The following services will be provided by the Contractor under the terms of the contract:
Scope
• Review the Electrical Design Bid Drawings
• Relocate the main electrical feeds coming into building
• Relocated the main electrical mast
• Install new main disconnect, CT cabinet and relocate electrical meter
• Install new three phase electrical panel
• Reconfigure a number of electrical circuits/breakers
• Pull required permits for work
• Schedule shutdown with Northwestern Energy
• Work with City of Bozeman on shutdown schedule, IT servers in building support Life Safety
Systems
• Provide electrical support for generator back-up to IT servers
• Afterhours or weekend installation should be accounted for in quote
• Contractor will be responsible for following all municipal, state, and federal regulatory
requirements
• A City of Bozeman Construction Contract will be created for this project
• A Pre-Construction meeting will take place with CDS Engineering and the City once the award to
proceed is issued.
Construction Specification
• Basic construction drawing were provided to contractor that detailed layout that needs to be
followed.