HomeMy WebLinkAbout19- Change Order 4 - Williams Brother Construction - WRF Small Works Project Change Order No. 04
Date of Issuance: 6/3/2019 Effective Date: 6/3/2019
Owner: City of Bozeman Owner's Contract No.:
Contractor: Williams Brother Construction Contractor's Project No.:
Engineer: HDR Engineering Engineer's Project No.:
Project: Bozeman WU Small Works Project Contract Name:
The Contract is modified as follows upon execution of this Change Order:
Description: Includes CPR No. 11
Attachments: CPR's No. 11
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES
[note changes in Milestones if applicable]
Original Contract Price: Original Contract Times:
Substantial Completion: April 14, 2018
$ 838,800.00 Ready for Final Payment: May 4, 2018
days or dates
Increase from previously approved Change Orders No. 1 Increase from previously approved Change Orders No.
to No. 3 to No. 3 :
Substantial Completion: July 2, 2019
$ 354,074.63 Ready for Final Payment: July 21, 2019
days or dates
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: July 2, 2019
$1,192,874.63 Ready for Final Payment: July 21, 2019
days or dates
Increase of this Change Order: Increase of this Change Order:
Substantial Completion: 0
$11,689.00 Ready for Final Payment: 0
days or dates
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial Completion: July 2, 2019
$ 1,204,563.63 Ready for Final Payment: July 21, 2019
days or dates
RECOMMENDED: ACCEPTED: ACCEPTED:
By: By: IrBy.:,
EPir f required) Owner(Authorize n ure) ont for Authorized Signature)
Title: Project Manager Title: � Title:
Date: 6/3/2019 Date c�� s , �j)� Date
EJCDC'C-941,Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Page 1 of 1
FRONT[ER
e ectric
Bozeman WWTP Boiler install
Prepared By: Robert Levandowski Work: 406-438-1789
118 6ch Ave. Cell: 406-431-3368
Havre, MT. 59501 Fax: 406-443-1789 Email
Engineer: HDR Project: Dated:
Frontier Electric will be pleased to perform all Conduit Installation, Wire Pulls, and Points Terminations,
for the above referenced project in Bozeman, Montana.
Work listed is by our discussion with Coralynn:
Conduit and wire from temp probe to the boiler.
Install Boiler emergency shutdown at three doors (incorporate with the existing):
New contacts, or push buttons, Tray cable, Boxes, cord grips. Reroute existing boiler shutdown cabling,
New conduit run may be needed.
Pump
The Circulation pump control circuits are 24 volts so we can run the following in the existing control
conduit between the Circ pump and boiler.
1-2 wire#16 shielded cable ran between pump and Boiler for pump run command.
1-2 wire#16 shielded cable ran between pump and Boiler for pump speed command.
1-2 wire#16 shielded cable ran between pump and Boiler for future Modbus communication.
We still need 1 pair of discrete wires from SCADA to pump in existing power conduit to circulator.
Boiler
Install one Ethernet cable in existing control conduit from SCADA to Boiler
Install one shielded 2 wire #16 cable in existing control conduit for future use.
Boiler Install Parts $ 5298.00 l ,
Boiler Install Labor $ 5525.00
Price Includes:
Exclude:
Total Bid: $10,823.00
Acknowledge Addendums:
1
FRONTIER
e ectric
Frontier Electric Essentials:
Montana Contractor# 163033
Mt Electrical Contractor ELE-CO-LIC-2505
MDT listed DBE 0295 Expires 31 OCT 2020
Member NFPA
Member IEC
Honorary Board Member MT Chapter IAEI
Employees have 30-hour OSHA certificates.
2