HomeMy WebLinkAbout08-20-19 Downtown URD Minutes
Downtown Urban Renewal District
Board Meeting Minutes
August 20, 2019
Attending: Bobby Bear, Cory Lawrence, Marley McKenna, Tony Renslow, Bill Stoddart, Kate
Wiggins, Nick Zelver, Jeff Krauss, Chris Naumann, Emily Cope
Absent: None
Public Comment: None
Chris introduced: Emily Cope as the Partnership’s District Manager; Nick Zelver as a new voting
board member; Kate Wiggins as a “new” voting board member; and Marley McKenna as a new
non-voting board member
Minutes
ACTION: Cory Lawrence moved to approve the June minutes as presented.
Nick Zelver seconded the motion.
All voted in favor.
Financial Report
Chris presented the draft year-end finances as of June 30, 2019. Revised income figures
include: $1,849, 204 year-begin balance; $423,573 TIF income; $693,000 to date but estimated
$830,000 COB Interlocal Share; $56,050 Entitlement Share; $33,777 earned interest.
Updated expense figures: $120,302 for operations; $382,194 for improvements; $155,511 for
planning; $433,573 for parking. The Board did not have any questions about the finance report.
Executive Director’s Report
Technical Assistance Program Update
Four planning grants have been awarded in FY19. One grant remains from FY2018 for the
Osborne Building. As a reminder, the Planning grants have a $7500 cap and the Façade grants
are capped at $3000.
Date Project Name Project Address Applicant Professional Type Value
4/16/2018 Osborne Building 233 East Main Strreet Casey Durham Locati Arch Plan/Façade 10,500$
Total 10,500$
Date Project Name Project Address Applicant Professional Type Value
8/20/2018 BSWB Building 106 East Babcock Randy Scully Intrinsik Planning 7,500$
8/23/2018 Garage Restaurant 451 East Main Pete Strom Intrinsik Planning 7,500$
8/28/2018 240 East Mend 240 East Mendenhall Stacy Hooks Intrinsik Planning 7,500$
4/24/2019 I-Ho's Korean Restaurant 323 West Main Derik Pomeroy Architecture 118 Planning 7,500$
Total 30,000$
Technical Assistance Program FY2018 Report
Technical Assistance Program FY2019 Report
Other Financial Program Updates
Streetscape Grants-None open Life-Safety Grants-None open
Hotel Incentive Grant-Etha Hotel—Pending
Fiber Connectivity Grant-Nova Café—Completed, ERA Landmark—Pending
Building Project Updates
Armory Hotel Substantial completion scheduled for December 31, 2019.
Black & Olive Apartments under construction to be completed Fall 2019
Osborne Building (233 East Main) 4-story mixed use building with 2 floors of restaurant
use and 2 floors of offices. Construction began October 2018.
“OSM” Building 5 story mixed use building proposed on southwest corner of Babcock
and Wallace—construction began Spring 2019
BG Mill Building 5 story mixed use building proposed on southwest corner of
Mendenhall and Broadway—final site plan submitted
One 11 Lofts (corner of North Willson and West Lamme) 50-unit apartment building with
53 parking spaces. Construction began spring 2019.
Merin Condos (on North Bozeman across from Dave’s Sushi) 28 units of owner-
occupied housing. In Final Site Plan review.
Village Downtown 84 new residential loft units have been approved and 30 new
residential condo units are under review by the City
AC Hotel (5 East Mendenhall) 6 story 140 room full-service hotel. Currently in
development review.
East End Flats (240 East Mendenhall) 6-story mixed use project. Currently in
development review.
Veranda Apartments (111 South Church) proposed new construction of 6 units.
New Businesses Update
• Good Food Company—229 East Main—restaurant to open in Osborne Building
• Blackbird Kitchen—140 East Main—former Chocolate Moose—expansion
• Chocolate Moose—25 South Willson—relocated—OPEN
• TBD—2 East Main—former Miller’s Jewelry location
• TBD—23 West Main—formerly Bent Lens
• TBD—17 East Main—formerly Sun Dog Gallery
• TBD—544 East Main—formerly Heeb’s
Planning Updates
In this section, I will provide update about several ongoing City planning processes.
Community Plan (City Growth Policy) Update
Consultants: Logan Simpson (Ft. Collins)
Update: Draft Plan is to be publicly released in September 2019.
https://www.bozeman.net/city-projects/bozeman-community-plan-update
NCOD and Design Guidelines Update
Consultants: Bendon Adams Consulting (Aspen, CO) and Orion Planning
(Missoula, MT)
Update: Final Document was released in August 2019.
https://www.bozeman.net/city-projects/ncod-review
Housing Needs Assessment and Action Plan
Consultants: Navigate, LLC Workforce Housing Solutions
Update: the draft Community Housing action plan is being drafted. There is a
public workshop for community input August 20 (11am–1pm & 5pm–7pm).
https://www.bozeman.net/city-projects/community-housing-action-plan
https://www.bozeman.net/city-projects/community-housing-needs-assessment
FEMA Floodplain Mapping Update
Next Steps:
• The final draft map will be released in 2nd quarter of 2020.
• The City then has 180 days to amend its floodplain regulations to
incorporate the new maps.
• The new regulatory floodplain map would become effective by the
beginning of 2021.
North Black Pocket Park
Construction of the North Black Pocket Park in southwest corner of Black Lot public parking lot
begins this week. The project will include three elements: create new pocket park; relocate
Black Lot egress; install new streetscape including sidewalk, streetlamps, and street trees.
AV Construction will begin work the week of August 19th with plans to complete the project in
October. Below is a basic construction schedule:
• 8/19—8/21 Mobilization and site preparations
• 8/21—9/11 Demo and excavation
• 9/3—10/7 Concrete and electrical installation
• 10/8—10/19 Landscaping installation
Discussion and Decision Items
Downtown Plan (DBIP) Updates
Chris presented an overview of the DBIP projects funded in the FY2020 URD work plan and
budget (included by below). The projects include transportation planning, code amendments,
design guidelines, and general implementation. Chris said he would periodically present an
updated version as the projects progress.
TIF Funding Plan
Chris presented an estimate of the URD’s TIF bonding capacity based on a spreadsheet
provided by the City of Bozeman Finance Department (included below). In summary, a City
Interlocal Share of $850,000, a coverage ratio of 125%, an interest rate of 5%, and a term of 11
years, the bond proceeds would be approximately $5.7 million. For context, Chris reminded the
board that the existing $6.5 million garage bond will cost the URD $10.8 million when you
include the $4.3 million of interest paid by 2032.
Chris challenged the board to start thinking about how best to invest TIF funds considering the
district will expire in 12 years and the primary objectives of the 2019 Downtown Plan. The board
agreed there would be more demands for funding than capacity which will require making some
difficult decisions.
Meeting was adjourned at 1:10 pm
2019 Downtown Bozeman Improvement Plan
URD Funded Projects
as of August 20, 2019
Transportation Planning
Scope of Work drafted with Sanderson Stewart (URD Term Contract lead) to advance the
transportation recommendations in the 2019 DBIP. Next steps are to ask City and MDT
engineering staff to review and comment on the draft SOW.
Further analysis will include:
• 3-lane Main Street with diagonal parking
• 2-way cycle track on Babcock
• ‘Super’ sharrow on Mendenhall
• Traffic signals at Black-Mendenhall and Black-Babcock
• Black bicycle corridor improvements
• Pedestrian intersection improvements at Babcock-Wallace, Babcock-Grand, and
Mendenhall-Grand
Code Amendments
Contracted with Susan Riggs, Groundprint, to draft the formal code language necessary to
advance the UDC revisions recommended in the 2019 DBIP. The Community Development
Department is planning to advance a host of proposed UDC revisions to the Planning Board in
September and then the City Commission in October.
Design Guidelines
Meeting with Marty Matsen, Community Development Director, and Phil Gonzalez, Historic
Preservation Manager, on September 4th to discuss how best to proceed and advance both the
NCOD and DBIP recommendations.
General Implementation
Renewed mySidewalk contract for State of Downtown demographic dashboard with a few
improvements and referencing the 2019 DBIP. The City Economic Development Department
contributed $1000 to renew the contract.
Estimate of Downtown TIF Bonding CapacityAFTER REAPPRAISAL - ESTIMATE 20% Reduction in Taxable Values, no New Constructioncalculated 2-15-18ALLCity & SD7City & CoCity OnlyEstimate for FY18Total Taxable Value5,098,612.00 Base Taxable Value(1,328,695.00) Incremental Taxable Value3,769,917.00 TIF Mill Levy - estimate float700.062Dollar Value of TIF2,639,176$ Less: Debt Payment(425,000)$ Uncommitted Dollars Available County Share430,594$ -$ 430,594$ -$ City Share815,471$ 815,471$ 815,471$ 815,471$ SD #7 Share968,111$ 968,111$ -$ -$ Total Uncommitted Dollars Available2,214,176$ 1,783,582$ 1,246,065$ 815,471$ Bonding Estimates Coverage Requirement 130%130%130%130% Amount for Annual Debt Service 1,703,212$ 1,371,986$ 958,512$ 627,285$ Interest Rate of Bonds5.00%5.00%5.00%5.00% Term in Years (final pmt Tax Year 2032)12121212 ESTIMATED PRINCIPAL ABLE TO BE ISSUED15,230,961$ 12,268,974$ 8,571,483$ 5,609,495$ ALLCity & SDCity & CoCity Only5.00%115,700,241$ City Only2019 UNOFFICIAL ESTIMATES850,000$ 850,000$ 125%680,000$
City of Bozeman 2007 2019
Downtown Parking Garage With Final Bond Sizing Actual Realized
& Final Buy Sell Sources & Uses
Sources of Funds:
Federal Award - Direct 1,901,339 1,901,339
Federal Award - GANS 2,123,320 2,123,320
TIF Bonds 6,280,896 6,280,896
TIF Cash 230,000 230,000
TIF Debt Service Interest 4,317,196
Investment Earnings 75,000 75,000
Sale of Commercial Space 1,290,842 1,290,842
11,901,397$ 16,218,593$
Uses of Funds:
Construction - Phase I 9,266,046 9,266,046
Construction - Phase II 1,297,710 1,297,710
Construction Services - Arch. & Inspect 190,000 190,000
Costs of Issuance of the Bonds 174,255 174,255
Debt Service Reserve Fund 426,383 426,383
Debt Service Intereste Payments 4,317,196
Equipment (& Interior Painting) ***386,000 386,000
Commercial Space Closing Costs & Appraisal 15,000 15,000
Buildout of Public Restroom Space (200/sq ft)89,600 89,600
Painting costs 20% over our $100k Estimate 20,000 20,000
Building Signage 30,000 30,000
11,894,994$ 16,212,190$
Cost per Space (435 spaces)27,344.81$ 37,269.40$
TIF Expenses/Investments 6,510,896$ 10,828,092$
NOTE: "2019" column reflective of total costs including interest upon debt retirement in 2032