February 5, 2019
Mr. Bob Murray,PE
City of Bozeman
20 East Olive St.
Bozeman,MT 59715
Reference: City of Bozeman Land Agent Services
Project Scope of Services—Task Order No. #4
Norton Sewer/Davis Lane Lift Station
Dear Bob:
Sanderson Stewart is pleased to provide this scope of services for land agent services for street and
utility improvements for the Norton Sewer/Davis Lane Lift Station project along Davis Lane,near
the intersection with Valley Center Road. These services are to be performed under the Professional
Services Agreement for Streets and Land Agent Services (FY 2018—FY 2020) term contract for
realty and engineering services. If this scope of services is acceptable to you,please execute this
agreement where noted.
Overview
We understand the City of Bozeman intends to construct sewer main improvements along Davis
Lane in the near future. The project improvements will provide an improved sanitary sewer main
distribution system to cover current and future development growth in the northwest part of
Bozeman. To facilitate the improvements,additional permanent and temporary right-of-way may be
required. Sanderson Stewart will provide professional right-of-way (R/W) acquisition services to
begin early property owner coordination efforts in the vicinity of Davis Lane and Valley Center
Road to determine the feasibility of acquiring additional R/W for a potential sewer lift station site.
Scope of Services
1. Project Research
This phase includes the preliminary R/W activities to obtain pertinent project information.
Tasks under Item 1 include the following:
%rMM� To Plan and Design
ikHOTFI RM
Enduring Communities...
www.sandersonstewart. com
Mr. Bob Murray
February 5,2019
Page 2
• Obtain and review available preliminary design plans and project documentation
• Coordination meeting with the project team members
• Obtain current deeds and ownership information for two (2) parcels
2. Initial Property Owner Contact
This phase includes initiating coordination efforts with affected property owners.Tasks
under Item 2 include the following:
• Compile contact information
• Initiate contact with two (2) owners of potentially affected property.The potentially
affected properties are the parcels on the southwest and southeast corner of the
intersection of Davis Lane and Valley Center Drive in Bozeman,Montana.
3. Appraisals and Valuations
This phase includes the preparation of appraisal and valuation documents to value the
property rights to be acquired.Tasks under Item 3 include the following:
• Full appraisal narratives or waiver valuations will not be prepared for this project.
• A review of current real estate market trends and property values will be researched
to determine an estimated land value cost for R/W to be acquired. Final land value
estimates will not be prepared for this project. The estimated land value information
will be used in early coordination discussions with two affected property owners as
noted above in Item 2.
• Team coordination
4. Project Administration
This phase includes activities to manage the project requirements, deliverables,and subtasks.
Tasks under Item 4 include the following:
• Project status updates
• Budget and schedule monitoring and planning
• Invoicing and billing
The following items are not included in the scope of services or project budget for this project and
are therefore specifically excluded from this scope of services:
Mr. Bob Murray
February 5, 2019
Page 3
• Preparation of R/W acquisition agreements,including easements, deeds, exhibits,
appraisals, and closing documents
• Engineering or R/W design services
• Eminent domain proceedings, expert witness testimony, costs, or other services
necessary for legal proceedings
• Additional costs related to the actual purchase price of property interests as detailed
in R/W acquisition agreements
• Relocation costs paid to property owners as detailed in R/W acquisition agreements
If needed, these items will be added as a separate task order or contract amendment.
Project Schedule
Once Sanderson Stewart receives authorization to proceed, Sanderson Stewart will proceed with
fulfilling the project scope of services immediately.The intent is to complete the R/W acquisition
activities in as short amount of time as necessary.The anticipated schedule for this project consists
of completing the final R/W acquisition within two weeks from the notice to proceed. This schedule
shall be equitably adjusted as the project progresses, allowing for changes in scope, character, or size
of the project requested by the Client, or for delays or other causes beyond Sanderson Stewart's
reasonable control.
The Client and Sanderson Stewart are aware that many factors outside Sanderson Stewart's control
may affect Sanderson Stewart's ability to complete the services to be provided under this agreement.
Sanderson Stewart will perform these services with reasonable diligence and expediency consistent
with sound professional practices.
Fees and Billing Arrangements
Task Fee
1. Project Research $362.50
2. Initial Property Owner Contact $337.50
3. Appraisals and Valuations $337.50
4. Project Administration $177.50
Total $1,215.00
Sanderson Stewart will bill for its services on a time and materials basis with a total cost not to
exceed 12$ , 15.00. Sanderson Stewart will begin work once this agreement has been executed by both
parties
I
r, 1
Mr. Bob Murray
February 5, 2019
Page 4
Sanderson Stewart shall submit invoices to the Client for work accomplished during each calendar
month. Monthly invoices shall include, separately listed, any charges for services for which time
charges and/or unit costs shall apply. Such invoices shall also include, separately listed,any charges
for consultants retained by Sanderson Stewart, and reimbursable costs. Such invoices shall be
submitted by Sanderson Stewart as soon as possible after the end of the month in which the work
was accomplished and shall be due and payable by the Client upon receipt. The Client agrees that
the monthly invoice from Sanderson Stewart is correct, conclusive,and binding on the Client unless
the Client,within 20 working days from the date of receipt of such invoice,notifies Sanderson
Stewart in writing of alleged inaccuracies, discrepancies, errors in the invoice, or the need for
additional backup.
**** END OF SCOPE OF SERVICES EXCEPT FOR SIGNATURES ****
This Task Order is dated reb.wawl s" , 20 1c%—between City of Bozeman,Montana (City)
and Sanderson Stewart(Contractor).
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and
year first above written.
CITY OF BOZEMAN, MONTANA SANDERSON STEWART
B B
Y: Y:
Print Name: A - Print Name: `, _nu G.d.4.
Print Title: ' cy- Print Title: Peo 7 t,G f
Date: Date: