HomeMy WebLinkAbout18- Change Order 1 - Knife River - Baxter Lane from Davis Lane to North 19th Avenue CHANGE ORDER
No. 1
DATE OF ISSUANCE rYY 711ryg� N EFFECTIVE DATE
OWNER City of Bozeman CONTRACTOR Knife River
Contract: Baxter Lane from Davis Lane to N. 19"'Ave.
Project: Baxter Lane,from Davis Lane to N. 19"Ave. OWNER's Contract No.
ENGINEER RPA ENGINEER's Contract No. 14509
You are directed to make the following changes in the Contract Documents:
• Revise the original 37"pavement section(5"asphalt, 8"base course,24"subbase course)to a 23"
pavement section(6"asphalt, 17"base course)per the Geotechnical Report alternate pavement section.
Includes the addition of a new bid item for Embankment/Borrow material to balance the project
earthwork,since the project no longer has excess excavation with the shallower pavement section.
• Remove chip seal.
• Remove thermoplastic pavement markings and replace with Epoxy. Increase the quantity of Remove
Pavement Markings(outside of reconstruction areas)due to the removal of the chip seal that would have
previously covered the existing markings.
• Remove the proposed concrete driveway, sump, and trench drain at 55+50 LT. (per the developer)and
place the new driveway at 60+25 LT. (per developer)as a City Standard Non-Residential driveway.
• Revise the proposed asphalt driveway at 76+60 LT. to a City Standard Non-Residential driveway at
77+00 LT.Replace asphalt surfacing behind sidewalk with gravel surfacing(final asphalt connection to
be completed by the developer after their site plan is approved)
Reason for Change Order: To reduce project scope of work and cost to fit within the budget amount.Revise
driveways due to current adjacent private site plan development.
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times:
Substantial Completion: 170 calendar days
$4,147,364.00 Ready for final payment:
(days or dates
Net Increase(Decrease)from previous Change Net change from previous Change Orders No._to
Orders No. to No._
Substantial Completion: n/a
$n/a Ready for final payment:
(da ys)
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: 170 calendar days
S 4,147,364.00 Ready for final payment:
(days or dates)
Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order:
Substantial Completion: 0 calendar days
(S272,166.00) Ready for final payment:
(days)
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
Substantial Completion: 170 calendar days
$3.875,198.00 Ready for final payment:
(days or dates)
CHANGE ORDER FORM
Pagel of 3
Contractor certifies and agrees that there are no additional costs or claims for extra work,additional time,delays or
omitted items,of any nature whatsoever,associated with the subject change order items,except as identified and set
forth herein and unless expressly stated otherwise in the Change Order. And further,that the price agreed-upon herein
represents the full cost and value for the subject work performed and the materials supplied under the terms of the
contract and that the work quantities and value were properly determined and are correct.
ZZ:x—
�7ATe"C R(Authorized Signature) Oate
RECOMMENDED BY: APPROVED BY:
*0
9/19/18
(ENGINEER- Signature) Date OWNER(Aut orizedSignature) Date
II
i
�I
CHANGE ORDER FORM
Page 2 of 3
CHANGE ORDER
INSTRUCTIONS
A. GENERAL INFORMATION
This document was developed to provide a uniform format for handling contract changes that affect Contract
Price or Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into
a subsequent Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The
practice of accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes.
If Milestones have been listed in the Agreement,any effect of a Change Order thereon should be addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times,
a Field Order should be used.
E. COMPLETING THE CHANGE ORDER FORM
Engineer normally initiates the form, including a description of the changes involved and attachments based upon
documents and proposals submitted by Contractor,or requests from Owner, or both.
Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval,
depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated
agreement for a previously performed change. After approval by one contracting party,all copies should be sent
to the other party for approval. Engineer should make distribution of executed copies after approval by both
parties.
If a change only applies to price or to times,cross out the part of the tabulation that does not apply.
CHANGE ORDER FORM
Page 3 of 3
CHANGE ORDER #1
PROJECT TITLE: Baxter Lane from Davis Lane to N. 19'h Ave.
CHANGE ORDERED ITEMS
Item Description Quantity Units Unit Price Amount Extra Basis of Unit Price
No. Work
Days
53 Increase Asphalt thickness from 914 TON $70.00 $63,980.00 n/a Bid Proposal
5"to 6"(from 4,812 to 5,740 tons)
Reduce at 76+60 driveway(from
17 tons to 3 tons
52 Increase Crushed Base Course 4,796 CY $32.00 $153,472.00 n/a Bid Proposal
from 8"to 17" (4,430 to 9,230 CY)
Reduce at 76+60 driveway(from
22 to 18 CY
51 Reduce Subbase Course from CY $28.00 -$355,o 00 n/a Bid Proposal
24"to 0" 12,679 to 0 CY
47 Reduce Street Exc.for surfacing CY $18.00 -$112,770.00 n/a Bid Proposal
revision 17,520 to 11,255 CY
NEW Add Embankment 6,500 CY $25.00 $162,500.00 n/a Negotiated with
80 Contractor _
55 Remove Asphalt Seal &Chip SY $2.00 .$59,840.00 n/a Bid Proposal
Coat
75 Adjust Pavement Markings 1 LS >-140,000 $140,000.00 n/a Negotiated with
(Replace thermoplastic with Contractor
epoxy markings. Revise LS cost
from $204,000 to$64,000
23 Remove Trench Drain item of LF $200.00 -$6,600.00 n/a Bid Proposal
work
45 Remove Sump Inlet item of work EA $3,800.00 800.00 n/a Bid Pro osal
58 Add Curb&Gutter for non-resid. 16 LF $13.50 $216.00 n/a Bid Proposal
Drivewayat 76+60
56 Reduce Concrete Sidewalk for SY $51.00 $3,P64,0(' n/a Bid Proposal
driveway aprons
NEW Add Remove Pavement Markings 1 LS $28,952.00 $28,952.00 n/a Negotiated with
81 outside reconstruction limits (for Contractor
chi seal removal
Total Change Ordered Amount= -$212,
Extra Work Days Granted= 0 days
Change Order
Page 1
AMMOUlEi01M UCOMPMNY www.loi arkwAmm
Inbennouniatn Region-Belgrade Division
PO Box 9
Belgrade,MT 59714
(406)388-6832
(406)388-8347 Fax
Robert Peccia and Associates September 11"',2018
Staci Venner, P.E.
3810 Valley Commons Dr.#4
Bozeman,MT 59718
RE: Baxter Lane Improvements Project—Davis Lane to 19"'Ave.
Additional Pavement Marking Removals
Dear Staci,
Per your request Knife River is providing the following pricing for the additional pavement marking
removals based on the revised plans and updated quantities.
Description Unit Quantity I Unit Price Total
Remove Pavement Markings LS 1 1 1 $ 28,952.00 $ 28,952.00
1.) Above pricing is based on the updated removal quantities.
a. Thermoplastic Removal—1,470 SQFT
b. Additional Epoxy Removal—2,620 SQIFT
2.) Thermoplastic removal includes removal of thermoplastic pavement markings with hot mix
asphalt patch at the various locations.
3.) Additional epoxy removal includes use of line gander. No asphalt patching or fog seal is
included.
Please feel free to call (406-209-7372)with any questions.
Sin e�
I
Josh Walter
Project Manager/Estimator
Knife River-Belgrade
EQUAL OPPORTUNITY EMPLOYER
• KNIFE RIVF-R
AN YDU RESOURCF.f COrAE1IWY Yrww.loiihrireroom
Intem mntsin Reglon-Belgrade Division
PO Banc 9
Belgrade,MT 59714
(406)388-8832
(406)388-8347 Fax
June 271',2018
Robert Peccia and Associates
Staci Venner,P.E.
3810 Valley Commons Dr.#4
Bozeman, MT 59718
RE: Baxter Lane Improvements Project—Davis Lane to 19'"Ave.
Cost Savings
Dear Staci,
Per your request Knife River is providing the following letter concerning the potential cost saving
measures on the above referenced project:
1. Revised Pavement Section
We have reviewed the revised quantities on changing the original 37" pavement section(S"
Asphalt,8" Base Course and 24"of Subbase)to a 23"pavement section(6"Asphalt and 17"
Base Course)and offering the following revised pricing for this change:
odginsi Revised
Item Description Quantity Unit Unit Pdw Total Quantity Unit Unit Price Total Savings
47 Street Excavation 17520 CY $18.00 $315,360.00 12255 CY $18.00 $202,590.00
Embankment-NEW ITEM 650D CY $25.00 $162,SW.00 $MS00.00
51 Subbase 12679 CY $28.00 $355,01Z00 0 CY $0.0D $0.00
52 Crushed Base 4430 CY $32.00 $141,760.00 9425 CY $32.00 $301,600.00 $159,UD.00
53 Asphalt Paving -iia--T TN $70.00 $336,840.00 5775 TN $70.00 $404,250 00 1 $67,410.00
2. Chip Seal Removal
We have reviewed the removal of the chip seal from our scope and are acceptable with this
change.
Original Revised
Item IDescription Quantity JUnItl Unit Price I Total I Quantity I Unit I Unit Price I Total Savings
55 IChip Seal M20 1 Sy 1 $2.00 109,TIM00 L 0 1 Sy $0.00 $0.00
EQUAL OPPORTUNITY EMPLOYER
3. Remove all Thermoplastic Pavement Markings and Replace with Epoxy
We have reviewed the change from thermoplastic pavement markings to all epoxy pavement
markings and offer the following revised pricing for this change.
- - --- -- Original - - --- _ - Revised
Item Desaf tion Quantity Unit Unit Price Total Quantity Unit unitOrioe Total Savin
75 Pavement Markings 1 LS $204,000.00 $204,00D.W 1 LS $64,000.00 $64,o00.OD
Based on the scope change and estimated quantity adjustments we anticipate an overall project cost
savings of approximately$277,872.00.
In addition,with the removal of the chip seal from the contract we anticipate additional pavement
marking removal will be required.This additional removal is not reflected in any of the above pricing.
Please feel free to call(406-924-5572)with any questions.
Sincere-ly,
Josh Walter
Project Manager/Estimator
Knife River-Belgrade