HomeMy WebLinkAbout18- Change Order 2 - Knife River Belgrade - East Tamarack Street Reconstruction Change Order
No. 2
Date of Issuance: October 18, 2018 Effective Date: October 18,2018
Project: East Tamarack Street Owner: City of Bozeman Owner's Contract No.: N/A
Reconstruction
Contract: East Tamarack Street Reconstruction Date of Contract: July 18,2018
Contractor: Knife River- Belgrade Engineer's Project No.: 16417100
The Contract Documents are modified as follows upon execution of this Change Order:
Description:
Add Pay Items for Additional Work for Project Fiber Conduit, including modifying the installation of a portion of
The conduit to open trench at a reduced unit cost.
Attachments (list documents supporting change):
Bid Item Summary of Changes
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: Original Contract Times: Working Calendar days
Substantial completion(days or date):
$ 1,627,588.00 Ready for final payment(days):
Increase fi•om previously approved Change Increase fiom previously approved Change Orders
Orders No. 1 to No. 1: No. to No.
Substantial completion(days):
$ 1,521.50 Ready for final payment(days): N/A
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial completion(days or date): N/A
$ 1,629,109.50 Ready for final payment(days):
Decrease of this Change Order: Increase of this Change Order:
Substantial completion(days or date): N/A
$ 10,262.50 Ready for final payment(days):
Contract Price incorporating this Change Contract Times with all approved Change Orders:
Substantial completion(days or date): N/A
$ 1,618,847 Ready for,final payment(date):
REC;ngineer
ED: AC PT D: ` ACCEPTED: �?
By: B By:
(AtlYhorizgd Signature) Owner(Authori ed ignature Contractor(Authorized Signature)
11 //
Date: Zd / j(� Date: 1 1 Date: /0-
Approved by Funding Agency(if applicable):
Date:
EJCDC C-941 Change Order
Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute.
Page 1 of 2
Date of Issuance: October 18, 2018 Effective Date: October 18, 2018
Project: E. Tamarack Street Owner: City of Bozeman Owner's Contract No.: N/A
Reconstruction
Contract: E. Tamarack Street Reconstruction Date of Contract: July 18, 2018
Contractor: Knife River-Belgrade Engineer's Project No.: 16417100
You are hereby requested to comply with the following changes from the contract plans and specifications:
Bid Item Description of Changes DECREASE INCREASE
No. in Contract Price in Contract Price
A101 Delete 350 LF of BM60(4X2"SDRI I HDPE,Bundled with 20 $28,525.00
Ga.Tracer Wire $81.50/LF
A103 Add 350 LF of BM60(4X2"SDRI1 HDPE,Bundled with 20 Ga. $7,875.00
Tracer Wire)—Open Trench Installation $22.50/LF
A104 Add 90 LF of BM60(4X2"SDRI 1 HDPE,Bundled with 20 Ga $1,687.50
Tracer Wire)-Installed through existing conduit @$18.75/1,17
A 105 Add 90 LF of BM60(1—2"SDRI 1 HDPE,Bundled with 20 Ga. $3,600.00
Tracer Wire)—Directional Drill Installation $40/LF
A106 Add 4 EA of BHF 30X48X36 T—Labor Only $1,275/EA $5,100.00
TOTALS $28,525.60 $18,262.50
NET CHANGE IN CONTRACT PRICE $10,262.50