HomeMy WebLinkAbout19- Amendment 2 to PSA - Morrison-Maierle - Capital Improvement Projects Field Survey v 'L
o }
SECOND AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
THIS SECOND AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT
FOR CAPITAL IMPROVEMENT PROJECTS FIELD SURVEY, dated June 181h. 2018 (the
"Agreement") is made and entered into this _I day of JAJLA , 20 Pay and between
the CITY OF BOZEMAN, MONTANA, a self governing municipal corporation organized and
existing under its Charter and the laws of the State of Montana, 121 North Rouse Street,Bozeman,
Montana,with a mailing address of PO Box 1230, Bozeman, MT 59771, hereinafter referred to as
"City," and MORRISON-MAIERLE, hereinafter referred to as "Contractor."
In consideration of the mutual covenants and agreements herein contained, the receipt and
sufficiency whereof being hereby acknowledged,the parties hereto agree to amend the Agreement
as follows:
1. Addition to Scope of Work. Task 600 — South 5`h Avenue, Task 700 — West Harrison
Street, and Task 800—North Bozeman Avenue have been added to the scope of services.
These tasks shall be completed using traditional survey methods and delivered to the City
of Bozeman by the end of October 2019. See Figures D and E attached.
Task 900—Parks Department on-call services has been added to the scope of services. See
Exhibit 900.
2. Addition to Payment. See Exhibits 600, 700, 800, 900 and Summary — Fee Estimate
attached.
3. Agreement still valid. All remaining terms and provisions of the Agreement remain valid.
**** END OF AGREEMENT EXCEPT FOR SIGNATURES ****
Second Amendment to Professional Services Agreement for Capital Improvement Projects Field Survey
FY 2018—FY 2021
Page 1 of 2
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and
year first above written.
CITY OF BOZEMAN, MONTANA MORRISON-MAIERLE
By �44: , �� — By L4-w '
Andrea Surratt,�City- anager Print Name: T vis e,!4f-iv
Title: ✓cE P&s;ANi
APPROVED AS TO FORM
By Z, L A
Greg-Str�, Bozeman City Attorney
1L.5W-V% s� havr��. 3 Achrl
Second Amendment to Professional Services Agreement for Capital Improvement Projects Field Survey
FY 2018—FY 2021
Page 2 of 2
S. 5th AVE.
7.4 ACRES
OLIVE
STORY
HARRISON
CURTISS
DICKERSON 9-
F'T '1
CLEVELAND
9
KOCH
ALDERSON
w
ARTHUR Z
w Z
w
z a
w
w Q ul)
Q Ln
x `n
H vi
`n STORY
vi
GARFIELD COLLEGE
-N-
HAYES HARRISON
0 200
( IN FEET )
Morrison 2880 Technology Blvd West DRAWNBY: DS CITY OF BOZEMAN CAPITOL IMPROVEMENT PROJECT NO.
!� Bozeman,MT 59718 DSGN.BY: PROJECTS FIELD SURVEY CITYSURVEY
M a i e rl e v 406.587.0721 APPR BY: BOZEMAN MONTANA
FIGURE NUMBER
vr�v v.m-m.net DATE: 0512019
engineers surveyors Planners scientists GOPIRIGIRO S.5th AVE,W.HAYES ST.TO W.OLIVE ST. D
IAOflRI50NAAAlERLE,INC.,2019
W. HARRISON ST.
4.1 ACRES - 0.4 ACRES = 3.7 ACRES @ S. 5TH AVENUE (AREA ACCOUNTED FOR IN FIG D)
............... .............................. F-1
W. HARRISON ST.
o
z
`F �14— + C9
N. BOZEMAN AVE.
2.3 ACRES
TAMARACK
�WHARRISON ST.
h'.
z O u
ASPEN
ui
Q
NOWr-41M z
w
N
O
It m
z
COTTONWOOD
-N-
0 200
( IN FEET )
PEACH
Morrison 2880 Technology Blvd West DRAWN BY: DS CITY OF BOZEMAN CAPITOL IMPROVEMENT PROJECT NO.
v Bozeman,MT 59718 DSGN.BY: PROJECTS FIELD SURVEY CiTYSURVEY
M a i e rl e ` 406.587.0721 APPR BY: BOZEMAN MONTANA
—.n-rn.net DATE: 0512019 W.HARRISON ST.-S.6TH AVE.TO S.TRACY AVE. FIGURE NUMBER
engineers- surveyors planners scientists
Cs F-1.7IROMORRISON-MNERIE,INC.2019 N.BOZEMAN AVE.-E.PEACH ST.TO E TAMARACK ST.
Exhibit 600 - Fee Estimate Morrison
City of Bozeman, MT- Capital Improvement Projects Field Survey 2018 Maierle
Prepared For: Kellen Gamradt, P.E.
Survey / Engineering Services May-2019
LaborStaff , •
Task Assigned Hours Rate Labor Cost
600-South Sth Avenue(Trad.Survey)
601.Office Research and Computations Land Surveyor II 10.00 $124.00 $1,240.00
602.Horizontal and Vertical Field Control Two Person Survey Crew 15.00 $223.00 $3,345.00
603.Topographic Field Survey Land Surveyor II 6.00 $124.00 $744.00
Two Person Survey Crew 56.00 $223.00 $12,488.00
604.Office Survev Data Processing Land Surveyor II 30.00 $124.00 $3,720.00
605.Field Survey Verifications Land Surve or II 12.00 $124.00 $1,488.00
606.Deliverables Land Surveyor II 10.00 $124.00 $1,240.00
607.Coordination-City,Utilities Land Surveyor II 8.00 $124.00 $992.00
Senior Engineer I 8.00 $155.00 $1,240.00
608.Quality Assurance/Quality Control Senior Engineer I 8.00 $155.00 $1,240.00
Senior Surve Mana er 3.00 $175.00 $525.00
LaborSubtotal- . . 10 $28,262.00
ExpensesDirect Quantity or • • • Expense
Vehicle mi 250.00 0.68 . .170.00
GPS/Total Station(days) 10.50 $240.00 2 520.00
Survey Materials(days) 10.50 $20.00 $210.00
Deliverable Package 1 $40.00 $40.00
Subtotal-Direct Expenses • •00
TotalTask • 1 11
N:\0417\082\01 Project Management\Contracts\Amendment#2\Exhibits-Engineering Fee Estimate Amend#2.xis 6/11/2019
Exhibit 700 - Fee Estimate Morrison
City of Bozeman, MT- Capital Improvement Projects Field Survey 2018 Maierle
Prepared For: Kellen Gamradt, P.E. qb" w••r= p4mww 'm"""
Survey / Engineering Services May-2019
Staff Labor Labor Total
Task Assigned Hours Rate Labor Cost
700-West Harrison Street(Trad.Survey) Ll
701.Office Research and Computations Land Surveyor II 4.00 $124.00 $496.00
702.Horizontal and Vertical Field Control Two Person Survey Crew 7.00 $223.00 $1,561.00
703.Topographic Field Survey Land Surveyor II 3.00 $124.00 $372.00
Two Person Survey Crew 28.00 $223.00 $6,244.00
704.Office Survey Data Processing Land Surveyor II 14.00 $124.00 $1,736.00
705.Field Survey Verifications Land Surveyor II 6.00 $124.00 $744.00
706.Deliverables Land Surveyor II 4.00 $124.00 $496.00
707.Coordination-City,Utilities Land Surveyor II 3.00 $124.00 $372.00
Senior Engineer I 4.00 $155.00 $620.00
708.Quality Assurance/Quality Control Senior En ineer I 4.00 $155.00 $620.00
Senior Survey Mana er 2.00 $175.00 350.00
Subtotal- Labor Costs 79.00
ExpensesDirect Quantity or • • • Expense
Vehicle mi 100.00 8 . 66.00
GPS/Total Station(days) 5.00 0 1 200.00
SurveyMaterials(days) 5.00 0 75.00
Deliverable Package 1 Ntr3snn 1 $35.00
ExpensesSubtotal-Direct
Task Total-West Harrison Street •' 11
N:\0417\082\01 Project Management\Contracts\Amendment#2\Exhibits-Engineering Fee Estimate Amend#2.xls 6/11/2019
Exhibit 800 - Fee Estimate �t Morrison
City of Bozeman, MT- Capital Improvement Projects Field Survey 2018 oll Maierle
Prepared For: Kellen Gamradt, P.E. 01- --"1--P,
Survey / Engineering Services May-2019
Staff Labor Labor Total
Task Assigned Hours Rate Labor Cost
800-North Bozeman Avenue(Trad.Survey) Ll
801.Office Research and Computations Land Surveyor II 3.00 $117.00 $351.00
802.Horizontal and Vertical Field Control Two Person Survey Crew 4.00 $210.00 $840.00
803.Topographic Field Survey Land Surveyor II 2.00 $117.00 $234.00
Two Person Survey Crew 18.00 $210.00 $3,780.00
804.Office Survev Data Processing Land Surveyor II 12.00 $117.00 $1,404.00
805.Field Survey Verifications Land Surveyor II 4.00 $117.00 468.00
806.Deliverables Land Surveyor II 3.00 $117.00 $351.00
807.Coordination-City,Utilities Land Surveyor II 2.00 $117.00 $234.00
Senior Engineer I 3.00 $146.00 $438.00
808.Quality Assurance/Quality Control Senior Enciineer I 3.00 $146.00 $438.00
Senior SurveM Mana er 1.50 $167.00 $250.50
Subtotal- Labor i
ExpensesDirect Quantity or •n Charge Rate
.• Expense
hiclemi Ve 100.00 0.70 70.00
GPS/Total Station(days) 3.75 240.00 900.00
SurveyMaterials(days) 3.75 15.00 56.25
Deliverable Package 1 $35.00 $35.00
ExpensesSubtotal-Direct 0.
Task Total-North Bozeman Avenue $9,849.75
N:\0417\082\01 Project Management\Contracts\Amendment#2\Exhibits-Engineering Fee Estimate Amend#2.xis 6/11/2019
Morrison
Maierle
engineers surveyors planners scientists
Exhibit 900 - Scope of Services
Capital Improvement Projects Field Survey
2018 - 2021
Task 900 - Parks Department on-call services
Task 900 to be completed as requested.
A combination of sub-tasks may be used to complete the requested work.
Estimated effort to be determined at time of defined scope. A budget of$1,500.00 is placed for
Task 900. Actual effort to be separately billed as time and materials not to exceed$1,500.00
without prior written approval from the City of Bozeman.
1
Exhibit Summary - Fee Estimate Morrison
City of Bozeman, MT-Capital Improvement Projects Field Survey(2018) Maierle
Prepared For: Kellen Gamradt, P.E. "°'"''"""'°"'0---
Summary - Survey / Engineering Services May-2019
Total Total
Task Acres cost
100-West Koch Street Scanned Surve 5.7 H
200-North TracyAvenue Scanned Survey) 1.8
300-North 17th Avenue Scanned Survey) 2.8
400-North Bozeman Avenue rad.Survey) 2.9
500-Augusta Drive rad.Survey) 2.5
600-South 5th Avenue rad.Survey) 7.4
700-West Harrison Street rad.Survey) 3.7
800-North Bozeman Avenue(Trad.Survey) 2.3 $9,849.75
900-Parks Deriartment on-call services N A 1 500.00
Total Project Cost 29.1 $119,936.00