*CONTRACT NAME: Modification # 1 to County Contract with LSC Transportation
Consultants
*BRIEF DESCRIPTION OF CONTRACT: Contract for Feasibility Assessment of a Pro Dosed
Public Transportation System
If this contract amends or is a change/task order to a previous contract, provide original contract #.
*ORIGINAl CONTRACT #: ~6f)~7
*RESPONSIBLE DEPARTMENT: Grants & Proiects Administration
*ACCOUNT #: ~qDD ~ *CONTRACT AMOUNTIf { :2-, 4:-L3
I
*EFFECTIVE DATE: ~ / - *EXPIRATION DATE: ~_/_
*DATE SIGNED BY OUTSIDE PARTIES: _/ /_;~ /_;~ /-
CAO APPROVED (For Dept. Heads Only): DATE: ~ /-
FISCAL OFFICER APPROVED: DATE: 2- /~/~
COUNTY ATTORNEY APPROVED: DATE:L / 2-Lj /~
DATE SIGNED BY BOARD OF COUNTY COMMISSIONERS: ~/ Cj57 / ~
CLERK AND RECORDER KEEPS AN ORIGINAL AND WILL ROUTE A COpy OF
THE APPROVED CONTRACT TO THE FOLLOWING DEPARTMENTS:
./ RESPONSIBLE/ORIGINATING DEPARTMENT
" bEPUTY COUNTY ATTORNEY'S OFFICE - ATTN: HELEN BALDWI~ ~ r;2) "Vl
./ AUDITOR ~ L~- U
./ FINANCE DEPT.
DATE CLERK AND RECORDER DISBURSED COPIES: fli!;2J!IEi.-/cp0 /_
THE RESPONSIBLE/ORIGINATING DEPARTMENT IS REQUIRED TO MAIL
COPIES AND/OR DUPLICATE ORIGINALS OF COMPLETED CONTRACTS
TO ALL INTERESTED PARTIES.
. t
MODIFICATION TO CONTRACT DOCUMENTS
CHANGES IN PHASE TWO SCOPE OF WORK AND FINANCIAL
COMPENSATION
This addendum to contract documents dated March 31, 2004, by and between Gallatin
County, a political subdivision of the State of Montana, with an address of 311 West
Main Street, Bozeman, MT 59715, hereinafter referred to as "County" and LSC
Transportation Consultants, Inc. with an address of 516 North Tejon Street, Colorado
Springs, CO 80903.
WHEREAS, Gallatin County and LSC Transportation Consultants entered into certain
contract documents as defined below, beginning on the 31 st day of March, 2004 for
specific services to be performed to conduct a comprehensive assessment of a Proposed
Public Transportation System; and
WHEREAS, upon completion and acceptance of Phase I of the contract the County
desires to make changes to the remaining Phase II portion of the project; and
WHEREAS, the Contractor has developed changes in the scope of work and financial
compensation for Phase II that have been found to be acceptable to the County; and
WHEREAS, the County and LSC Transportation Consultants, Inc. are desirous of
facilitating a modification to the contract that will facilitate the proposed changes.
1. PHASE II SCOPE OF WORK
The project activities defined as being Phase 11 of the contract have been
modified and are attached to this agreement as AttacIunent A.
2. COMPENSATION. Total compensation to LSC Transportation Consultants
will be in amount not-to-exceed $49,978 as described in detail as Attachment
"A" to this document. The Phase II portion of this compensation will be in an
amount not-to-exceed $12.423.
..
c::::;;;;;;:<';-;;;; ~"-- :;.K _~
Title: ~ ,.....: .j>c./ Date: .:l//ro~
t ,
MODIFICA TION TO CONTRACT DOCUMENTS
CHANGES TN PHASE TWO SCOPE OF WORK AND FINANCIAL
COMPENSA nON
This addendum to contract documents dated March 31, 2004, by and between Gallatin
County, a political subdivision of the State of Montana, with an address of 311 West
Main Street, Bozeman, MT 59715, hereinafter referred to as "County" and LSC
Transportation Consultants, Inc. with an address of 516 North Tejon Street, Colorado
Springs, CO 80903.
WHEREAS, Gallatin County and LSC Transportation Consultants entered into certain
contract documents as defined below, beginning on the 31 st day of March, 2004 for
specific services to be performed to conduct a comprehensive assessment of a Proposed
Public Transportation System; and
WHEREAS, upon completion and acceptance of Phase I of the contract the County
desires to make changes to the remaining Phase II portion of the project; and
WHEREAS, the Contractor has developed changes in the scope of work and financial
compensation for Phase II that have been fouod to be acceptable to the County; and
WHEREAS, the County and LSC Transportation Consultants, Inc. are desirous of
facilitating a modification to the contract that will facilitate the proposed changes.
1. PHASE II SCOPE OF WORK
The project activities defined as being Phase II of the contract have been
modified and are attached to this agreement as Attachment A.
2. COMPENSATION. Total compensation to LSC Transportation Consultants
will be in amount not-to-exceed $49.978 as described in detail as Attachment
"A" to this document. The Phase II portion of this compensation will be in an
amount not-to-exceed $12.423.
..
CONSULTANT
... -~';;; ~-~_/~
.:::. ; A
Title: ~,.....<. '1'41 Date: .2.f'a/d ~
.
Table 3
Phase One Project Cost Estimate
Labor: Technical Clerical
Stoddard Donahue Spielberg Support Support TOTAL
Task 1: Project Administration 4 2 6
Task 2: Public Involvement Program 16 20 4 4 44
Task 3: Prepare Community Profile 4 24 4 32
Task 4: Community Telephone Survey 12 8 4 24
Task 5: Identify Transit Demand 4 12 4 4 24
Task 6: Develop Strategic Plan 12 12 2 26
Task 7; Evaluate Transit Service Scenarios 12 8 12 8 8 48
Task 8; Phase One Report 12 8 4 8 8 40
0
Total Hours 76 72 36 24 36 244
Direct Labor Rate $47.79 $23.89 $49.50 $22.00 $18.25
Direct Labor Cost $3,632 $1,720 $1,782 $528 $657 $8,319
Overhead $5,375 $2,546 $2,441 $781 $972 $12,116
Labor Subtotal $20,435
Direct Costs:
Item Cost
Travel $3,700
Per Diem $1,500
Printing/Copying $930
Telephone Survey $8,696
Courier/Postage $150
Telephone $100
Direct Costs Subtotal: $15,076
Fee (10 % of Labor) $2,044
Total Estimate: $37,555
..
. ,
Table 4
Phase Two Project Cost Estimate
Labor: Technical Clerical
Stoddard Donahue Spielberg Support Support TOTAL
Task 1: Project Administration 4 1 5
Task 9: Organizational Structure 8 8 8 2 26
Task 10: Financial Plan 8 16 2 26
Task 11: Implementation Plan 12 16 8 4 40
Task 12: Phase Two Report 4 16 2 4 26
0
Total Hours 36 56 18 0 13 123
Direct Labor Rate $47.79 $23.89 $49.50 $22.00 $18.25
Direct Labor Cost $1,720 $1,338 $891 $0 $237 $4,187
Overhead $2,546 $1,980 $1,221 $0 $351 $6,098
Labor Subtotal $10,285
Direct Costs:
Item Cost
Travel $640
Per Diem $250
Printing/Copying $120
Courier/Postage $50
Telephone $50
Direct Costs Subtotal: $1,110
Fee (10 % of Labor) $1,028
Total Estimate: $12,423
"
,
ATTACHMENT A
Scope of Work
LSC proposes the following specific approach to the project based on our undcrstanding of
Gallatin County's RFP and successful experience with other similar projects. A detailed Work
Plan is included to complete the public transit feasibility study. The overall approach will
include the collection of data, assessment of needs, identification of existing resourccs,
develQpment of alternatives to provide service, and recommendation of implementation actions.
The team will work closely with local staff to complete each proposcd task. We have found
through experience in previous transit planning studies that this manncr of approaching the
proposed Work Plan provides for a cost-effective use of resources as well as allowing the client
staff to keep well apprised of our progress.
~ Task 1: Project Administration and Coordination
Purpose: To ensufC coordination between the County Project Director and the LSC
Project Manager.
Approach: We will submit a monthly progress report with a detailed invoice. The progress
report will describe the work completed during thc previous month, the
percentage completed for each task, any problems cncountered and the resolu-
tion, and the anticipated work during the coming month.
LSC will develop and provide a list of data items nceded for the study. An initial
"kick-off' meeting will be held in Bozeman among the Consultant Team, the
Project Team, and others at the discretion of the local Project Director.
Goals for the "kick-off' meeting include:
. Review the data list to identify missing itcms and to decide a
course of action to collect or develop additional data.
. Finalize public involvement process to be used for the project
such as strategies to be used with various interest groups and
meeting dates.
The Project Manager will also be in regular contact with the Gallatin County -
.. Project Director to discuss aspects of the work program. This will include
progress on upcoming interim reports, coordination of on-site activities, and
scheduling meetings.
Product: The end product of this task will be the ongoing coordination throughout the
project.
LSC
Gallatin County Public Transportation System Assessment Page 1
.
PHASE ONE: PUBLIC OUTREACH
/iliiIiilI Task 2: Public Involvement Program
Purpose: To provide opportunities for community involvement in preparing the public
transportation needs study.
Approach: We propose to use a variety of techniques to involve the community in the
evaluation of transportation needs.
We propose to work with the Public Transit Stakeholders Advisory Board
throughout the project. These stakeholders should represent a cross section of
the community and provide input regarding nceds of their constituencies.
We will prepare a summary brochure to be distributed at key points during the
project. These will include an outline of the proposed strategic plan, the transit
service scenarios, and the draft service recommendations. We will preparc and
print the brochures for distribution. Distribution should include places for dis-
semination of public interest information. We will also develop a mailing list of
interested individuals and agencies and will send the information brochures to
everyone on the mailing list.
Public meetings will be held at key points during the project. The first meeting
will bc an informational meeting to bc held early in the course of the project.
This will be an opportunity for community residents to identify issues and pro-
vide input on transportation needs. The first open house will be conducted at one
or more community locations such as a grocery store, the library, or the mall.
Several locations will be scheduled on one or two consecutive days.
The second public meeting will be a workshop to present elements of the
strategic transit plan and to reccive comments from the community on the
strategic transit plan. At this time we will also attend a chamber of Commerce
"Business After Hours" meeting to present the strategic plan. These two
meetings should be scheduled on the same day.
The third public meeting will be held to present the Phase One Draft Report and
receive public comment.
LSC will prepare a questionnaire to be sent by email to MSU students. The
University will be responsible for sending the email. The questionnaires will be
.~ returned to LSC for compilation and analysis.
We also propose to provide a toll-free telephone number which may be used to
contact members of the consultant team. Project reports will be posted on the
Internet for easy access by community residents. Citizens will have the oppor-
tunity to provide comment directly to the consultant team bye-mail. We have
found dissemination of project reports via the Internet to be a vcry effective
LSC
Gallatin County Public Transportation System ASSessment Page 2
.
means of reaching many members ofthe community. Residents may use either
their own computers or access the Internet at the local library.
Product: This task will provide the opportunity for involvement of local citizcns in the
planning process.
~ Task 3: Prepare Community Profile
Purpose: To compile a database of current community economics and demographics.
Approach: LSC proposes to include an updated demographic analysis of the Gallatin
County area. The 2000 census data will be used as base data; and the updated
census data from the local planning staff, social services agencies, and state
agencies will be uscd as available. The analysis will rcflect the most recent
information for the following:
. General population
. Youth (age IO to 15)
. Elderly persons (65 years of age and older)
. Persons with disabilities
. University students
. Automobile availability
. Income
. Employment
Maps will be prepared for each of the demographic characteristics listed above
using ArcView GIS software.
In addition, LSC will collect updated information concerning major transit trip
generators such as elementary schools, middle schools, high schools, social
service program sites, hospitals, shopping centers, recreation areas, and
employment centers. We will review local planning documents to identify
potential new areas of transit demand within the community.
This task will provide the baseline information which will be used to estimate
public transportation needs and to establish areas of the community which
should be given priority for transportation services.
Product: The results of this task will be presented as part of Working Paper #1.
~ Task 4: Conduct Community Telephone Survey
Purpose: The purpose of the community telephonc survey is to identify needs of the local
residents and attitudes or pcrceptions regarding public transportation service and
the willingness to fund the service.
LSC
Gallatin County Public Transportation System Assessment Page 3
~ ,
Approach: The team recommends conducting a lO-minute random digit dial (RDD) tele-
phone survey of residents within the study area. The survey will be conducted
using a computer-assisted telephone interviewing (CATI) system. This type of
survey will allow for the collection of high quality data in a relatively short
period of time that can be used in making critical management decisions.
The total number of interviews proposed is entirely based on the level of anal-
ysis that is to be conducted with the data. At a minimum, the team recommends
a sample size of no less than 384 surveys, which would provide a representative
sample of the entire population with results significant at the 95 percent con-
fidence level with a standard error of:l:5 percent. The sample size would increase
as samples of independent market segments increase. A sample size of 1,200
will provide the 95 percent /:1:5 percent results for up to four market segments.
Our proposal is to use a sample size of 400 rcsponses, but we would be pleased
to increase the size if additional data are desired by Gallatin County.
We will provide a draft questionnaire to the Stakeholders Board for review and
approval prior to initiating the data collection. Input for the questionnaire will
be solicited from the Stakeholders Board during the project kick-off meeting.
Attempts will be made to include cell phone numbers in the randomly selected
sample.
Product: The telephone survey methodology and findings will be presented in Working
Paper #1 for review by the Advisory Board.
~ Task 5: Identify Transit Demand
Purpose: To develop an updated assessment of transit demand in the study area and to
determine the needs of specific transit user groups and their demand for transit
servIces.
Approach: LSC will employ a series of small city demand estimation techniques for both
the general population and particular market segments including elderly and
disabled populations, youth, employment, educational trips, and social service
demand. LSC has developed and used these techniques successfully in the past.
Peer-based methodologies also will be applied to assess transit demand.
The demand estimation will be determined by census block groups and will be
an accurate and reproducible method for projecting ridership.
.. The assessment of transit needs will identify demand for the current period and
projections for three, five, and ten-year planning horizons.
Product: The product of this task will be transit demand estimates reported in a series of
tables and graphics. The needs analysis and demand estimates will be presented
as part of Working Paper # 1 which will be submitted at the end of this task.
LSC
Gallatin County Public Transportation System Assessment Page 4
.
l;ij Task 6: Develop Strategic Public Transportation Plan
Purpose: To develop a long-range vision and strategic plan for transportation services in
the Bozeman area.
Approach: This task is probably the single most important task in the entire project. During
this task, the long-range vision for transportation serviccs will be identified and
then a strategic plan will be developed.
We propose to conduct a half-day workshop with the Advisory Board to develop
the vision and strategic plan. The workshop should be scheduled to follow sub-
mittal of Working Papcr # 1. This will ensure that all the background information
is available to the Advisory Board to help formulate the strategic plan.
The workshop will be conducted by A. T. Stoddard and Frank Spielberg. Both
have experience working with boards to develop a vision and strategic plan.
During the workshop, we will identify the vision for public transportation
services. This vision will set the broad direction for transit services over the next
20 years. We will then develop goals for public transportation services. The
goals will include long-range goals for 10 years and short-range goals for the
next 5 years. We will outline specific objcctives for each of the goals.
Following the workshop, we will prepare the draft strategic plan. We will
document the results of the workshop and formulate this into a strategic plan.
The draft strategic plan will be submitted as Working Paper #2. We will again
meet with the Project Team to revise the strategic plan based on their review.
Product: The draft strategic plan will be submitted as Working Paper #2.
4lii!il Task 7: Develop and Evaluate Transit Service Scenarios
Purpose: The purpose of this task is to identify service alternatives for three different
transit service scenarios.
Approach: We will work with the local staff and the Project Team to develop three transit
service scenarios. We will also work cooperatively to identify service
alternatives to be considered for each of the scenarios. The alternatives will be
formulated based on the unmet needs identified in Task 5. These alternatives
will also address the issues which are developed as part ofthe study process and
will be evaluated using the goals and objectives set by the Advisory Board as
~ part of the strategic plan.
Alternatives to be considered may include fixed-route service, demand-response
service, checkpoint service, and flexible routing. The types of service will be
considered based on the geographic relationship of transit needs and the
estimates of demand.
LSC
Gallatin County Public Transportation System A..se.".ment Page 5
..
The Consultant Team will develop descriptive information on each service
alternative. The information will be used in the analysis of each alternative and
the development of recommendations to the Projcct Team. The following
information will be providcd for each alternative:
. Type of service to be offered.
. Operating characteristics over the term of the plan. These charactcristics
include service areas, routes and schedules, hours of operation, vehicle
mileage, ridership, etc.
. Financial characteristics including operating, capital and administrative
costs, fare, charter, advertising, tax, and other revenues.
. Legal considerations including institutional structure and constraints.
. Equipment needs including a capital equipment plan showing equipment to
be purchased.
. Provisions for meeting the needs of the elderly, persons with disabilities,
and other transit-dependent populations.
. Projected vehicle mileage and the potential for rehabilitating vehicles prior
to new purchases.
LSC will participate in a public meeting at the end of this task to present the
findings of the analysis to residents of the community. Again, it will be
extremely important to involve the public at this stage to select the preferred set
of alternatives and to participate in the refinement of that set.
Comments from the public will be incorporated into the selection of a preferred
alternative which may incorporate elements trom a number of different
alternatives which have been analyzed.
Product: The analysis of alternatives and the three scenarios will be described in Working
Paper #3. The Consultant will also meet with the TAC to present the results of
the analysis and to assist in the selection of a recommendation.
~ Task 8: Phase One Report
"Purpose: To provide a Final Report for Phase One to be reviewed by the Advisory Board
and the community.
Approach: The work from the previous tasks will be compiled into a Draft Phase One
Report which will be submitted forreview. We will present the Draft Report at
a meeting of the Advisory Board. The Draft Report will contain conclusions and
recommendations regarding:
LSC
Gallatin County Public Transportation System A.'sessmenl Page 6
'.
. Boundaries of the transit district
. Costs of operating the district
. District demographics and potential transit demand
. Public and private support for fonnation of a transit district
. Service plan
Following presentation and review of the Draft Report, we will prepare and
submit the Phase One Final Report.
Product: This task will result in the Phase One Draft and Pinal Reports.
PHASE TWO: FEASIBILITY OF ESTABLISHMENT OF URBAN
TRANSPORTATION DISTRICT
~ Task 9: Organizational Structure
Purpose: To detennine the administrative feasibility of implementing an Urban Trans-
portation District.
Approach: Based on Montana Statues, we will identify the composition and powers of the
Urban Transportation District. We will also include a peer analysis of the other
Urban Transportation Districts in Montana which operate public transit services
in Great Falls and Missoula. We will also provide a comparison with Billings
which operates as a branch of City Government. The final institutional structure
to be examined will be operation of public transit service by a nonprofit
corporation. The advantages and disadvantages ofthe institutional structures will
be identified. We will specifically address the advantages of each institutional
structure with respect to the ability to coordinate with or to provide regional
transportation services in multiple counties. Although there are advantages to
forming a separate district, there are other options such as an agency fonned by
intergovernmental agreement or a nonprofit corporation that may he more ben-
eficial.
Product: The organizational and administrative structure will be presented as part of the
Phase Two Draft Report.
~ Task 10: Financial Plan
Purpose: To provide a financial plan which will direct implementation of a fiscally-
constrained operations plan.
..
Approach: Operating costs will be developed based upon type and level of service indicated
in the final plan. Sources of operating revenue (e.g., fares, advertising) will be
calculated for each year ofthe Transit Plan. The Capitallmprovement Program
will identify capital costs by year. Operating costs will be combined with annual
capital expenses to determine total annual system costs. Potential sources of
LSC
Gallatin County Public Transportation System Assessment Page 7
..
funding from private, local, state, and federal agencies will be examined so that
the annual operating deficit is covered by a realistic financial support program.
Product: The financial plan will be presented as part of the Phase Two Draft Report.
~ Task 11: Implementation Plan
Purpose: The purpose of this task is to refine the recommended alternatives to provide
local staff and decision-makers with a blueprint for operation, funding, and
management of the recommended transit service.
Approach: Following a review and approval of the Phase One Report, we will develop an
implementation plan.
Information from previous tasks will be used to compile the implementation
plan. Following the selection of the preferred alternative, the implementation
and operations program will be developed in more detaiL The interim plan being
developed by a local task force will be used as the starting point for the
implementation plan. We will identify the interim budget and operations plan
which will be in place in 2006. This interim plan will fonn the basis for
developing the five-year implementation plan to move to establish the preferred
service plan. The elements of the program to be addrcssed include:
. Service and Operations Plan - An operational plan will be developed for
the selected alternatives and will include, as appropriate, the type and level
of service, operational management, routes, headways, major stops, farc
structure, and other operating aspects. A rccommendation will be provided
whether to set up operations in-house within the proposed organization or
to contract for all or a portion of the operations.
. Capital and Support Facility Plan ~ Bascd upon the selected transit
service alternatives and level of service, a capital and support facility plan
will be developed. This will include, as appropriate, number and type of
vehicles, signs, shelters, administrative space and equipment, dispatching
equipment, and all other capital expenditures and procurement during the
planning period.
. Implementation Plan - LSC will develop a detailed schedule to ensure that
the recommended changcs can be implemented in a workable manner. This
schedule will identify the entities responsible for implementation of each
.. plan element.
All ofthese plan elements will be prepared for the planning period. Specifically,
the Transit Plan will identify the recommended transit service and provide a
series of readily-understandable "snapshots" of how the transit service will
mature over the planning horizon.
LSC
Gallatin County Public Transportation System Assessment Page 8
.,
Product: The product of this task will be part of the Phase Two Draft Report.
- Task 12: Phase Two Final Report
Purpose: To provide a Final Report for Phase Onc to be reviewed by the Advisory Board
and the community.
Approach: The work from the previous tasks will be compiled into a Draft Phase Two
Report which will be submitted for rcview. We will present the Draft Report at
a meeting of the Advisory Board.
Following presentation and review of the Draft Report, we will prepare and
submit the Phase Two Final Report
Product: This task will result in the Phase Two Draft and final Reports.
"
LSC
Gallatin County Public Transportation System A,\'sessment Page 9
!
..
Table 3
Phase One Project Cost Estimate
Labor: Technical Clerical
Stoddard Donahue Spielberg Support Support TOTAL
Task 1: Project Administration 4 2 6
Task 2: Public Involvement Program 16 28 4 4 52
Task 3: Prepare Community Profile 4 24 4 32
Task 4: Community Telephone Survey 12 8 4 24
Task 5: Identify Transit Demand 4 12 4 4 24
Task 6: Develop Strategic Plan 12 12 2 26
Task 7: Evaluate Transit Service Scenarios 12 8 12 8 8 48
Task 8: Phase One Report 12 8 4 8 8 40
0
Total Hours 76 80 36 24 36 252
Dlrecllabor Rate $47.79 $23.89 $49.50 $22.00 $18.25
Dlrecllabor Cost $3,632 $1,911 $1,782 $528 $657 $8,510
Overhead $5,375 $2,829 $2,441 $781 $972 $12,399
Labor Subtotal $20,909
Direct Costs:
Item Cost
Travel $3,700
Per Diem $1,500
Printing/Copying $930
Telephone Survey $10,000
Courier/Postage $150
Telephone $100
Direct Costs Subtotal: $16,380
Fee (10 % of Labor) $2,091
Total Estimate: $39,380
... .'
Tabla.
Phase Two Project Cost Estimate
labor: Technical Clencal
Stoddard Donahue Spielberg Support Su pport TOTAL
Task 1: Project Administration 4 1 5
laRk 9: Organizational Structure 8 8 8 2 26
Task 10: Financial Plan 8 16 2 26
Task 11: Implemenlation Plan 12 16 8 4 40
Task 12: Phaee Two Report 4 16 2 4 26
0
Total Hours 36 56 18 0 13 123
Direct Labor Rate $47.79 $23.89 $49.50 $noo $18,25
Direct Labor Cost $1,720 $1,338 $891 $0 $237 $4,187
Overhead $2,546 $1,980 $1,221 $0 $351 $6,098
labor Subtotal $10,285
Direct Costs:
Item Cost
Travel $640
Per Diem $250
Printing/Copying $120
Courier/Postage $50
Telephone $50
Direct Costs Subtotal' $1,110
Fee (10 % of labor) $1,028
Total Estimate: $12,423
..
(;
~
.
Task Month
q
'I .. . ~
I!
"I
[] I'
n::y? II
-:--F.-4':-
,j
~ '
[J !l
:.-.. II
k~--_
"
~ ~
II
l
~ ~
P
,I
.. II
:~ ~ 0
~ ~ ~
~ ~
II 0
~ ~
--~''--
"
'"
~, .
LEGEND
o Public Transportation Stakeholders Advisory Board Meeting
iE; &" Draft Report
t!L o Final Report
~-~:::--~
"K~~.
," ---_: -~-
...__~_a.-~ .,
---, ,y:~
----..--.-::'-.-:----'---,---.,.::.::.-------'--,-
.- ---.-.-.---. .-- -.-.'.
TRAN~P9RT A TION
CONS L ANTS. tNC.