HomeMy WebLinkAbout11-18-19 City Commission Packet Materials - A2. Arterial and Collector District CIP for FY21-25
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Kristin Donald, Finance Director
SUBJECT: Adopt the Arterial and Collector District Capital Improvement Plan
(CIP) for Fiscal Years 2021-2025.
AGENDA ITEM TYPE: Action
MEETING DATE: November 18, 2019
RECOMMENDATION: Adopt the Arterial and Collector District Capital Improvement
Plan (CIP) for Fiscal Years 2021-2025.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. The Public Works
Department, City Manager, and other city staff met during September - October to develop the
attached Capital Improvement Plan (CIP) for the capital needs of the Arterial and Collector
District (A&CD).
A&CD funds the local share of Street Impact Fee projects. The Impact Fee Advisory Committee
met on November 5, 2019 and approved the Street Impact fee CIP. The Committee did ask for
use to make clearer the total cost of project between the two funds. Based on this feedback we
have added a table to both showing the project fund shares and totals.
Relationship to the Strategic Plan:
• All the street projects funded by the Arterial and Collector District CIP will include bike
lanes and aid in our efforts towards item 4.5 a -Enhance Non-motorized Transportation.
322
Major Project Highlights Underway in the Prior Year:
Improvements to Baxter Lane from Davis Lane to 19th Avenue were completed in the summer
of 2019 including the addition of a signalized intersection at Baxter Lane and Davis Lane.
Improvements that will serve the new high school are under construction and will be complete
well in advance of the new high school opening including improvements to Oak Street,
Cottonwood Road, and Durston Road and major intersections in the vicinity of the new high
school.
ALTERNATIVES: As suggested by the City Commission.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY21.
Report compiled on: November 6, 2019
Attached: Arterial and Collector District CIP Section
323
ARTERIAL & COLLECTOR DISTRICT FUND FINANCIAL SUMMARY Financial Summary Current YearFY20 FY21 FY22 FY23 FY24 FY25UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 158,798$ (118,377)$ 807,071$ 903,015$ (829,681)$ 416,224$ Plus: Assessment Revenues Dedicated to CIP 1,410,808$ 1,400,131$ 1,442,134$ 1,485,398$ 1,529,960$ 1,575,859$ ‐$ Plus: Payback Revenue 522,557$ 300,667$ 300,667$ Plus: New Gas Tax dollars 655,000$ 674,650$ 688,143$ 701,906$ 715,944$ 730,263$ Plus: Contribution from High School SIF105, SIF13, SIF113 1,587,157$ Plus: Gas tax for FY19 projects 837,801$ Less: FY19 Carry Forward (2,894,498)$ Less: Scheduled CIP Project Costs (2,396,000)$ (1,450,000)$ (2,335,000)$ (3,920,000)$ (1,000,000)$ (1,376,000)$ (2,650,000)$ Projected Year‐End Cash Dedicated to CIP (118,377)$ 807,071$ 903,015$ (829,681)$ 416,224$ 1,346,346$ Beginning Balance of Payback Improvements: (2,544,666)$ (2,544,666)$ (2,243,999)$ (1,943,332)$ (1,943,332)$ (1,943,332)$ (1,943,332)$ SIF080 ‐ Gallatin County SID 300,667$ 300,667$ 300,667$ SIF080‐ Flanders Payback 221,891$ SIF113 ‐Griffin (7th to Rouse) Payback District (666,667)$ SIF114‐ Fowler Connection (Huffine to Oak) Construction PayabackDistrict (1,250,000)$ SIF117 ‐ Storymill (Griffen to Bridger) Payback District (83,333)$ SIF138‐ Cottonwood Road (Oak to Baxter) Payback District(333,333)$ Ending Balance of Payback Improvements: (2,544,666)$ (2,243,999)$ (1,943,332)$ (1,943,332)$ (1,943,332)$ (1,943,332)$ (1,943,332)$ Assumptions Made for Revenue Estimates Current YearFY20 FY21 FY22 FY23 FY24 FY25Estimated Annual Assessment Revenues* 1,333,458$ 1,333,458$ 1,400,131$ 1,442,134$ 1,485,398$ 1,529,960$ Estimated Growth Annual Increase 0% 3% 3% 3% 3% 3% Estimated Rate Annual Increase 0% 2% 0% 0% 0% 0%Total Estimated Revenues 1,333,458$ 1,400,131$ 1,442,134$ 1,485,398$ 1,529,960$ 1,575,859$ Current Revenues Dedicated to CIP % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%Total Estimated Revenues Dedicated to CIP 1,333,458$ 1,400,131$ 1,442,134$ 1,485,398$ 1,529,960$ 1,575,859$ ProjectedProjectedCURRENT$(1,450,000)$(2,335,000)$(3,920,000)$(1,000,000)$(1,376,000)$(2,650,000)FY20 FY21 FY22 FY23 FY24 FY25 UNSCHEDULEDARTERIAL & COLLECTOR PROJECTS 324
ARTERIAL & COLLECTOR DISTRICT FUND PROJECT SUMMARY Project # Project Name FY2021 FY2022 FY2023 FY2024 FY2025 UnscheduledSIF086BAXTER & COTTONWOOD (INTERSECTION IMPROVEMENTS) ‐ CONSTRUCTION‐ ‐ 500,000 ‐ ‐ ‐ SIF110MANLEY & GRIFFIN 400,000 SIF113GRIFFIN (7TH TO ROUSE) ‐ CONSTRUCTION 500,000 1,500,000 ‐ ‐ ‐ ‐ SIF114FOWLER CONNECTION (HUFFINE TO OAK) ‐ CONSTRUCTION ‐ ‐ 1,750,000 750,000 ‐ ‐ SIF116BRIDGER DR & STORY MILL RD (INTERSECTION IMPROVEMENTS) ‐ CONSTRUCTION 300,000 ‐ ‐ SIF117STORY MILL (GRIFFIN TO BRIDGER) ‐ CONSTRUCTION 250,000 ‐ ‐ ‐ ‐ ‐ SIF118BABCOCK (15TH TO 19TH) ‐ 750,000 ‐ ‐ ‐ ‐ SIF138COTTONWOOD ROAD, OAK TO BAXTER ‐ CONSTRUCTION ‐ ‐ 1,670,000 ‐ ‐ ‐ SIF145‐ 85,000 ‐ ‐ ‐ ‐ SIF 147OAK & 19TH INTERSECTION IMPROVEMENTS ‐ ‐ ‐ 250,000 500,000 ‐ SIF149BABCOCK ‐ 11TH TO 15TH CONSTRUCTION ‐ ‐ ‐ ‐ ‐ 500,000 SIF152N 27TH ‐ BAXTER TO CATTAIL ‐ ‐ ‐ ‐ ‐ 1,000,000 SIF153DURSTON & 27TH INTERSECTION IMPROVEMENTS ‐ ‐ ‐ ‐ ‐ 350,000 SIF154CATTAIL & 27TH INTERSECTION IMPROVEMENTS ‐ ‐ ‐ ‐ ‐ 300,000 SIF156HIGHLAND/KAGY INTERSECTION IMPROVEMENTS ‐ ‐ ‐ ‐ ‐ 500,000 SIF158College (8th to 19th) ‐ ‐ ‐ ‐ 876,000 ‐ Fiscal Year totals 1,450,000 2,335,000 3,920,000 1,000,000 1,376,000 2,650,000 325
Project # ProjectStreet Impact Fee FundingArterial & Collector FundingTotal Project FundingSIF086 *BAXTER & COTTONWOOD (INTERSECTION IMPROVEMENTS) CONSTRUCTION 2,000,000 500,000 2,500,000 SIF110 *MANLEY & GRIFFIN (INTERSECTION IMPROVEMENTS) 1,600,000 400,000 2,000,000 SIF113 *GRIFFIN (7TH TO ROUSE) ‐ CONSTRUCTION 3,500,000 2,000,000 5,500,000 SIF114 *FOWLER CONNECTION (HUFFINE TO OAK) 5,000,000 2,500,000 7,500,000 SIF116 *BRIDGER DR & STORY MILL RD (INTERSECTION IMPROVEMENTS) CONSTRUCTION 1,200,000 300,000 1,500,000 SIF117 *STORY MILL (GRIFFIN TO BRIDGER) 250,000 250,000 500,000 SIF118 *BABCOCK (15TH TO 19TH) 750,000 750,000 1,500,000 SIF138 *COTTONWOOD ROAD, OAK TO BAXTER 1,670,000 1,670,000 3,340,000 SIF147 *OAK & 19TH INTERSECTION IMPROVEMENTS 750,000 750,000 1,500,000 SIF149 *BABCOCK ‐ 11TH TO 15TH 1,800,000 500,000 2,300,000 SIF152 *N 27TH ‐ BAXTER TO CATTAIL 4,000,000 1,000,000 5,000,000 SIF153 *DURSTON & 27TH INTERSECTION IMPROVEMENTS 1,400,000 350,000 1,750,000 SIF154 *CATTAIL & 27TH INTERSECTION 1,200,000 300,000 1,500,000 SIF156 *HIGHLAND/KAGY INTERSECTION IMPROVEMENTS 2,000,000 500,000 2,500,000 SIF158 *COLLEGE(8TH TO 19TH)‐CONSTRUCTION 876,000 876,000 1,752,000 326
ARTERIAL & COLLECTOR DISTRICT FUND DETAIL BACKGROUND Due to the role Street Impact Fees play in the expansion of our Arterial & Collector streets, the A&CD capital plan is tied to projects on the Street Impact Fee CIP. Most projects receive funding from both sources. The District will be providing the “local share” of some projects in advance of development. The city intends to create a payback district to recover the “local share” once an adjacent project is developed. This payback will be deposited to the Arterial & Collector Fund. We have recorded the amount of “local share” payback improvements are funded each year on the Financial Summary. We anticipate that some of these payback amounts will come back to the Arterial & Collector Fund as projects develop; but for purposes of this plan, we have not relied on receiving any of that money to fund projects. Similar to the Street Impact Fee schedule, this CIP is also impacted by the development waiver policy for certain projects that are within the first 3 years of the Capital Improvements Plan and have all the necessary right‐of‐way and funding plans. The first year of assessment was FY2016 and it has increased in 2017 and 2018. The District’s revenues projections are based on the amounts that were discussed when created the district with a reduction with the increase in gas tax revenue in FY19 and no change in FY20. We are projecting a rate increase of 2% to keep up with inflation. Below are the revenue trends of the assessment and with the gas tax: 565,000 1,095,000 1,826,572 1,333,458 ‐‐221,891 708,000 565,000 1,095,000 2,048,463 2,041,458 ‐ 500,000 1,000,000 1,500,000 2,000,000 2,500,0002016 2017 2018 2019Revenue HistoryAssessmentGas TaxTotal327
CAPITAL PLAN SUMMARY Larger projects that will expand capacity to our road network are SIF 113 Griffin (7th to Rouse), which has been coordinated with MDT’s project in the area. SIF114 Fowler Connection (Huffine to Oak) scheduled for FY23 and FY24 that will increase capacity and extends an important north‐south corridor. SIF157 and SIF158 Is a project for College between 8th and 19th has been moved later in the plan due to funding and other projects. A new project was added to FY 2025 to upgrade the intersection of Oak and 19th (SIF147), which would add an additional lane to the eastbound leg of the intersection. Significant delays are observed on the eastbound leg of this intersection, and this project would improve intersection operations at this location. All the road projects funded by the Arterial & Collector District fund will include bike lanes and aid in our efforts towards the Strategic Plan 4.5 a Enhance Non‐motorized Transportation. 328
SIF155
SIF117
SIF149SIF118
SIF150
SIF138
SIF152
SIF158
SIF113
SIF155SIF009
SIF114
SIF151
SIF086
SIF116
SIF110
SIF147
SIF144
SIF153
SIF154
SIF156
FY21-25 Street Impact Fees + Arterial & Collector District
This map was created by the City of Bozeman GIS Department on 11/5/19 and is intended for planning purposes only.
¯0 0.5 10.25 Miles19th19thBaxter
Main
PeachDurston
Oak
Huffine College
Kagy
Bridger
CottonwoodFergusonFowlerS11th7thRouseChurchHighlandI90
Babcock
Oak
Griffin
DavisI90
Story MillFY21
FY22
FY23
FY24
FY25
Unscheduled
FY21
FY22
FY23
FY24
FY25
Unscheduled
A&C Project 329
Project NameYear Description Amount Total Project #BAXTER & COTTONWOOD (INTERSECTION IMPROVEMENTS) ‐ 500,000 CONSTRUCTION ‐ DESCRIPTION: ‐ IMPROVE THE INTERSECTION AT BAXTER AND COTTONWOOD. ‐ THIS INTERSECTION IS CURRENTLY 1‐WAY STOP ‐ CONTROLLED. REPLACING IT WITH A SIGNAL OR ‐ ROUNDABOUT WILL GREATLY INCREASE ITS CAPACITY. ‐ EAST‐WEST CONNECTIVITY ALREADY EXISTS AT THIS ‐ LOCATION. NORTH‐SOUTH CONNECTIVITY IS STILL ‐ LACKING. THE LEVEL OF SERVICE (LOS) STANDARD (BMC) ‐ AND CONFORMANCE WITH THE TRANSPORTATION MASTER ‐ PLAN WILL BE ATTAINED AT COMPLETION. OTHER ‐ AFFECTED PROJECTS INCLUDE COTTONWOOD CORRIDOR ‐ IMPROVEMENTS AND BAXTER CORRIDOR IMPROVEMENTS. ‐ ALTERNATIVES CONSIDERED: ‐ IDENTIFIED IN THE TRANSPORTATION PLAN UPDATE. ‐ INCLUDES INSTALLATION OF A TRAFFIC SIGNAL, ‐ ROUNDABOUT OR OTHER ADEQUATE TRAFFIC CONTROL ‐ DEVICE WHEN WARRANTS ARE MET. ‐ ADVANTAGES OF APPROVAL: ‐ INCREASED CAPACITY AND SAFETY AT THIS INTERSECTION ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ BAXTER & COTTONWOOD (INTERSECTION IMPROVEMENTS) ‐ CONSTRUCTION 2023500,000$ SIF086330
Project NameYear Description Amount Total Project #MANLEY & GRIFFIN INTERSECTION IMPROVEMENTS 400,000 DESCRIPTION: ‐ IMPROVE THE INTERSECTION CONTROL AT MANLEY & ‐ GRIFFIN. THIS INTERSECTION IS CURRENTLY 1‐WAY ‐ STOP CONTROLLED. REPLACING IT WITH A SIGNAL WILL ‐ GREATLY INCREASE ITS CAPACITY. FUTURE DEVELOPMENTS ‐ WHICH IMPACT THIS INTERSECTION AREA MAY NOT BE ‐ ALLOWED TO PROCEED UNTIL IMPROVEMENTS ARE IN ‐ PLACE. FUNCTIONALITY OF THE NETWORK AT LARGE IS ‐ DEPENDENT ON THIS ELEMENT FUNCTIONING AS INTENDED. ‐ THE INCOMPLETE TRANSPORTATION NETWORK IN THIS ‐ VICINITY IS PUTTING UNNECESSARY DEMAND ON THOSE ‐ ELEMENTS OF THE STREET NETWORK THAT ARE IN PLACE. ‐ THE LEVEL OF SERVICE (LOS) STANDARD (BMC) AND ‐ CONFORMANCE WITH THE TRANSPORTATION MASTER PLAN ‐ WILL BE ATTAINED AT COMPLETION. A PAYBACK DISTRICT ‐ OR SID MAY BE CREATED TO LEVERAGE OTHER ‐ STAKEHOLDERS. THIS PROJECT WAS MOVED TO COINCIDE ‐ WITH THE GRIFFIN CORRIDOR CONSTRUCTION & MDT'S ‐ GRIFFIN & 7TH PROJECT. ‐ ALTERNATIVES CONSIDERED: ‐ ACCEPT THE CURRENT LOS ‐ ADVANTAGES OF APPROVAL: ‐ INCREASED CAPACITY AND SAFETY AT THIS INTERSECTION ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ MANLEY & GRIFFIN INTERSECTION IMPROVEMENTS 2021SIF110400,000$ 331
Project NameYear Description Amount Total Project #GRIFFIN (7TH TO ROUSE) ‐ CONSTRUCTION PHASE 1 500,000 DESCRIPTION: ‐ CONSTRUCT W GRIFFIN CORRIDOR IMPROVEMENTS FROM N. ‐ 7TH TO ROUSE TO AN URBAN MINOR ARTERIAL STANDARD. ‐ DESIGNED IMPROVEMENTS WILL IMPROVE LOS AT THE KEY ‐ INTERSECTIONS AND WILL INCREASE CAPACITY IN THE ‐ CORRIDOR AS A WHOLE. CONNECTIVITY ALREADY EXISTS ‐ AT THIS LOCATION, IT IS CAPACITY WHICH IS BEING ‐ EXPANDED. FUTURE DEVELOPMENTS WHICH IMPACT THIS ‐ INTERSECTION AREA MAY NOT BE ALLOWED TO PROCEED ‐ UNTIL IMPROVEMENTS ARE IN PLACE. FUNCTIONALITY OF ‐ THE NETWORK AT LARGE IS DEPENDENT ON THIS ELEMENT ‐ FUNCTIONING AS INTENDED. THE INCOMPLETE ‐ TRANSPORTATION NETWORK IN THIS VICINITY IS PUTTING ‐ UNNECESSARY DEMAND ON THOSE ELEMENTS OF THE STREET ‐ NETWORK THAT ARE IN PLACE. THE LEVEL OF SERVICE ‐ (LOS) STANDARD (BMC) AND CONFORMANCE WITH THE ‐ TRANSPORTATION MASTER PLAN WILL BE ATTAINED AT THE ‐ COMPLETION OF THIS PROJECT. A PAYBACK DISTRICT OR ‐ SID MAY BE CREATED TO LEVERAGE OTHER STAKEHOLDERS. ‐ OTHER AFFECTED PROJECTS INCLUDE INTERSECTION ‐ IMPROVEMENTS AT GRIFFIN AND 7TH AND GRIFFIN AND ‐ ROUSE. ‐ ALTERNATIVES CONSIDERED: ‐ ACCEPT THE CURRENT LEVEL OF SERVICE (DO NOTHING). ‐ ADVANTAGES OF APPROVAL: ‐ THIS PROJECT WILL EXPAND THE CAPACITY OF OUR ‐ STREET NETWORK AND IMPROVE SAFETY FOR DRIVERS AND ‐ PEDESTRIANS. FACILITATES DEVELOPMENT CURRENTLY ‐ OCCURRING IN THIS PART OF THE CITY AND NETWORK ‐ PERFORMANCE OVERALL. ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ GRIFFIN (7TH TO ROUSE) ‐ CONSTRUCTION PHASE 12021500,000$ SIF113 (FY21)332
Project NameYear Description Amount Total Project #GRIFFIN (7TH TO ROUSE) ‐ CONSTRUCTION PHASE 2 1,500,000 DESCRIPTION: ‐ CONSTRUCT W GRIFFIN CORRIDOR IMPROVEMENTS FROM N. ‐ 7TH TO ROUSE TO AN URBAN MINOR ARTERIAL STANDARD. ‐ DESIGNED IMPROVEMENTS WILL IMPROVE LOS AT THE KEY ‐ INTERSECTIONS AND WILL INCREASE CAPACITY IN THE ‐ CORRIDOR AS A WHOLE. CONNECTIVITY ALREADY EXISTS ‐ AT THIS LOCATION, IT IS CAPACITY WHICH IS BEING ‐ EXPANDED. FUTURE DEVELOPMENTS WHICH IMPACT THIS ‐ INTERSECTION AREA MAY NOT BE ALLOWED TO PROCEED ‐ UNTIL IMPROVEMENTS ARE IN PLACE. FUNCTIONALITY OF ‐ THE NETWORK AT LARGE IS DEPENDENT ON THIS ELEMENT ‐ FUNCTIONING AS INTENDED. THE INCOMPLETE ‐ TRANSPORTATION NETWORK IN THIS VICINITY IS PUTTING ‐ UNNECESSARY DEMAND ON THOSE ELEMENTS OF THE STREET ‐ NETWORK THAT ARE IN PLACE. THE LEVEL OF SERVICE ‐ (LOS) STANDARD (BMC) AND CONFORMANCE WITH THE ‐ TRANSPORTATION MASTER PLAN WILL BE ATTAINED AT THE ‐ COMPLETION OF THIS PROJECT. A PAYBACK DISTRICT OR ‐ SID MAY BE CREATED TO LEVERAGE OTHER STAKEHOLDERS. ‐ OTHER AFFECTED PROJECTS INCLUDE INTERSECTION ‐ IMPROVEMENTS AT GRIFFIN AND 7TH AND GRIFFIN AND ‐ ROUSE. ‐ ALTERNATIVES CONSIDERED: ‐ ACCEPT THE CURRENT LEVEL OF SERVICE (DO NOTHING). ‐ ADVANTAGES OF APPROVAL: ‐ THIS PROJECT WILL EXPAND THE CAPACITY OF OUR ‐ STREET NETWORK AND IMPROVE SAFETY FOR DRIVERS AND ‐ PEDESTRIANS. FACILITATES DEVELOPMENT CURRENTLY ‐ OCCURRING IN THIS PART OF THE CITY AND NETWORK ‐ PERFORMANCE OVERALL. ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ GRIFFIN (7TH TO ROUSE) ‐ CONSTRUCTION PHASE 220221,500,000$ SIF113 (FY22)333
Project NameYear Description Amount Total Project #FOWLER CONNECTION (HUFFINE TO OAK) ‐ CONSTRUCTION 1,750,000 DESCRIPTION: ‐ COMPLETE THE SECTION OF FOWLER FROM HUFFINE TO OAK ‐ THIS PROJECT ALLOWS FOR EXTENSION OF FOWLER AVENUE ‐ WHICH WILL DIRECTLY INCREASE CAPACITY, AND IT ‐ EXTENDS AN IMPORTANT NORTH‐SOUTH CORRIDOR ON THE ‐ WEST SIDE OF THE CITY. FUTURE DEVELOPMENTS WHICH ‐ IMPACT THIS INTERSECTION AREA MAY NOT BE ALLOWED ‐ TO PROCEED UNTIL IMPROVEMENTS ARE IN PLACE. ‐ FUNCTIONALITY OF THE NETWORK AT LARGE IS DEPENDENT ‐ ON THIS ELEMENT FUNCTIONING AS INTENDED. THE ‐ INCOMPLETE TRANSPORTATION NETWORK IN THIS VICINITY ‐ IS PUTTING UNNECESSARY DEMAND ON THOSE ELEMENTS OF ‐ THE STREET NETWORK THAT ARE IN PLACE. CONFORMANCE ‐ WITH THE TRANSPORTATION MASTER PLAN WILL BE ‐ ATTAINED AT THE COMPLETION OF THIS PROJECT. OTHER ‐ AFFECTED PROJECTS INCLUDE INTERSECTION IMPROVEMENT ‐ ON FOWLER AT HUFFINE, BABCOCK, DURSTON AND OAK. ‐ ALTERNATIVES CONSIDERED: ‐ WAIT FOR ADJACENT DEVELOPMENT TO OCCUR AND ‐ CONSTRUCT THE ROAD INCREMENTALLY. ‐ ADVANTAGES OF APPROVAL: ‐ COMPLETES AN IMPORTANT NORTH‐SOUTH LINK IN THE ‐ TRANSPORTATION NETWORK WHICH REDUCES DEMAND ON ‐ OTHER ADJACENT CORRIDORS. ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ FOWLER CONNECTION (HUFFINE TO OAK) ‐ CONSTRUCTION 20231,750,000$ SIF114 (FY23)334
Project NameYear Description Amount Total Project #FOWLER CONNECTION (HUFFINE TO OAK) ‐ CONSTRUCTION 750,000 DESCRIPTION: ‐ COMPLETE THE SECTION OF FOWLER FROM HUFFINE TO OAK ‐ THIS PROJECT ALLOWS FOR EXTENSION OF FOWLER AVENUE ‐ WHICH WILL DIRECTLY INCREASE CAPACITY, AND IT ‐ EXTENDS AN IMPORTANT NORTH‐SOUTH CORRIDOR ON THE ‐ WEST SIDE OF THE CITY. FUTURE DEVELOPMENTS WHICH ‐ IMPACT THIS INTERSECTION AREA MAY NOT BE ALLOWED ‐ TO PROCEED UNTIL IMPROVEMENTS ARE IN PLACE. ‐ FUNCTIONALITY OF THE NETWORK AT LARGE IS DEPENDENT ‐ ON THIS ELEMENT FUNCTIONING AS INTENDED. THE ‐ INCOMPLETE TRANSPORTATION NETWORK IN THIS VICINITY ‐ IS PUTTING UNNECESSARY DEMAND ON THOSE ELEMENTS OF ‐ THE STREET NETWORK THAT ARE IN PLACE. CONFORMANCE ‐ WITH THE TRANSPORTATION MASTER PLAN WILL BE ‐ ATTAINED AT THE COMPLETION OF THIS PROJECT. OTHER ‐ AFFECTED PROJECTS INCLUDE INTERSECTION IMPROVEMENT ‐ ON FOWLER AT HUFFINE, BABCOCK, DURSTON AND OAK. ‐ ALTERNATIVES CONSIDERED: ‐ WAIT FOR ADJACENT DEVELOPMENT TO OCCUR AND ‐ CONSTRUCT THE ROAD INCREMENTALLY. ‐ ADVANTAGES OF APPROVAL: ‐ COMPLETES AN IMPORTANT NORTH‐SOUTH LINK IN THE ‐ TRANSPORTATION NETWORK WHICH REDUCES DEMAND ON ‐ OTHER ADJACENT CORRIDORS. ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ FOWLER CONNECTION (HUFFINE TO OAK) ‐ CONSTRUCTION 2024750,000$ SIF114 (FY24)335
Project NameYear Description Amount Total Project #BRIDGER DR & STORY MILL RD (INTERSECTION 300,000 IMPROVEMENTS) ‐ CONSTRUCTION ‐ DESCRIPTION: ‐ IMPROVE THE INTERSECTION CONTROL AT BRIDGER AND ‐ STORY MILL. ADDING ADDITIONAL PHASES AND ‐ IMPROVING GEOMETRY WILL INCREASE CAPACITY FOR ‐ DEFICIENT MOVEMENTS AT THIS INTERSECTION. FUTURE ‐ DEVELOPMENTS WHICH IMPACT THIS INTERSECTION AREA ‐ MAY NOT BE ALLOWED TO PROCEED UNTIL IMPROVEMENTS ‐ ARE IN PLACE. FUNCTIONALITY OF THE NETWORK AT ‐ LARGE IS DEPENDENT ON THIS ELEMENT FUNCTIONING AS ‐ INTENDED. THE INCOMPLETE TRANSPORTATION NETWORK IN ‐ THIS VICINITY IS PUTTING UNNECESSARY DEMAND ON ‐ THOSE ELEMENTS OF THE STREET NETWORK THAT ARE IN ‐ PLACE. CONFORMANCE WITH THE TRANSPORTATION MASTER ‐ PLAN WILL BE ATTAINED AT COMPLETION. OTHER ‐ AFFECTED PROJECTS INCLUDE STORY MILL, GRIFFIN TO ‐ BRIDGER DRIVE ‐ ALTERNATIVES CONSIDERED: ‐ ACCEPT THE CURRENT LOS ‐ ADVANTAGES OF APPROVAL: ‐ INCREASED CAPACITY AND SAFETY AT THIS INTERSECTION ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ BRIDGER DR & STORY MILL RD (INTERSECTION IMPROVEMENTS) ‐ CONSTRUCTION 2021300,000$ SIF116336
Project NameYear Description Amount Total Project #STORY MILL (GRIFFIN TO BRIDGER) ‐ CONSTRUCTION* 250,000 DESCRIPTION: ‐ IMPROVE STORY MILL FROM GRIFFIN TO BRIDGER. THIS ‐ PROJECT DIRECTLY INCREASES CAPACITY BY ADDING ‐ ADDITIONAL TRAVEL LANES, DEDICATED BIKE LANES AND ‐ SIDEWALKS. FUTURE DEVELOPMENTS WHICH IMPACT THIS ‐ INTERSECTION AREA MAY NOT BE ALLOWED TO PROCEED ‐ UNTIL IMPROVEMENTS ARE IN PLACE. FUNCTIONALITY OF ‐ THE NETWORK AT LARGE IS DEPENDENT ON THIS ELEMENT ‐ FUNCTIONING AS INTENDED. THE INCOMPLETE ‐ TRANSPORTATION NETWORK IN THIS VICINITY IS PUTTING ‐ UNNECESSARY DEMAND ON THOSE ELEMENTS OF THE STREET ‐ NETWORK THAT ARE IN PLACE. CONFORMANCE WITH THE ‐ TRANSPORTATION MASTER PLAN WILL BE ATTAINED AT THE ‐ COMPLETION OF THIS PROJECT. A PAYBACK DISTRICT OR ‐ SID MAY BE CREATED TO LEVERAGE OTHER STAKEHOLDERS. ‐ OTHER AFFECTED PROJECTS INCLUDE INTERSECTION ‐ IMPROVEMENTS TO STORY MILL AND BRIDGER DRIVE. ‐ ALTERNATIVES CONSIDERED: ‐ WAIT FOR ADJACENT DEVELOPMENT TO OCCUR AND ‐ CONSTRUCT THE ROAD INCREMENTALLY. ‐ ADVANTAGES OF APPROVAL: ‐ IMPROVES AN IMPORTANT NORTH‐SOUTH LINK IN THE ‐ TRANSPORTATION NETWORK WHICH REDUCES DEMAND ON ‐ OTHER ADJACENT CORRIDORS. ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ SIF117STORY MILL (GRIFFIN TO BRIDGER) ‐ CONSTRUCTION2021250,000$ 337
Project NameYear Description Amount Total Project #BABCOCK (15TH TO 19TH) 750,000 DESCRIPTION: ‐ IMPROVE BABCOCK FROM 15TH TO 19TH. FUTURE ‐ DEVELOPMENTS WHICH IMPACT THIS AREA MAY NOT BE ‐ ALLOWED TO PROCEED UNTIL IMPROVEMENTS ARE IN ‐ PLACE. FUNCTIONALITY OF THE NETWORK AT LARGE IS ‐ DEPENDENT ON THIS ELEMENT FUNCTIONING AS INTENDED. ‐ THE INCOMPLETE TRANSPORTATION NETWORK IN THIS ‐ VICINITY IS PUTTING UNNECESSARY DEMAND ON THOSE ‐ ELEMENTS OF THE STREET NETWORK THAT ARE IN PLACE. ‐ THIS PROJECT INCREASES CAPACITY DIRECTLY BY ADDING ‐ LANES, DEDICATED BIKE LANES AND SIDEWALKS. A ‐ PAYBACK DISTRICT OR SID MAY BE CREATED TO LEVERAGE ‐ OTHER STAKEHOLDERS. ‐ ALTERNATIVES CONSIDERED: ‐ WAIT FOR ADJACENT DEVELOPMENT TO INSTALL THE ‐ IMPROVEMENTS SECTION BY SECTION. ‐ ADVANTAGES OF APPROVAL: ‐ ALLOWS FOR IMPROVEMENTS TO BE MADE TO THE CORRIDOR ‐ AT A TIME MORE FAVORABLE TO THE CITY. ‐ ADDITIONAL OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING & ‐ GENERAL MAINTENANCE COSTS. ‐ BABCOCK (15TH TO 19TH) 2022750,000$ SIF118338
Project NameYear Description Amount Total Project #COTTONWOOD ROAD, OAK TO BAXTER ‐ CONSTRUCTION* 1,000,000 DESCRIPTION: ‐ CONSTRUCTION OF A 5 LANE PRINCIPAL ARTERIAL STREET ‐ ALTERNATIVES CONSIDERED: ‐ SID, PAYBACK DISTRICT, TOPS, INCREMENTAL ‐ CONSTRUCTION BY ADJACENT DEVELOPERS. ‐ ADVANTAGES OF APPROVAL: ‐ THE PROJECT WILL EXPAND THE CAPACITY AND IMPROVE ‐ THE CONNECTIVITY OF THE CITY STREET NETWORK. IT ‐ WILL IMPROVE SAFETY FOR DRIVERS AND PEDESTRIANS ‐ AND IMPROVE ACCESS TO THE SPORTS PARK. IT WILL ‐ FACILITATE DEVELOPMENT CURRENTLY OCCURRING IN ‐ THIS PART OF THE CITY. ‐ ADD OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING AND ‐ GENERAL MAINTENANCE COSTS. ‐ CHANGES FROM LAST CIP: ‐ UPDATED COSTS BASED ON LATEST CONSTRUCTION COST 670,000 DATA. COSTS ASSUME A MINIMUM 1/3 PARTICIPATION BY ‐ DEVELOPER WEST OF COTTONWOOD ROAD. ‐ KAGY/SOURDOUGH INTERSECTION IMPROVEMENTS 85,000 DESCRIPTION: ‐ CITY SHARE OF MDT PROJECT. ‐ ALTERNATIVES CONSIDERED: ‐ NONE ‐ ADDITIONAL OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING & ‐ GENERAL MAINTENANCE COSTS ‐ CHANGES FROM LAST CIP: ‐ MDT RECENTLY ADDED THIS INTERSECTION UPGRADE TO ‐ ITS CAPITAL PLAN AS A SAFETY UPGRADE. $85,000 IS ‐ THE CITY'S SHARE OF THAT UPGRADE. ‐ SIF138KAGY/SOURDOUGH INTERSECTION IMPROVEMENTS 202285,000$ SIF145COTTONWOOD ROAD, OAK TO BAXTER ‐ CONSTRUCTION20231,670,000$ 339
Project NameYear Description Amount Total Project #OAK & 19TH INTERSECTION IMPROVEMENTS ‐ DESIGN 250,000 DESCRIPTION: ‐ EASTBOUND LANE RECONFIGURATION & SIGNAL UPGRADE. ‐ ALTERNATIVES CONSIDERED: ‐ DO NOTHING. ‐ ADDITIONAL OPERATING COSTS: ‐ INCREMENTAL INCREASES, GENERAL MAINTENANCE. ‐ CHANGES FROM LAST CIP: ‐ NEW ITEM. ‐ OAK & 19TH INTERSECTION IMPROVEMENTS 500,000 DESCRIPTION: ‐ EASTBOUND LANE RECONFIGURATION & SIGNAL UPGRADE. ‐ ALTERNATIVES CONSIDERED: ‐ DO NOTHING. ‐ ADDITIONAL OPERATING COSTS: ‐ INCREMENTAL INCREASES. GENERAL MAINTENANCE. ‐ CHANGES FROM LAST CIP: ‐ NEW ITEM ‐ OAK & 19TH INTERSECTION IMPROVEMENTS OAK & 19TH INTERSECTION IMPROVEMENTS 20242025250,000$ 500,000$ SIF147 (FY24)SIF147 (FY25)340
Project NameYear Description Amount Total Project #BABCOCK ‐ 11TH TO 15TH CONSTRUCTION 500,000 DESCRIPTION: ‐ IMPROVE BABCOCK FROM 11TH TO 15TH. FUTURE ‐ DEVELOPMENTS WHICH IMPACT THIS AREA MAY NOT BE ‐ ALLOWED TO PROCEED UNTIL IMPROVEMENTS ARE IN ‐ PLACE. FUNCTIONALITY OF THE NETWORK AT LARGE IS ‐ DEPENDENT ON THIS ELEMENT FUNCTIONING AS INTENDED. ‐ THE INCOMPLETE TRANSPORTATION NETWORK IN THIS ‐ VICINITY IS PUTTING UNNECESSARY DEMAND ON THOSE ‐ ELEMENTS OF THE STREET NETWORK THAT ARE IN PLACE. ‐ THIS PROJECT INCREASES CAPACITY DIRECTLY BY ‐ ADDING LANES, DEDICATED BIKE LANES, AND SIDEWALKS. ‐ A PAYBACK DISTRICT OR SID MAY BE CREATED TO ‐ LEVERAGE OTHER STAKEHOLDERS. ‐ ALTERNATIVES CONSIDERED: ‐ WAIT FOR ADJACENT DEVELOPMENT TO INSTALL THE ‐ IMPROVEMENTS SECTION BY SECTION. ‐ ADDITIONAL OPERATING COSTS: ‐ INCREMENTAL INCREASES IN SWEEPING, PLOWING, & ‐ GENERAL MAINTENANCE COSTS. ‐ CHANGES FROM LAST CIP: ‐ NEW ITEMS. ‐ BABCOCK ‐ 11TH TO 15TH CONSTRUCTION UNSCHEDULED500,000$ SIF149341
Project NameYear Description Amount Total Project #N 27TH ‐ BAXTER TO CATTAIL 1,000,000 1,000,000$ DESCRIPTION: ‐ CONSTRUCT N 27TH TO A CITY COLLECTOR STREET ‐ STANDARD BETWEEN BAXTER AND CATTAIL. ‐ DURSTON & 27TH INTERSECTION IMPROVEMENTS 350,000 DESCRIPTION: ‐ CONSTRUCT THE INTERSECTION OF DURSTON & 27TH. ‐ ROUNDABOUT OR SIGNAL. ‐ CATTAIL & 27TH INTERSECTION IMPROVEMENTS 300,000 DESCRIPTION: ‐ CONSTRUCT THE INTERSECITON OF DURSTON & 27TH ‐ ROUNDABOUT OR SIGNAL. ‐ HIGHLAND/KAGY INTERSECTION IMPROVEMENTS 500,000 DESCRIPTION: ‐ UPGRADES TO THE INTERSECTION OF HIGHLAND AND KAGY, ‐ MOST LIKELY A SIGNALIZED INTERSECTION, TO ADDRESS ‐ LEVEL OF SERVICE. ‐ ALTERNATIVES CONSIDERED: ‐ DO NOTHING. ‐ ADD OPERATING COSTS: ‐ CHANGES FROM LAST CIP: ‐ NEW ITEM. ‐ UNSCHEDULEDHIGHLAND/KAGY INTERSECTION IMPROVEMENTS SIF156500,000$ N 27TH ‐ BAXTER TO CATTAIL UNSCHEDULEDSIF152UNSCHEDULEDDURSTON & 27TH INTERSECTION IMPROVEMENTS SIF153350,000$ UNSCHEDULEDCATTAIL & 27TH INTERSECTION IMPROVEMENTS SIF154300,000$ 342
Project NameYear Description Amount Total Project #COLLEGE(8TH TO 19TH)‐CONSTRUCTION 876,000 DESCRIPTION: ‐ REDESIGN COLLEGE, FROM 19TH TO 8TH, TO AN URBAN ‐ MINOR ARTERIAL STANDARD. THE STREET IS ALREADY IN ‐ A FAILING CONDITION AND CONTINUES TO FUNCTION; ‐ HOWEVER, EVENTUALLY THE STREET WILL BECOME ‐ DETERIORATED TO A POINT WHERE IT IS UNFEASIBLE TO ‐ MAINTAIN AND KEEP OPEN TO PUBLIC USE. THIS PROJECT ‐ WILL PROVIDE THE DESIGN FOR A CITY STANDARD STREET ‐ SECTION, WITH ADA COMPLIANT PEDESTRIAN RAMPS, ‐ PAVEMENT MARKINGS, AND SIGNAGE WHICH WILL IMPROVE ‐ PEDESTRIAN SAFETY. ALSO, NEW ASPHALT AND DRAINAGE ‐ IMPROVEMENTS WILL ELIMINATE POTHOLES AND MINIMIZE ‐ ICE BUILDUP. ADA COMPLIANCE AND MS4 PERMIT ‐ COMPLIANCE WILL BE MET AT COMPLETION. ‐ ALTERNATIVES CONSIDERED: ‐ ACCEPT THE CURRENT FAILING CONFIGURATION. ‐ ADVANTAGES OF APPROVAL: ‐ ENHANCES SAFETY AND DRAINAGE, PRESERVES PAVEMENT. ‐ ADD OPERATING COSTS: ‐ NONE ‐ COLLEGE(8TH TO 19TH)‐CONSTRUCTION 2025876,000$ SIF158343