HomeMy WebLinkAbout02-25-19 City Commission Packet Materials - C6. Construction Agreement with Lutey Construction for Streamline Bus AreaPage 1 of 2 Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Chuck Winn, Assistant City Manager SUBJECT: Construction Agreement with Lutey Construction for the remodel of the Streamline Bus waiting area into offices for the Parking Division and a smaller indoor waiting area and public restroom for Streamline. MEETING DATE: February 25, 2019 AGENDA ITEM TYPE: Consent RECOMMENDATION: Ratify City Manager’s signature on the Construction Agreement with Lutey Construction for the remodel of the former Streamline waiting area in the Bridger Park Parking Garage.. BACKGROUND: The City constructed the Bridger Park Parking Garage in 2009. An important part of the project was the addition of retail condominium spaces along three sides of the garage which allowed private investment in the project and brought mixed use and occupancy to the structure. The City owns one condominium unit which has been used by HRDC as a waiting area and public restrooms for bus patrons at the Streamline Transfer Station since 2009. HRDC has been responsible for maintenance and upkeep of the waiting area and Transfer Station. Over the years, the waiting area has been subjected to vandalism and other types of undesirable activity. Last year, police calls to the waiting area for criminal complaints reached a level that the Police Department closed the waiting area on President’s Day and strongly recommended it not be reopened until a plan for security could be implemented. Since that time, we have explored various options to increase security and safety at the site. We believe the best plan is to relocate the Parking Enforcement Division from the Stiff Professional Building to the remodeled space. This will accomplish three important things; 1. It will provide a parking staff presence at the garage which is our busiest public parking asset; 2. Having the Parking Division staff on-site will allow more oversight of the smaller waiting area and public restroom; and, 3. It will free up critical space in the Stiff Professional Building for additional employees authorized in this year’s budget but not yet hired due to space constraints. PROJECT: 46 Page 2 of 2 FISCAL EFFECTS: UNRESOLVED ISSUES: ALTERNATIVES: None identified. Attachments: Exhibit A: Construction Agreement Report compiled on: 02/07/2019 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 76 77 78 79