Storm Water Design Report
South University District — Phase 1 B Subdivision
April, 2018
Submitted to:
City of Bozeman Engineering Department
20 East Olive
Bozeman, MT 59715
Prepared by:
Stahly Engineering and Associates
851 Bridger Drive, Suite 1
Bozeman, MT 59715
(406) 522-9526
����NEE�jyc
STAHLY
e 1970
AffDC1 R'f�S��
Engineer of Record:
Mark Juras, PE
Quality Control Reviewer: y P..►,.(
Cordell Pool, PE
Storm Water Plan
Contents
Description of Phase 1 B Project
General Information
Existing Conditions and General Design Criteria
Storm Drainage Plan Description
Estimation of Runoff
Pre-development Runoff
Post-development Runoff
Storage/Treatment Facilities
OutFall Structure Weir Sizing
Curb and Gutter Capacity
Inlet Capacity
Facilities Maintenance
Figures and Tables
Figure 1. Inlet Basin Exhibit
Table 1. Runoff Calculations
Table 2. OutFall Structure Weir Sizing
Table 3. Curb and Gutter Capacity Calculations
Table 4. Phase 1 Inlet Basin and Pipe Capacity Calculations
Table 5. Phase 1 Detention Basin Calculations
Storm Water Plan 1 4/23/2018
Description of Phase 1 B Project
The South University District (SUD) - Phase 1 B is a subsequent minor
subdivision of Lot 2, Phase 1 of the South University District project. The
subsequent division will provide right of way dedications for South 14th Avenue
and State Street and will result in a 3.66 acre lot (Lot 2A), which will be the
location of the Phase 1 B on-site development.
In 2014, the storm water infrastructure for SUD Phase 1 was constructed as part
of the development of the Stadium View Apartments in Lot 1. This existing
network of storm drains and the two detention basins is the backbone for the
improvements to Phase 1 B, as originally intended.
The previously submitted Storm Water Plan for the South University District
Phase 1 subdivision accounted for the storm water that is contributed by the
development of Phase 1 B. In the following report, Phase 1 B (referred to as Lot
2A) was designated as an entire drainage basin (Drainage Basin 1A) in the runoff
estimates. With the development of a grading plan for Phase 1 B, the drainage
basin has been further divided into smaller basins to more accurately represent
storm water flow.
The amendments updating the Storm Water Plan with improvements from Phase
1 B are as follows:
- The Phase 1 B drainage basin has been broken down into sub basins 1 A.1
through 1A.5 as shown in the updated Inlet Basin Exhibit (Figure 1).
- Updates have been made to storm water runoff and detention storage
calculations to include the sub basins 1A.1 through 1A.5.
- Content changes to update the report reflecting the current status of the
project within the SUD development.
General Information
The South University District - Phase 1 subdivision is located within the City of
Bozeman adjacent to South 11t" Street and south of Kagy Boulevard. The
subdivision is located west of Bobcat Stadium and is south of the existing
Stadium Center Subdivision. Phase 1 consists of 2 lots, road right-of-way, and
park, with a gross area of 16.23 acres. Lot 1 is a 9.82 acre site that has already
been developed into the Stadium View Apartments, which has a total of 499
beds. Lot 2 is a 6.41 Acre lot that is mostly undeveloped. A portion of Campus
boulevard was constructed in 2017. The proposed lot 2A, also known as Phase
1 B, is a 3.66 acre lot with an estimated total of 194 beds. The calculated
drainage area for the improved areas of Phase 1 is 16.77 acres.
The proposed storm drainage improvements include modifications to those
already installed in Phase 1 including; new curb inlets on existing main,
Storm Water Plan 2 4/23/2018
extending a stub with three new inlets, adjusting finish grade on existing
manholes, and replacing existing manhole inlets as needed to meet the new
design.
The developer's contact information is:
CCC — Bozeman LLC
431 Office Park Drive
Birmingham, AL 35223
Existing Conditions and General Design Criteria
The existing condition at the Phase 1 B site is undeveloped agricultural land.
Phase 1 has been developed into the Stadium View Apartments. Down-gradient
development has restricted storm drainage paths leaving the property to the
north. An existing creek (Mandeville Creek) runs along the west edge of Phase 1
and is the only acceptable location for storm water to leave the site. Mandeville
Creek continues to flow north through the City to the East Gallatin River.
In accordance with the City of Bozeman Design Standards and Specifications
Policy (COB Standards) an engineering analysis has been conducted for the
South University District (SUD) property to limit post-development runoff to pre-
development rates. Storm runoff originating on the site will be detained on-site
and released at rates less than the pre-development rates. Furthermore,
detention basins will reduce storm water velocity and allow solids, silt, oils,
grease, and other pollutants to settle from the runoff before the flows leave the
site.
Inlets and storm sewers are sized to pass the 25-year event without surcharging
or overtopping roadways. Should a larger event occur, the roadways were
designed to divert storm water away from structures.
Storm Drainage Plan
The overall storm drainage plan for Phase 1 and Phase 1 B is depicted on Figure
1 at the end of this report. Overall drainage direction on the proposed
development is indicated by arrows showing the proposed drainage patterns and
inlet locations.
Estimation of Runoff
The rational method was used to estimate peak flow rates and volumes from
storm runoff. Standard assumptions in using the rational method include that
rainfall is uniformly distributed over a watershed for the duration of a storm event,
the peak runoff rate occurs when the storm duration equals the time of
concentration, and the runoff coefficient for a watershed is constant for similar
Storm Water Plan 3 4/23/2018
land use. Time of concentration was determined from the slope of the basin,
rational runoff coefficient and flow length (COB Standards — Equation II.E.6).
Pre-development Runoff
A runoff coefficient of 0.20 for open land was selected for pre-development
conditions. An average overland slope of 2.1% over a basin length of 1,650 feet
provides a time of concentration of 53.4 minutes. The Bozeman IDF curves
show a rainfall intensity for the 10-year design storm event of 0.69 in/hr.
Applying this over the 16.77 acre site produces a runoff flow rate of 2.32 cfs at
the downstream end of the basin.
Post-development Runoff
Post-construction runoff was calculated using a runoff coefficient of 0.60
(commercial neighborhood) to account for future site development in accordance
with the master plan. The rational method peak runoff rates are displayed in the
following table.
Table 1: Runoff Calculations
Pre-development Post-Development Post-Development
Open Land Commercial Commercial
Land Use Neighborhood Neighborhood
Drainage Area (acres) 16.77 16.77 16.77
Slope % 2.1 2.1 2.1
Overland Runoff Coefficients 0.2 0.6 0.6
Frequency Adjustment Factor, Cf 1 1 1.1
Design Storm Frequency 10- ear 10- ear 25- ear
Basin Length ft 1,650 425 425
Time of Concentration, Tc min 53.4 15.1 13.2
Intensity at Tc (Figure 1-2 pg.
29) (in/hr 0.69 1.57 2.05
Runoff Rate(cfs) 2.32 15.82 20.64
The rational method provides a 10-year peak runoff rate of 15.82 cfs. The same
analysis for a 25-year event provides a peak runoff rate of 20.64 cfs.
In addition to the overall storm runoff calculations, the 25-year storm runoff flow
rate for each storm drainage inlet basin has been determined based on the
drainage plan shown on Figure 1. These calculations were used for sizing of
conveyance pipes and are provided in Table 4 at the end of this report.
Storage/Treatment Facilities
Pond routing using the modified rational method was utilized to determine the
hydraulics of the detention basin. Calculations are provided for Phase 1 in Table
5 at the end of the report. The inflow hydrograph and limited pond outflow
resulted in a required maximum storage of 14,851 cubic feet of runoff for the 10-
Storm Water Plan 4 4/23/2018
year event for Phase 1. The Phase 1 pond has a bottom area of 9075 square
feet and 4:1 side slopes. The bottom elevation is 4928.00 and surface overflow
to the west is provided at an elevation of 4930.50. The maximum depth is 1.5
feet, with a total volume of approximately 16,344 cubic feet. The Phase 1
detention basin is located at the northwest (down-gradient) end of the site and is
vegetated with grass. The Phase 1 detention basin is labeled "Detention Basin
A" on Figure 1. Detention Basin B on Figure 1 is a separate system provided for
Phases 2 and 3 of the South University District (SUD) development.
Outfall Structure Weir Sizing
The detention basin outflow for the Phase 1 development is restricted by a typical
control structure as depicted in COB Standards Figure A-2. Using the weir
calculation equation given in Section II.D.2 of the COB Standards, the slot width
of the weir structure was determined. The slot width for the Phase 1 pond
discharge structure is 5 inches. This slot width limits the discharge from the
structure to pre-developed rates at the maximum depth of 1.5 feet.
Table 2: Outfall Structure Weir Sizin
Phase 1
Pre-developed Runoff(cfs 2.32
Weir Coefficient"C" 3.33
Head ft 1.5
Slot Width in 5
In the occurrence of an event greater than the 10-year event, the pond will
overflow to the west to Mandeville Creek.
Curb and Gutter Capacity
Storm runoff will be collected in street and parking lot curb and gutters. The
hydraulic capacity of the curb and gutter was analyzed to determine if the curb
would be overtopped in a 25-year event. The maximum 25-year event for any of
the curb inlet basins produces approximately 2.70 cfs of runoff. The capacity of
the curb at the lowest designed slope of 0.5% is 5.03 cfs at a depth of .15 feet
below the top of the curb. Therefore, curb capacities in the development are
adequate to carry the 25-year event.
Storm Water Plan 5 4/23/2018
Table 3: Curb and Gutter Capacity Calculations
Right-side slope X:1 0.05
Left-side slope X:1 33.00
Channel bottom width ft 0
Flow Depth ft 0.350
Flow Area ft^2 2.024
Wetted Perimeter ft 11.906
Width 0.035
Hydraulic Radius ft 0.170
Mannin 's Roughness 0.013
Slope ft/ft 0.005
Average Velocity ft/sec) 2.49
Flow ft^3/sec 5.03
Inlet Capacity
The curb inlets on the roadways in the development were analyzed to ensure
they have capacity to accept flows conveyed to them without reaching a point
0.15 feet from the top of the curb. The COB approved Neenah Foundry R-3067-
L inlet structure has a capacity of 5.98 cfs at 0.35 feet of head (0.15 below top of
curb). This capacity will convey the necessary flows.
Facilities Maintenance
The proposed storm drainage facilities will be operated and maintained by the
property owner. The owner is responsible for quarterly maintenance of all storm
water facilities. The maintenance includes, but is not limited to, visual inspection
and removal of sediment from curbs, inlets, detention basins, and outlet
structures as well as any necessary repairs to the facilities.
Storm Water Plan 6 4/23/2018
STAH LY
CO)
PIPE 6A PIPE 12A PIPE 15A w
DETENTION BASIN A PIPE 1A PIPE 4A PIPE 5A om�
C I
PIPE 3 1BASM TA.2 ol1r . 7a. . . . . . .
ad ST TE STREET Corn w e§
BASIN 4A
1.03 ac 0 pe)2
Lo 4)
Imp W)m
0.79 ac @a E U)
acC 0
PIPE l9j �16A
W
-".ASIN
z
J.. . . . . . .
w'e BASIN
LU 2 u)
1 18
!0.32 ac U)
7A— U)ca t
PIPE 13A z
tPIPE
LU L6
L
I 17TMM
PIPE PIPE '9� PIPE 14A
A
BASIN 6A
Efl
2.11 ac
0
Li
Co
p ;- co.;41
j
j3ASIN B FOR
Jl
PH,ASES 2&3 0
THE SUD D 1 -� l�- 14aL �- ^ .� L ; 1 W K a N
BA J1111 m
ASTER PLAN IN
1A BASIN 1A.5 Cn M
—M 71-10
5 cl ac 3.66 ac G7777797777M 17 1777-711' 177
PIPE 1 1A
flTN
BASIN A
BASIN 9A
1.83
2.09 a 17 1
. 4a
6
>
s II II ; — p — l l — — — — l _ _� x 26
LU
4MMM-
Z<
ZO
Z W
>
in�C-AM Rus; BEND 00 Z 2�
uj U) lu
z 3
- - - \ - - - - r - - - >
m 0N
Z 0
[,Fl-tC.NEB CDP
DRAWN CDP
CHECKED Cl)p
DATE 2/20/15
iv
0 5.0 100 200 SHEET
IN FEET /\, _FIGURE I,)
Table 4
Phase 1 Inlet Basin and Pipe Capacity Calculations
Inlet Drainage Basin
Inlet Basin 1A.1 1A.2 1A.3 1A.4 1A.5 2A 3A 4A 5A 6A 7A 8A 9A 10A 11A
Land Use REMU REMU REMU REMU REMU REMU REMU REMU REMU REMU REMU REMU REMU REMU REMU
Drainage Area(acres) 0.55 0.17 0.53 0.15 3.66 0.32 0.79 1.03 1.84 2.11 0.52 0.69 1.83 2.09 0.49
Slope(% 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1 2.1
Runoff Coefficients 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6
Frequency Adjustment Factor,Cf
Basin Length(ft) 660 190 630 180 425 180 1 307 410 357 377 263 581 387 439 340
Time of Concentration(min) 16.5 8.9 16.1 8.6 13.2 8.6 11.3 13.0 12.1 12.5 10.4 15.5 12.6 13.5 11.8
Peak Flow Calculations
Design Storm 25yr 25 r 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr
Intensit of Tr_. Fi ure I-2 p .29 (inlhr) 1.78 2.65 1.81 2.70 2.05 2.70 2.28 2.07 2.17 2.13 2.39 1.86 2.11 2.03 2.20
Peak Runoff Rate at Tc(Q =CIA)(cfs) 0.59 0.27 0.58 0.24 4.50 0.52 1.07 1.28 2.39 2.70 0.75 0.7f 2.32 255 0.64
Detention Basin A- Pipe Network A Capacity
Pipe Number 1A 2A 17 3A 4A 5A 19 6A 20 7A 8A 9A 10A 11A 12A 13A 1 .0 150 0 15.000 18.00
16 18
Pipe Size in 30.00 18.00 18.00 30.00 15.00 30.00 12.00 30.00 12.00 18.00 15.00 15.00 18.00 15.00 15.00 15.00 15.00 15.0
Pi
Mannin 's"n"(PVC) 0.013 0.013 0.013 0.013 0.013 0.0,13 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.0'13 0.013 0.013 0.013 0.013 0.013 0.013
Area (ft`) 4.91 1.77 1.77 4.91 1.23 4.91 0.79 4.91 0.79 1.77 1.23 1.23 1.77 1.23 1.23 1.23 1.23 1.23 1.23 1.77
Wetted Perimeter(ft) 7.85 4.71 4.71 7.85 3.93 7.85 3.14 7.85 3.14 4.71 3.93 3.93 4.71 3.93 3.93 3.93 3.93 3.93 3.93 4.71
Hydraulic Radius ft) 0.63 0.38 0.38 0.63 0.31 0.63 0.25 0.63 0.25 0.38 0.31 0.31 0.38 0.31 0 0 .01 0.31 .00 0.31 0.3II
Slope(fUft 0.0027 0.0050 0.0050 O.U027 0.0100 0.0027 0.0050 0.0027 0.0050 0.0100 0.0050 0.0050 0.0100 0.0050 U.0050 0.0100 0.0100 0.0050 0.0050 0.0050
Full Flow Capacity(cfs) 21.37 7.45 7.45 21.37 6.48 21.37 2.53 21.37 2.53 10.53 4.58 4.58 10.53 4.58 4.58 6.48 6.48 4.58 4.58 7.45
Velocity(ft1sec) 4.35 4.21 4.21 1 4.35 5.28 4.35 3 22 4.35 3.22 5.96 3.73 3.73 5.96 3.73 3.73 5.28 5.28 3.73 3.73 4.21
ContributingWet Basin NONE 1A.1. 1A.2 1A,3, 1A.4 NQNE 1`12:af3A 1/20 of4A 1l2tif , N aA = -'Q;A, NNE NONE 8h1 1A,5
Contributing Pipes 2A 17A 20A 4A NONE 6A NONE 7A NONE 8A NONE NONE 11A NONE 13A 14A I NONE I6A NONE NONE
3A 5A 18A 12A 9A 15A
19A 10A
Actual Pipe Flow(cfs) 21.18 6.18 5.32 15.00 0.52 14.48 0.54 13.41 0.64 9.97 2.39 2.70 4.87 2,55 2 16 1.40 0.64 0.76 0.76 4.50
% Capacity 99% 83% 71% 70% 8% 68% 21% 63% 25% 95% 52% 59% 46% 56% 47% 22% 10% 17% 17% Fi0%
Table 5
Phase 1 Detention Basin Calculations
Time of Concentration Calculations Preconstruction Postconstruction Storm Sewer Flow
Land Use Open Land REMU REMU
Drainage Area(acres) 1677 16.77 16.77
Slope(%) 2-1 2.1 2-1
Runoff Coefficients 0.2 0.6 0.6
Frequency Adjustment Factor,Cf 1 1 1.1
Basin Length(it) 1650 425 425 Basin length based on typical inlet area
Time of Concentration(min) 53.4 15.1 13.2
Peak Flow Calculations
Design Storm 10-Year 10-Year 25-Year
Intensity at Tc (Figure 1-2 pg.29)(in/hr) 0.69 1.57 2.05
Peak Runoff Rate at Tc(Q=CIA)(cfs) 2.32 15.82 20.64
(max release rate)
Required Storage Volume MAX VOL
14850.09
Storm Duration Intensity Future Runoff Rate Runoff Volume Release Volume Required Storage Notes
(minutes) (hdltr) (Q=CIA)(cfs) (co (cf) (cf)
2 5.84 58.75 7049.76 277.91 6771.85
4 3.72 37.44 8985.35 555.81 8429.53
6 2.86 28.76 10355.40 833.72 9521.68
8 2.37 23.86 11452.37 1111.63 10340.74
10 2.05 20.64 12382.66 1389,54 10993.12
12 1.82 18.33 13198.58 1667.44 11531.14
14 1.65 16.58 13930.24 1945.35 11984.89
16 1.51 15.20 14596.74 2223.26 12373.48
18 1.40 14.08 15211,05 2501.16 12709.89
20 1.31 13.15 15782.45 2779.07 13003.38
24 1.16 11.68 16822.39 3334.89 13487.51
26 1.10 11.09 17300.34 3612,79 13687.54
28 1.05 10.57 17754.94 3890.70 13864.24
30 1.00 10.10 18188.89 4168.61 14020.29
32 0.96 9.69 18604.43 4446.52 14157.91
34 0.93 9.32 19003.41 4724.42 14278.98
36 0.89 8.98 19387.41 5002.33 14385.08
38 0.86 8.67 19757.78 5280.24 14477.54
40 0.83 8.38 20115.69 5558.14 14557,54
42 0.81 8.12 20462.14 5836.05 14626.09
44 0.78 7.88 20798.03 6113.96 14684.08
46 0.76 7.65 21124.14 6391.87 14732.28
48 0.74 7.44 21441.16 6669.77 14771.39
50 0.72 7.25 21749.70 6947.68 14802.02
52 0.70 7.07 22050.33 7225.59 14824.74
54 069 690 22343.52 7503.49 14840.03
56 0.67 6.74 22629.74 7781.40 14848.34
58 0.65 6.58 z22909.40 8059.31 14850.09 Required Storage
60 0.64 644 23182.85 8337.22 14845.63
62 0.63 6.30 23450.44 8615.12 14835,31
64 0.61 6.18 23712.47 8893.03 14819.44
66 0.60 605 23969.24 9170.94 14798.30
68 0.59 5.94 24220.99 9448.85 14772.15
70 0.58 5.83 24467.98 9726.75 14741.23
72 0.57 5.72 24710.43 10004.66 14705.77
74 0.56 5.62 24948.53 10282.57 14665.96
76 0.55 5.52 25182.49 10560-47 14622.01
78 0.54 5.43 25412.47 10838.38 14574.09
80 0.53 5.34 25638.66 11116.29 14522.37
82 0.52 5.26 25861.20 11394.20 14467.01
84 0.51 5.17 26080.24 11672.10 14408.14
86 0.51 5.10 26295.92 11950.01 14345.91
88 0.50 5.02 26508.36 12227.92 14280.44
90 0.49 4.95 26717.68 12505.82 14211.85
92 0.48 4.88 26924.00 12783.73 14140.27
94 0.48 4.81 27127.43 13061.64 14065.79
96 0.47 4.74 27328.06 13339.55 13988.51
98 0.47 4.68 27525.99 13617,45 13908.54
100 0.46 4.62 27721.32 13895.36 13825.96
102 0.45 4.56 27914.12 14173.27 13740.85
104 0.45 4.50 28104.48 14451.17 13653.30
106 0.44 4.45 28292.47 14729.08 13563.39
108 0.44 4.39 28478.18 15006.99 13471.19
110 0.43 4.34 28661.66 15284.90 13376.76
112 0.43 4.29 28842.98 15562.80 13280.18
114 0.42 4.24 29022.21 15840.71 13181.50
116 0.42 4.20 29199.41 16118.62 13080.80
118 0.41 4.15 29374.64 16396.53 12978.11
120 0.41 4.10 29547.95 16674.43 12873.51