BOZEMAN PARKING COMMISSION
Parking Program Manager's Report
Date: March 8, 2018
To: Bozeman Parking Commission
From: Ed Meece, Parking Program Manager
An update of major developments, in February, includes:
• T2: A second 'data pull' from the previous vendor is being completed by T2, at which point the City will undergo
additional testing and refinement in preparation for the third/final extraction process.All relevant staff members
are completing job specific training modules. Preparations are being made for installation of the LUKE II pay
stations,and an internal 'transition plan'that includes public marketing efforts is underway as well.
• The PPM is continues to work with the City Attorney, Bozeman Police, and HRDC to develop an agreement that
outlines responsibility for cleaning,maintenance,and monitoring of the Streamline Bus Station at the Bridger Park
Downtown Garage. A part of this effort was attending a meeting with parking garage condominium owners to
discuss the impacts that bad behavior at the bus station/parking garage has on their businesses (2/28).The PPM
is also developing signage for the parking garage that will display both the code of conduct and security camera
warnings.
• The City Attorney's Office continues to review the proposed changes to the parking regulations within the
Bozeman Municipal Code (submitted to legal, 8/6/17). Upon completion of their review, an updated version will
be presented to the Bozeman Parking Commission for further consideration and action.
• The PPM continues to work with the Downtown Business Partnership and Rialto Theater on how to accommodate
large bus/trailer parking(Rialto events) in an effective manner for neighbors and the Rialto.
• The PPM and PEO Tucker presented the City of Bozeman's case for a 48 hour violation, at Municipal Court.
• The PPM attended a webinar "Strategic Parking Management for Small Communities", sponsored by the
Community Builders, Inc.
• The Parking Services Division, Facilities Management, and IT held a joint security camera policy and operations
training; in accordance with the BPC's recent adoption of a security camera policy.
• The PPM served as a facilitator for High Performing Organization team training; "Future Shocks&City Resilience"
• The PPM, Chairman Naumann, Brit Fontiot (COB Economic Development), and Daniel Rosinsky-Larson, met with
Brian Sprenger (Bozeman Airport General Manager) to discuss the airport's construction of a new garage and
other pending changes to their overall parking program.
• The PPM submitted a Strategic Staffing Plan to the Human Resources Department that reorganizes the
enforcement officer staff into three levels(as opposed to two,currently)and modifies job duties and expectations
as a result.
• PEO I Tucker's enforcement vehicle was struck be a citizen on 2/26/18(they were charged).The PSD is borrowing
a fleet vehicle from the Police Department while our enforcement vehicle is out of service.
• Parking Enforcement Officer II Tom McCardle celebrated his six year service anniversary on February 215e i
Financial Update
Revenues for the fiscal year are at 102%(w/out TIFD funds).
Expenditures for the fiscal year are at 72.94%(w/out TIFD funds).
Parking Services Fund-Operating(3/1/18�
February 2018-Revenue&Expenditures Report
9�0 %
FY 18 FY 18 EARNED EXPECTED
REVENUE BUDGET ACTUAL YTD YTD NOTES
Parking Lot Permits $25,000.00 $37,650.00 150.60% 64%
Garage Permits $250,000.00 $343,060.00 137.22% 64%
Garage-Transient Revenue $75,500.00 $76,185.00 100.91% 64%
Garage Validation Coupons $3,000.00 $2,765.00 92.17% 64%
Residential Nghbd.Permits $13,000.00 $32,507.00 250.05% 64%
Employee Ngbad. Permits $2,000.00 $4,702.00 235.10% 64%
Visitor Ngbad. Permits $10,500.00 $21,410.00 203.90% 64%
Admin/Late Fees $42,000.00 $33,194.00 79.03% 64%
Boot Fees $2,000.00 $450.00 22.50% 64%
The result of several
months of short staffing
&increased attention to
snow removal rather
than citation
Citation Revenue $300,000.00 $178,118.00 59.37% 64% enforcement.
Misc. Revenue $0.00 $3,014.00 NA 64%
Rents/Royalties/Other $2,000.00 $1,837.00 91.85% 64%
Interest Income $750.00 $0.00 0.00% 64%
Loan Interest $840.00 $509.00 60.60% 64%
Refunds& Reimbursements $0.00 $506.00 0.00% 64%
Collection Fees $6,000.00 $12,780.00 213.00% 64%
Transfer Other Funds(TIFD) $250,000.00 $250,000.00 100.00% 64%
TOTAL(w/TIFD Transfer) $982,590.00 $998,687.00 101.64% 64%
TOTAL (w/out TIFD Transfer) $732,590.00 $748,687.00 102.20% 64%
FY 18 FY 18 SPENT EXPECTED
EXPENDITURE BUDGET ACTUAL YTD YTD NOTES
Accounting error?
Reported to Finance
Admin-Personnel 100127 82050 81.95% 64% Dept.3/1/18
$5,000 in undbudgeted
security camera
expenditures;higher than
expected insurance costs;
increased DUNCAN fees
related to customer
Admin--Operating 159232 124138 77.96% 64% activity
Admin--Capital 250000 105794 42.32% 64%
Enforcement--Personnel 202384 131849 65.15% 64%
Enforcement--Operating 49465 23690 47.89% 64%
Enforcement--Capital 10000 0 N/A 64%
Garage--Personnel 40122 26758 66.69% 64%
Higher than expected
Garage--Operating 156900 135419 86.31% 64% snow removal costs
Garage--Capital 0 0 N/A 64%
TOTAL(w/Admin Capital-TIFD) 968230 629698 65.04% 64%
TOTAL(w/out Admin Capital-TIFD] 718230 523904 72.94% 64%
Active Projects:Strategic Parking Management Plan COMPLETED
PENDING
March 2018 HOLD/NOT STARTED
PROJECTED ACTUAL
STRATEGY DESCRIPTION COMPLETION COMPLETION COMMENTS
Formalize the guiding principles
as policies within the parking and Adopted by the BPC in
1 transporation system plan. Aug-16 8/2016.
Adopt the 85%rule as the
standard for measuring
performance of the parking
supply and triggering specific Adopted by the BPC in
2 management strategies. Aug-16 8/2016.
Strengthen the role of the
Parking Manager and the Parking
Services Division-to better PPM attending DRC
integrate with the Community meetings,and offering
Development and Economic data/comment as staff
3 Development planning. On-Going On-Going review.
Establish a policy for adjusting Adopted by the BPC in
4 rates(on and off-street) Oct-16 10/2016.
BPC approved Resolution
2017-03(6/2017);City
Commission approved
Establish a Capital Maintenance CC Approval Resolution#4837 on
5 Reserve Fund Jul-16 8/14/17 8/14/17.
PPM is working with the
Comm.Dev.Department;
CDD has assigned this a'fall
2018'priority status;The
PPM is re-assembling an
internal"Parking Strategy
Team"(at instruction of
City Manager)to develop
strategies for addressing
#6,#7,#8 in a single
Re-evaluate and restructure comprehensive manner,
6 current cash-in-lieu program. TBD 3/1/18;
PPM worked with the ED
dept on changes to the
minimum parking standards
(UDC)in the 62M zone,
approved by CC 9/2017;
PPM actively attending
internal DRC meetings to
offer guidance on policy
issues and prepare for 2018
effort to modify the parking
standards section of the
UDC;The PPM is re-
assembling an internal
"Parking Strategy Team"(at
instruction of City
Manager)to develop
strategies for addressing
#6,#7,#8 in a single
Re-evaluate code based comprehensive manner,
7 minimum parking requirements 3/1/18;
PPM is waiting on the
Admin./Legal Depts.For
further instruction on this
isue;The PPM is re-
assembling an internal
"Parking Strategy Team"(at
instruction of City
Re-evaluate and clarify the Manager)to develop
purpose and intent of the strategies for addressing
current code section regarding #6,#7,#8 in a single
Special Improvement District# comprehensive manner,
8 565. TBD 3/1/18;
PPM is completing research
for facility mgt.best
Implement a Facilities practices,starting to draft
9 Maintenance Plan. 12/30/2017 On-going Fac.Mgt.plan,8/17;
Data collection ocurred,
following the Strategic
Parking Management Plan,
Spring and Summer 2017;
WTI report(draft)submitted
9/2017,under staff review
at this time;Final comments
submitted to WTI for
modification,10/23/17;The
Develop a reasonable schedule final WTI Parking
of data collection to assess Occupancy Report was
performance,including an released on 11/14/2017,
accurate on and off street analysis is underway-
inventory(public and private) including
and an occupancy/utilization review/memorandum from
10 analysis. 5/1/17&7/1/17 11/14/2017 Rick Williams Consulting.
1st shared use agreement
negotiated and approved
with Big Sky Western Bank
Identify off-street shared use (June 2017);Completion of
opportunities based on data the WTI Parking Occupancy
from strategy 9.Establish goals Study on 11/14/17 is
for transitioning employees, expected to demonstrate
begin outreach to opportunity areas where new shared
sites,negotiate agreements,and space agreements will be
11 assign employees to facilities. On-Going most effective.
Complete the 2008 Parking
District Identification
12 Signage/Branding Plan No activity at this time.
Clarify current on-street parking
signage,particularly in areas
where unlimited parking is
allowed.Consider incorporating
the current City parking logo into
13 on-street signage. No activity at this time.
Rename all publicly owned lots
14 and garages by address. No activity at this time.
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17:
Project kickoff call held
11/10/17,data conversion
and preliminary staff
training underway;Data
conversion is nearing
completion of second data
extraction,staff training is
underway,transition
Upgrade the access/revenue planning on-going;
control system at the Bridger estimated GOLIVE of
15 Garage. 5/1/2018 On-going 4/28/18.
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17;
Project kick off call held
11/10/17,data conversion
and preliminary staff
training underway;Data
conversion is nearing
completion of second data
extraction,staff training is
underway,transition
Install a vehicle counter system planning on-going;
at Bridger Garage and at the estimated GOLIVE of
16 Surface lots. 6/30/2017 On-Going 4/28/18.
Establish best practice protocols Court/Appeals Packet
and performance metrics for (4/17);Uniform Policy
existing enforcement personnal (8/17);Enhanced Safety
and support enforcement with Procedures;Security
17 appropriate technology. On-going Camera Policy;
Expand bike parking
network to create
connections between
parking and the
downtown to encourage
employee bike commute
trips and draw customers
18 to sowntown businesses. No activity at this time.
Explore changes to
existing residential on
City Commission requested
street permit programs (11/20/17)that this effort
and evaluate potentially be complete,with
implement new residential recommendation to them,
parking permit districts in by late Spring/Early
Summer 2018.PPM will
the neighborhood northa provide preliminary repor
nd south of the downtown to BPC on 3/8/18,final
19 commercial district. 7/1/2018 On-going report on 4/12/18.
Evaluate on street pricing
20 in high occupancy areas. No activity at this time.
Explore expanding access
capacity with new parking
21 supply and/or transit No activity at this time.
Develop cost forecasts for
preferred parking supply
22 and shuttle options. No activity at this time.
Explore and develop
23 funding options. No activity at this time.
Explore the
implementation of on
24 street pricing. No activity at this time.
Consider consolidating
current users of the
Carnegie Lot into the
Bridger Garage.Sell the
Carnegie Lot to fund
acquisition of(better
located parking parcels
and/or construction of a
25 parking garage. No activity at this time.
Initiate new capacity
26 expansion. No activity at this time.