HomeMy WebLinkAbout19- Change Order 4 - Montana Civil Contractors, Inc. - 5.3 MG Water Storage Tank CHANGE ORDER
No. 4
DATE OF ISSUANCE June 25th,2019 EFFECTIVE DATE Upon Owner Authorization
OWNER City of Bozeman CONTRACTOR Montana Civil Contractors, Inc.
Contract: Dated May 5` , 2017
Project: 5.3 MG Water Storage Tank OWNER's Contract No.
ENGINEER Robert Peccia&Associates ENGINEER's Contract No. 14702
You are directed to make the following changes in the Contract Documents:
Description:
1) Tank Electrical Panel Support is an increase of$1,830.15.
2) Re-Route Water Sample Line is an increase of$17,821.00.
3) Time extension: 3 calendar days for change order related work and 8 weather calendar days= 11 total
calendar days.
Reason for Change Order: Changes during construction to the contract.
Attachments: Montana Civil Contractors Inc. —Change Order/Price Increase Summary
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times:
Substantial Completion: 300 calendar days
$ 7,665,349.00 Ready for final payment:
(days or dates
Net(Increase)from previous Net change from previous Change Orders No. 1 to No.
Change Orders No. 1 to 3: 3
Substantial Completion: 39 calendar days
$36,719.74 Ready for final payment:
(days)
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: 339 calendar days
$ 7,702,068.74 Ready for final payment:
(days or dates
Net(Increase)of this Change Order: Net(increase)this Change Order:
Substantial Completion: 11 calendar days
$ 19,651.15 Ready for final payment:
(days)
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
Substantial Completion: 350 calendar days
$7,721,719.89. Ready for final payment:
(days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or
omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and
set forth herein and unless ex ressly stated otherwise in the Change Order. And further,that the price agreed-upon
herein represen full co and value for the subject work performed and the materials supplied under the terms
0 ontract nd tha e ork quantities and value were properly determined and are correct.
ONTRAC (A orized Signature) Date
RECO NDED BY: APPROVED BY•
0Ll
GINEER- S' ature) Date OWNER(Authorized Signature) Date
CHANGE ORDER FORM
Page 1 of 2
CHANGE ORDER
INSTRUCTIONS
A. GENERAL INFORMATION
This document was developed to provide a uniform format for handling contract changes that affect Contract
Price or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into
a subsequent Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The
practice of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes.
If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times,
a Field Order should be used.
B. COMPLETING THE CHANGE ORDER FORM
Engineer normally initiates the form, including a description of the changes involved and attachments based upon
documents and proposals submitted by Contractor, or requests from Owner,or both.
Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval,
depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated
agreement for a previously performed change. After approval by one contracting party, all copies should be sent
to the other party for approval. Engineer should make distribution of executed copies after approval by both
parties.
If a change only applies to price or to times,cross out the part of the tabulation that does not apply.
CHANGE ORDER FORM
Page 2 of 2
� Montana
civil
ContTactors Inc.
P.O. Box 1019, Belgrade, AIT59714 wini%nionlanaciviL con? T.•406-388-1740 1;: 406-388-510.5
Change Order/ Price Increase
Project: 5.3 MG Water Storage Tank Date: 6— 14-2019
Dear Chris,
In reference to the requested changed/added work items per conversations between
RPA and Montana Civil Contractors, we are pleased to provide the City of Bozeman with the
prices and items below.
• Item One: Tank Panel Upright
o Tank site panel (Detail 3 Sheet E-1) changed to (2)4"galvanized rigid conduit
upright supports with galvanized channel attached horizontally for panel mounting.
Posts poured in bagged concrete mixed on site. Pedestal built oversized to
accommodate future needs.
■ Price includes:procurement and installation of materials, labor and
equipment.
Revised Tank Panel Up ri ht
Vertex Electric 1 $1,743.00 5% Markup $1,830.15
Revised Tank Panel Upright $1,830.15
• Item Two: Re-Route of Fluoride Sample Line
o Additional excavation, placement, and backfill of added length of buried fluoride line
from Flowmeter vault to northwest corner of building.
o Excavation and exposure of west foundation wall. Excavation will be sized properly
to accommodate safe access for subcontractor and drill.
o Core Drill Exterior wall with 5" core drill
0 4.5" Steel casing driven through concrete screen rock (as shown in planset provided
to MCC from RPA)to interior sump pit wall. Screen rock inside casing will be
removed.
o Core drill interior wall with 4" core drill and extension into sump pit.
0 3" Schedule 40 pvc pipe to be installed in casing.
0 3" Schedule 40 pvc pipe will then be attached to sump pit wall, ran down to the floor
and along edge of wall approximately 20' and terminated.
o Exterioer and Interior spacing around steel casing and 3" schedule 40 PVC will be
grouted.
o Exterior excavation for coring will be backfilled and surface graded.
• Equipment Break Down;
• Caterpillar 320 Excavator
• Wacker Neuson Trench Compactor
• John Deere 644K Loader
• Jumping Jack
• Misc. Small Tools
Montana
Civil
Contractors Inc.
• Crew Break Down;
• Superintendent
• Part Time PM
• Operators
o Price Break Down;
• Materials Procurement
• Steel Casing, PVC pipe, Grout, Hardware
Materials
Steel Casing $400.00 15% Markup $460,00
Sch. 40 PVC $50.00 15% Markup $57.50
Pipe/Bends/Glue
Grout&Tools $150.00 15% Markup $172.50
Brackets & Fastners $100.00 15% Markup $115.00
Misc. $100.00 15% Markup $115.00
$920.00
Excavate/Set/BF Additional Sections & Piping
320 Excavator 22 hrs $125.00 $2,750.00
Loader 22 hrs $105.00 $2,310.00
Trench Compactor 22 hrs $48.00 $1,056.00
Operator 55 hrs $113.00 $6,215.00
* Labor wage includes overtime
$12,331
Finish Grade Area
320 Excavator 2 hrs $125.00 $250.00
700 Dozer 1 hrs $105.00 $105.00
Loader 1 hrs $105.00 $105.00
Trench Compactor 2 hrs $48.00 $96.00
Operator 6 hrs $113.00 $678.00
* Labor wage includes overtime
$1,234.00
Overhead/Subcontractor Support
Superintendent 22 hrs $110.00 $2,420.00
Project Manager 4 hrs $110.00 $440.00
320 Excavator 2 hrs $125.00 $250.00
I Montana
Civi[
Contractors Inc.
Operator 2 hrs $113.00 $226.00
* Labor wage includes overtime
$3,336.00
Fluoride Sample Re-Route $17,821.00
Change Order#3 Total $19,651.15
Time Extension request: 3 contract calendar days
erely,
en Str
Montana Civil Contractors
CIVIL ENGINEERING I PLANNING I SURVEYING I LANDSCAPE ARCHITECTURE
ROBERT PECCIA & ASSOCIATES
July 8th, 2019
Bob Murray—City Engineer
City of Bozeman Public Works
20 East Olive, P.O. Box 1230
Bozeman, MT 59771
RE: 5.3 MG Water Storage Tank—Change Order#4 Summary
Bob,
Please see the Summary of Change Order#4 below.
Item#1 —Tank Electrical Panel Support: RPA agrees with this item for$1,830.15. We feel this
electrical panel support is an upgrade and matches the panel supports used at the water treatment
plant site.
Item#2—Re-route Water Sample Line: RPA agrees with this item for$17,821.00 and 3
calendar days. The location of the existing water sample line to be connected onto was shown
incorrectly on the as-builts. The contractor attempted to locate the water sample line with
excavation equipment to no avail. RPA, MCC, and water treatment plant staff worked together
to come up with an alternative plan for bringing the water sample line into the treatment
building.
Item#3 - Time Extension: 3 calendar days for C.O. work+ 8 weather calendar days due to rain
= 11 extra calendar days.
Please call me if you have any questions.
Sincerely,
ROBERT PECCIA&ASSOCIATES
Chris Hayes, P.E.
Project Manager
wvvw.rpa-hin.com