HomeMy WebLinkAbout08-20-18 City Commission Packet Materials - C13. Res. 4951, CO1 with Williams Bro. for WRF Small Works Project
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission FROM: Brian Heaston, Senior Engineer
Shawn Kohtz, Interim Director of Public Works
SUBJECT: Resolution 4951 Authorizing Change Order No. 1 to the WRF Small Works Construction Project
MEETING DATE: August 20, 2018
AGENDA ITEM TYPE: Consent RECOMMENDATION: Approve Resolution 4951 authorizing Change Order No. 1 to the
WRF Small Works Construction Project.
BACKGROUND: Attached is Resolution 4951 and Change Order No. 1 for the above referenced project. The change order covers minor items identified during construction requiring work not included in the construction contract but authorized under change proposal requests
made by the Contractor and negotiated and approved by the Engineer and City during the
progress of the work. Change Order No. 1 amends the contract price by a net increase of $20,254.63 and adds 67 days to the contract time. The contract time extension was necessary to allow membrane roof replacement for Digester 1, Digester 2 and the old admin building to occur during dry weather conditions.
FISCAL EFFECTS: Work authorized under the change proposal requests made by the Contractor and approved by the Engineer have already been paid. Change Order No. 1 amends the contract price for the project to $859,054.63. Sufficient capital funding exists in the WRF budget to cover the total amended contract price.
ALTERNATIVES: As suggested by the Commission ATTACHMENTS: Resolution 4951 Change Order No. 1
221
RESOLUTION NO. 4951
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH
WILLIAMS BROTHER CONSTRUCTION, LLC, SPOKANE, WASHINGTON
WHEREAS, The City Commission did, on the August 28, 2017, authorize award of the bid
for the WRF Small Works Construction Project to Williams Brother Construction, LLC, Spokane,
Washington; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such
alterations or modifications of the specifications and/or plans of the contract be made by
resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations
or modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of
Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the
City of Bozeman, a municipal corporation, and Williams Brother Construction, LLC, as contained
in Change Order No. 1, attached hereto, be and the same are hereby approved; and the City
Manager is hereby authorized and directed to execute the contract change order for and on behalf
of the City; and the City Clerk is authorized and directed to attest such signature.
222
PASSED, ADOPTED, AND APPROVED by the City Commission of the City of
Bozeman, Montana, at a regular session thereof held on the 20th day of August, 2018.
___________________________________
CYNTHIA L. ANDRUS
Mayor
ATTEST:
__________________________________
ROBIN CROUGH
City Clerk
APPROVED AS TO FORM:
___________________________________
GREG SULLIVAN
City Attorney
223
EJCDC® C-941, Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Page 1 of 2
Change Order No. 01
Date of Issuance: 8/1/2018 Effective Date: 8/1/2018
Owner: City of Bozeman Owner's Contract No.:
Contractor: Williams Brother Construction Contractor’s Project No.:
Engineer: HDR Engineering Engineer's Project No.:
Project: Bozeman WRF Small Works Project Contract Name:
The Contract is modified as follows upon execution of this Change Order:
Description: Includes CPR’s No. 1 through 8:
CPR No. 1 Mixer gaskets $1,950.00
CPR No. 2 Additional Mixer Bolts $4,523.98
CPR No. 3 Digester No. 1 Risers and paint $ 8,413.66
CPR No. 4 Credit for Digester Cleaning $ (2,295.00)
CPR No. 5 Electrical Broken Connections $246.24
CPR No. 6 VFD replacement $6,713.75
CPR No. 7 Conduit for PSH's on WAS Pumps $702.00
CPR No. 8 No cost time extension $0.00
Subtotal $20,254.63
Attachments: CPR’s No. 1 through 8
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES
[note changes in Milestones if applicable]
Original Contract Price: Original Contract Times: Substantial Completion: April 14, 2018
$ 838,800.00 Ready for Final Payment: May 4, 2018
days or dates
Increase from previously approved Change Orders No.
to No. :
Increase from previously approved Change Orders No.
to No. :
Substantial Completion: N/A
$ N/A Ready for Final Payment:
days
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: April 14, 2018
$ 838,800.00 Ready for Final Payment: May 4, 2018
days or dates
Increase of this Change Order: Increase of this Change Order:
Substantial Completion: June 20, 2018
$ 20,254.63 Ready for Final Payment: July 10, 2018
days or dates
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial Completion: June 20, 2018
224
225
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order) HDR ENGINEERING, INC. Project: Bozeman WRF Small Works CPR No: 01 CPR Date: 10/30/2017 Date Sent to Contractor: 10/30/2017 Date Rec'd from Contractor: ________________ TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
During removal of the draft tubes for Digester No. 2, it was noted that the two lower gaskets were in need of replacement. It is
assumed that the gaskets should be closed-cell neoprene, ¼” thick, matching the existing size and bolt pattern. Please provide
costs for replacing the four (4) gaskets.
HDR: Coralynn Revis___________________________________________________ Date: 10/30/2017
TO: HDR Engineering, Inc. Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:) Contractor: ________________________________________________ Date: __________________________ TO: Town of Stevensville
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________
226
Bozeman Small Works BWC
Gaskets for Mixers Date: 11-13-17
Unit Cost Items
Description Unit Quantity Cost (NWP)
New Gaskets $243.75 ea 8 $1,950.00
Subtotal $1,950.00
Markup
TOTAL $1,950.00
227
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order) HDR ENGINEERING, INC. Project: Bozeman WRF Small Works CPR No: 02 CPR Date: 10/30/2017 Date Sent to Contractor: 10/30/2017 Date Rec'd from Contractor: ________________ TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
Replacement of bolts as needed for Digester No. 2 per response to RFI.
HDR: Coralynn Revis___________________________________________________ Date: 10/30/2017
TO: HDR Engineering, Inc. Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:) Contractor: ________________________________________________ Date: __________________________ TO: City of Bozeman
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________
228
Bozeman Small Works BWC
Field Order to remove and Replace 46 Additional Bolts Date: 11-13-17
Unit Cost Items
Description Unit Quantity Cost (NWP)
3/4" SSHilti Bolts $10.00 ea 46 $460.00
Hilti Hit Epoxy $37.50 ea 9 $337.50
Core Drill Bits $78.00 ea 2 $156.00
Labor
Description Unit Quantity Cost
Laborer $39.36 hr 27.5 $1,082.40
Millwright $51.30 hr 27.5 $1,410.75
Superitendant $45.00 hr 8 $360.00
Equipment
Description Unit Quantity Cost
Core Drill $5.00 hr 12 $60.00
Sub- Contractors
Description Unit Quantity Cost
Subtotal $3,866.65
Markup $657.33
TOTAL $4,523.98
229
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order) HDR ENGINEERING, INC. Project: Bozeman WRF Small Works CPR No: 03 CPR Date: 12/18/2017 Date Sent to Contractor: 12/18/2017 Date Rec'd from Contractor: ________________ TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
The support risers on Digester No. 1 joint appears lower than planned from the as-builts. It is assumed a cold joint exists right
along the roof line. Provide costs for removal and replacement of both risers by chipping down to the cold joint along the roof
and replacement.
HDR: Coralynn Revis___________________________________________________ Date: 12/18/2017
TO: HDR Engineering, Inc. Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:) Contractor: ________________________________________________ Date: __________________________
230
Bozeman Small Works HDR/WBC
CPR 03 Time and Materials 3/27/2018
Unit Cost Items
Description Unit Quantity Cost (NWP)
Extra Concrete and Rebar $500.00
Labor
Description Unit Quantity Cost
Demolition
Superintendent-3/26/2018 $45.00 hr 8 $360.00
Superintendent-3/27/2018 $45.00 hr 7.5 $337.50
Superintendent-3/28/2018 $45.00 hr 4 $180.00
Superintendent 3/29/2018 $45.00 hr 8 $360.00
Superintendent 04/04/2018 $45.00 hr 5.5 $247.50
Super 4/16 $45.00 hr 6 $270.00
Super 4/17 $45.00 hr 8 $360.00
Laborer 4/17 $39.36 hr 6 $236.16
Equipment
Description Unit Quantity Cost
18" Hydraulic wet saw $20.00 hr 8 $160.00
Electric Demo Hammer $15.00 hr 12 $180.00
Sub- Contractors
Description Unit Quantity Cost
T&L Painting $4,000.00
Subtotal
Markup $7,191.16
TOTAL $1,222.50
$8,413.66
231
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order) HDR ENGINEERING, INC. Project: Bozeman WRF Small Works CPR No: 04 CPR Date: 1/29/2018 Date Sent to Contractor: 1/29/2018 Date Rec'd from Contractor: ________________ TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
Modification of CY of Digester No. 1 cleaning for reconciliation with bid. Planned bid was 520 CY, total was 493 CY. Credit is
for 27 CY. Credit of $2,295 due.
HDR: Coralynn Revis___________________________________________________ Date: 1/29/2018
TO: HDR Engineering, Inc. Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:) Contractor: ________________________________________________ Date: __________________________ TO: City of Bozeman
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________
232
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order) HDR ENGINEERING, INC. Project: Bozeman WRF Small Works CPR No: 05 CPR Date: 1/29/2018 Date Sent to Contractor: 1/29/2018 Date Rec'd from Contractor: ________________ TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
Electrical addition for broken connections at Digester No. 2 mixers.
HDR: Coralynn Revis___________________________________________________ Date: 1/29/2018
TO: HDR Engineering, Inc. Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:) Contractor: ________________________________________________ Date: __________________________ TO: City of Bozeman
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________
233
51 Lost trail
Clancy, MT 59634, U.S.A. (406) 431-3368 - Cell (406) 438-1789 - Office rlevandowski@frontierelectric.us
REQUEST FOR A CHANGE
Date: December 13, 2017
To: Barry Curtis
From: Robert Levandowski
Project No.: City of Bozeman WRF Small Works Project No. 1
CHANGE: Frontier Electric hereby submits a request for a change on the above-referenced project. DESCRIPTION: Plant personnel disconnected the motors and broke/lost pieces for the re-
installation. $222.24 for parts/ $24.00 rental fee.
This proposed change will result in an increase cost of $246.24
RESPONSE:
Approved: ____________________________ Date: _______________________________________ Since time is of the essence and the impact of this change may be significant, Frontier Electric requests
that Williams Brothers Construction (Barry Curtis) respond to this
request within 10 working days.
Sincerely,
Robert Levandowski
Project Manager
Frontier Electric
234
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order)
HDR ENGINEERING, INC.
Project: Bozeman WRF Small Works CPR No: 06
CPR Date: 2/27/2018
Date Sent to Contractor: 2/27/2018
Date Rec'd from Contractor: ________________
TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
Replace specified 5HP VFDs with ABB # ACS310-03U-17A2-4+J400/7.5 kw10HP Lift 1: Install new rating plugs (30A) in the two breakers and run #10 wire to the 10HP VFDs. Recommended rating plugs are found on the following page. Lift 2: Replace 7 amp breaker with 30 amp and installation of #10 wire. Recommended breaker is displayed on following page.
HDR: Ben Fennelly, Dan Harmon, Cora Revis________________________________________________ Date: 2/27/2018
TO: HDR Engineering, Inc.
Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:)
Contractor: ________________________________________________ Date: __________________________
TO: City of Bozeman
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________
235
City of Bozeman WRF Small Works Project No. 1
RECOMMENDED RATING PLUG:
GENERAL ELECTRIC SRPE30A30 RATING PLUG
RECOMMENDED 30 AMP BREAKER:
EATON / CUTLER HAMMER HFD3030 3 POLE CIRCUIT BREAKER
236
Item Part #Note QNTY Cost ea.Cost Labor hours Labor cost
10 HP VFDs ACS310-03U-17A2-4+j400 3 $1,562.25 4,688.25 3 $240.00
GE 30 amp plug SRPE30A30 2 $277.00 $554.00 2 $160.00
Eaton 30 Amp Breaker HFD3030 1 $836.00 $836.00 2 $160.00
Credit 1 $900.00 $900.00 0 $0.00
$0.00 0 $0.00
0 $0.00
$0.00 0 $0.00
$0.00 0 $0.00
$0.00 0 $0.00
$5,178.25 $560.00
Bozeman WWTP 10 HP VFDs
TOTAL $5,738.25
237
Work order for Time and Materials
Thank You For Your Business
MT LIC #2505 Phone Order Date:
51 Lost Trail 2/27/2018
Clancy, MT 59634 Order taken Robert
406-431-3368 Job Site:
Bill To:
[x ] Day W [ ] Contract [ ] Extra
Qty Materials Price Total
Discription of Work
0 ABB 10 HP 480VAC VFDs $0.00 $0.00
3 #ACS310-03U-17A2-4+J400 $1,562.75 $4,688.25
0 GE 30 amp plugs $0.00
2 #SRPE30A30 $277.00 $554.00
0 Eaton 30 amp Breaker $0.00
1 HFD3030 $836.00 $836.00
$0.00
1 Credit -$900.00 -$900.00 Other Charges
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00 Total Other $0.00
$0.00 LABOR HRS RATE AMOUNT
$0.00 Call out 0 $125.00 $0.00
$0.00 Labor 7 $80.00 $560.00
$0.00 Electrical services 0 $60.00 $0.00
$0.00 Misc 0 $30.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 Total Labor 7 $560.00
Total Materials $5,178.25 Total Materials $5,178.25
Competed Date Other Total $0.00
Ordered By:
Tax
Signature________________________________________TOTAL $5,738.25
ELECTRICAL SERVICES
Replace the VFDs with ABB Drives for WAS 1,2,3
Change Breaker Rate plugs WAS 1&2
Change Breaker in WAS 3
Williams Brothers Construction
1123 Cerise Rd
Billings, MT. 59101
Bozeman WRF Small Works
Change order CPR-06
238
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order) HDR ENGINEERING, INC. Project: Bozeman WRF Small Works CPR No: 07 CPR Date: 4/12/2018 Date Sent to Contractor: 4/12/2018 Date Rec'd from Contractor: ________________ TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
Run conduit to connect the PSH’s for the WAS pumps to the motor control bucket or PLC, as directed on-site.
HDR: Cora Revis________________________________________________ Date: 4/12/2018
TO: HDR Engineering, Inc. Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:) Contractor: ________________________________________________ Date: __________________________
TO: City of Bozeman
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________
239
240
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order)
HDR ENGINEERING, INC.
Project: Bozeman WRF Small Works CPR No: 07
CPR Date: 4/12/2018
Date Sent to Contractor: 4/12/2018
Date Rec'd from Contractor: ________________
TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
Run conduit to connect the PSH’s for the WAS pumps to the motor control bucket or PLC, as directed on-site.
HDR: Cora Revis________________________________________________ Date: 4/12/2018
TO: HDR Engineering, Inc.
Proposal: ______price is for all three psi switches _///_80 ft of conduit, 3/4 pulling elbows , nipples, straps,
Unistrut, anchors, 16 gauge single pair wire. Parts $150 Labor $450
________________________________________________________________________________________
_ __________________________________________________________________________________________
Cost: _____$600.00_________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:)
Contractor: Frontier Electric , Robert Levandowski____ Date: _____4/12/2018
TO: City of Bozeman
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________
241
City of Bozeman WRF Small Works Project No. 1
CHANGE PROPOSAL REQUEST
(Not a Change Order) HDR ENGINEERING, INC. Project: Bozeman WRF Small Works CPR No: 08 CPR Date: 4/12/2018 Date Sent to Contractor: 4/12/2018 Date Rec'd from Contractor: ________________ TO: Williams Brother Construction
Please furnish your proposal for executing the following changes(s):
This is a no-cost change order to extend the contract time to June 20 to allow good weather for roofing.
HDR: Cora Revis________________________________________________ Date: 4/12/2018
TO: HDR Engineering, Inc. Proposal: ___________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Cost: _____________________________________________________ Credit: ____________________________
(A time extension is not required for this modification unless otherwise detailed and justified:) Contractor: ________________________________________________ Date: __________________________
TO: City of Bozeman
Accepted/Not Accepted _______________________________/ HDR Date: ________________________
Accepted/Not Accepted ______________________________/ Owner Date_________________________