Loading...
HomeMy WebLinkAbout04-23-18 City Commission Packet Materials - A2. Law and Justice Center Refined Options and PricingPage 1 of 15 Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Chuck Winn, Assistant City Manager Andrea Surratt, City Manager SUBJECT: Presentation of Refined Options and Pricing; Joint Project with Gallatin County for Law Enforcement Building and a Bozeman Public Safety Facility (BPSF) on City-Owned Property on Rouse Avenue. MEETING DATE: April 23, 2018 AGENDA ITEM TYPE: Action RECOMMENDATION: Listen to presentation by staff, ask questions, and provide direction to the City Manager. POSSIBLE MOTION: After listening to the presentations and taking public comment, I move to direct the City Manager to finalize plans for a Bozeman Public Safety Facility on city-owned property on Rouse Avenue and return to the Commission with draft mill levy and bond information for a future election. OR POSSIBLE MOTION: After listening to the presentations and taking public comment, I move to direct the City Manager to work with Gallatin County to finalize a joint law enforcement project on the Law and Justice Center site and bring back to the City Commission draft mill levy ballot funding language for a November 2018 election. OR Other motion as determined by the Commission INTRODUCTION: On January 22, 2018, the City Commission considered two options to address facility deficiencies for Bozeman’s public safety and criminal justice functions. One option was to partner with Gallatin County on a phased approach to a joint project previously defeated by voters in November 2016. The second option was to construct a city public safety facility on city-owned land that included the Police Department, Fire Department, Bozeman Municipal Courts and support functions, and Bozeman prosecution functions on city-owned property on North Rouse. After deliberation, the City Commission directed staff to further explore the city public safety facility option and return to the Commission in April for further consideration. 167 Page 2 of 15 APPROACH: To efficiently develop concept plans and accurate estimates for a city public safety facility, we engaged the services of the architect and general contractor/construction manager who had developed plans and estimates for both the previous joint project with Gallatin County and the Rouse Justice Center (RJC). The basis for the new facility was the RJC modified to include Bozeman Fire Station 1. This approach allowed us to take advantage of design and cost estimating work already completed and apply it to this project without significant redesign and redundant effort. It also provided an opportunity to reevaluate the facility and service assumptions made in 2014 and update as needed in 2018. Policy Considerations: For the purposes of this discussion it is important to note that these are two very different projects that address two very different problems. As you will see, the two different scenarios have different costs, timelines, benefits and risks. In addition, to evaluate them on costs alone would miss a critical policy question about how the entirety of City services are provided to residents and visitors of the City of Bozeman. Bozeman is a rapidly growing municipality. With this growth comes increased demands for city services including those provided by the Bozeman Police and Fire Departments and the Municipal Courts. In the past, the City has been most effective providing public safety services when it has been able to engage city voters and make decisions directly. Working with the County on joint public safety facilities adds a level of complexity and uncertainty to any project as the City Commission and City voters do not have direct authority to make decisions that impact these critical services. It can be argued that Bozeman is of a sufficient size (nearing 50,000) and complexity that the needs of the growing municipal population are best served by focusing city resources on city services. There are functions where partnerships make sense by reducing redundancy and improving efficiency (i.e. City/County Health Department, 911 Dispatch, etc.), but the Bozeman Police Department, Municipal Courts, City Attorney’s Office, and Bozeman Fire Department are funded entirely by City taxpayers and provide direct services within the corporate city limits. Gallatin County taxpayers outside the City limits do not provide funding for these services. Does it make sense for City voters, taxpayers, and policy makers to be able to focus their efforts and resources on making decisions that are in the best interests of the City without having to get permission from Gallatin County? OVERVIEW The initial phase of the joint project at the Law & Justice Center provides space for the Bozeman Police Department but does not address any of the facility needs of the Municipal Courts, the City Prosecution staff or important judicial support services such as victim services, court clerk staff, and citizen jury facilities. Facilities for those services are planned to be provided in the future through a voted mill levy determined by the County Commission. It also does not address the needs of the City’s Fire Department. Main components of each option: County Option – Phased Approach: Law Enforcement-Only Building Includes: 168 Page 3 of 15 • Bozeman Police • County Sheriff • Shared Evidence Processing and Storage • Shared Law Enforcement Records • Future Phase: Courts Building City Option – Bozeman Public Safety Facility Includes: • Bozeman Police • City Evidence Processing and Storage • City Law Enforcement Records • Municipal Courts and Court Services (Clerks and Victim Services) • Prosecution • Bozeman Fire Station 1 The Bozeman Public Safety Facility (BPSF) Project Description: The City has three major public safety facility challenges to meet the demands of the growing community; a Bozeman Police Station, Municipal Courts and Court Services, and the relocation of Fire Stations 1 and 2. The Fire Department Master Plan as recently accepted by the City Commission finds that the construction and staffing of a fourth fire station can be delayed, and current services improved, through the relocation of both Fire Station 1 (built in 1963) and Fire Station 2 (built in 1974). The Fire Master Plan identifies the city-owned property on Rouse as an ideal location for Station 1. The City will immediately solve three of its most important public safety facility challenges with the construction of a joint public safety building on Rouse Avenue. As a starting point for the BPSF project, we used the design previously completed for the Police and Municipal Courts project presented to the voters in 2014 and added fire station programming required for the relocation of Fire Station 1. This new effort allowed us to take advantage of building systems and site considerations to provide an efficient design and layout. The cost estimates in this memo are provided using current material and labor pricing. There are significant benefits to collocating City public safety functions together on the Rouse site. Shared Spaces. The Police and Fire Departments are both emergency public safety services and can share important resources within the building. These include, but are not limited to, staff meeting and training areas, public meeting facilities, command and emergency operation spaces and equipment. Police and Fire Department staff work closely together on the street, as they respond to public safety emergencies throughout town. Many incidents have both Police and Fire first responders present. Being located in the same facility will have the benefit of improving working relationships between department members. Common Spaces. Common elements in the buildings including lobbies, mechanical and other facilities support rooms, hallways, public meeting and restrooms, and stairwells would be shared by the courts, attorneys, police and fire. This sharing resulted in reduced square footage by eliminating redundant spaces. 169 Page 4 of 15 Emergency Services. Facilities for both Police and Fire require construction to the essential services provisions of the building code. It is critical Bozeman public safety agencies are able to provide life-safety services to the community during times of extreme emergency. The BPSF is designed to withstand seismic events and utility interruptions of up to 72 hours to provide a base of operations for Bozeman’s primary emergency response agencies. Land and Financing Issues: 1. Land Ownership. The land on which the BPSF would be built is approximately 8 acres and is owned by the City. The property is currently being used to store public works equipment previously stored at the City Shops. 2. Ownership Structure. The City would own the entire project and have control over operations and maintenance. 3. Project Debt • City Bond Election. Construction of the BPSF would be funded through the sale of municipal bonds authorized by voters and paid back over 20 years. The City’s bond rating has recently been improved and is the same as the County (Moody’s Aa2). The site that is currently Fire Station 1 could be sold in order to decrease the amount of debt that must be borrowed for the project. • Mill Levy Question(s). Operating and maintenance costs could be funded through a voted increase to the City’s mill levy or funded through the levying of additional mills authorized within the existing cap but not currently levied. Ongoing Operations and Maintenance: The City would need to increase budget authorization for operations and maintenance of the new facility. These new costs could be offset with funds currently paid to Gallatin County as described below. Additionally, the City entered into a 40-year lease to the County in 1994 and prepaid $765,000. The provisions in that agreement allow the City to vacate the building, and under certain conditions, require the County to refund unused lease funds. The amount of the refund would be determined by the date the City moved out but would be approximately $267,000 if the project was approved by the voters in 2018 and the lease was terminated by mutual agreement in year 26 of the contract. 170 Page 5 of 15 Bozeman Public Safety Facility – Project Costs Construction: The Bozeman Public Safety Facility building project is estimated to cost $40.1 million. Sale of the current Fire Station #1 property and cash from the Fire and Equipment Capital fund could reduce the bond costs by $3,150,000. The bond for construction would total $36.9 million. The table below details the Cost of the Construction of the Project: Operational Costs: The City would seek to be released from our current long-term lease and no longer have annual maintenance costs at the current Law and Justice Center. There would be an increase to the City’s budget that would need to be levied for operations. We estimated the utilities and maintenance based on the City’s buildings expenses per square foot. To estimate these costs, we used the average cost per square foot of four City’s buildings (City Hall, Stiff Professional Building, Fire Station 1 and the Library). With the move of operations to this new building, there will be a need to increase staffing. The records division (currently run by Gallatin County and funded through the 911 Levy) would require an additional 2.5 FTE and a .5 FTE evidence technician would be added. Court security will need staffing of 2.0 FTE for security services while court is in session. NOTE: this building security function is new for this project and is not currently provided by the County at the L&J Center even after being identified as a major safety concern for several years. Maintenance, utilities and staffing could be funded by asking voters for an operating levy or use of a portion of the 15.97 mill still under the current cap (9.00 mills related to 911-Records, and 6.97 below for general fund cuts/carryover). The net effect would be an estimated 5.18 mill increase for City residents. Below is the summary table of expenses: Building Construction Cost 40,115,362.00$ Minus: Sale of Current Fire Station One (pending true appraisal)(2,500,000.00)$ Minus: Fire & Equip fund contribution (650,000.00)$ Total Bonded amount 36,965,362.00$ Total Bozeman Public Safety Building Construction Cost debt funded 36,965,362.00$ Bozeman Public Safety Building Construction Costs Savings from Current L&J Operating Agreement (145,000.00)$ Utilities 181,611.50$ Building & Grounds Maintenance 185,398.68$ FTE- Evidence, Records and Security 302,302.41$ Court Operations Costs: 524,312.60$ Operational Costs (Operational Levy Needed or use portion remainder of levy cap 15.97) 171 Page 6 of 15 Impact on Median Home The median home taxable value in the City of Bozeman is $292,000. Based on this value we estimate the annual cost of the levy for building construction would be $101.78 in the first year and the operating levy (if current available mills is not used) in the first year would be $19.67. This totals $121.45 per year in the first year. The City’s taxable value has grown at an average rate of 3.6% per year over the past 10 years. Using that as an indicator of future tax-base growth, the amount that tax payers would be required to pay each year of the 20-year bond would decline. For instance, by year 2028 we estimate that the median home would pay $86.25 per year for the bond. Bond Levy Estimated Annual Payment 2,713,373.34$ Current Annual Mill Value 101,195.00$ Estimated # of Mills 26.81 Annual Cost of Levy to Median Home 101.78$ Monthly Dollar Cost of Levy to Median home 8.48$ Operational Levy Estimated Annual Amount 524,312.60$ Estimated Annual Mill Value 101,195.00$ Current Annual Mill Value 5.18 Annual Cost of Levy to Median Home 19.67$ Monthly Dollar Cost of Levy to Median home 1.64$ Total Impact Estimated Annual Payment & Operations 3,237,685.94$ Current Annual Mill Value 101,195.00$ Estimated # of Mills 31.99 Annual Cost of Levy to Median Home 121.45$ Monthly Dollar Cost of Levy to Median home 10.12$ Bozeman Public Safety Complex Impact on Median Home 172 Page 7 of 15 Other Considerations County Sheriff & Courts Building: If the City decides to build its own Bozeman Public Safety Facility, Gallatin County has discussed also asking voters to construct a building for County Sheriff and Courts functions at an estimated $40 Million cost, paid for by all county property owners. We admittedly do not have many details about this plan. However, if approved, we estimate that this project will add an additional $39.07 in property taxes for City tax payers. County Sheriff & Courts Building Impact on City Bozeman Median Home Bond Levy $ 40,000,000 Estimated Annual Payment $ 2,953,704 Current Annual Mill Value $ 286,963 Estimated # of Mills 10.29 Annual Cost of Levy to Median Home $ 39.07 Monthly Dollar Cost of Levy to Median home $ 3.26 Combined city tax payer impact of both the BPSF and the County Sheriff & Courts buildings will equal $160.52 per year in first year. Total Impact on Median Home with BPSF and County Project - 2018 Estimated Annual Payment & Operations $ 6,191,389.94 Annual Cost of Levy to Median Home $ 160.52 Monthly Dollar Cost of Levy to Median home $ 13.38 173 Page 8 of 15 The costs of these projects in 2021 (for comparison purposes with the Joint Project described later) are estimated to be: Total Impact on Median Home with City and County Projects - 2021 Estimated Annual Payment & Operations $ 6,191,389.94 Annual Cost of Levy to Median Home $ 146.14 Monthly Dollar Cost of Levy to Median home $ 12.18 Fire Station 2 Relocation: The City of Bozeman will also need to look at funding the relocation of Fire Station 2. Relocating both Station 1 and Station 2 will postpone the need to build Fire Station 4 for approximately 10 years, saving the City around $1.2 million in salaries and benefits each year. Joint Law Enforcement Building on the L&J Site – Project Description: As originally designed, the project consisted of two separate buildings constructed on the L&J campus; a Courts building and a law enforcement building. The total estimated square footage for both buildings was 181,658. With this new phased approach, the law enforcement building would be constructed first. This fall, the County began construction of a records and vehicle storage building that had been planned before the joint project but put on hold as the storage could easily be included in the joint project. Approximately 4,900 sq. ft. has been removed from the law enforcement building. The new estimated cost allocations are outlined below. The cost of construction of the law enforcement building would be allocated to the City and the County in proportion to the relative square footages of each party’s condominium units except as otherwise noted here. Shared Spaces. The cost of construction of certain project elements, designed on the architect’s plans as “shared” spaces, would be shared equally. Examples of these shared elements are certain reception areas, shared conference rooms, restrooms, and break rooms. The City and County anticipate that their respective use of these shared areas will be more or less equivalent, $- $50.00 $100.00 $150.00 201820192020202120222023202420252026202720282029203020312032203320342035203620372038City and County Projects Impact on City Median Home $292k Tax Per Median Home- City Project Tax Per Median Home- County Project 174 Page 9 of 15 and that an equal allocation of the costs of these spaces is fair based on the anticipated levels of use. Common Spaces. The remaining common elements in the buildings, including lobbies, mechanical and other facilities support rooms, hallways, and stairwells would be shared on a pro-rata basis based on the relative size of the City’s and County’s condominium units. The City and County have reviewed the layout and function of the law enforcement building and have agreed on the allocations. Land and Financing Issues: 1. Land Ownership. The land on which the law enforcement building would be constructed is approximately 4.95 acres and is currently owned by the County. The City’s payment to the County for its undivided interest in the project’s real property is being discussed and would be different than the formula agreed to in the 2016 project. For the purposes of discussing project costs in this memo, we have assumed 50% ownership of 2.5 acres, totaling $375,000. 2. Ownership Structure. If both the bond and operating levy questions are approved by voters, the City and County would jointly own the law enforcement building as condominiums. This is the same form of property ownership chosen by the County and City for the joint 911 Center/Fire Station 3 property. Under this form, each party would own their condominium unit (the areas of the buildings exclusively occupied by that party), plus an undivided property interest in the common elements, expressed as a percentage. It is anticipated the City and County would each have a 50% voting interest in the condominium’s common elements. The condominium declaration will include a dispute resolution mechanism to resolve any deadlocks. 3. Project Debt a. County Bond Election. As in the 2016 project, the County would issue the bonds for construction. The City would annually pay the County for its share of the project costs. All voters in the county would be asked to approve the full $26M bond. b. Mill Levy • City residents would be asked to approve a debt service mill levy to reimburse the County for the City’s proportional share of the Project costs financed through the bond. The City’s share equates to $13.4M – see fiscal effects. • Operating and maintenance costs could be funded through a voted increase to the City’s mill levy or funded through the levying of additional mills authorized within the existing cap but not currently levied. Ongoing Operations and Maintenance: The City and County have been discussing opportunities to share resources and expertise as it relates to operation, maintenance, and support of the building and the services contained within. Both entities recommend the County assume responsibility for facilities operation and maintenance and the City assume the information and technology services for the new building. 175 Page 10 of 15 1. Facility Services. The shared expenses for ongoing operations, maintenance, insurance, and other common expenses would be allocated based on the 50/50 space allocations for the project. 2. Information and Technology Services. The City would assume primary responsibility for providing information technology services for the new law enforcement building. The scope of services to be provided by the City and the parties’ respective obligations would be detailed in a separate agreement. The costs for each service have not yet been determined. Written agreements for those services will be finalized should the project receive voter approval. Further details related to operations, maintenance, and governance of the condominium association will be included in the condominium declaration and bylaws. Joint Law Enforcement Building on L&J Site – Financing Construction: The Joint Law Enforcement building project is $28.4 million, of which both the County and the City have already funded $2.3 million. The bonded amount for the project will be $26 million total. The City obligation for the building construction is 50% of the costs, or $13.4 million. As described above, the County has requested that the City provide $375,000 for its condominium interest in the 4.95-acre site. That cost has been included in the project cost below. Between construction and land costs, the total obligation for the City portion of the building will be $13.4 million. The annual debt payment would be $984,908. With the value of a current mill at $101,195, this is equivalent to 9.73 mills at today’s mill value. Annual Operations: The City will be providing full information technology support to both the Police Department and the Sheriff’s Office located in the building, while the County will be providing facility maintenance. Under a yet-to-be-written operating agreement, the City will make payment to the County for facility maintenance, and the County will pay the City for information technology support. At this time, we believe those amounts will roughly offset each other. The main operation budget increase would be the City’s portion of utilities. To estimate utility costs, we used the average cost per square foot of four of the City’s larger buildings (City Hall, Stiff Professional Building, Fire Station 1 and the Library). The estimated annual budget increase needed would be about $61,000 and adjusted each year for inflation. Building Construction Cost 28,425,953.00$ Minus: Planning Costs already spent by both County and City (2,351,730.00)$ Total project costs to be bonded 26,074,223.00$ City Share of Construction Costs:13,037,111.50$ City Land Payment to County*375,000.00$ Total City Amount to be bonded: 13,412,111.50$ *County will likely decrease their bond amount for City Land Payment Joint Law Enforcement Building Construction Costs 176 Page 11 of 15 We will be continuing our lease with the County for at least the Courts space in the current Law & Justice Center, so lease payments and operational costs for the current Law and Justice Center will need to remain in the budget for a number of years until the courts are constructed ($174,000 a year.) Also, because we will not be vacating the Courts space, we will not receive a residual payment from our capital investment under the capital lease (an element of our previous project.) Impact on Median Home The median home taxable value in the City of Bozeman is $292,000. Based on this value and our current mill value, we estimate the annual property tax increase from the bond for the median homeowner within the City of Bozeman would be $51.52 for the first year as described in the table below. The City’s taxable value has grown at an average rate of 3.6% per year over the past 10 years. Using that as an indicator of future tax-base growth, the amount that tax payers would be required to pay each year of the 20-year bond would decline. For instance, by year 2028 we estimate that the median home would pay $36.67 per year for the bond. City Only Portion Estimated Annual Payment 984,908.19$ Estimated Annual Mill Value 101,195.00$ Estimated # of Mills 9.73 Annual Cost of Levy to Median Home 36.95$ Monthly Dollar Cost of Levy to Median home 3.08$ County Only Portion Estimated Annual Payment 929,021.44$ Estimated Annual Mill Value 286,963.00$ Estimated # of Mills 3.24 Annual Cost of Levy to Median Home 12.29$ Monthly Dollar Cost of Levy to Median home 1.02$ Operation Costs Levy (City Only) Estimated Annual Payment 61,000.00$ Estimated Annual Mill Value 101,195.00$ Estimated # of Mills 0.60$ Annual Cost of Levy to Median Home 2.29$ Monthly Dollar Cost of Levy to Median home 0.19$ City of Bozeman Resident (City and County) Estimated Total Annual Payment 1,974,929.63$ Estimated Total Annual Cost of Levy to Median Home 51.52$ Estimated Total Monthly Dollar Cost of Levy to Median home 4.29$ Joint Law Enforcement Building Impact on Median Home 177 Page 12 of 15 Bozeman property owners will pay for all of the project that is directly attributable to the City’s Police Department and pay for a portion of the project attributable to the Gallatin County Sheriff’s Department. Currently, the City pays 34.7% of every county-wide mill that is levied. As a result, City property owners will pay 67% of this project’s total cost ($19.1 Million) and County property owners outside the City will pay 33% of the project’s total cost ($9.3 Million). Paid by City Property Tax Payers, $19,145,000 67% Paid by County Property Tax Payers Outside the City of Bozeman, $9,281,000 33% Joint Law Enforcement Building 178 Page 13 of 15 Other Considerations Joint Courts Building: Two years following the Law Enforcement building the County Commission has expressed interest in proceeding with a voted bond levy to construct the second phase of the original project; the Joint Courts Building estimated at $53.1 million. Fire Station 1: According to our adopted capital plan, the City will look to fund the relocation of Fire Station #1 in FY20. City voters will need to approve these projects, and their property taxes will increase as a result, in the years the projects are built. Keeping the current median home value of $292,000, and assuming average tax-base growth of 3.6%, the following table illustrates that all three projects (Law Enforcement Building, Fire Station #1 Relocation, and Courts building) would cumulatively impact the median home by a total of $129.58 in 2021. Other Considerations of Note FY 20 Fire Station One Relocation (inflation included) $ 5,530,400.00 Additional cost to estimated Median home in FY20 $ 14.27 FY21 Joint Courts Building Project total (inflation included) $ 53,146,280.00 FY21 Joint Courts Building (CITY SHARE) $ 21,258,512.00 Additional cost to estimated Median home in FY21) CITY & COUNTY $ 69.22 FY 20 Total estimated additional project impact on median home $ 62.47 FY 21 Total estimated additional project impact on median home $ 129.58 179 Page 14 of 15 Estimated Cost Comparison of the two options: There is a desire to understand the total impact on property tax payers for each of these separate paths: • Bozeman Public Safety Facility (also assuming County Sheriff & Courts Building), or • Joint Law Enforcement Building (also assuming Fire Station #1 and Joint Courts Building) To make that comparison, we are required to make many assumptions: 1. Assuming all ballot measures are approved by voters the first time we present them. 2. Assuming that the County Sheriff & Courts Building has a total project cost of $40 Million. 3. Assuming that construction costs escalate at 6%/year. 4. Assuming that taxable values grow as they have on average for the past 10 years. 5. Assuming that no other elements are added to these projects that increase scope/project costs. Given those assumptions, by the time both scenarios would be fully funded: • Bozeman Public Safety Facility & County Sheriff & Courts Building would cost city taxpayers $146.14 in 2021. • Joint Law Enforcement Building & Fire Station #1 and Joint Courts Building would cost city taxpayers $129.52 in 2021. Courts Building Fire Station 180 Page 15 of 15 The Bozeman Public Safety Facility option, along with Gallatin County having its own project with the costs assumed in this memo, would cost the median city taxpayer $16.62 per year more than the Joint Law Enforcement Building option. ALTERNATIVES: As suggested by Commission Attachments: Exhibit A: L&J Site Plan for Phased Construction Exhibit B:BPSF site plan Report compiled on: April 18, 2018 $146.14 129.58 $- $50.00 $100.00 $150.00 $200.00 20182019202020212022202320242025202620272028202920302031203220332034203520362037203820392040Comparison of Separate and Joint Projects with Fire Station City Project and County Project Joint Law, Fire Station 1, and Court Building 181 UP UP UP 115 SF RECORDS MGR. 111 87 SF MONITOR 124 1,084 SF COMMUNITY MTG 102 83 SF INT. 130 205 SF INT. WAITING RM 125 153 SF MAIL 108 327 SF FILES 110 319 SF STAIR #1 132 1,690 SF RECORDS 107 172 SF VEST 164 4,467 SF GARAGE 199 300 SF VEST 100 96 SF COPY 109 82 SF INT 129 82 SF INT 128 117 SF INT. 127 70 SF TOILET 113 91 SF STOR. 112 255 SF CORRIDOR 126 189 SF COFFEE 115 273 SF CHIEF 134A 156 SF DEPUTY CHIEF 134B 300 SF WAITING/COPY 134 164 SF DEPUTY CHIEF 134C 162 SF CAPTAIN 135 162 SF CAPTAIN 136 162 SF CAPTAIN 137 318 SF PATROL LT. 138 459 SF INVESTIGATION PROJECT ROOM 139 349 SF EXEC CONF 140 430 SF BRIEFING 141 157 SF CPT 143 160 SF CPT 144 117 SF CHAPLAIN 142 124 SF ADMIN MGR. 145 160 SF CPT 146C 296 SF WAITING/COPY 146 160 SF U.S. 146B 274 SF SHERIFF 146A 224 SF STAIR #2 147 72 SF INT. 167 155 SF LT. 168 67 SF INT 170 76 SF TOILET 171 252 SF DTF STORAGE 172 872 SF DTF 169 152 SF GEN. STORAGE 173 428 SF QUARTER MASTER 179B 134 SF P.D. ARMORY 177 423 SF BLDG STOR/ FACILITIES 179C 83 SF RECEIVING 180 303 SF G.C. ARMORY 182 93 SF WEAPONS MAINTENANCE 181 318 SF CORONER INTAKE 185 758 SF VEH. EXAM 188112 SF COOLER 1 187A 205 SF COOLER 2 187B 516 SF SRT STORAGE 179A 129 SF OFFICE 186 153 SF EVID. OFFICE 189B 364 SF EVIDENCE TECH 189A 143 SF SRT ARM. 178 97 SF LAB VEST. 189C 53 SF STOR 189D 409 SF ID LAB 190 840 SF EVIDENCE INTAKE 192 80 SF LARGE EVID. LOCKER 192A 132 SF DISCOVERY 194 102 SF PUBLIC RETURN 193 36 SF KENNEL 196B 34 SF KENNEL 196C 96 SF K-9 196A 35 SF DRY 197A 35 SF DRY 197B 125 SF NARC STOR 195A 209 SF BIKES 199A 341 SF MOTORS 199B 1,252 SF EVIDENCE STOR 195 1,091 SF LOBBY 101 269 SF FUTURE OFFICE 133 52 SF ELEV 117 50 SF JAN. 118 186 SF MEN 119 191 SF WOMEN 120 148 SF TELECOMM. 121 148 SF ELECT. 122 1,132 SF PD INVESTIGATIONS 148 1,143 SF PATROL SUPPORT SVCS 149 1,107 SF PD. PATROL SGT. 150 302 SF ICAC 155 282 SF PD PATROL EQ. STOR PATROL GEN STOR 156 282 SF GC PATROL EQ. STOR PATROL GEN STOR 157 620 SF SERVER ROOM 158 296 SF PATROL FILES/ COPY 160 214 SF HOUSEKEEPING 183 65 SF JUV. TOILET 152 79 SF JUV. LOUNGE 151 118 SF MEN 103 122 SF WOMEN 104 191 SF ELECTRICAL 159 79 SF WATER ENTRY 174 1,107 SF GC PATROL SGT. 153 1,132 SF GC INVESTIGATIONS 154 507 SFCORRIDOR1162,024 SF CORRIDOR 131 214 SF WORK ROOM 158A2,497 SF REPORTS 161 2,939 SF CORRIDOR 162 RedundantRoomCORRIDOR165117 SFVESTIBULE166847 SF BAG TAG 191 154 SF MEN 175 164 SF WOMEN 176 75 SF REPORT TAKING 105 76 SF REPORT TAKING 106 118 SF STOR. 102A 141 SF COUNSELING 123 88 SF JAN. 159A CITY: 7,536 SF COUNTY: 12,453 SF SHARED (50/50): 14,742 SF LEVEL 1 LEVEL 1 GROSS SF: 49,068 SF COMMON (PRO-RATA): 14,337 SF 121 SF IT 198 TOTAL CITY: 8,858 SF TOTAL COUNTY: 13,196 SF TOTAL SHARED (50/50): 19,455 SF LAW ENFORCEMENT TOTAL TOTAL GROSS SF: 59,718 SF TOTAL COMMON (PRO-RATA): 18,209 SF COP YRIGHT 2016P R E L I M I N A R YD R A W I N G SN O T F O RC O N S T R U C T I O N Architect: ThinkOne 101 East Main St. Studio 1 Bozeman, MT 59715 406-586-7020 Associate Architect: AndersonMasonDale Architects 3198 Speer Blvd. Denver, CO 80211 303-294-9448 Associate Architect: McClaren, Wilson & Lawrie, Inc. Architects 8705 N. Central Ave. Phoenix, AZ 85020 602-331-4141 Engineer: Morrison-Maierle, Inc. 2880 Technology Blvd. Bozeman, MT 59715 406-587-0721 6/16/2016 12:17:32 PMO-001 DESIGN DEVELOPMENT 2016-06-17 1514GALLATIN COUNTY AND CITY OF BOZEMANLAW & JUSTICE CAMPUS - LAW ENFORCEMENT CENTER615 SOUTH 16TH AVENUE, BOZEMAN, MONTANA, 59715OWNERSHIP DIAGRAM - FIRST FLOOR 1/16" = 1'-0"O-001 1FIRST FLOOR PLAN 4,767 sf Garage Storage Bays:Gross = 4,767 SFNet = 4467 SF CITY: 7,536 SF COUNTY: 12,453 SF SHARED (50/50): 14,742 SF LEVEL 1 LEVEL 1 GROSS SF: 49,068 SF COMMON (PRO-RATA): 14,337 SF TOTAL CITY: 8,858 SF TOTAL COUNTY: 13,196 SF TOTAL SHARED (50/50): 19,455 SF LAW ENFORCEMENT TOTAL TOTAL GROSS SF: 59,718 SF TOTAL COMMON (PRO-RATA): 18,209 SF Initial SF percentages:(utilizes outside face of structure for gross square footage calculation) Revised SF percentages (Jan. 3, 2018):(updates gross square footage calculation to outside face of exterior finish) (same) Revisions (deduct vehicle garage bays) (same) (sf inclusive of ext. finish) (sf inclusive of ext. finish & deductsvehicle garage bays) 7,536 SF 7,986 SF 14,742 SF 45,233 SF 14,969 SF 50,000 SF (calc. to outsideface of ext. finish) 61,400 SF (calc. to outsideface of ext. finish) Revisions 8,858 SF 8,729 SF 19,455 SF 56,633 SF 19,591 SF (same) (deduct vehicle garage bays) (same) (sf inclusive of ext. finish) (sf inclusive of ext. finish & deductsvehicle garage bays) 2018-01-02 Total Occupied SF % Bozeman Police – 15.64% Gallatin Co. Sheriff - 15.41% Total Shared - 34.36% Total Common - 34.59% Ownership & Usage ~ 50/50 182 DN DN DN DW REF.REF. 52 SF ELEV #1 210 620 SF FITNESS 208 799 SF LUNCH RM 204227 SF STAIRS #1 202 218 SF STAIRS #2 209 1,135 SF DEFENSIVE TACTICS & TRAINING RM 207 236 SF D.T. STOR 206 2,125 SF LOCKERS 203 236 SF TASK CHAIR STOR 205 95 SF 1st AID/ SLEEP 213 115 SF T/SHWR 219 90 SF ELECT 220 77 SF T/LAV 218 90 SF T/LAV 217 82 SF T/LAV 216 85 SF T/LAV 215 108 SF T/SHWR 214 90 SF 1st AID/ SLEEP 212 758 SF STORAGE 201 497 SF MECH/SUPPORT 223 2,092 SF BREAKOUT 221 OPEN TO BELOW 107 SF JAN. 222 161 SF ROOF ACCESS 225 254 SF STORAGE 224 OPEN TO LOBBY BELOW CITY: 1,322 SF COUNTY: 743 SF SHARED (50/50): 4,713 SF LEVEL 2 LEVEL 2 GROSS SF: 10,650 SF COMMON (PRO-RATA): 3,872 SF COP YRIGHT 2016P R E L I M I N A R YD R A W I N G SN O T F O RC O N S T R U C T I O N Architect: ThinkOne 101 East Main St. Studio 1 Bozeman, MT 59715 406-586-7020 Associate Architect: AndersonMasonDale Architects 3198 Speer Blvd. Denver, CO 80211 303-294-9448 Associate Architect: McClaren, Wilson & Lawrie, Inc. Architects 8705 N. Central Ave. Phoenix, AZ 85020 602-331-4141 Engineer: Morrison-Maierle, Inc. 2880 Technology Blvd. Bozeman, MT 59715 406-587-0721 6/16/2016 12:17:35 PMO-002 DESIGN DEVELOPMENT 2016-06-17 1514GALLATIN COUNTY AND CITY OF BOZEMANLAW & JUSTICE CAMPUS - LAW ENFORCEMENT CENTER615 SOUTH 16TH AVENUE, BOZEMAN, MONTANA, 59715OWNERSHIP DIAGRAM - SECOND FLOOR 1/16" = 1'-0"O-002 1SECOND LEVEL FLOOR PLAN - OWNERSHIP Initial SF percentages:(utilizes outside face of structure for gross square footage calculation) Revised SF percentages (Jan. 3, 2018):(updates gross square footage calculation to outside face of exterior finish) 11, 400 SF (calc. to outsideface of ext. finish) CITY: 1,322 SF COUNTY: 743 SF SHARED (50/50): 4,713 SF LEVEL 2 LEVEL 2 GROSS SF: 10,650 SF COMMON (PRO-RATA): 3,872 SF (same) Revisions (same) (same) (sf inclusive of ext. finish) (sf inclusive of ext. finish) 1,322 SF 743 SF 4,713 SF 11,400 SF 4,622 SF 2018-01-02 183 DWF.E.C.F.E.C.F.E.C.F.E.C.F.E.C.UPUP UPUP5 4 3 2 1COMMON BUILDINGVICTIM'S SERVICESCITY OF BOZEMAN POLICE DEPARTMENTBZN PD/FD TRAINING ROOMBZN PD/FD EXERCISE ROOMBZN PD/FD DECON BAYCITY OF BOZEMAN FIRE STATION #1COPYRIGHT 2014PRELIMINARY DRAWINGS NOT FOR CONSTRUCTIONThinkOne 101 East Main St.Studio 1Bozeman . MT 59715406.586.7020Anderson Mason Dale 3198 Speer Blvd.Denver . CO 80211303.294.9448Morrison-Maierle, Inc. 2880 Technology Blvd.Bozeman . MT 59715406.587.0721KEY PLAN3/30/2018 11:20:12 AMBPS1.0PRE DESIGN INVESTIGATION03.30.2018CITY OF BOZEMAN PUBLIC SAFETY CAMPUS N. ROUSE AVE. & E. OAK ST., BOZEMAN MT OVERALL FIRST FLOOR PLAN 1/16" = 1'-0"BPS1.01OVERALL FIRST LEVEL PLAN - PRESENTATION184 REF.F.E.C.F.E.C.F.E.C.F.E.C.F.E.C.F.E.C.EJDNOPEN TO BELOWEXITENTER F.E.C. F.E.C.COMMON BUILDINGMUNICIPAL COURTSCLERK SUITECITY ATTORNEY COMMON BUILDING(MECHANICAL)MECHANICAL MEZZANINE EST. 1,900 SFMECHANICAL PENTHOUSE EST. 1,300 SFCOPYRIGHT 2014PRELIMINARY DRAWINGS NOT FOR CONSTRUCTIONThinkOne 101 East Main St.Studio 1Bozeman . MT 59715406.586.7020Anderson Mason Dale 3198 Speer Blvd.Denver . CO 80211303.294.9448Morrison-Maierle, Inc. 2880 Technology Blvd.Bozeman . MT 59715406.587.0721KEY PLAN3/30/2018 11:20:17 AMBPS1.1PRE DESIGN INVESTIGATION03.30.2018CITY OF BOZEMAN PUBLIC SAFETY CAMPUS N. ROUSE AVE. & E. OAK ST., BOZEMAN MT OVERALL SECOND FLOOR PLAN 1/16" = 1'-0"BPS1.11OVERALL SECOND LEVEL - PRESENTATION185 DWF.E.C.F.E.C.F.E.C.F.E.C.F.E.C.TRAINING ROOM1-186WATER ENTRY1-173ELECT.1-179ARMORY1-168SRT ARMORY1-213BIKE PATROL1-211PATROL1-137OP SERGEANT1-151COMMANDER1-150TEAM MTG /CONFERENCE1-161INVESTIGATIONS1-135POLICE INFO SPEC1-146DET SERGEANT1-145COMMANDER1-144COMMANDER1-143CHIEF1-141RECEPTION1-140INTERVIEW1-129RECORDS1-126WAITING1-109OFFICE1-111OFFICE1-110RECEPTION1-108WOMENS RR1-115INTERVIEW1-118MENS RR1-120COMMUNITYROOM1-104PUBLIC LOBBY1-102ELEV. MR1-103GEAR BAGS 1-139REPORT WRITING1-138SUPPORT SERVICES1-134SECURE CORRIDOR1-196STAIR 3 S-3 IT1-155ASST. CHIEF1-142IT1-165LARGE INTERVIEWROOM1-157REPORT WRITING1-152REPORT WRITING1-153POLICE INFO SPEC1-148FUTURE OFFICE1-149SECURE VESTIBULE1-187SECURE CORRIDOR1-124SHARED WORK AREA 1-136SECURECIRCULATION1-131STAIR 2S-2SPECIAL PROJECTS1-158BRIEFING1-162RR1-159JAN1-172BUNK ROOM1-177BUNK ROOM1-171ELEV MR1-133CONFERENCEROOM1-132ELEVATOR 2E-2MAIL / WORK ROOM 1-147 ELEV. MR1-167STORAGE1-156GEAR BAGSCLR.5' - 0" 16' - 6"CLR.5' - 0" 2' - 2" GEAR BAGS 7' - 0"ELECT.1-160SECURECIRCULATION1-174STORAGE1-185BRUSH TRUCK EQUIPMENT ISSUEEXERCISE ROOMDECON /EXTRACTORDECONBATHROOMSHOWER ROOMSHOWER ROOMSCBA,MAINTENANCE &STORAGEBUNKER STORAGERESTROOMSHOWER ROOMSECURERESTROOMCHANGINGROOMCHANGINGROOMLOCKER ROOMBOOT WASH, HOSE REELS, HOTSY, ETC.WAITINGVIEWINGLARGE INTERVIEWSM. INTERVIEW SM. INTERVIEW SRT STORAGE ELECTRICAL DELIVERYSRT WEAPONSMAINTENANCEEVIDENCE OFFICELABVESTIBULEVEHICLE EXAMBAYEVIDENCE TECHSTORAGELARGE EVIDENCENARCOTICSDRY ROOMDRY ROOMBAG TAGEVIDENCEPROCESSINGPUBLIC EVIDENCEVIEWINGDISCOVERYROOMEVIDENCESTORAGEVAULTEVIDENCE LABSALLY PORTSHOWER ROOMSCBA COMPRESSOR INTERVIEW1-130TABLE & CHAIRSTORAGEFREE WEIGHTSMEDICINE BALLSSTORAGERRRRJAN.QUARTER MASTEROFFICE1-112RR1-117WORKROOM1-121KITCHENETTE 1-116 FILE STORAGE1-12772 LARGE LOCKERS18 SMALL LOCKERSCOPYRIGHT 2014PRELIMINARY DRAWINGS NOT FOR CONSTRUCTIONThinkOne 101 East Main St.Studio 1Bozeman . MT 59715406.586.7020Anderson Mason Dale 3198 Speer Blvd.Denver . CO 80211303.294.9448Morrison-Maierle, Inc. 2880 Technology Blvd.Bozeman . MT 59715406.587.0721KEY PLAN3/30/2018 11:20:23 AMBPS1.2PRE DESIGN INVESTIGATION03.30.2018CITY OF BOZEMAN PUBLIC SAFETY CAMPUS N. ROUSE AVE. & E. OAK ST., BOZEMAN MT AREA A FLOOR PLAN 1" = 10'-0"BPS1.21FIRST LEVEL PLAN - AREA A - WITH FIRE STATION186 DW F.E.C.F.E.C.UPTRAINING ROOM1-186WATER ENTRY1-173ELECT.1-179ARMORY1-168SRT ARMORY1-213BIKE PATROL1-211PATROL1-137OP SERGEANT1-151COMMANDER1-150GEAR BAGS 1-139REPORT WRITING1-138SECURE CORRIDOR1-196STAIR 3 S-3 IT1-165REPORT WRITING1-152REPORT WRITING1-153POLICE INFO SPEC1-148FUTURE OFFICE1-149SECURE VESTIBULE1-187BRIEFING1-162RR1-164STORAGE1-163JAN1-172BUNK ROOM1-177BUNK ROOM1-171ELEV. MR1-16724' - 6" 8' - 0" 16' - 0"11' - 0" 11' - 0" 11' - 0" 11' - 0" GEAR BAGSCLR.5' - 0" 16' - 6"CLR.5' - 0" 2' - 2" GEAR BAGS 7' - 0"SECURECIRCULATION1-174STORAGE1-1855 4 3 2 1SLEEPING ROOMSLEEPING ROOMSLEEPING ROOMSLEEPING ROOMSLEEPING ROOMLAUNDRY/JANITORTOILET|SHOWER24' - 0" 10' - 3" 10' - 6" 10' - 6" 10' - 3" 12' - 3" 18' - 3" 2' - 6"FIRE MARSHALOPS CHIEFEMSSUPERVISORTRAININGOFFICEREMERGENCYMANAGERBATTALION CHIEFINTERPRETIVELOBBYDININGKITCHENDAY ROOMCONFERENCEROOMENTRY VESTIBULEEXTERIOR PATIOFIRE ENGINE LADDER TRUCK HAZ-MAT | RESCUE TRAILER AMBULANCE HAZ-MAT TRUCK CHEVY 1500 EXT. CAB FORD EXPLORER INTERCEPTOR LANDSCAPE BUFFER ADJACENT TO SLEEPING ROOMSSCREEN WALL TO CREATE A PRIVATE SPACE FOR BBQ'S, EXTERIOR DINING, ETC.PUBLIC ENTRYCAPTAINS OFFICEEMSOFFICESECURE ACCESSSLEEPING ROOMCHIEF'S OFFICE14' - 0" 20' - 0"30' - 0" 8' - 0"TOILET|SHOWERTOILET|SHOWERFIRE FIGHTER'SWORK AREADISPLAYDECON PARKING BAY (SHARED) BRUSH TRUCK5' - 0" 18' - 0" 18' - 0" 18' - 0" 18' - 0" 18' - 0" DISPLAY 7' - 0"16' - 0"7' - 0"IT ROOMOFFICE ADMINWAITING ROOMRESTROOMSILSBYEQUIPMENT ISSUEEXERCISE ROOMDECON /EXTRACTORDECONBATHROOMSHOWER ROOMSHOWER ROOMSCBA,MAINTENANCE &STORAGEBUNKER STORAGERESTROOMSHOWER ROOMSECURERESTROOMCHANGINGROOMCHANGINGROOMLOCKER ROOMBOOT WASH, HOSE REELS, HOTSY, ETC.WAITINGVIEWINGLARGE INTERVIEWSM. INTERVIEW SM. INTERVIEW 5' - 0"SRT STORAGE ELECTRICAL DELIVERYSRT WEAPONSMAINTENANCEEVIDENCE OFFICELABVESTIBULEVEHICLE EXAMBAYEVIDENCE TECHSTORAGELARGE EVIDENCENARCOTICSDRY ROOMDRY ROOMBAG TAGEVIDENCEPROCESSINGPUBLIC EVIDENCEVIEWINGDISCOVERYROOMEVIDENCESTORAGEVAULTEVIDENCE LABSALLY PORT72 LARGE LOCKERS18 SMALL LOCKERSSHOWER ROOMSCBA COMPRESSOR WORKROOMSTORAGEFREE WEIGHTSMEDICINE BALLSPUBLICRESTROOM70' - 0"SLEEPING ROOM8' - 6" 12' - 6" 10' - 0" 8' - 0" 72' - 0" 4' - 1" FIRE INSPECTOR OPEN OFFICE 108' - 8" 20' - 0" 10' - 6" 10' - 6" 19' - 0" 18' - 0" 18' - 8" 12' - 0"COPYRIGHT 2014PRELIMINARY DRAWINGS NOT FOR CONSTRUCTIONThinkOne 101 East Main St.Studio 1Bozeman . MT 59715406.586.7020Anderson Mason Dale 3198 Speer Blvd.Denver . CO 80211303.294.9448Morrison-Maierle, Inc. 2880 Technology Blvd.Bozeman . MT 59715406.587.0721KEY PLAN3/30/2018 11:20:28 AMBPS1.3PRE DESIGN INVESTIGATION03.30.2018CITY OF BOZEMAN PUBLIC SAFETY CAMPUS N. ROUSE AVE. & E. OAK ST., BOZEMAN MT AREA B FLOOR PLAN 1" = 10'-0"BPS1.31FIRST LEVEL PLAN - AREA B - WITH FIRE STATION187