HomeMy WebLinkAbout18- Task Order 1 - Sanderson Stewart - Right-of-Way Acquisition at Baxter Lane and Cottonwood Road S A N D E R S O N t!•�
STEWART
September 18,2018 SEP i 8 2014
Mr.Rick Hixson,PE,City Engineer
City of Bozeman
20 East Olive St.
Bozeman,MT 59715
Reference: City of Bozeman Land Agent Services
Project Scope of Services—Task Order No. 1
Baxter and Cottonwood Intersection
Dear Rick:
Sanderson Stewart is pleased to provide this scope of services for land agent services for street and utility
improvements at the intersection of Baxter Lane and Cottonwood Road. These services are to be performed
under the Professional Services Agreement for Streets and Land Agent Services (FY 2018 —FY 2020) term
contract for realty and engineering services. If this scope of services is acceptable to you,please execute this
agreement where noted.
Project Overview:
We understand the City is planning to construct new roadway improvements at the intersection of Baxter Lane
and Cottonwood Road. As part of a previous contract with another firm,discussions with adjacent land owners
had taken place,but agreements were not finalized to acquire the required right-of-way. Since then,an adjacent
land owner has approached the City to complete the acquisition process. To complete the acquisition process,
Sanderson Stewart will provide professional right-of-way (R/W) acquisition services to acquire new roadway
R/W for the new intersection improvements as shown on the attached Figure 1.
Scope of Services:
1. Project Research
This phase is not included in this scope of services.
2. Initial Property Owner Contact
This phase is not included in this scope of services.
3. Survey
This phase is not included in this scope of services.
4. R/W Mapping&Exhibits
This phase consists of the preparation of R/W exhibits to acquire property interests. Tasks under Item 4
include the following:
• An easement exhibit had already been prepared. The City will provide the completed exhibit.
5. Title Commitments
This phase consists of the preparation of title commitments by a licensed title company. Tasks under Item
5 include the following:
• A title commitment had already been prepared over one year ago. A new title commitment will be
ordered for Parcel 1.
• Team coordination.
6. Appraisals and Valuations
This phase includes the preparation of appraisal and valuation documents to value the property rights to
be acquired. Tasks under Item 6 include the following:
• A full narrative appraisal was prepared November 18,2016. The City will provide the appraisal.
• Due to the age of the appraisal, an adjustment to the compensation is anticipated to be requested
during acquisition meetings. Sanderson Stewart will prepare one (1) administrative settlement form to
address compensation adjustments.
• QA/QC of the administrative settlement.
7. Prepare Contracts
This phase includes the preparation of offer packages to acquire R/W, including agreements, deeds,
easements, exhibits, figures,and correspondence letters. Tasks under Item 7 include the following:
• A completed offer package had already been prepared. The City will provide the offer package
documents.
• The initial offer package will be updated to include the administrative settlement.
• QA/QC of documents.
8. Acquisitions
This phase includes conducting the acquisition meetings with affected property owners and modifying the
initial offer packages based on owner/client meetings. Tasks under Item 8 include the following:
• Conduct acquisition meetings with the owners of Parcel 1 (minimum of 5 meetings).
• Prepare final acquisition documents.
• Prepare final acquisition costs.
• QA/QC of documents.
9. R/W and Design Plan Updates
This phase is not included in this scope of services.
10. Relocation Services
This phase is not included in this scope of services.
11. Title Clearing and Closing
This phase includes coordinating and completing the title closing process with the title company. Tasks
under Item 11 include the following:
• Prepare final tide transfer documents,and schedule closing date.
• Obtain mortgage releases, clear taxes and leans, as required.
• Submittal of completed R/W acquisition offer packages to the City for review and execution.
• Team coordination.
• Attend closing meetings.
12. Final Submittal and Closeout
This phase includes the final project activities to finalize and submit executed R/W acquisition and title
transferring documents. Tasks under Item 12 include the following:
• Prepare R/W acquisition project submittal packet.
• Deliver completed tide transfer documents.
• Project closeout.
13. Contingency
The scope of services for this project includes all the necessary steps to acquire property interests from
private owners. A majority of the acquisition process relies on good cooperation and timely responses
from all parties involved in the process. Due to the nature of coordination activities, the amount of time
required to work with individual property owners varies significantly. This task serves to capture the
potential additional costs incurred during the acquisition process due to challenging coordination activities
with property owners.
The following items are not included in the scope of services or project budget for this project and are therefore
specifically excluded from this scope of services:
• Engineering or right-of-way design services.
• Eminent domain proceedings, expert witness testimony, costs, or other services necessary for legal
proceedings.
• Additional costs related to the actual purchase price of property interests as detailed in R/W acquisition
agreements.
• Relocation costs paid to property owners as detailed in R/W acquisition agreements.
If needed, these items will be added as a separate task order or contract amendment.
Fees and Billing Arrangements:
Task Fee
1. Project Research $0.00
2. Initial Property Owner Contact $0.00
i
3. Survey $0.00
4. R/W Mapping&Exhibits $0.00 .
5. Title Commitments $552.50
6. Appraisals and Valuations $570.00
7. Prepare Contracts $577.50
8. Acquisitions $2,610.00
9. R/W and Design Plan Updates $0.00
10. Relocation Services $0.00
11. Title Clearing and Closing $1,012.50
12. Final Submittal and Closeout $392.50
13. Contingency $1,530.00
14. Project Administration $255.00
Subconsultant $0.00
Total $7,500.00
Sanderson Stewart will bill for its services on a time and materials basis with a total cost not to exceed 7 500.00.
Sanderson Stewart shall submit invoices to the Client for work accomplished during each calendar month.
Monthly invoices shall include, separately listed, any charges for services for which time charges and/or unit
costs shall apply. Such invoices shall also include, separately listed, any charges for consultants retained by
Sanderson Stewart,and reimbursable costs.
Project Schedule:
Once Sanderson Stewart receives authorization to proceed, Sanderson Stewart will proceed with fulfilling the
project scope of services immediately. The intent is to complete the R/W acquisition activities in as short
amount of time as necessary. The anticipated schedule for this project consists of completing the filial R/W
acquisition within 4 months from the notice to proceed.
****END OF SCOPE OF SERVICES EXCEPT FOR SIGNATURES ****
This Task Order is dated ,20_between City of Bozeman,Montana (City) and
Sanderson Stewart(Contractor).
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and year first
above written.
CITY OF BOZEMAN,MONTANA SANDERSON STEWART
By: By:
Print Name: &d yra Print Name: Trw
Print Title: (MN V1/19 .r Print Title: Piro►ed Itil��o•Cw
Date: . I Z�61 V, Dater h0 8
FIGURE 1
PRELIMINARY R/W ACQUISITION
WITHIN
TRACT 5 OF C.O.S. 2202
PREPARED FOR CITY OF BOZEMAN AUGUST, 2018
PREPARED BY SANDERSONSTEWARTW BOZEMAN, MONTANA
EXISTING
PROPERTY LINE
(TYP)
PARCEL 1 PUE
NEW PUBLIC USE
I \ \ \EASEMENT
O
LLI
t
V\ \
( t \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \
LLI
Q ...:_........_...:<..........
------------------
:_::..
t.._.
....._. ........
.......__........_:..... .....__....._......::.:::.._._._:.:-..::.:.._.:
PA
3 4`
4 3 E
R_/W LEGEND
20 0 20 40 ® EXISTING ROAD R/W
w NEW EASEMENT AREA BAXTER-COTTONWOOD
NORTH SCALE:1:40_XREF AREA REMAINING PARCEL 1
FIGURE t.DWG OS/15/18 TG