Contract Change Order Proposal
Date:JApril 17,2019 Change Order#2
From: FieldTurf USA,Inc. To: City of Bozeman,Montana
175N Industrial P.O.Box 1231
Calhoun,GA 30701 Bozeman,MT 59771-1231
Phone:1 800 724 2969
Project: Bozeman Sports Park Contact: Mitchell Overton,Director Parks&Rec
Construction Agreement Phone: 406.582.3222
4600 Baxter Lane Fax:
Bozeman,MT59718 Email: Moverton@ BOZEMAN.NET
Original Contract: $ 796,396.58
Previous Change Orders: $ 428,831.71
Current Change Order: $ 262,418.00
Revised Contract Total: $ 1,487,646.29
Additional Pricing&Scope per plan set dated 08/24/18.Work is outside of synthetic turf fields and within
grading limits of plans.
Scope of Work to be Added to Contract:
-Strip&Respread topsoil outside of synthetic turf fields and within grading limits.Topsoil that is stripped
onsite will be reused/respread onsite.
Site grading to proposed grades per plans(outside of synthetic turf fields and within grading limits).
-Grade for new asphalt path and aggregate trails
Furnish&install asphalt area geotextile,aggregates and paving
Furnish&install trail aggregates
Fine grading of topsoil and aggregates placed
Description Total Cost
Strip existing topsoil outside of synthetic field and within grading limits and stockpile.
Res read existing stockpiled topsoil upon completion of project. Fine grade. $ 46,283.07
Site Grading to proposed grades per plans-outside of synthetic turf fields and within grading
limits. $ 38,175.46
Asphalt area excavation and trail excavation. $ 35,803.13
Asphalt area geotextile,aggregates and paving. $ 115,319.25
Trail aggregates. $ 22,958.99
SUBTOTAL: $ 258,539.90
PERFORMANCE&PAYMENT BOND: $ 3,878.10
TOTAL: $ 262,418.00
Notes/Exclusions: Does not
include hazardous materials,export of excess materials offsite,dewatering,permits,testing,screening of topsoil,
importing of topsoil,irrigation,drywells,fencing,seeding,turf establishment,any restoration other than listed
above. Quote is valid for
thirty(30)calendar days
The Contract Time will be increased by_20_days.
It is mutually agreed that for the above-referenced changes to take place,the original contract price will be adjusted by the
above-referenced amount,which will become payable in accordance with the same terms and conditions as in the original
contract or purchase order:
$ 262,418.00
If all the terms of this change order are acceptable please have an authorized representative sign the bottom of this document
and return it to FieldTurrs Montreal office,or as otherwise provided in the contract documents.FieldTurf will,in turn,provide
a fully executed copy for your records.Once this document is fully executed,it will be considered a revision/modification to
the original contract or purchase order.
FieldTurf USA,Inc. City of Bo
uth ' eman,Montana
d epre entative 1�_3&zed Repre11senta've
Date Date