REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Shawn Kohtz, City Engineer
SUBJECT: Lead Service Line Removal and Replacement Project Contract Agreement
MEETING DATE: February 4th
, 2019
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Authorize the City Manager to sign the Contract Agreement with
Omdahl Excavation and Utilities, Inc. for a task order contract not to exceed $75,000.
BACKGROUND: Attached is a copy of the Contract Agreement for the above referenced
project. The project is for the individual lead service line replacement projects on a task order
basis. For each task order, the contractor will provide the City with a cost estimate and schedule
for the City’s approval prior to commencing work. The contractor(s) selected for each location
will be responsible for the replacement of the lead service lines from the water main up to and
including the curb stop and box inside of property. If lead or galvanized pipe still exists after the
curb box inside of property, it will be the contractor’s responsibility to replace that service line to
the residence. The contractor will also be responsible for abandoning the service lines at the
water main per City of Bozeman Water Department policy. The contractor(s) will be responsible
for the restoration of any asphalt, landscape or concrete removed during the project.
A request for qualifications and proposals was advertised on June 3rd
and June 10th
, with the
proposals dune on June 22nd
. Two contractors submitted proposals on the project. The proposals
were reviewed by a selection committee comprised of three City employees and both were
deemed qualified. A task order contract was previously executed with one of the contractors.
This is for the other. The project is budgeted in the FY19 Capital Improvement Plan (CIP) at
$200,000.00.
UNRESOLVED ISSUES: None
ALTERNATIVES: As suggested by the Commission.
FISCAL EFFECTS: The project will be paid from the Water Operations Fund.
Attachments: Contract Agreement, Bonds and Insurance
Report compiled on: 1/18/19