: 0 0 i Total: 22,352 3,268 25,620 i Key Indicators i Balanced Markup / Total Labor = Balanced Markup/Total Labor i 3,268.34 / 15,403.09 = 21,22% j i Indirect Cost / Direct Cost = Indirect Cost/Direct Cost 682.50 / 21,106.34 = 3.23% ! Direct Manhours + Indirect Manhours = total manhours 268.00 + 0.00 = 268.00 i 1 I 1 i I 1l t� t f , 1 l 'i '1 i ( 1 i i j Quotation SIMKINS HALLIN 326 N. Broadway— PO Box 938—Bozeman,Montana 59771-0938 278945 j Phone 406-586-5495-Fax 406-586-2653- 1-800-823-8733 Quote No Quote Date 10/11/2019 I i Invoice Address Delivery Address Customer COD-Hoga4040 Hogan, Kirk JOB: 1222 South 6th Job Ref 1222 South 6th 664 Terrance Loop 1222 South 6th Bozeman, Montana, 59718 Bozeman, Montana,59715 Contact Your Ref i Taken By Brendan Dore Delivery By 10/11/2019-FRIDAY Page 1 of 1 Speciallnsiructlons Notes. Line Product Code=. Description' , Qly/Footage Price PeY = Total I I j 1 6967 2x4-12 CA-C Brown Treated 6 ea 930.80 mbf 44.68 j 6/12 4 2 6968 2x4-16 CA-C Brown Treated 2 ea 956.80 mbf 20.41 j 2116 3 3436 Sill Sealer Foam 1/4"x 5.1/2"x 50' 2 ea 4.29 ea 8.58 4 002 2x4-10 42&Blr Whitewood 92 ea 530.40 mbf 325.31 92110 f 5 003 2x4-12 412&Bir Whitewood 6 ea 530.40 mbf 25.46 i i 6/12 i 6 005 2x4-16 412&Btr Whitewood 2 ea 540.80 mbf 11.54 r 2/16 3 i 7 010 2x6-12112&Bir Whitewood 10 ea 525.20 mbf 63.02 IIII I 10/12 8 3165 Blue Board Dow SB Square Edge Styrofoam 25 PSI 4x8 2" 36 ea 28.96 ea 1,042.56 9 10231ite 4x8 518 USG lightweight Firecode Type X GYP-Board 38 ea 420.16 msf 510.91 10 2744158 1-5/8"G&S Black Coarse Sheelrocl<Screw DC6158/DWC6156 20 LB 2,29 LB 45.80 s I 11 zz_SP-SGEA_2413 4xl0 FRP Glasliner White 30 ea 52.59 ea 1,577.70 12 zz SP-SGEA_2414 Frp Divider White 10' 22 ea 2,69 ea 59.18 j i 13 6764 FRP Adhesive Henry FP00444069#444 4 Gallon 6 ea 55,35 ea 332.10 r 1 1 i TotalAmount $4,067.25 i Sales Tax $0.00 Quotation Total $4,067.25 I 1 By your signature below,you are agreeing to the Terms&Conditions of sale set forth on the back of this document. If j ffi { Buyer Dale j If not paid vrithin terms,I understand Ural I am liable to pay for all finance charges(15%APR),3id party collection court costslltres,all reasonable court costs and altanay fees Incurred by SfmWns Hallin,Inc. Simkins Hallin,Inc,charge accounts are due the I01h of the lollotvtng month(Net 10ih).Terms&Conditions of sale are on the back of this document, Simldns Hallin delivers onto private property at cuslamers direction.Customer assumes risk and responsibility for resulting properly damage unless Simkins Hallin has acted negligently. 10/15/2019 8:44:23AM Page 1 of 1 j i i Western Municipal Construction,Inc. 12/12/2019 13:38 KH-1904-1 CO2 Pear Booster Station-CO2 FRP LABOR USE REPORT RESOURCE DESCRIPTION QUAN RATE BASE BURDEN TOTAL LA02 Labor Group2 134.00 MH 23.47 3,459.48 2,261.81 5,721.29 OPFORM Operator Foreman 67.00 MH 30.95 2 281.02 1415.29 3 696.31 p > SUPER Superintendent 67.00 MH 50.00 3,685.00 2,300.49 5,985.49 Grand Total 268.00 9,425.50 5,977.59 15,403.09 1 Western Municipal Construction,Inc. Report Printed On: 12/12/2019 13:35 KH-1904-1 CO Pear Booster Station-CO2 FRP Page: 1 Bond Calculations Table: A Description: Underground Utilities Contract Amount Rate per 1000 Bond Amount First: $ 500,000 12.00 $ 307.45 Next: $ 2,000,000 7.25 $ 0.00 Next: $ 2,500,000 5.83 $ 0.00 Next: $ 2,500,000 5.42 $ 0.00 Next: $ 7,500,000 5.00 $ 0.00 Remainder: 5.83 $ 0.00 Subtotal: $ 307.45 Time Threshold 1: 0 Extended Time Rate 1: 0.0000% $ 0.00 Time Threshold 2: 0 Extended Time Rate 2: 0.0000% $ 0.00 Length of Job: 3 Total Bond Amount: $ 307.45 Western Municipal Construction,Inc. 12/12/2019 13 : 34 KH-1904-1CO2 Pear Booster Station-CO2 FRP List of Addons Addon Description Basis % Cost Total Amt 1 MT Gross Reciepts Tax JB 1.0000 Y 256.21 2 Gen.Liability Insurance JB 0.0000 Y 0.00 3 Buliders Risk LS 0.0000 Y 0.00 4 OCP JB 0.0000 Y 0.00 5 Small Tools and Supplies TH 0.0000 Y 0.00 6 Safety Expense TH 0.0000 Y 0.00 256.21 Addon Basis Codes and Descriptions Used in this Estimate: JB-Job Value LS-Lump Sum TH-Total man Hours 1 Western Municipal Construction,Inc. 12/12/2019 13:33 KH-1904-1 CO2 Pear Booster Station-CO2 FRP Page: 1 Bid Summary Totals Report Standard Markup Instructions Previous Run Summary: 10/16/2019 5:07 PM Cost Basis Markup% Markup Spread: 10/16/2019 5:07 PM Labor: 9,426 15.00 1,414 Summary run on Takeoff Quan and Adjusted to Bid Quan. Burden: 5,978 15.00 897 Perm Matl: 4,267 15.00 640 Standard Spreads Const Mad: 983 15.00 147 Indirect Spread: Total less Sub Sub: 0 5.00 0 Markup Spread: Markup% Eq. Op.Exp: 268 15.00 40 Addon/Bond Spread: Total Co.Equip: 268 15.00 40 Rented Eq.: 0 15.00 0 Totals as of Last Spread Indirect/O: 600 15.00 90 Cost: Markup: Total: Misc2: 0 15.00 0 Direct: 21,106 3,166 24,272 Misc3: 0 15.00 0 Indirect: 683 102 785 Overrides: 0 0 Addons: 256 0 256 Total: 21,790 15.00 3,268 Bond: 307 307 SubTotal: 22,352 3,268 25,620 Selected Bond Table: A Pass Through: 0 0 Total: 22,352 3,268 25,620 Key Indicators Balanced Markup / Total Labor = Balanced Markup/Total Labor 3,268.34 / 15,403.09 = 21.22% Indirect Cost / Direct Cost = Indirect Cost/Direct Cost 682.50 / 21,106.34 = 3.23% Direct Manhours + Indirect Manhours = total manhours 268.00 + 0.00 = 268.00 Western Municipal Construction,Inc. 12/12/2019 13:40 KH-1904-1 CO2 Pear Booster Station-CO2 FRP ***Kirk Hogan MATERIAL/SUB REQUIREMENTS REPORT Cost Code Desc Sel Vendor Quantity Unit Unit Cost Tax/OT% Pcs/W Total Esc% 2STRFIR 1.000 LS 4,067.250 100.00 4,067.25 100.00 Interior Firring Package 2STRMOP 1.000 EA 200.000 100.00 200.00 100.00 Rubber Mop Liner COST TYPE TOTAL 4,267.25 3DUMPFEE 1.000 LD 350.000 100.00 350.00 100.00 10cy Rolloff 3STGS01 150.000 MH 0.400 100.00 60.00 100.00 Job STS 3STGS02 150.000 MH 0.150 100.00 22.50 100.00 STS/PPE 3STGS03 0.000 LS 1,500.000 100.00 0.00 100.00 Job Tooling 3STGSO4 0.000 EA 350.000 100.00 0.00 100.00 Sawblades(Concrete) 3STGS05 0.000 RL 50.000 100.00 0.00 100.00 Orange Plastic Safety Fence 3STGS06 0.000 RL 100.000 100.00 0.00 100.00 Orange Woven Barrier Fence 3STGS07 0.000 EA 2.450 100.00 0.00 100.00 Galv.Metal T-Post Stakes 3STHILTI 1.000 EA 150.000 100.00 150.00 100.00 Hilti Shot&Nails 3STPIPELABEL 0.000 LS 500.000 100.00 0.00 100.00 Buy Pipe Labelling 3STSSAFETY 1.000 EA 250.000 100.00 250.00 100.00 Dust Masks&Eye Protect 3STZIP 1.000 EA 150.000 100.00 150.00 100.00 Zip Ties and Temp Bracing COST TYPE TOTAL 982.50 REPORT TOTAL 5,249.75 Cost Types Selected:Permanent Materials, Construction Materials,Subcontractor Subtotal selected vendor, quantity, units, and unit price only display if they are the same for all line items in the subtotal. 1 Western Municipal Construction,Inc. 12/12/2019 13:39 K-H-1904-ICO2 Pear Booster Station-CO2 FRP EQUIPMENT USE BY EQUIPMENT Biditem/ Activity/ Rut EOE Inside Outside Category Resource Description Quantity Unit Pcs % % Equipment Equipment EOE Other Total 8TKPU Truck,Pickup 3/4 ton ***8TKPU Truck,Pickup 3/4 ton 67.00 268 268 536 ***REPORT TOTALS*** 268 268 536 indicates non-additNe item 1 MN�I�PAVL Western Municipal Construction, Inc. 2066 Stadium Drive Bozeman, MT 59715 Phone(406)624-6219 Billin . MT Q oorr� December 11,2019 AE2S Attn:Brian Viall,PE 1288 North 14"Ave,Unit 103 Bozeman,MT 59715 406-579-5104 RE: PCO5—Request for Time Extension Due to Misc.Change of Conditions Pear Street Booster Station Project—Bozeman,MT I Mr.Viall: This Proposed Change Order(PCO)outlines miscellaneous field conditions differing from the conditions represented in the Project Drawings and Specifications for the Bozeman Pear Street Booster Station Rehabilitation Project and,resulting from these changes,requests an extension in Contract Time. For projects similar to the Pear Street Booster Station,we expect a certain level of changes to be identified in the field and hope the City will agree. Because Western Municipal Construction strives to build reputation with our Owners based upon positive relationships,we have not previously asked for any change in Contract Price—nor are we asking for any increase in Contract Price in this PCO.WMC proposes to absorb the additional cost of these changes in exchange for a reasonable extension in Contract Time. A brief summary of the changes significantly impacting our Construction Schedule is outlined below with an associated time extension WMC feels is reasonable. 1. 25 hp pump shipped with incorrect pump skid. a. All reasonable efforts were made to coordinate the details of the pump skid with the process piping based on reviews of the submittal drawings provided by the pump Supplier.However,upon arrival of the pump shipment,we identified a discrepancy in the shop drawings and the pump skid actually provided by the supplier. The discrepancy resulted in the alignment on the pump suction and discharge connections being more than 3 inches off from the alignment we had set our pump pad and process piping to match. Had the pump arrived with the proper skid,all of the other time delays could have been absorbed into the Contract Time's previously included in Change Orders and Work Change Directives to date,however given this change of conditions was only identified on December 3,2019,there was not sufficient time remaining on our contract to make 1 the adjustment. NC" i. Additional Contract Price Requested:$0.00 ,ii. Additional Contract Days Requested, 2. Pump Supplier Changed Ownership Between Design,Bidding,and Construction: a. Industrial Systems(IS)was the pump supplier for the Pear Street Booster Station.WMC understands IS was one of the suppliers AE2S worked most directly with during design. In the Summer of 2019,IS changed Ownership. Given so Hutch administrative turn-over, WMC put in extra time to work with the new business owners to coordinate the approval, manufacture,shipment,and delivery of these pumps. Though we acknowledge this change of conditions is a natural part of construction supply chains and is completely out of AE2S' or the City's control,we also feel this change is out of WMC's control and respectfully request a time extension to cover the time this change in supplier ownership caused on the project. Most directly,it was the shipment and delivery schedule provided from the pump supplier that influenced WMC's decision to start construction on September 23 rather than September 15(the day the Contract would have allowed us to start). b. Additional Contract Fee Requested: $0.00 n„ _ � /A),* c. Additional Contract Days Requested + ^'�'r�ct 3. Existing Process Pipe Alignments Differ from Project Drawing The existing process piping was"fixed"by the concrete floor penetrations and presented the following complications during the course of construction: a. Supply line in NW corner was represented as 10"in record drawings and in the Project Drawings. That line is actually 12"and required an additional reducer to replace where a new 12"valve was scheduled to be installed.This one change then matriculated down the distribution manifold and the bypass line because of the fitting dimensions. WMC will offer a Cost Deduct for the difference in cost between the Fitting and the Valve. i. Credit for Contract Fee:-$581.12 ii. Additional Contract Days Requested:3 Days b. Pump discharge lines are represented as uniform and centered r a single line. Th pipes are in fact not in any single alignment,nor are they perfectly parallel to the suction header as the drawings would imply. This required numerous changes to process pipe layout and required custom sizing fittings and spools for field installation. i. Additional Contract Fee Requested: $0.00 ii. Additional Contract Days Requested:4 Days c. Pipe supports—WMC supplied and installed pipe supports ab and beyond the umber of pipe supports specifically identified in the project drawings. These were installed at WMC's option given our expertise in field installation and support of process pipe. Additionally,the revisions included in WCD No.2,had unforeseen impacts to the pipe supports along the back wall for the PRV on the suction side supply header. i. Additional Contract Fee Requested:$0.00 ii. Additional Contract Days Requested: 0 Days d. Surge Anticipation Line orientation—plans show a pair of 45 deg angles to get the surge line out of the building. Due to the orientation of the existing bolt pattern on the existing flange—fixed by the discharge pipe penetrating through the concrete floor-this could not be built as drawn with the 45 Degree fittings already purchased. Measurements had to be taken and new fittings(tea 22.5-deg, lea 9.3-deg flange wedge)were ordered at no additional cost to the owner. ^,, i. Additional Contract Fee Requested:$!4�4 00 ii. Additional Contract Days Requested: ays 4. Changed the Location of the Electrical Light Switch. a. We submitted an RF1 for the location of the main light switch in the building that was installed per plan by our electrician. After installation,we requested the location be reconsidered as it was drawn and installed in a less then optimal location for the City's use. AE2S approved the RFI and agreed it would be more convenient for the Owner to have the switch on the other side of the door. There was no cost associated with this change and we are not requesting any additional contract days at this time. i. Additional Contract Fee Requested:$0.00 ii. Additional Contract Days Requested:0 Days i 5. Addition of security bypass switch for door contact. a. 12/9/19 John Alston asked how the door contact would be shutoff when someone enters. This is not addressed on the plans and the door contact would be live at all times,thus resulting in constant alarms and the City Shop. On 12/10/19 we had our electrician install an operational bypass switch for the door contact.There was no cost to the City associated with this change and WMC will waive any additional time this work required. i. Additional Contract Fee Requested:$0.00 ii. Additional Contract Days Requested:0 Day �L 6. 60 Ton of Aggregate added for improved site access and maintenance. a. Since being on-site,WMC purchased and laid 60TN of aggregate to improve site drainage,access,and maintenance. We did this for our workers safety,work-site and facility cleanliness,and to build and maintain a cooperative relationship with the City's neighbor to the west that has been inconvenienced by this job. WMC is not requesting j any additional payment or contract time for this project improvement,however,we hope that the City's perception of this addition is positive and shows a good-faith-effort to complete this project to the City's utmost satisfaction. i. Additional Contract Fee Requested: $0.00 ii. Additional Contract Days Requested 0 Days. If painting is also required for the City to issue WMC's Certificate of Substantial Completion,we would also request that a"Stop Work Order"be issued for the oliday Season. With the Stop Work Order, WMC would not work on site between December o January 5,2020. With the City's approval of these Contract Time Extensions and Stop Work Orders,WMC estimates that Substantial Completion would be obtained on or before January 19,2020 with Final completion achieved by February 22,2020. We have enjoyed working on this job and appreciate the open lines of communication with AE2S and the City of Bozeman Operations(John and Nick). We hope this request is fulfilled to allow us to finish this project with the utmost quality and care for the City of Bozeman. Thank you again for your time and consideration of this request. Regard , 14 Kirk Hogan Project Manager II 9 i I ii 1 I 1 1 i