HomeMy WebLinkAbout04-25-18 Presentation re Headwaters Benefits of Shared Use Pathhttps://headwaterseconomics.org
Benefit Analysis:Belgrade-Bozeman Frontage Path
https://headwaterseconomics.orghttps://headwaterseconomics.org
Headwaters Economics is an independent,
nonprofit research group that works to
improve community development and land
management decisions.
https://headwaterseconomics.org
https://headwaterseconomics.org
Methods & Assumptions
•20 year lifespan
•2 years to construct
•7% discount rate
•Conservative assumptions
https://headwaterseconomics.org
Overall Results
Benefits: +$22.8 million
https://headwaterseconomics.org
Overall Results
Benefits: +$22.8 million
Costs: $8.9-11.7 million
https://headwaterseconomics.org
1. Public Health & Safety $21.7 million
Increased Safety
•Records show 5 crashes over 6 year period
•16 crashes avoided
https://headwaterseconomics.org
1. Public Health & Safety $21.7 million
Increased Safety
•Records show 5 crashes over 6 year period
•16 crashes avoided
Improved Community Health
•60% of inactive residents increase physical activity with new trail
https://headwaterseconomics.org
2. Economic Benefits
Increased Property Values
•5-10% higher near trails
https://headwaterseconomics.org
2. Economic Benefits
Increased Property Values
•5-10% higher near trails
Business Attraction & Growth
•Commercial areas benefit
•Those arriving by bike or foot spend more money
https://headwaterseconomics.org
3. Environmental Sustainability $978,000
Reduced Greenhouse Gas Emissions
•Increased non-motorized commuting
•34,545 metric tons of CO2 removed
https://headwaterseconomics.org
4. Quality of Life $81,000
Improved Experience
•Estimate 3,000 new trips per year
https://headwaterseconomics.org
4. Quality of Life $81,000
Improved Experience
•Estimate 3,000 new trips per year
Socioeconomic Opportunity & Social Cohesion
•Benefits of trails only available to those with access
•Residents use trails to meet neighbors and engage in community activities
https://headwaterseconomics.org
5. Community Planning Priorities
Ranked High in all Plans
•Gallatin County Trails Plan, Transportation Plan
•Bozeman PROST, Transportation, Strategic Plan
•Belgrade Transportation, Growth Policy
•MDT Corridor Study
https://headwaterseconomics.org
Summary
•Benefits over 20 years estimated at $22.8 million
•Many additional benefits cannot be monetized
•Twice the estimated cost of construction and maintenance
https://headwaterseconomics.org
Thank You!
Kelly Pohl
406-599-7841
kelly@headwaterseconomics.org