HomeMy WebLinkAbout04- Sourdough Transmission Main, Big X Co. Change Order No. 1 , . . CHANGE ORDER ORDER NO. 1 DATE 9/24/2004 AGREEMENT DATE: 10/22/2001 NAME OF PROJECT Sourdou~h Transmission Main OWNER City of Bozeman CONTRACTOR Big; X Construction The following changes are hereby made to the CONTRACT DOCUMENTS: Justification: Adjustment of actual bid quantities necessary to complete the work and addition of construction and installation of insulated panels for the intake structure to prevent freezing. Original CONTRACT PRICE: $ 423,885,00 Current CONTRACT PRICE adjusted by previous CHANGE ORDER:$ 423.885.00 The CONTRACT PRICE due to this CHANGE ORDER will be (increased) (decreased) by: $31,971.75 The new CONTRACT PRICE including this CHANGE ORDER will be $ 391,913.25 CHANGE of CONTRACT TIME: 0 days The date for completion of all work will be 2/11/2002 (date ). Recommended~ti-~~/ /fIr; -1 7?Yc Contractor / / Approved by : A7?~ 9 It-I( /tJ tj Engmeer Acceptedby: ('~~ ~ 11/1/2004 Owner