HomeMy WebLinkAboutExisting Bozeman HS TIS Update Addendum 03.06.19 MARVIN & ASSOCIATES 1300 N. Transtech Way Billings, MT 59102 Existing Bozeman High School TIS Update Addendum 1 Kyle Scarr, PE TD&H Engineering 234 E Babcock, Suite 3 Bozeman, MT 59715 July 12, 2018 Re: Existing Bozeman High Traffic Impact Study Update Addendum This letter along with the attached figures and appendix constitute an addendum to the Traffic Impact Study (TIS) update submitted in April of 2018. The TIS update addendum is necessitated by a request from the City of Bozeman to address impacts to North 15th Avenue intersections with Durston Road and Main Street. Since the proposed pick-up and drop-off area improvements at the Beall Street school access on N 15th Avenue would draw the majority of traffic from current pick-up and drop-off operations on N 11th Avenue, there are concerns that traffic redistribution would negatively impact the N 15th Avenue intersections. This addendum addresses those concerns. Trip Generation Considerations Trip generation and distribution estimates were derived from existing school data in the original TIS. The existing school currently has a student population of approximately 2,140 students that generates approximately 224 pick-up and drop-off trips (112 entering and 112 exiting) in the am hour and 76 trips in the pm hour on N 11th Street. In the year 2020, when the new school is in operation, the existing high school will only have 1,750 students and the number of pick-up and drop-off trips will drop by 162 in the am hour and 157 in the pm hour. The number of pick-up and drop-off traffic using the N 15th Avenue Beall Street access would be minimalized by the net reduction in overall trips. The 2018 TIS update used the above noted trip generation reduction factors to estimate trip attractions that would be created by additional parking areas and pick-up and drop-off traffic that could be served by the N 15th Avenue access. In the future, when the existing high school stabilizes at its ultimate capacity of 1,500 students, pick-up and drop-off activity would only be 70% of existing operations. Traffic Counts Traffic counts at the N 15th Avenue intersections of Durston Road and Main Street were not made available when the original TIS was completed. Due to time limitations associated with this addendum, counts had to be completed on Tuesday July 3, 2018 (see appendix). Because these counts do not include school traffic, the counts had to be transformed by using counts taken on Main Street and on N 15th Avenue for the original TIS. All school access volumes on N 15th Avenue and Main Street during the am and pm peak school hours were summed by direction of approach and departure and proportionately added to pertinent movements at both intersections. Since, the through traffic movements were higher on Main Street and North 15th Avenue in 2017 than the 2018, thru movement volumes were increased to replicate in-session conditions. The final design hour school peak am and pm hour traffic volumes were balanced and rounded up to the nearest 5 vehicles (see Appendix). MARVIN & ASSOCIATES 1300 N. Transtech Way Billings, MT 59102 Existing Bozeman High School TIS Update Addendum 2 Interim & Future Traffic Projections Traffic projection for the Beal Street access on N 15th Avenue were developed in the April 2018 TIS Update and used to determine relative traffic volumes that would contribute to changes at the N 15th Avenue intersections with Durston Road and Main Street. The Appendix contains a figure that illustrates the existing, Year 2020 Interim, and year 2035 Future traffic projections at the two intersections. It should be noted that through traffic volumes on Durston Road and Main Street remain relatively static for both future conditions, as was stated in the original TIS. Even if traffic increases on those streets were to increase, it would be due to external forces, since the school’s development scenario would have a positive impact on the area street system by reducing overall traffic volumes. Intersection Capacity Impacts Capacity calculations were completed using year 2020 interim and year 2035 future traffic projections (see Appendix). The table below compares the results of that analysis. LOS Delay Qmax LOS Delay Qmax LOS Delay Qmax LOS Delay Qmax LOS Delay Qmax LOS Delay Qmax Durston & N 15th Left A5 . 12 A6 . 12 A5 . 12 A6 . 52 A5 . 12 A6 . 52 Thru/Right C 24.1 11 B 17.4 7 C 24.1 11 B 18.1 7 B 24.1 11 B 18.1 7 A Left A8 . 72 A6 . 13 A9 . 22 A6 . 51 A8 . 61 B6 . 51 Thru/Right B 14.3 4 B 17.9 7 B 14.3 4 B 19 8 B 14.3 4 C 19 8 Left C 22.6 3 C 22.2 3 C 22.6 2 C 22.6 4 C 22.6 3 C 22.6 4 Thru/Right C 22.6 3 C 24.9 5 C 22.7 3 C 26.2 6 C 22.6 5 C 26.2 6 Left C 21.5 2 C 22.2 2 C 21.5 2 C 21.5 1 C 21.5 2 C 21.5 1 Thru/Right C 23.7 4 C 22.2 3 C 23.7 4 C 22.6 3 C 23.7 4 C 22.6 3 C 20.5 B 18.8 C 20.4 B 19.5 C 20.5 B 19.5 Main Street & N 15th Left B 10.3 6 B 16.9 5 B 10.3 6 B 16.9 5 B 10.3 6 B 16.9 5 Thru/Right B 11.6 8 B 10.4 5 B 11.6 9 B 10.4 5 B 11.6 8 B 10.4 5 Left B 19.7 0 B 15.1 0 B 19.7 0 B 15.1 0 B 19.7 0 B 15.1 0 Thru C 27 9 C 217 11 C 27 8 C 27 12 C 27 9 C 27 12 Right C 22.2 1 B 17.1 2 C 21.9 1 B 17.4 2 C 22.2 1 B 17.4 2 Thru/LT/RT B 19.6 0 C 21.4 0 B 19.6 0 C 21.4 0 B 19.6 0 C 21.4 0 Left C 22.1 3 C 25.3 4 C 21.4 2 C 26 6 C 22.1 3 C 25.6 6 Thru/Right C 20.4 2 C 22.5 2 C 20.4 2 C 22.5 2 C 20.4 2 C 22.6 3 B 17.5 C 21 B 17.4 C 21.1 B 17.5 C 21 Intersection/Movement EB Overall Intersection WB NB SB EB WB NB SB Overall Intersection Capacity Calculation Summary Existing, Interim & Future Conditions Peak PM Hour Existing Conditions Year 2020 Interim Operations Peak AM Hour Peak PM Hour Year 2035 Future Operations Peak AM Hour Peak PM HourPeak AM Hour MARVIN & ASSOCIATES 1300 N. Transtech Way Billings, MT 59102 Existing Bozeman High School TIS Update Addendum 3 It can be seen that both intersections and all movements at both intersections currently operate at LOS “C” or better and that little if any difference would be introduced by redistribution of existing high traffic operations in the future. Conclusions The TIS Addendum analysis indicates that with the proposed site access improvements currently under design as a part of Existing Bozeman High School development, operations of the school in the years 2020 and 2035 would not measurably impact operations at the intersections of Main Street and Durston Road with of N 15th Avenue in either the peak am or pm hours of operation. Very little in-fill development could occur in the area served by both intersections and future traffic volumes are not expected to see appreciable growth. The majority of peak hour traffic on N 15th Avenue is high school traffic and the expected 30% reduction in high school traffic would provide a positive impact during the am and peak hours of high school operations. Robert R. Marvin, P.E., P.T.O.E Intersection:Date: Begin Total Time LeftThru RightL eftThru RightL eftThru RightL eftThru RightV ehicles 7:00 96 8 7 16 7 1 41 7 5 7:15 8 121 1 77 6 19 7 239 7:30 9 132 97 11 17 6 272 7:45 17 203 99 18 25 20 382 8:00 18 137 120 17 25 18 335 8:15 8 147 101 22 26 15 319 8:30 23 164 111 24 21 15 358 8:45 14 172 117 20 17 16 356 Peak AM Hour 52 593 1 393 52 86 51 1228 3:00 16 198 2 233 29 55 13 546 3:15 16 204 249 44 21 16 550 3:30 14 136 248 39 32 17 486 3:45 18 137 2 252 31 36 14 490 4:00 27 140 3 250 28 33 12 493 4:15 20 181 216 36 24 15 492 4:30 17 164 238 41 36 21 517 4:45 21 160 1 210 66 34 13 505 Peak PM Hour 75 617 5 999 142 122 59 2019 0.80 0.92 Intersection:Date: Begin Total Time LeftThru RightL eftThru RightL eftThru RightL eftThru RightV ehicles 7:00 9 6 5 66 2 0 165514 1 0 1 3 8 7:15 5 5 4 64 3 8 36755 1 0 81 5 1 7:30 7 7 8 03 3 3 24993 1 5 71 7 0 7:45 15 146 0 3 50 8 10 12 11 8 16 8 287 8:00 12 86 11 3 33 5 11 10 6 8 21 3 209 8:15 4 1 2 75 6 2 88554 1 5 31 3 8 8:30 49 70 65 04 71 66 71 5 1 02 2 2 8:45 7 9 2 95 5 6 1 1 7 1 5 85612 2 2 Peak AM Hour 39 364 17 13 154 18 31 38 31 24 62 26 817 3:00 8 88 9 7 121 22 8 29 10 8 15 8 333 3:15 11 100 8 10 91 17 8 27 13 19 15 2 321 3:30 9 8 51 1 71 0 8 1 2 6 2 61 41 02 2 5 3 1 5 3:45 11 84 15 9 98 8 5 25 19 11 16 8 309 4:00 7 9 81 01 09 52 21 03 5 9 1 21 2 5 3 2 5 4:15 10 91 4 9 116 12 8 27 13 10 22 6 328 4:30 6 9 31 51 88 8 9 7 2 01 51 22 41 0 3 1 7 4:45 1 39 51 0 8 9 91 81 13 61 61 42 6 6 3 5 2 Peak PM Hour 38 367 44 36 392 59 29 113 55 52 65 20 1270 0.71 0.98 AM phf = PM phf = N 15th Avenue & Durston Road July 2018 Durston Road N 15th Avenue Eastbound Westbound Northbound Southbound AM phf = PM phf = N 15th Avenue & Main Street Eastbound Westbound Northbound Southbound Main Street N 15th Avenue July 2018  Peak School Hour Traffic  (Typical) HCM Analysis Summary Existing Conditions R Marvin Peak AM Hour Analysis Duration: 15 mins. Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Exist AM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 2 1 2 1 2 1 2 1 L 12.0 L 12.0 L 12.0 L 12.0 TR 12.0 TR 12.0 TR 12.0 TR 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 TR 3 L 3 TR 3 L 3 TR 3 40 0.71 2 365 0.71 2 80 0.71 2 55 0.71 2 155 0.71 2 25 0.71 2 50 0.71 1 60 0.71 1 45 0.71 1 25 0.71 1 125 0.71 1 25 0.71 1 20 5 0 0 --- --- 5 5 0 0 --- --- 15 5 0 0 --- --- 5 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y L L LTP LTP LTP LTP 0 10.0 4.0 0.0 30.0 3.5 1.5 16.0 3.5 1.5 Pretimed 70.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 462 0.000 0.500 22.5 C Lpro 253 0.032 0.143 L 0.078 5.1 A * TR 781 0.329 0.429 TR 0.767 24.1 C WB Lper 176 0.000 0.500 12.9 B * Lpro 253 0.044 0.143 L 0.179 8.7 A TR 784 0.134 0.429 TR 0.314 14.3 B NB L 237 0.068 0.229 L 0.295 22.6 C 22.6 C TR 407 0.071 0.229 TR 0.312 22.6 C SB L 288 0.028 0.229 L 0.122 21.5 C 23.4 C * TR 421 0.111 0.229 TR 0.485 23.7 C Intersection: Delay = 20.5sec/veh Int. LOS=C Xc= 0.60 * Critical Lane Group (v/s)Crit= 0.48 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Existing Conditions R Marvin Peak AM Hour Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Exist AM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 1 / 2 21.2 0.0 TR 8 / 11 11.1 0.0 All 11.8 0.0 WB L 1 / 2 17.9 0.0 TR 3 / 4 14.8 0.0 All 15.3 0.0 NB L 1 / 3 6.1 0.0 TR 2 / 3 14.6 0.0 All 12.1 0.0 SB L 1 / 2 11.4 0.0 TR 3 / 4 11.6 0.0 All 11.6 0.0 Intersect. 12.4 SIG/Cinema v3.08 Marvin & Associates Page 2 40 365 80 55 155 25 50 60 45 25 125 25 1 10 04 1 10 04 2 29 24 2 29 24 3 15 24 3 15 24 HCM Analysis Summary Existing Conditions R Marvin Peak PM Hour Analysis Duration: 15 mins. Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Exist PM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 2 1 2 1 2 1 2 1 L 12.0 L 12.0 L 12.0 L 12.0 TR 12.0 TR 12.0 TR 12.0 TR 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 TR 3 L 3 TR 3 L 3 TR 3 40 0.98 2 365 0.98 2 65 0.98 2 55 0.98 2 390 0.98 2 60 0.98 2 70 0.98 1 160 0.98 1 90 0.98 1 50 0.98 1 90 0.98 1 20 0.98 1 20 5 0 0 --- --- 20 5 0 0 --- --- 25 5 0 0 --- --- 5 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y L L LTP LTP LTP LTP 0 10.0 4.0 0.0 30.0 3.5 1.5 16.0 3.5 1.5 Pretimed 70.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 299 0.000 0.500 16.4 B Lpro 253 0.023 0.143 L 0.074 6.1 A TR 785 0.228 0.429 TR 0.532 17.4 B WB Lper 316 0.000 0.500 16.5 B * Lpro 253 0.032 0.143 L 0.098 6.1 A * TR 787 0.239 0.429 TR 0.558 17.9 B NB L 293 0.055 0.229 L 0.242 22.2 C 24.3 C * TR 410 0.128 0.229 TR 0.559 24.9 C SB L 216 0.054 0.229 L 0.236 22.2 C 22.2 C TR 420 0.058 0.229 TR 0.255 22.2 C Intersection: Delay = 18.8sec/veh Int. LOS=B Xc= 0.50 * Critical Lane Group (v/s)Crit= 0.40 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Existing Conditions R Marvin Peak PM Hour Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Exist PM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 1 / 2 21.3 0.0 TR 5 / 7 13.3 0.0 All 14.0 0.0 WB L 1 / 3 20.2 0.0 TR 5 / 7 13.3 0.0 All 13.7 0.0 NB L 1 / 3 6.6 0.0 TR 3 / 5 14.8 0.0 All 12.7 0.0 SB L 1 / 2 5.9 0.0 TR 2 / 3 13.8 0.0 All 11.6 0.0 Intersect. 13.3 SIG/Cinema v3.08 Marvin & Associates Page 2 40 365 65 55 390 60 70 160 90 50 90 20 1 10 04 1 10 04 2 29 24 2 29 24 3 15 24 3 15 24 HCM Analysis Summary Year 2020 Operations R Marvin Peak AM Hour Analysis Duration: 15 mins. Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Year 2020 AM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 2 1 2 1 2 1 2 1 L 12.0 L 12.0 L 12.0 L 12.0 TR 12.0 TR 12.0 TR 12.0 TR 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 TR 3 L 3 TR 3 L 3 TR 3 40 0.71 2 365 0.71 2 80 0.71 2 70 0.71 2 155 0.71 2 25 0.71 2 50 0.71 1 60 0.71 1 50 0.71 1 25 0.71 1 125 0.71 1 25 0.71 1 20 5 0 0 --- --- 5 5 0 0 --- --- 15 5 0 0 --- --- 5 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y L L LTP LTP LTP LTP 0 10.0 4.0 0.0 30.0 3.5 1.5 16.0 3.5 1.5 Pretimed 70.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 462 0.000 0.500 22.5 C Lpro 253 0.032 0.143 L 0.078 5.1 A * TR 781 0.329 0.429 TR 0.767 24.1 C WB Lper 176 0.000 0.500 12.8 B * Lpro 253 0.056 0.143 L 0.231 9.2 A TR 784 0.134 0.429 TR 0.314 14.3 B NB L 237 0.068 0.229 L 0.295 22.6 C 22.7 C TR 405 0.076 0.229 TR 0.331 22.7 C SB L 286 0.028 0.229 L 0.122 21.5 C 23.4 C * TR 421 0.111 0.229 TR 0.485 23.7 C Intersection: Delay = 20.4sec/veh Int. LOS=C Xc= 0.62 * Critical Lane Group (v/s)Crit= 0.50 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2020 Operations R Marvin Peak AM Hour Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Year 2020 AM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 1 / 2 21.2 0.0 TR 8 / 11 11.1 0.0 All 11.8 0.0 WB L 0 / 2 23.5 0.0 TR 3 / 4 15.5 0.0 All 16.7 0.0 NB L 1 / 2 6.7 0.0 TR 2 / 3 15.2 0.0 All 12.9 0.0 SB L 1 / 2 11.5 0.0 TR 3 / 4 11.7 0.0 All 11.6 0.0 Intersect. 12.8 SIG/Cinema v3.08 Marvin & Associates Page 2 40 365 80 70 155 25 50 60 50 25 125 25 1 10 04 1 10 04 2 29 24 2 29 24 3 15 24 3 15 24 HCM Analysis Summary Year 2020 Operations R Marvin Peak PM Hour Analysis Duration: 15 mins. Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Year 2020 PM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 2 1 2 1 2 1 2 1 L 12.0 L 12.0 L 12.0 L 12.0 TR 12.0 TR 12.0 TR 12.0 TR 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 TR 3 L 3 TR 3 L 3 TR 3 40 0.92 2 365 0.92 2 65 0.92 2 65 0.92 2 390 0.92 2 65 0.92 2 80 0.92 1 160 0.92 1 100 0.92 1 20 0.92 1 90 0.92 1 50 0.92 1 20 5 0 0 --- --- 15 5 0 0 --- --- 30 5 0 0 --- --- 20 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y L L LTP LTP LTP LTP 0 10.0 4.0 0.0 30.0 3.5 1.5 16.0 3.5 1.5 Pretimed 70.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 268 0.000 0.500 17.1 B Lpro 253 0.024 0.143 L 0.083 6.5 A TR 785 0.244 0.429 TR 0.568 18.1 B WB Lper 293 0.000 0.500 17.4 B * Lpro 253 0.040 0.143 L 0.130 6.5 A * TR 784 0.261 0.429 TR 0.610 19.0 B NB L 287 0.069 0.229 L 0.303 22.6 C 25.2 C * TR 409 0.140 0.229 TR 0.611 26.2 C SB L 198 0.025 0.229 L 0.111 21.5 C 22.5 C TR 413 0.073 0.229 TR 0.317 22.6 C Intersection: Delay = 19.5sec/veh Int. LOS=B Xc= 0.55 * Critical Lane Group (v/s)Crit= 0.44 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2020 Operations R Marvin Peak PM Hour Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 10th Year 2020 PM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 1 / 2 19.9 0.0 TR 5 / 7 13.8 0.0 All 14.3 0.0 WB L 1 / 1 21.2 0.0 TR 6 / 8 13.0 0.0 All 13.4 0.0 NB L 1 / 4 6.8 0.0 TR 4 / 6 12.1 0.0 All 11.0 0.0 SB L 0 / 1 8.1 0.0 TR 2 / 3 13.8 0.0 All 13.2 0.0 Intersect. 13.0 SIG/Cinema v3.08 Marvin & Associates Page 2 40 365 65 65 390 65 80 160 100 20 90 50 1 10 04 1 10 04 2 29 24 2 29 24 3 15 24 3 15 24 HCM Analysis Summary Year 2035 Operations R Marvin Peak AM Hour Analysis Duration: 15 mins. Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 15th Year 2035 AM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 2 1 2 1 2 1 2 1 L 12.0 L 12.0 L 12.0 L 12.0 TR 12.0 TR 12.0 TR 12.0 TR 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 TR 3 L 3 TR 3 L 3 TR 3 40 0.71 2 365 0.71 2 80 0.71 2 50 0.71 2 155 0.71 2 25 0.71 2 50 0.71 1 60 0.71 1 45 0.71 1 25 0.71 1 125 0.71 1 25 0.71 1 20 5 0 0 --- --- 5 5 0 0 --- --- 15 5 0 0 --- --- 5 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y L L LTP LTP LTP LTP 0 10.0 4.0 0.0 30.0 3.5 1.5 16.0 3.5 1.5 Pretimed 70.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 462 0.000 0.500 22.5 C Lpro 253 0.032 0.143 L 0.078 5.1 A * TR 781 0.329 0.429 TR 0.767 24.1 C WB Lper 176 0.000 0.500 13.0 B * Lpro 253 0.040 0.143 L 0.163 8.6 A TR 784 0.134 0.429 TR 0.314 14.3 B NB L 237 0.068 0.229 L 0.295 22.6 C 22.6 C TR 407 0.071 0.229 TR 0.312 22.6 C SB L 288 0.028 0.229 L 0.122 21.5 C 23.4 C * TR 421 0.111 0.229 TR 0.485 23.7 C Intersection: Delay = 20.5sec/veh Int. LOS=C Xc= 0.60 * Critical Lane Group (v/s)Crit= 0.48 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2035 Operations R Marvin Peak AM Hour Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 15th Year 2035 AM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 1 / 2 21.2 0.0 TR 8 / 11 11.1 0.0 All 11.8 0.0 WB L 0 / 1 19.7 0.0 TR 3 / 4 14.7 0.0 All 15.4 0.0 NB L 1 / 3 6.1 0.0 TR 2 / 3 14.7 0.0 All 12.2 0.0 SB L 1 / 2 11.3 0.0 TR 3 / 4 11.7 0.0 All 11.6 0.0 Intersect. 12.5 SIG/Cinema v3.08 Marvin & Associates Page 2 40 365 80 50 155 25 50 60 45 25 125 25 1 10 04 1 10 04 2 29 24 2 29 24 3 15 24 3 15 24 HCM Analysis Summary Year 2035 Operations R Marvin Peak PM Hour Analysis Duration: 15 mins. Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 15th Year 2035 PM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 2 1 2 1 2 1 2 1 L 12.0 L 12.0 L 12.0 L 12.0 TR 12.0 TR 12.0 TR 12.0 TR 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 TR 3 L 3 TR 3 L 3 TR 3 40 0.92 2 365 0.92 2 65 0.92 2 65 0.92 2 390 0.92 2 65 0.92 2 80 0.92 1 160 0.92 1 100 0.92 1 20 0.92 1 90 0.92 1 50 0.92 1 20 5 0 0 --- --- 15 5 0 0 --- --- 30 5 0 0 --- --- 20 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y L L LTP LTP LTP LTP 0 10.0 4.0 0.0 30.0 3.5 1.5 16.0 3.5 1.5 Pretimed 70.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 268 0.000 0.500 17.1 B Lpro 253 0.024 0.143 L 0.083 6.5 A TR 785 0.244 0.429 TR 0.568 18.1 B WB Lper 293 0.000 0.500 17.4 B * Lpro 253 0.040 0.143 L 0.130 6.5 A * TR 784 0.261 0.429 TR 0.610 19.0 B NB L 287 0.069 0.229 L 0.303 22.6 C 25.2 C * TR 409 0.140 0.229 TR 0.611 26.2 C SB L 198 0.025 0.229 L 0.111 21.5 C 22.5 C TR 413 0.073 0.229 TR 0.317 22.6 C Intersection: Delay = 19.5sec/veh Int. LOS=B Xc= 0.55 * Critical Lane Group (v/s)Crit= 0.44 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2035 Operations R Marvin Peak PM Hour Durston Road/N 15th Avenue 07/11/2018 Case: Durston & N 15th Year 2035 PM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 1 / 2 19.9 0.0 TR 5 / 7 13.8 0.0 All 14.3 0.0 WB L 1 / 1 21.2 0.0 TR 6 / 8 13.0 0.0 All 13.4 0.0 NB L 1 / 4 6.8 0.0 TR 4 / 6 12.1 0.0 All 11.0 0.0 SB L 0 / 1 8.1 0.0 TR 2 / 3 13.8 0.0 All 13.2 0.0 Intersect. 13.0 SIG/Cinema v3.08 Marvin & Associates Page 2 40 365 65 65 390 65 80 160 100 20 90 50 1 10 04 1 10 04 2 29 24 2 29 24 3 15 24 3 15 24 HCM Analysis Summary Existing Conditions R Marvin Peak AM Hour Analysis Duration: 15 mins. Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Existing AM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 3 2 4 2 1 1 2 1 L 12.0 L 12.0 LTR 12.0 L 12.0 T 12.0 T 12.0 TR 12.0 TR 12.0 T 12.0 R 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 T 3 R 3 LTR 3 L 3 TR 3 130 0.80 1 880 0.80 3 0 0.80 0 1 0.80 0 530 0.80 3 130 0.80 1 0 0.80 0 0 0.80 0 1 0.80 0 120 0.80 2 0 0.80 0 75 0.80 2 0 5 0 0 --- --- 40 5 0 0 --- --- 0 0 0 0 --- --- 25 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y LTP LTP LTP LTP LTP 0 18.0 4.0 0.0 24.0 3.5 1.5 24.0 3.5 1.5 Pretimed 80.0 Sec 10.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 146 0.000 0.363 11.4 B Lpro 402 0.091 0.225 L 0.296 10.3 B * TR 2015 0.314 0.575 TR 0.546 11.6 B WB L 148 0.002 0.300 L 0.007 19.7 B 26.3 C T 1052 0.189 0.300 T 0.629 27.0 C R 476 0.071 0.300 R 0.235 22.2 C NB LTR 493 0.001 0.300 LTR 0.002 19.6 B 19.6 B SB * L 423 0.106 0.300 L 0.355 22.1 C 21.6 C TR 473 0.039 0.300 TR 0.131 20.4 C Intersection: Delay = 17.5sec/veh Int. LOS=B Xc= 0.48 * Critical Lane Group (v/s)Crit= 0.42 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Existing Conditions R Marvin Peak AM Hour Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Existing AM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 3 / 6 12.3 0.0 TR 6 / 8 16.4 0.0 All 15.7 0.0 WB L 0 / 0 0.0 0.0 T 6 / 9 10.3 0.0 R 1 / 1 23.7 0.0 All 10.9 0.0 NB LTR 0 / 0 0.0 0.0 All 0.0 0.0 SB L 2 / 3 9.3 0.0 TR 1 / 2 21.3 0.0 All 15.5 0.0 Intersect. 13.6 SIG/Cinema v3.08 Marvin & Associates Page 2 130 880 0 1 530 130 0 0 1 120 0 75 1 18 04 2 23 24 2 23 24 3 23 24 3 23 24 HCM Analysis Summary Existing Conditions R Marvin Peak PM Hour Analysis Duration: 15 mins. Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Existing PM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 3 2 4 2 1 1 2 1 L 12.0 L 12.0 LTR 12.0 L 12.0 T 12.0 T 12.0 TR 12.0 TR 12.0 T 12.0 R 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 T 3 R 3 LTR 3 L 3 TR 3 95 0.92 1 620 0.92 3 1 0.92 0 1 0.92 0 1080 0.92 3 170 0.92 1 0 0.92 0 0 0.92 0 1 0.92 0 190 0.92 2 0 0.92 0 95 0.92 2 0 5 0 0 --- --- 45 5 0 0 --- --- 0 0 0 0 --- --- 25 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y LTP LTP LTP LTP LTP 0 10.0 4.0 0.0 38.0 3.5 1.5 28.0 3.5 1.5 Pretimed 90.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 84 0.000 0.478 11.2 B * Lpro 199 0.058 0.111 L 0.364 16.9 B TR 2025 0.193 0.578 TR 0.333 10.4 B WB L 316 0.001 0.422 L 0.003 15.1 B 26.0 C * T 1480 0.335 0.422 T 0.793 27.0 C R 671 0.086 0.422 R 0.203 17.1 B NB LTR 511 0.001 0.311 LTR 0.002 21.4 C 21.4 C SB * L 439 0.147 0.311 L 0.472 25.3 C 24.6 C TR 490 0.048 0.311 TR 0.155 22.5 C Intersection: Delay = 21.0sec/veh Int. LOS=C Xc= 0.64 * Critical Lane Group (v/s)Crit= 0.54 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Existing Conditions R Marvin Peak PM Hour Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Existing PM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 3 / 5 9.4 0.0 TR 4 / 5 17.5 0.0 All 15.5 0.0 WB L 0 / 0 0.0 0.0 T 10 / 11 10.6 0.0 R 1 / 2 23.3 0.0 All 11.2 0.0 NB LTR 0 / 0 0.0 0.0 All 0.0 0.0 SB L 3 / 4 7.4 0.0 TR 1 / 2 19.3 0.0 All 12.4 0.0 Intersect. 12.5 SIG/Cinema v3.08 Marvin & Associates Page 2 95 620 1 1 1080 170 0 0 1 190 0 95 1 10 04 2 37 24 2 37 24 3 27 24 3 27 24 HCM Analysis Summary Year 2020 Conditions R Marvin Peak AM Hour Analysis Duration: 15 mins. Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2020 AM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 3 2 4 2 1 1 2 1 L 12.0 L 12.0 LTR 12.0 L 12.0 T 12.0 T 12.0 TR 12.0 TR 12.0 T 12.0 R 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 T 3 R 3 LTR 3 L 3 TR 3 130 0.80 1 880 0.80 3 0 0.80 0 1 0.80 0 530 0.80 3 120 0.80 1 0 0.80 0 0 0.80 0 1 0.80 0 90 0.80 2 0 0.80 0 75 0.80 2 0 5 0 0 --- --- 40 5 0 0 --- --- 0 0 0 0 --- --- 25 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y LTP LTP LTP LTP LTP 0 18.0 4.0 0.0 24.0 3.5 1.5 24.0 3.5 1.5 Pretimed 80.0 Sec 10.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 146 0.000 0.363 11.4 B Lpro 402 0.091 0.225 L 0.296 10.3 B * TR 2015 0.314 0.575 TR 0.546 11.6 B WB L 148 0.002 0.300 L 0.007 19.7 B 26.3 C T 1052 0.189 0.300 T 0.629 27.0 C R 476 0.063 0.300 R 0.210 21.9 C NB LTR 493 0.001 0.300 LTR 0.002 19.6 B 19.6 B SB * L 423 0.079 0.300 L 0.265 21.4 C 21.1 C TR 473 0.039 0.300 TR 0.131 20.4 C Intersection: Delay = 17.4sec/veh Int. LOS=B Xc= 0.45 * Critical Lane Group (v/s)Crit= 0.39 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2020 Conditions R Marvin Peak AM Hour Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2020 AM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 3 / 6 13.1 0.0 TR 6 / 9 16.5 0.0 All 15.9 0.0 WB L 0 / 0 0.0 0.0 T 6 / 8 10.3 0.0 R 1 / 1 23.9 0.0 All 10.8 0.0 NB LTR 0 / 0 0.0 0.0 All 0.0 0.0 SB L 1 / 2 8.3 0.0 TR 1 / 2 22.9 0.0 All 16.3 0.0 Intersect. 13.7 SIG/Cinema v3.08 Marvin & Associates Page 2 130 880 0 1 530 120 0 0 1 90 0 75 1 18 04 2 23 24 2 23 24 3 23 24 3 23 24 HCM Analysis Summary Year 2020 Conditions R Marvin Peak PM Hour Analysis Duration: 15 mins. Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2020 PM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 3 2 4 2 1 1 2 1 L 12.0 L 12.0 LTR 12.0 L 12.0 T 12.0 T 12.0 TR 12.0 TR 12.0 T 12.0 R 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 T 3 R 3 LTR 3 L 3 TR 3 95 0.92 1 620 0.92 3 1 0.92 0 1 0.92 0 1080 0.92 3 195 0.92 1 0 0.92 0 0 0.92 0 1 0.92 0 210 0.92 2 0 0.92 0 95 0.92 2 0 5 0 0 --- --- 55 5 0 0 --- --- 0 0 0 0 --- --- 25 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y LTP LTP LTP LTP LTP 0 10.0 4.0 0.0 38.0 3.5 1.5 28.0 3.5 1.5 Pretimed 90.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 84 0.000 0.478 11.2 B * Lpro 199 0.058 0.111 L 0.364 16.9 B TR 2025 0.193 0.578 TR 0.333 10.4 B WB L 316 0.001 0.422 L 0.003 15.1 B 25.9 C * T 1480 0.335 0.422 T 0.793 27.0 C R 671 0.096 0.422 R 0.227 17.4 B NB LTR 511 0.001 0.311 LTR 0.002 21.4 C 21.4 C SB * L 439 0.162 0.311 L 0.519 26.0 C 25.1 C TR 490 0.048 0.311 TR 0.155 22.5 C Intersection: Delay = 21.1sec/veh Int. LOS=C Xc= 0.66 * Critical Lane Group (v/s)Crit= 0.55 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2020 Conditions R Marvin Peak PM Hour Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2020 PM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 3 / 5 11.1 0.0 TR 4 / 5 17.5 0.0 All 16.1 0.0 WB L 0 / 0 0.0 0.0 T 9 / 12 11.2 0.0 R 1 / 2 22.8 0.0 All 11.9 0.0 NB LTR 0 / 0 0.0 0.0 All 0.0 0.0 SB L 3 / 6 6.9 0.0 TR 2 / 3 18.6 0.0 All 11.6 0.0 Intersect. 12.9 SIG/Cinema v3.08 Marvin & Associates Page 2 95 620 1 1 1080 195 0 0 1 210 0 95 1 10 04 2 37 24 2 37 24 3 27 24 3 27 24 HCM Analysis Summary Year 2035 Conditions R Marvin Peak AM Hour Analysis Duration: 15 mins. Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2035 AM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 3 2 4 2 1 1 2 1 L 12.0 L 12.0 LTR 12.0 L 12.0 T 12.0 T 12.0 TR 12.0 TR 12.0 T 12.0 R 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 T 3 R 3 LTR 3 L 3 TR 3 130 0.80 1 880 0.80 3 0 0.80 0 1 0.80 0 530 0.80 3 130 0.80 1 0 0.80 0 0 0.80 0 1 0.80 0 120 0.80 2 0 0.80 0 75 0.80 2 0 5 0 0 --- --- 40 5 0 0 --- --- 0 0 0 0 --- --- 25 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y LTP LTP LTP LTP LTP 0 18.0 4.0 0.0 24.0 3.5 1.5 24.0 3.5 1.5 Pretimed 80.0 Sec 10.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 146 0.000 0.363 11.4 B Lpro 402 0.091 0.225 L 0.296 10.3 B * TR 2015 0.314 0.575 TR 0.546 11.6 B WB L 148 0.002 0.300 L 0.007 19.7 B 26.3 C T 1052 0.189 0.300 T 0.629 27.0 C R 476 0.071 0.300 R 0.235 22.2 C NB LTR 493 0.001 0.300 LTR 0.002 19.6 B 19.6 B SB * L 423 0.106 0.300 L 0.355 22.1 C 21.6 C TR 473 0.039 0.300 TR 0.131 20.4 C Intersection: Delay = 17.5sec/veh Int. LOS=B Xc= 0.48 * Critical Lane Group (v/s)Crit= 0.42 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2035 Conditions R Marvin Peak AM Hour Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2035 AM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 3 / 6 12.3 0.0 TR 6 / 8 16.4 0.0 All 15.7 0.0 WB L 0 / 0 0.0 0.0 T 6 / 9 10.3 0.0 R 1 / 1 23.7 0.0 All 10.9 0.0 NB LTR 0 / 0 0.0 0.0 All 0.0 0.0 SB L 2 / 3 9.3 0.0 TR 1 / 2 21.3 0.0 All 15.5 0.0 Intersect. 13.6 SIG/Cinema v3.08 Marvin & Associates Page 2 130 880 0 1 530 130 0 0 1 120 0 75 1 18 04 2 23 24 2 23 24 3 23 24 3 23 24 HCM Analysis Summary Year 2035 Conditions R Marvin Peak PM Hour Analysis Duration: 15 mins. Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2035 PM Area Type: Non CBD Lanes Geometry: Movements Serviced by Lane and Lane Widths (feet) Approach Outbound Lane 1 Lane 2 Lane 3 Lane 4 Lane 5 Lane 6 EB WB NB SB 3 2 4 2 1 1 2 1 L 12.0 L 12.0 LTR 12.0 L 12.0 T 12.0 T 12.0 TR 12.0 TR 12.0 T 12.0 R 12.0 East West North South LTRLTRLTRLTRData Movement Volume (vph) PHF % Heavy Vehicles Lane Groups Arrival Type RTOR Vol (vph) Peds/Hour % Grade Buses/Hour Parkers/Hour (Left|Right) L 3 TR 3 L 3 T 3 R 3 LTR 3 L 3 TR 3 95 0.92 1 620 0.92 3 1 0.92 0 1 0.92 0 1080 0.92 3 200 0.92 1 0 0.92 0 0 0.92 0 1 0.92 0 200 0.92 2 0 0.92 0 105 0.92 2 0 5 0 0 --- --- 60 5 0 0 --- --- 0 0 0 0 --- --- 30 5 0 0 --- --- Signal Settings: Operational Analysis Cycle Length: Lost Time Per Cycle: Phase: EB WB NB SB Green Yellow All Red 12345678 P e d O n l y LTP LTP LTP LTP LTP 0 10.0 4.0 0.0 38.0 3.5 1.5 28.0 3.5 1.5 Pretimed 90.0 Sec 14.0 Sec Capacity Analysis Results Approach: App GroupLane Cap(vph)v/sRatio g/CRatio LaneGroup v/cRatio Delay(sec/veh) LOS Delay(sec/veh) LOSEB Lper 84 0.000 0.478 11.2 B * Lpro 199 0.058 0.111 L 0.364 16.9 B TR 2025 0.193 0.578 TR 0.333 10.4 B WB L 316 0.001 0.422 L 0.003 15.1 B 25.9 C * T 1480 0.335 0.422 T 0.793 27.0 C R 671 0.096 0.422 R 0.227 17.4 B NB LTR 511 0.001 0.311 LTR 0.002 21.4 C 21.4 C SB * L 439 0.154 0.311 L 0.494 25.6 C 24.7 C TR 490 0.052 0.311 TR 0.167 22.6 C Intersection: Delay = 21.0sec/veh Int. LOS=C Xc= 0.65 * Critical Lane Group (v/s)Crit= 0.55 SIG/Cinema v3.08 Marvin & Associates Page 1 NETSIM Summary Results Year 2035 Conditions R Marvin Peak PM Hour Main Street/N 15th Avenue 07/11/2018 Case: Main & N 15th Year 2035 PM App Group Lane (veh) Avg/MaxPer LaneQueues (mph) SpeedAverage Period) (% of PeakWorst LaneSpillback in EB L 3 / 5 11.5 0.0 TR 4 / 5 17.5 0.0 All 16.2 0.0 WB L 0 / 0 0.0 0.0 T 9 / 12 11.1 0.0 R 1 / 2 23.1 0.0 All 11.8 0.0 NB LTR 0 / 0 0.0 0.0 All 0.0 0.0 SB L 3 / 6 7.5 0.0 TR 2 / 3 19.1 0.0 All 12.5 0.0 Intersect. 13.0 SIG/Cinema v3.08 Marvin & Associates Page 2 95 620 1 1 1080 200 0 0 1 200 0 105 1 10 04 2 37 24 2 37 24 3 27 24 3 27 24