BOZEMAN PARKING COMMISSION
Parking Program Manager's Report
Date: February 8, 2018
To: Bozeman Parking Commission
From: Ed Meece, Parking Program Manager
An update of major developments, in January, includes:
• T2: The Parking Division and Finance Department have finalized the 'Data Conversion Worksheet' which will
provide the data-mapping necessary, so as to allow the first pull of data from the existing vendor database. The
Parking Services Division and IT Department finalized the design for,and ordered,new citation stock for the PEO's
mobile printers. Position-specific training (on-line) began, in the Parking Services Division. The Finance
Department has initiated the process to create on-line payment gateways(credit card)for the permit and citation
payments; likewise,a similar effort has started with regard to collection services.
• The Parking Services Division has dedicated considerable staff resources, in January,toward moving and removing
vehicles that are bermed-in, parked over 48 hours, or causing difficulties for the Street Departments' snow
plowing and removal efforts. So far, over 150+vehicles have been "voluntarily moved" and two dozen towed for
this purpose. At this point, the process requires that 2 PEO's patrol the identified 'priority' streets from Public
Works; placing two "This Vehicle Must Be Moved by 3 AM on INSERT DAY OF WEEK or it will be Towed" signs at
each violating vehicle. Forty-eight hours later,two PEO's return to the area, and cite/photograph/tow any signed
vehicles that still remain; in addition to reclaiming any signs in the area. Maintaining an on-going daily rotation of
signage and towing requires at least two of the PEO's for two to four hours.
• The PPM, in conjunction with the Facilities Director, has ordered parking permit hang-tags for COB staff assigned
to the Stiff Professional Building, and is preparing to implement a new 'parking policy'for staff.
• On a related note, the PPM is working with City Management to prepare for a pending rehabilitation of the Stiff
Professional Building that will likely shift the Parking Services Division offices to the basement.
• The PPM is working with the City Attorney, Bozeman Police, and HRDC to develop an agreement that outlines
responsibility for cleaning, maintenance, and monitoring of the Streamline Bus Station at the Bridger Park
Downtown Garage. Of special importance is the need for a 'behavior policy' which empowers the Police
Department to remove individuals from the bus station, under certain circumstances, and provides an appeal
process for such removals.This policy will likely be very similar to policies already in place at the Library and in the
Parks and Recreation Department.
• The City Attorney's Office continues to review the proposed changes to the parking regulations within the
Bozeman Municipal Code (submitted to legal, 8/6/17). Upon completion of their review, an updated version will
be presented to the Bozeman Parking Commission for further consideration and action.
Financial Update
Revenues for the fiscal year are at 94%(w/out TIFD funds).
Expenditures for the fiscal year are at 58.83%(w/out TIFD funds).
Parking Services Fund -Operating(2/2/18)
January 2018-Revenue&Expenditures Report
FY 18 FY 18 EARNED EXPECTED
REVENUE BUDGET ACTUAL YTD YTD
Parking Lot Permits $25,000.00 $36,399.00 145.60% 56%
Garage Permits $250,000.00 $328,065.00 131.23% 56%
Garage-Transient Revenue $75,500.00 $64,736.00 85.74% 56%
Garage Validation Coupons $3,000.00 $2,515.00 83.83% 56%
Residential Nghbd.Permits $13,000.00 $31,945.00 245.73% 56%
Employee Ngbad. Permits $2,000.00 $4,565.00 228.25% 56%
Visitor Ngbad. Permits $10,500.00 $21,135.00 201.29% 56%
Admin/Late Fees $42,000.00 $28,584.00 68.06% 56%
Boot Fees $2,000.00 $450.00 22.50% 56%
Citation Revenue $300,000.00 $154,564.00 51.52% 56%
Misc. Revenue $0.00 $3,014.00 NA 56%
Rents/Royalties/Other $2,000.00 $1,170.00 58.50% 56%
Interest Income $750.00 $0.00 0.00% 56%
Loan Interest $840.00 $446.00 53.10% 56%
Refunds & Reimbursements $0.00 $256.00 0.00% 56%
Collection Fees $6,000.00 $11,183.00 186.38% 56%
Transfer Other Funds (TIFD) $250,000.00 $0.00 0.00% 56%
TOTAL(w/TIFD Transfer) $982,590.00 $689,027.00 70.12% 56%
TOTAL (w/out TIFD Transfer) $732,590.00 $689,027.00 94.05% 56%
FY 18 FY 18 SPENT EXPECTED
EXPENDITURE BUDGET ACTUAL YTD YTD
Admin - Personnel $100,127.00 $58,128.00 58.05% 56%
Admin --Operating $159,232.00 $119,164.00 74.84% 56%
Admin --Capital $250,000.00 $78,205.00 31.28% 56%
Enforcement-- Personnel $202,384.00 $90,085.00 44.51% 56%
Enforcement--Operating $49,465.00 $21,338.00 43.14% 56%
Enforcement--Capital $10,000.00 N/A 56%
Garage-- Personnel $40,122.00 $20,070.00 50.02% 56%
Garage--Operating $156,900.00 $113,723.00 72.48% 56%
Garage--Capital $0.00 $0.00 N/A 56%
TOTAL(w/Admin Capital-TIFD) $968,230.00 $500,713.00 51.71% 56%
TOTAL(w/out Admin Capital-TIFD) $718,230.00 $422,508.00 58.83% 56%
Active Projects:Strategic Parking Management Plan COMPLETED
PENDING
February 2018 HOLD/NOT STARTED
PROJECTED ACTUAL
STRATEGY DESCRIPTION COMPLETION COMPLETION COMMENTS
Formalize the guiding principles
as policies within the parking and Adopted by the BPC in
1 transporation system plan. Aug-16 8/2016.
Adopt the 85%rule as the
standard for measuring
performance of the parking
supply and triggering specific Adopted by the BPC in
2 management strategies. Aug-16 8/2016.
Strengthen the role of the
Parking Manager and the Parking
Services Division-to better PPM attending DRC
integrate with the Community meetings,and offering
Development and Economic data/comment as staff
3 Development planning. On-Going On-Going review.
Establish a policy for adjusting Adopted by the BPC in
4 rates(on and off-street) Oct-16 10/2016.
BPC approved Resolution
2017-03(6/2017);City
Commission approved
Establish a Capital Maintenance CC Approval Resolution#4837 on
5 Reserve Fund Jul-16 8/14/17 8/14/17.
PPM is working with the
Comm.Dev.Department;
Re-evaluate and restructure CDD has assigned this a'fall
6 current cash-in-lieu program. TBD 2018'priority status.
PPM worked with the ED
dept on changes to the
minimum parking standards
(UDC)in the 62M zone,
approved by CC 9/2017;
PPM actively attending
internal DRC meetings to
offer guidance on policy
issues and prepare for 2018
effort to modify the parking
Re-evaluate code based standards section of the
7 minimum parking requirements UDC.
Re-evaluate and clarify the
purpose and intent of the PPM is waiting on the
current code section regarding Admin./Legal Depts.For
Special Improvement District# further instruction on this
8 565. TBD isue.
PPM is completing research
for facility mgt.best
Implement a Facilities practices,starting to draft
9 Maintenance Plan. 12/30/2017 On-going Fac.Mgt.plan,8/17;
Data collection ocurred,
following the Strategic
Parking Management Plan,
Spring and Summer 2017;
WTI report(draft)submitted
9/2017,under staff review
at this time;Final comments
submitted to WTI for
modification,10/23/17;The
Develop a reasonable schedule final WTI Parking
of data collection to assess Occupancy Report was
performance,including an released on 11/14/2017,
accurate on and off street analysis is underway-
inventory(public and private) including
and an occupancy/utilization review/memorandum from
10 analysis. 5/1/17&7/1/17 11/14/2017 Rick Williams Consulting.
1st shared use agreement
negotiated and approved
with Big Sky Western Bank
Identify off-street shared use (June 2017);Completion of
opportunities based on data the WTI Parking Occupancy
from strategy 9.Establish goals Study on 11/14/17 is
for transitioning employees, expected to demonstrate
begin outreach to opportunity areas where new shared
sites,negotiate agreements,and space agreements will be
11 assign employees to facilities. On-Going most effective.
Complete the 2008 Parking
District Identification
12 Signage/Branding Plan No activity at this time.
Clarify current on-street parking
signage,particularly in areas
where unlimited parking is
allowed.Consider incorporating
the current City parking logo into
13 on-street signage. No activity at this time.
Rename all publicly owned lots
14 and garages by address. No activity at this time.
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17:
Project kick off call held
Upgrade the access/revenue 11/10/17,data conversion
control system at the Bridger and preliminary staff
15 Garage. 5/1/2018 On-going training underway;
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17;
Project kick off call held
Install a vehicle counter system 11/10/17,data conversion
at Bridger Garage and at the and preliminary staff
16 Surface lots. 6/30/2017 On-Going training underway;
Establish best practice protocols
and performance metrics for
existing enforcement personnal Court/Appeals Packet
and support enforcement with (4/17);Uniform Policy
17 appropriate technology. On-going (8/17);
Expand bike parking
network to create
connections between
parking and the
downtown to encourage
employee bike commute
trips and draw customers
18 to sowntown businesses.
Explore changes to
existing residential on City Commission
street permit programs requested (11/20/17)
and evaluate potentially that this effort be
implement new residential complete,with
parking permit districts in recommendation to
the neighborhood northa them, by late
nd south of the downtown Spring/Early Summer
19 commercial district. 7/1/2018 On-going 2018.
Evaluate on street pricing
20 in high occupancy areas.
Explore expanding access
capacity with new parking
21 supply and/or transit
Develop cost forecasts for
preferred parking supply
22 and shuttle options.
Explore and develop
23 funding options.
Explore the
implementation of on
24 street pricing.
Consider consolidating
current users of the
Carnegie Lot into the
Bridger Garage.Sell the
Carnegie Lot to fund
acquisition of(better
located parking parcels
and/or construction of a
25 parking garage.
Initiate new capacity
26 expansion.