HomeMy WebLinkAbout19- Early Work Amendment 1 to GC-CM Agreement - Martel Construction, Inc. - Bogert Pavilion Winter Stabilization EARLY WORK AMENDMENT(EWA) NO. 1
TO AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
Pursuant to Subparagraphs 3.7.1-3.7.3 and 4.12 of the Preconstruction Services Conditions Agreement
between Owner and Construction Manager this amendment dated the 18t"day of November, 2019,
between City of Bozeman ("Owner") and Martel Construction, Inc. ("Contractor")for the Bogert Pavilion
Project, hereby establishes a Guaranteed Maximum Price and Contract Time for the portion of the
Project as set forth below:
GUARANTEED MAXIMUM PRICE FOR WINTER STABILIZATION
The Construction Manager's Guaranteed Maximum Price (GMP)for the Work, including the Cost of the
Work and the Construction Manager's Fee is as follows:
General Requirements $8,047
Existing Conditions $11,931
Thermal & Moisture Protection $1,286
Fire Suppression $3,331
Electrical $500
Subtotal $25,095
General Liability Insurance $267
Gross Receipts Tax $300
Builders Risk $54
Bond $246
Construction Fee $1,498
Construction Contingency $2,510
TOTAL GUARANTEED MAXIMUM PRICE $29,970
CONTRACT TIME
The date of Substantial Completion for the Work outlined above is: December 315t, 2019
OWNER: CONTRACTOR:
City of Bozeman Martel Construction, Inc.
121 N. Rouse Ave. 1203 S. Church Ave.
Bozeman, MT 59715 Bozeman, MT 59715
By: By.
Andrea Surratt, City Ma ger Jason Martel, Executive Vice President