HomeMy WebLinkAbout11-19-18 City Commission Packet Materials - C8. Res 4976, Approve CO 2 with Knife-River for E. Tamarack Reconstruction Project Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Bob Murray, Project Engineer Rick Hixson, City Engineer SUBJECT: Approve Resolution 4976 authorizing Change Order No. 2 to the East Tamarack Street Reconstruction Project. MEETING DATE: November 19, 2018 AGENDA ITEM TYPE: Consent RECOMMENDATION: Approve Resolution 4976 authorizing Change Order No. 2 to the East Tamarack Street Reconstruction Project. BACKGROUND: Attached is a copy of resolution 4976 and change order number 2 for the above referenced project. This change order request includes adding pay items for the conduit work to reduce the cost and to add conduit crossings and handholes on the south side of Tamarack. A review with the contractor in the field identified approximately 350 lineal feet of conduit that could be installed by open trench in lieu of directional drilling resulting in a cost reduction. The additions to the south side of Tamarack were recommended by Bozeman Fiber to better serve the area. Overall the change will result in a decrease in the contract price of $10,262.50. There is no change to contract time. The final recommended change in cost and time for these items is reasonable and commensurate with the work involved. UNRESOLVED ISSUES: None ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: This change order decreases the contract amount by $10,262.50 from $$1,629,109.50 to $1,618,847.00. Attachments: Resolution No 4969, Change Order No 2 Report compiled on: 10/26/18 120 COMMISSION RESOLUTION NO. 4976 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH KNIFE RIVER - BELGRADE, BELGRADE, MONTANA. WHEREAS, the City Commission did, on the 11th day of June 2018, authorize award of the bid for the City of Bozeman East Tamarack Street Reconstruction project, to Knife River - Belgrade, Belgrade, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and Knife River - Belgrade, as contained in Change Order No. 2, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 121 PASSED, ADOPTED, AND APPROVED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 19th day of November, 2018. ______________________________________ CYNTHIA L. ANDRUS Mayor ATTEST: ___________________________________ ROBIN CROUGH City Clerk APPROVED AS TO FORM: ______________________________________ GREG SULLIVAN City Attorney 122 123 124