Loading...
HomeMy WebLinkAbout2020-02-20_Front Street Connector Memo STAFF MEMORANDUM TO: TOP Committee FROM: Addi Jadin, Parks Planner and Development Manager CC: Mitch Overton – Director of Parks and Recreation DATE: February 14, 2020 SUBJECT: Front Street Connector – Request for Additional Funding Background: This project proposes to construct an 8-ft. wide paved asphalt path between the intersection of E. Oak St. at N. Rouse Ave. and N. Wallace Ave., linking to the Story Mill spur trail and ultimately, the Path to the M. The project is sponsored by the Gallatin Valley Land Trust (GVLT) with a grant from the Northeast Urban Renewal District and funding from Collin’s Coalition. Construction has been delayed due to MDT's Rouse Avenue construction project. Resolution 4621 A was adopted on September 28, 2015 by the City Commission approving funding in the amount of $178,106 for the project. Due to inflation, required changes in the project design and other unforeseen costs, an additional $211,531.76 is needed to complete this project. The City of Bozeman Parks and Recreation Department together with GVLT is requesting an increase from TOP Funding up to $110,681.76. Since the December meeting when the preliminary revised budget for this project was shared with the TOP Committee, GVLT has worked to secure and apply for additional funding. They have increased their financial contribution from $33,600 proposed at the outset of the project to at least $80,000.00. The additional funding includes both an increase in their grant applied for from the Recreational Trails Program (RTP), from $10,000 to $45,000 and increased funding from Collin’s Coalition and other partners. GVLT has also applied for $20,850 from the City’s Cash-in-lieu of Parkland (CILP) funding sourced from two separate development projects at the Cannery District and Northside PUD (known collectively as the Cannery District). Staff has confirmed that use of the CILP funding is appropriate and the item is scheduled for review by the Recreation and Parks Advisory Board and the City Commission in March. Amount of Additional Funding Requested: up to $110,681.76 Application Materials Under Review and Correspondence: February 20, 2020 Meeting: Front Street Revised Estimate 2020 Letters of Support December 10 Meeting: TOP Financial Report 12/10/2019 Original Application and Approval Documents: GVLT Application - Front Street Connector Pathway Resolution 4621 A adopted on September 28, 2015. Funding amount awarded by Commission: $178,106