HomeMy WebLinkAboutFiscal Years 2019-2023 Capital Improvements Program, City of BozemanCAPITAL IMPROVEMENTS
PROGRAM
Fiscal Years 2019‐2023
City of Bozeman, Montana
Adopted
Capital Improvements Program
For Fiscal Years 2019‐2023
Presented And Adopted during Public Meetings held
November 2017 – December 2017
City Commission
Carson Taylor, Mayor
Cynthia Andrus, Deputy Mayor
Jeff Krauss, Commissioner
Chris Mehl, Commissioner
I‐Ho Pomeroy, Commissioner
Andrea Surratt, City Manager
Anna Rosenberry, Assistant City Manager
Kristin Donald, Finance Director
Robin Crough, City Clerk
LETTER FROM THE CITY MANAGER
Dear City Commission and Residents of Bozeman:
We are proud to present to you the City of Bozeman, 2019‐2023 Capital Improvement Program. This five‐year
Capital Improvement Plan (CIP) is a commitment to improving and maintaining the City of Bozeman’s facilities,
parks and roads to aid in the vision of Bozeman being the most livable place.
The CIP performed in compliance with State and municipal code, State Law requires the City to maintain
a Capital Improvement Plan for our Development Impact Fee programs. Under Montana Code Annotated
(MCA), this Capital Improvement Plan provides the schedules and cost projections required under MCA
§7‐6‐1602(2)(k)(i‐iv). In Article 5.06 of the adopted City Charter, the City Manager is responsible for
preparing and submitting a multi‐year capital program to the City Commission no later than December 15
for the ensuing fiscal year.
This five‐year plan includes long‐range plans for our current facilities while keeping in mind level of service
standards. In a community with relatively high cost of living, the ability of citizens to afford the needed utility
rate, fee, and assessment levels is of concern. At the same time, the City strives to keep existing facilities
properly maintained — and not pass deferred maintenance costs and problems on to future generations. The
staff have taken a lot of time and care in preparing this document.
At times of rapid growth, as we are experiencing once again, the need for expanded public facilities and services
is at its peak. A carefully developed CIP plans for these expansions and communicates our intent to citizens
and the development community. The plan has been developed with the strategic vision statements as a
driving force.
In closing, I respectfully submit the 2019‐2023 Capital Improvement Plan to the residents of the City of
Bozeman. The City will continue to invest in capital infrastructure in order to keep Bozeman as a vibrant and
active city.
Respectfully,
Andrea Surratt
Andrea Surratt
City Manager
TABLE OF CONTENTS
Introduction and Overview .............................................................................................................................. 1
Background .................................................................................................................................................. 1
CIP Process ................................................................................................................................................... 2
CIP Funding .................................................................................................................................................. 6
2019‐2023 CIP Project Summary ..................................................................................................................... 7
2019‐2023 CIP Financial Summary ................................................................................................................ 10
Fund Summaries:
Arterial & Collector District ....................................................................................................................... 11
Building Inspection ................................................................................................................................... 43
Community Development ......................................................................................................................... 49
Fire Equipment & Capital .......................................................................................................................... 55
Fire Impact Fee ......................................................................................................................................... 67
Forestry Tree Maintenance District .......................................................................................................... 71
General ..................................................................................................................................................... 79
Library Depreciation ............................................................................................................................... 163
Parking .................................................................................................................................................... 169
Solid Waste ............................................................................................................................................. 181
Stormwater ............................................................................................................................................. 193
Street & Curb Reconstruction ................................................................................................................. 213
Street Impact Fee.................................................................................................................................... 231
Street Maintenance ................................................................................................................................ 273
Wastewater ............................................................................................................................................ 321
Wastewater Impact Fee .......................................................................................................................... 351
Water ...................................................................................................................................................... 367
Water Impact Fee ................................................................................................................................... 419
INTRODUCTION AND OVERVIEW
One of the primary responsibilities of local government is to properly preserve, maintain, and improve a
community’s stock of buildings, streets, parks, water and sewer lines, and equipment. Planning for these
capital improvements is a matter of prudent financial management, as well as sound development
practice.
At times of rapid growth, as we are experiencing once again, the need for expanded public facilities and
services is at its peak. A carefully developed CIP plans for these expansions and communicates our intent
to citizens and the development community. In times of economic contraction, like the past‐prolonged
recession, capital improvements were often put off (deferred) as a way of trimming budgets. While this
can be appropriate in cases, an annual analysis and focus on necessary capital improvements helps to
ensure those capital deferrals, and their impact on the community, are fully vetted.
Background
To provide service to its citizens, a city government needs funding for costs such as salaries, supplies, and
other operating items. Most public services also entail costs for furniture, automobiles, other equipment
and vehicles, land, and construction of buildings or other public facilities. These costs are separated into
two large categories: (1) operating expenditures, and (2) capital outlays.
Operating expenditures include personnel costs, day‐to‐day maintenance and operation of City assets,
and the acquisition of goods that are consumed or used up as a service is provided. These types of
expenses cost less on a unit basis than most capital outlays, and they recur at roughly the same level from
year to year.
Capital outlays occur on a periodic basis. Within the broad category of capital outlay expenditures, there
are two subgroups: (a) capital equipment and (b) capital improvements. The City budgets capital
equipment annually through the CIP process. The City budgets capital improvements annually through
dedicated revenue. Capital improvement expenses also generate operating costs that must be recognized
and accommodated.
The CIP includes any planned expenditure of $10,000 or greater, that results in the acquisition of an asset
with a useful life of 3 years or more. There is a couple of “exceptions” or “extensions” of this definition
that we have found helpful and necessary in past years:
General Planning Documents (master plans, community surveys, etc.) are NOT included in our CIP;
Specific plans that involve pre‐engineering or preliminary design of facilities are often (but not
always) included in the CIP.
Software purchases that could potentially be “software as a service”. Cloud based services are
beginning to replace our purchase of outright software and hardware. In the CIP, we have treated
1
the software projects as a capital outlay purchase; although a “service” type, solution may actually
be chosen during the bidding/proposal process.
State law and City charter require the City to prepare the CIP. State Law requires the City to maintain a
Capital Improvement Plan for our Development Impact Fee programs. Under Montana Code Annotated
(MCA), this Capital Improvement Plan provides the schedules and cost projections required under MCA
§7‐6‐1602(2)(k)(i‐iv). In Article 5.06 of the adopted City Charter, the City Manager is responsible for
preparing and submitting a multi‐year capital program to the City Commission no later than December 15
for the ensuing fiscal year. The plan must be revised and extended each year with regard to projects not
yet completed. This plan is required to include:
1.A clear general summary of contents;
2.Identification of the long‐term goals of the community;
3.A list of all capital improvements and other capital expenditures which are proposed to be
undertaken during the fiscal years next ensuing, with appropriate supporting information as to
the necessity for each;
4.Cost estimates and recommended time schedules for each improvement or other capital
expenditure;
5.Method of financing upon which each capital expenditure is to be reliant;
6.The estimated annual cost of operating and maintaining the facilities to be constructed or
acquired;
7.A commentary on how the plan addresses the sustainability of the community or region of which
it is a part; and
8.Methods to measure outcomes and performance of the capital plan related to the long‐term goals
of the community.
CIP Process
Each year, we begin the process of updating our Capital Improvements Plan in September. Finance works
in coordination with City departments and the City manager’s Office to recommend projects that can be
undertaken within the funds available. The process is completed when the Commission adopts a final
budget with capital items approved, usually in the following June, see the following calendar:
2
There are many considerations when developing the plan from basi c o p e r a t i o n a l n e e d s t o g r o w t h . T h e
following descriptions are the areas considered when developing the CIP:
City Vision and Strategic Goals
The City recently adopted goals to develop a five‐year Strategic Plan and revised its vision. The Plan
has been the subject of numerous citizen engagement efforts and public meeting discussions. The
•Departments make new CIP requests
•Departments make note of any
changes to existing CIP projects.
September:
•City Manager and staff meet to review
new and existing projects; modify any
timing, cost or revenue estimates.
•Impact Fee Advisory Committee
receives and reviews proposed Impact
Fee CIP schedules and forwards
comments to City Commission.
October/November:
•City Manager presents Draft CIP to
City Commission prior to December
15th.
•City Commission holds public
hearings, takes public comment and
adopts CIP Plan for ensuing fiscal year.
November/December:
•Adopted CIP is integrated into City
Manager’s Recommended Budget for
ensuing fiscal year.
•Commission, via adopting a final
budget, appropriates dollars for CIP
projects for the fiscal year.
January‐ June:
3
Strategic Plan initiatives to date have been included and planned for in this CIP. Below are the vision
and vision statements adopted by the Commission May 15, 2017:
Vision
Bozeman remains a safe, inclusive community, fostering civic engagement and creativity, with a
thriving diversified economy, a strong environmental ethic, and a high quality of life as our community
grows and changes.
Strategic Vision Statements:
1) An Engaged Community. We foster a culture of engagement and civic leadership based on innovation
and best practices involving community members of all backgrounds and perspectives.
2) An Innovative Economy. We grow a diversified and innovative economy leveraging our natural
amenities, skilled and creative people, and educational resources to generate economic opportunities.
3) A Safe, Welcoming Community. We embrace a safe, healthy, welcoming and inclusive community.
4) A Well‐Planned City. We maintain our community's quality of life as it grows and changes, honoring
our sense of place and the 'Bozeman feel' as we plan for a livable, affordable, more connected city.
5) A Creative, Learning Culture. We expand learning, education, arts, expression and creativity for all
ages.
6) A Sustainable Environment. We cultivate a strong environmental ethic, protecting our clean air,
water, open spaces and climate, and promote environmentally sustainable businesses and lifestyles.
7) A High Performance Organization. We operate as an ethical, high performance organization
anticipating future needs, utilizing best practices, and striving for continuous improvement.
Level of Service (LOS) Standards
Most of the City’s long‐range plans establish level of service standards. These standards are
critical to planning for the needs of future city residents. In some cases, such as water quality or
wastewater discharge, these standards are often established or guided by outside regulating
bodies. The CIP does not frequently reference specific LOS, but the underlying facility and staffing
plans will contain detailed discussions of levels of service, and how the City should address
increasing or decreasing levels of service through infrastructure and staffing recommendations.
Policies for the Physical Development of our Community
The City’s Unified Development Code (UDC) is a combination of both Subdivision and Zoning
regulations for development within the City. The Code is subject to amendment by the
Commission, after public notices and hearings are held. The UDC applies to both private and city‐
owned projects. The City is currently underway with “The Bozeman Code Update,” a public
process to update the City’s Unified Development Code (UDC). The UDC covers a diverse range of
4
topics, including, zoning, design standards, subdivisions, wetland, and permit review procedures.
The key feature of the update is to translate the community's expectations for development as
expressed in the Community Plan into a concise and useable set of regulations.
Our Current Facilities and their Condition:
The City has a number of long‐range (20‐year) facility plans:
Water Treatment & Distribution Facilities
Wastewater Collection & Treatment Facilities
Stormwater Collection & Treatment Facilities
Fire Station, Equipment & Staffing
Police Station & Staffing
Parks, Recreation, Trails & Open Space
Transportation System Plan
These studies examine the condition and placement of existing facilities, area growth projections
and pattern, regulatory changes, and possible funding mechanisms. The plans analyze various
alternatives and make recommendations for implementation.
Our Community’s Ability to Pay for Planned Improvements
In a community with relatively high cost of living, the ability of citizens to afford the needed utility
rate, fee, and assessment levels is of concern. At the same time, the City strives to keep existing
facilities properly maintained — and not pass deferred maintenance costs and problems on to
future generations.
The City has adopted a Utility Rate Studies for Water and Wastewater services. These studies give
us an indication of how and when utility rates must be increased to pay for the needed water and
wastewater system improvements.
For General Fund (Administration, Parks, Recreation, Library, Police, and Fire) facilities and Street
construction, the City does not have the ability to easily increase tax levels for funding. The City’s
voters must approve any tax levy increase, and state law establishes maximum debt levels.
In November 2007, the City of Bozeman voters approved a four mill perpetual levy to establish a
Fire Equipment and Capital Replacement fund. This fund was added to the CIP plan, and the funds
are for replacements of fire engines, ladder trucks, and other capital improvements to fire
stations.
In the summer of 2015, the city successfully created a citywide Arterial & Collector Street Special
District, under the special distr i c t l a w s o f t h e s t a t e . T h e D istrict is meant to fund street
5
maintenance and (re)construction on Arterial & Collector streets that is NOT eligible to be funded
by impact fees. The CIP includes a 5‐year plan for capital projects for this new district.
CIP Funding
The program is designed and planned by fund. Within those funds, the method for funding the project is
determined. Some funds have fees or taxes that are specific to capital improvement or maintenance.
Some larger projects financing is required and bonds and other funding mechanisms need to be used. The
next chart shows the funding for each area in the plan with exception any debt issuance, which can vary
year to year depending on the projects and priority for the plan year. The Capital Improvement Program
is then adopted but is not considered funded until the Budget is adopted in June. In addition, certain
funding is not final until a passing on election ballot.
Arterial and Collector
District (Special Revenue
Fund)
•Assessment
•Local Share for projects
Building Inspection Fund
(Special Revenue Fund)
•Charges for services
Community Development
Fund (Special Revenue
Fund)
•Internal appropriation
and other restricted
cash
Fire Equipment and
Capital Fund (Special
Revenue Fund)
•Dedicated tax 4 Mills
Fire Impact Fee (Special
Revenue Fund)
•Impact Fee revenue
Forestry‐ Tree
Maintenance District
(Special Revenue Fund)
•Tree Assessment
General Fund
•Taxes and Charges for
services
Library Depreciation
Fund
•Appropriations from
General Fund
Parking (Enterprise Fund)
•Revenue for charges for
services and
enforcement
Solid Waste Fund
(Enterprise Fund)
•Charges for Services
Storm Water Fund
(Enterprise Fund)
•Charges for Services
Street and Curb
Reconstruction (Special
Revenue Fund)
•Assessment
Street Impact Fee
(Special Revenue Fund)
•Impact Fees
Street Maintenance
District (Special Revenue
Fund)
•Assessment
Wastewater Fund
(Enterprise Fund)
•Charge for Services
Wastewater Impact Fee
(Included in Wastewater
Fund)
•Impact fees
Water Fund (Enterprise
Fund)
•Charges for services
Water Impact Fee
(Included in Water Fund)
•Impact fees
6
2019‐2023 CIP PROJECT SUMMARY
This five‐year plan has $231 million in scheduled projects and $240 million unscheduled. For scheduled
by fund the General fund is the largest with some major projects on the horizon and the Water fund has
a tank replacement making it the second largest. Street Impact Fee is close with 12% with new projects
near the School District’s new High School.
2019
The plan includes large sewer capacity projects that aid in the School District’s efforts in building a new
High school. These infrastructure projects are the Davis Lift
Station WWIF24 and the Front Street Interceptor WWIF11,
and are scheduled in the Wastewater Impact Fee fund. Both
projects will require financing in order to be completed for a
total of just under $8 million. With these two capacity efforts
there are Street Impact Fee and Arterial Collector shared
projects to fund the building of the roads surrounding the new
high school. The Law & Justice Center has been presented as
a project occur in FY19 and FY21 but with the funding, we can
7
change the timing and funding for a different option. Beyond major projects, there is planned road
maintenance, vehicle replacements and building improvements.
2020
The outlook for the 2020 includes another sewer capacity‐expanding project that is dependent on the
Davis Lift Station being done in 2019. The Norton East
Ranch Outfall Diversion WWIF38 is $3,320,000 and
will need financing at this point in the plan. There are
again major roads funded through the Street Impact
Fee Fund and Arterial Collector fund a good portion
is for building of the roads surrounding the new high
school. Fire Station 1 is planned in this year; this will
be an expansion and relocation of the current
station. Along with these major projects road
maintenance, vehicle replacements and building
improvements are in the plan as well.
2021
This includes a water fund major project for the Lyman Tank and
Transmission Main Construction W88, which will be funded through
financing for $10million. Griffin 7th to Rouse SIF113 funded by Street
Impact Fees and Arterial collector funds is scheduled in FY21 for a
project total of $3.7 million. This is also the $20 million portion of
the Law Justice Center is scheduled.
2022
The Indoor/Outdoor aquatics center is planned for FY22 and
will be funded through bonds going to the citizens for a vote.
The Water fund has an over $6million projects, PRV Phase 2 ‐
Automation and Instrumentation Upgrades W71 which will
provide necessary water system maintenance work. Routine
vehicle replacements, pipe replacements and road
maintenance is planned.
2023
Fowler connection (Huffine to Oak) SIF114 funded by Street Impact Fees and Arterial collector funds is
scheduled in FY23 for a project total of $7.5 million. Wastewater Impact Fees has a capacity project N
8
Frontage Rd Interceptor WWIF20 scheduled for just under $5.3 million. The relocation of Fire Station 2 is
scheduled to align with service needs as outlined in the adopted master plan.
UNSCHEDULED
The unscheduled items are in need within the five years or just after. Several large and high dollar projects
remain unscheduled due to funding, timing and other unresolved issues.
9
20
1
9
‐
2
0
2
3
C
I
P
F
I
N
A
N
C
I
A
L
S
U
M
M
A
R
Y
10
Ar
t
e
r
i
a
l
&
C
o
l
l
e
c
t
o
r
D
i
s
t
r
i
c
t
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
4
7
4
,
9
1
7
$
2,
4
2
5
,
3
2
1
$
1,
2
8
6
,
5
4
3
$
3,
7
7
9
,
8
8
4
$
1,
2
4
7
,
7
1
0
$
3,
2
1
6
,
9
2
6
$
P
l
u
s
:
A
s
s
e
s
s
m
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1
,
8
0
6
,
5
1
3
$
1
,
1
2
8
,
6
4
3
$
1
,
1
5
1
,
2
1
6
$
1,
2
0
8
,
7
7
7
$
1,
2
6
9
,
2
1
6
$
1,
3
4
5
,
3
6
9
$
‐$
Pl
u
s
:
P
a
y
b
a
c
k
R
e
v
e
n
u
e
22
1
,
8
9
1
$
60
0
,
5
7
9
$
59
1
,
7
9
2
$
36
1
,
0
4
9
$
Pl
u
s
:
N
e
w
G
a
s
T
a
x
d
o
l
l
a
r
s
20
0
,
0
0
0
$
70
0
,
0
0
0
$
70
0
,
0
0
0
$
70
0
,
0
0
0
$
70
0
,
0
0
0
$
70
0
,
0
0
0
$
Pl
u
s
:
D
e
v
e
l
o
p
e
r
c
o
n
t
r
i
b
u
t
i
o
n
S
I
F
1
0
5
a
n
d
S
I
F
1
3
4
1
,
6
8
3
,
3
3
3
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(
1
,
2
7
8
,
0
0
0
)
$
(
3
,
5
6
8
,
0
0
0
)
$
(
1
,
6
3
3
,
0
0
0
)
$
(
4
,
8
0
2
,
0
0
0
)
$
‐
$
(
5
,
2
5
0
,
0
0
0
)
$
(7,454,000)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
2,
4
2
5
,
3
2
1
$
1,
2
8
6
,
5
4
3
$
3,
7
7
9
,
8
8
4
$
1,
2
4
7
,
7
1
0
$
3,
2
1
6
,
9
2
6
$
12
,
2
9
4
$
Be
g
i
n
n
i
n
g
B
a
l
a
n
c
e
o
f
P
a
y
b
a
c
k
I
m
p
r
o
v
e
m
e
n
t
s
:
(2
,
5
4
4
,
6
6
6
)
$
(2
,
3
2
2
,
7
7
5
)
$
(1
,
8
5
5
,
1
9
6
)
$
(1
,
2
6
3
,
4
0
5
)
$
(1
,
4
0
2
,
3
5
6
)
$
(1
,
4
0
2
,
3
5
6
)
$
(1,402,356)$
SI
F
0
3
6
‐
P
a
y
b
a
c
k
D
i
s
t
r
i
c
t
SI
F
0
4
6
‐
G
a
l
l
a
t
i
n
C
o
u
n
t
y
S
I
D
SI
F
0
7
3
‐
P
a
y
b
a
c
k
D
i
s
t
r
i
c
t
(404,000)$
SI
F
0
7
6
‐
P
a
y
b
a
c
k
D
i
s
t
r
i
c
t
(5
0
0
,
0
0
0
)
$
SI
F
0
8
0
‐
G
a
l
l
a
t
i
n
C
o
u
n
t
y
S
I
D
37
8
,
6
8
8
$
36
9
,
9
0
1
$
36
1
,
0
4
9
$
SI
F
0
8
0
‐
F
l
a
n
d
e
r
s
P
a
y
b
a
c
k
22
1
,
8
9
1
$
2
2
1
,
8
9
1
$
22
1
,
8
9
1
$
SI
F
1
0
9
‐
G
a
l
l
a
t
i
n
C
o
u
n
t
y
P
a
y
b
a
c
k
/
S
I
D
(1
3
3
,
0
0
0
)
$
SI
F
1
1
3
‐
P
a
y
b
a
c
k
D
i
s
t
r
i
c
t
(6
6
6
,
6
6
7
)
$
SI
F
1
1
7
‐
P
a
y
b
a
c
k
D
i
s
t
r
i
c
t
(8
3
,
3
3
3
)
$
SI
F
1
1
8
‐
P
a
y
b
a
c
k
D
i
s
t
r
i
c
t
(750,000)$
SI
F
1
3
8
‐
P
a
y
b
a
c
k
D
i
s
t
r
i
c
t
(3
3
3
,
3
3
3
)
$
En
d
i
n
g
B
a
l
a
n
c
e
o
f
P
a
y
b
a
c
k
I
m
p
r
o
v
e
m
e
n
t
s
:
(2
,
3
2
2
,
7
7
5
)
$
(1
,
8
5
5
,
1
9
6
)
$
(1
,
2
6
3
,
4
0
5
)
$
(1
,
4
0
2
,
3
5
6
)
$
(1
,
4
0
2
,
3
5
6
)
$
(1
,
4
0
2
,
3
5
6
)
$
(1,806,356)$
A ss
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
A
s
s
e
s
s
m
e
n
t
R
e
v
e
n
u
e
s
*
1,
0
9
5
,
0
0
0
$
1,
1
0
6
,
5
1
3
$
1,
1
2
8
,
6
4
3
$
1,
1
5
1
,
2
1
6
$
1,2
0
8
,
7
7
7
$
1,2
6
9
,
2
1
6
$
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
6
5
.
0
%
2%
2%
5%
5%
6%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
1,
8
0
6
,
5
1
3
$
1,
1
2
8
,
6
4
3
$
1,
1
5
1
,
2
1
6
$
1,
2
0
8
,
7
7
7
$
1,2
6
9
,
2
1
6
$
1,3
4
5
,
3
6
9
$
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
1
0
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.0
%
0.
0
%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
8
0
6
,
5
1
3
$
1,
1
2
8
,
6
4
3
$
1,
1
5
1
,
2
1
6
$
1,
2
0
8
,
7
7
7
$
1,2
6
9
,
2
1
6
$
1,3
4
5
,
3
6
9
$
*
A
s
s
e
s
s
m
e
n
t
w
i
l
l
d
e
c
r
e
a
s
e
w
i
t
h
i
n
c
r
e
a
s
e
d
G
a
s
T
a
x
F
u
n
d
i
n
g
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
1
,
6
3
3
,
0
0
0
)
$
(
4
,
8
0
2
,
0
0
0
)
$
‐
$
(
5
,
2
5
0
,
0
0
0
)
$
(
7
,
4
5
4
,
0
0
0
)
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY
2
3
U
N
S
C
H
E
D
U
L
E
D
AR
T
E
R
I
A
L
&
C
O
L
L
E
C
T
O
R
P
R
O
J
E
C
T
S
11
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
St
r
e
e
t
s
SI
F
0
5
7
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
OA
K
(
F
L
A
N
D
E
R
S
M
I
L
L
T
O
R
Y
U
N
S
U
N
WA
Y
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$5
0
0
,
0
0
0
SI
F
0
5
8
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
OA
K
&
N
2
7
T
H
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
D
E
S
I
G
N
&
CO
N
S
T
R
U
C
T
I
O
N
$2
0
0
,
0
0
0
SI
F
0
6
2
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
DU
R
S
T
O
N
(
F
O
W
L
E
R
T
O
F
E
R
G
U
S
O
N
)
-
CO
N
S
T
R
U
C
T
I
O
N
$7
6
0
,
0
0
0
SI
F
0
6
3
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
FO
W
L
E
R
&
B
A
B
C
O
C
K
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$400,000
SI
F
0
7
3
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
FO
W
L
E
R
&
D
U
R
S
T
O
N
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
*
$404,000
SI
F
0
7
6
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
FO
W
L
E
R
C
O
N
N
E
C
T
I
O
N
(
H
U
F
F
I
N
E
T
O
OA
K
)
-
D
E
S
I
G
N
(
I
N
C
L
U
D
E
S
3
IN
T
E
R
S
E
C
T
I
O
N
S
)
*
$5
0
0
,
0
0
0
SI
F
0
8
5
Ar
t
e
r
i
a
l
&
C
o
l
l
e
c
BA
X
T
E
R
(
7
T
H
T
O
1
9
T
H
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$1
,
5
0
0
,
0
0
0
SI
F
0
8
6
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
BA
X
T
E
R
&
C
O
T
T
O
N
W
O
O
D
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$500,000
SI
F
1
0
6
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
TR
A
N
S
P
O
R
T
A
T
I
O
N
D
E
M
A
N
D
MA
N
A
G
E
M
E
N
T
C
O
N
T
R
A
C
T
$5
0
,
0
0
0
SI
F
1
0
8
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
S
3
R
D
A
N
D
G
R
A
F
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$3
0
0
,
0
0
0
SI
F
1
0
9
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
OA
K
(
R
O
U
S
E
T
H
R
O
U
G
H
C
A
N
N
E
R
Y
DI
S
T
R
I
C
T
)
-
C
O
N
S
T
R
U
C
T
I
O
N
*
$1
3
3
,
0
0
0
SI
F
1
1
0
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
MA
N
L
E
Y
&
G
R
I
F
F
I
N
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$4
0
0
,
0
0
0
SI
F
1
1
1
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
HI
G
H
L
A
N
D
(
M
A
I
N
T
O
K
A
G
Y
)
-
CO
N
S
T
R
U
C
T
I
O
N
&
D
E
S
I
G
N
$5,000,000
SI
F
1
1
3
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
GR
I
F
F
I
N
(
7
T
H
T
O
R
O
U
S
E
)
-
CO
N
S
T
R
U
C
T
I
O
N
*
$2
,
0
0
0
,
0
0
0
SI
F
1
1
4
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
FO
W
L
E
R
C
O
N
N
E
C
T
I
O
N
(
H
U
F
F
I
N
E
T
O
OA
K
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$3,750,000
SI
F
1
1
6
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
BR
I
D
G
E
R
D
R
&
S
T
O
R
Y
M
I
L
L
R
D
(I
N
T
E
R
S
E
C
T
I
O
N
I
M
P
R
O
V
E
M
E
N
T
S
)
-
CO
N
S
T
R
U
C
T
I
O
N
$3
0
0
,
0
0
0
12
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
SI
F
1
1
7
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
ST
O
R
Y
M
I
L
L
(
G
R
I
F
F
I
N
T
O
B
R
I
D
G
E
R
)
-
CO
N
S
T
R
U
C
T
I
O
N
*
$2
5
0
,
0
0
0
SI
F
1
1
8
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
BA
B
C
O
C
K
(
1
1
T
H
A
V
E
T
O
1
9
T
H
A
V
E
)
-
CO
N
S
T
R
U
C
T
I
O
N
*
$750,000
SI
F
1
2
1
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
BA
X
T
E
R
&
D
A
V
I
S
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
R
O
U
N
D
A
B
O
U
T
CO
N
S
T
R
U
C
T
I
O
N
$5
0
0
,
0
0
0
SI
F
1
3
4
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
OA
K
(
C
O
T
T
O
N
W
O
O
D
T
O
F
L
A
N
D
E
R
S
MI
L
L
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$4
3
3
,
0
0
0
SI
F
1
3
8
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
CO
T
T
O
N
W
O
O
D
R
O
A
D
,
O
A
K
T
O
B
A
X
T
E
R
-
CO
N
S
T
R
U
C
T
I
O
N
*
$1,000,000
SI
F
1
4
2
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
DU
R
S
T
O
N
R
O
A
D
&
N
.
2
7
T
H
(I
N
T
E
R
S
E
C
T
I
O
N
I
M
P
R
O
V
E
M
E
N
T
S
)
-
CO
N
S
T
R
U
C
T
I
O
N
$300,000 $5,250,000
$3
,
4
4
3
,
0
0
0
$1
,
3
3
3
,
0
0
0
$3
,
0
5
0
,
0
0
0
$6,854,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
St
r
e
e
t
s
A&
C
0
0
1
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
OA
K
M
E
D
I
A
N
C
O
N
S
T
R
U
C
T
I
O
N
(
7
T
H
T
O
19
T
H
)
$600,000
A&
C
0
0
2
Ar
t
e
r
i
a
l
&
C
o
l
l
e
c
MI
O
V
I
S
I
O
N
T
R
A
F
F
I
C
D
A
T
A
S
Y
S
T
E
M
$5
0
,
0
0
0
A&
C
0
0
3
Ar
t
e
r
i
a
l
&
C
o
l
l
e
c
TR
A
F
F
I
C
M
O
D
E
L
I
N
G
S
O
F
T
W
A
R
E
$1
5
,
0
0
0
A&
C
0
0
4
Ar
t
e
r
i
a
l
&
C
o
l
l
e
c
OA
K
&
7
T
H
R
E
S
T
R
I
P
I
N
G
$6
0
,
0
0
0
A&
C
0
0
5
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
CO
L
L
E
G
E
(
8
T
H
T
O
1
9
T
H
)
-
D
E
S
I
G
N
RE
C
O
N
S
T
R
U
C
T
I
O
N
$3
0
0
,
0
0
0
A&
C
0
0
6
Ar
t
e
r
i
a
l
&
Co
l
l
e
c
t
o
r
CO
L
L
E
G
E
(
8
T
H
T
O
1
9
T
H
)
-
RE
C
O
N
S
T
R
U
C
T
I
O
N
$1
,
7
5
2
,
0
0
0
$1
2
5
,
0
0
0
$3
0
0
,
0
0
0
$1
,
7
5
2
,
0
0
0
$600,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
A
r
t
e
r
i
a
l
&
C
o
l
l
e
c
t
o
r
S
t
r
e
e
t
s
(
2
8
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$5,250,000
$3
,
5
6
8
,
0
0
0
$1
,
6
3
3
,
0
0
0
$7,454,000FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$4
,
8
0
2
,
0
0
0
FY
2
1
13
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C001
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Oak Median Construction (7th to 19th)
FY19 FY20 Unscheduled
$600,000
DESCRIPTION OF PROJECT
Replace the two way left turn lane with a landscaped median on Oak St between 7th and 19th. This project will also add street
lights along the corridor.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
This project may be used to limit access for some of th eprivate driveways, but is primarily an aesthetic improvement.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
14
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C002
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Miovision Traffic data system
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Purchase of modern traffic counting devices to provide current data for the City's new Transportation Model
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Allows us to populate our new transportation model with best available data resulting in best possible information
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
na
FUNDING SOURCES
na
New
Replacement
Equipment
Project
FY21 FY22 FY23
15
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C003
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Traffic Modeling Software
FY19
$15,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Traffic modeling guides many important decisions resulting in improved performance of the transportation network. This
software purchase will leverage considerable investments already in place (e.g., WTI & MDT modeling efforts). The model will
run alongside existing water and wastewater modeling packages to provide advanced understanding of current conditions,
including the impacts of future development.
ALTERNATIVES CONSIDERED
Use professional contracted services for modeling analysis.
ADVANTAGES OF APPROVAL
This software leverages previous investments in transportation modeling efforts while bringing maintenance responsibilities in-house.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual software maintenance costs are estimated to be under $2,500.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
16
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C004
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Oak & 7th Restriping
FY19
$60,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Restripe the intersection of Oak and 7th.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
17
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C005
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
College (8th to 19th) - Design Reconstruction
FY19 FY20
$300,000
Unscheduled
DESCRIPTION OF PROJECT
RDesign College, from 19th to 8th, to an urban minor arterial standard. The street is already in a failing condition and continues
to function; however, eventually the street will become deteriorated to a point where it is unfeasible to maintain and keep open
to public use. This project will provide the design for a city standard street section, with ADA compliant pedestrian ramps,
pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will eliminate
potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion.
ALTERNATIVES CONSIDERED
Accept the current failing configuration
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Arterial & Collector 100%
New
Replacement
Equipment
Project
FY21 FY22 FY23
18
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C006
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
College (8th to 19th) - Reconstruction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Reconstruct College, from 19th to 8th, to an urban minor arterial standard. The street is already in a failing condition and
continues to function; however, eventually the street will become deteriorated to a point where it is unfeasible to maintain and
keep open to public use. This project will provide a city standard street section, with ADA compliant pedestrian ramps, pavement
markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will eliminate potholes
and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion.
ALTERNATIVES CONSIDERED
Accept the current failing configuration
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Arterial & Collector 100%
New
Replacement
Equipment
Project
FY21
$1,752,000
FY22 FY23
19
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF057
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak (Flanders Mill to Ryun Sun Way) - Construction
FY19 FY20
$500,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Flanders Mill to Ryun Sun Way, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to proceed until these
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. This project will complete an important east-west link between Ferguson and Cottonwood, and conformance with
the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak and Ferguson, Oak
Street - New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,300,000) the Arterial & Collector District ($500.000) and local participation. The Flander's Mill
development is expected to be a partner in the construction of the segments adjacent to their development.
New
Replacement
Equipment
Project
FY21 FY22 FY23
20
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF058
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak & N 27th (Intersection Improvements) - Design & Construction
FY19
$200,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Oak and N 27th. This intersection is currently 2-way stop controlled.
Replacing it with a signal will greatly increase its capacity. The level of service at this intersection has degraded to unacceptable
levels. Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. Other affected projects include Oak
Street corridor projects and North 27th Street improvements project.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Secure additional financing by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
21
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF062
DEPARTMENT
Arterial & Collector
PROJECT NAME
Durston (Fowler to Ferguson) - Construction
FY19
$760,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete Durston Rd, from Cottonwood to Fowler, to a three-lane urban minor arterial standard. This project directly increase
capacity by adding additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. Connectivity already exists at this location, it is capacity that is affected. With completion, conformance
with the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders.
Other affected projects include intersection improvements at Durston & Ferguson, Durston & Fowler, Durston & Flanders Mill.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($757,421) and the Arterial & Collector District ($757,421). A payback district may be created to
reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
22
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF063
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler & Babcock (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$400,000
DESCRIPTION OF PROJECT
Install a traffic signal, roundabout, or other adequate traffic control device at the intersection of Fowler and Babcock. This
intersection is currently 1-way stop controlled. Replacing it with a signal or roundabout will greatly increase its capacity. East-
west connectivity already exists at this location. North-south connectivity is still lacking. Peak hour level of service for
northbound traffic is degrading due to lack of north-south connectivity in the network. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. A Payback District or SID may be
created to leverage other stakeholders. Other affected projects include Fowler corridor improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,600,000) and the Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF073
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler & Durston (Intersection Improvements) - Construction*
FY19 FY20 Unscheduled
$404,000
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Fowler and Durston. This intersection is currently 1- way stop controlled.
Replacing it with a signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location.
North-south connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation
Master Plan will be attained at completion. Other affected projects include Fowler corridor street improvements.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Improves an imporant connecting element in the network.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,616,000) and the Arterial & Collector District ($404,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $404,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
24
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF076
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler Connection (Huffine to Oak) - Design (Includes 3 Intersections)*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Design Fowler from Huffine to Oak to an urban minor arterial standard, including three intersections. This project directly
increase capacity by adding additional travel lanes, dedicated bike lanes and sidewalks and making improvements to the
intersections. Future developments which impact this intersection area may not be allowed to proceed until improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. This project
completes an important north-south connection on the west side of town. With its completion, the Level of Service (LOS)
Standard (BMC) and conformance with the Transportation Master Plan will be attained. A Payback District or SID may be created
to leverage other stakeholders. Other affected projects include intersection improvements at Fowler and Durston and Fowler
and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will complete an important north-south connection, expand the capacity of our street network and improve safety for drivers and
pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($500,000) and the Arterial & Collector District ($500,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $500,000).
New
Replacement
Equipment
Project
FY21
$500,000
FY22 FY23
25
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF085
DEPARTMENT
Arterial & Collector
PROJECT NAME
Baxter (7th to 19th) - Construction
FY19
$1,500,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Street Reconstruction
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded 100% by Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
26
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF086
DEPARTMENT
Arterial & Collector
PROJECT NAME
Baxter & Cottonwood (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection at Baxter and Cottonwood. This intersection is currently 1-way stop controlled. Replacing it with a
signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location. North-south
connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at completion. Other affected projects include Cottonwood corridor improvements and Baxter corridor
improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
$500,000
27
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF106
DEPARTMENT
Arterial & Collector
PROJECT NAME
Transportation Demand Management Contract
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Explore the potential for reducing vehicle demand on the network at peak hours by flexible start times, work from home
incentives etc. This project is important because the funding available to increase capacity by building physical improvements to
the network is unlikely to ever be sufficient. This project supplements that effort by reducing overall demand on the network.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
May improve peak hour LOS in many locations by directly reducing demand
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Three-year commitment with Western Transportation Institute and MSU. FY17 was the first year of funding. FY18 & FY19 are the remaining
years. 33% Impact Fee, 33% Montana State University, 33% Western Transportation Institute
New
Replacement
Equipment
Project
FY21 FY22 FY23
28
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF108
DEPARTMENT
Arterial & Collector
PROJECT NAME
S 3rd and Graf (Intersection Improvements) - Construction
FY19
$300,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at S 3rd and Graf. This is currently a stop controlled intersection. Installation of a roundabout
will directly increase capacity. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) will be attained at completion.
ALTERNATIVES CONSIDERED
Accept the existing level of service, create an SID for financing.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
29
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF109
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak (Rouse through Cannery District) - Construction*
FY19
$133,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of improving Oak from Rouse through the Cannery District to include curb, gutter, sidewalks, and a turning
lane to provide a complete arterial street standard. The Cannery District will be responsible for the cost of curb, gutter, and
sidewalk along their property frontage as well as the turn lane to access two drive accesses that allow a left turn movement from
Oak Street into the Cannery District. Future developments in this area may not be allowed to proceed until these improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Left turn traffic safety will be improved upon installation of left turn lanes. Pedestrian safety will be improved. Conformance with
the Transportation Master Plan will be attained with its completion. A payback District or SID may be created to leverage other
stakeholders. Cash-in-lieu of infrastructure is anticipated to be contributed from the Cannery District developer to cover the
cost of the left turn lanes needed for their drive accesses as well as the cost of curb, gutter, and sidewalk adjacent to their
property. Other affected projects include Oak Street Corridor improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians. There will be substantial
pedestrian traffic between the Fairgrounds and the Cannery District. Additionally, the traffic impact study for the Cannery District indicated the
need for left turn lanes for their drive accesses. As the City's transportation master plan identifies the need to upgrade the Oak Street Corridor
to an arterial standard, this is an opportunity to partner with the Cannery District developer to complete a portion of the Oak Street
improvements.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($133,000), the Arterial & Collector District ($133,000), and Developer share ($133,000). A
development payback district or SID may be created to reimburse the Arterial & Collector District for the County’s (project related) costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
30
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF110
DEPARTMENT
Arterial & Collector
PROJECT NAME
Manley & Griffin (Intersection Improvements) - Construction
FY19 FY20
$400,000
Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Manley & Griffin. This intersection is currently 1-way stop controlled. Replacing it with a
signal will greatly increase its capacity. Future developments which impact this intersection area may not be allowed to proceed
until improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained at
completion. A Payback District or SID may be created to leverage other stakeholders. Other affected projects include Griffin
corridor improvements.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Street Impact Fees ($1,600,000) and Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
31
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF111
DEPARTMENT
Arterial & Collector
PROJECT NAME
Highland (Main to Kagy) - Construction & Design
FY19 FY20 Unscheduled
$5,000,000
DESCRIPTION OF PROJECT
Upgrade Highland, from Main to Kagy. Future developments in this area may not be allowed to proceed until these improvements
are in place. This project directly increase capacity by adding additional lanes, dedicated bike lanes and sidewalks. Connectivity
already exists at this location, it is capacity that is affected. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at the completion of
the project. A payback District or SID may be created to leverage other stakeholders. Other affected projects include
Intersection improvements at Highland and Kagy, Highland and Ellis and Highland and Main Street.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs
FUNDING SOURCES
This project is funded by Street Impact Fees ($5,000,000) and the Arterial & Collector District ($5,000,000). A payback district may be
created to reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
32
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF113
DEPARTMENT
Arterial & Collector
PROJECT NAME
Griffin (7th to Rouse) - Construction*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construct W Griffin corridor improvements from N. 7th to Rouse to an urban minor arterial standard. Designed improvements
will improve LOS at the key intersections and will increase capacity in the corridor as a whole. Connectivity already exists at this
location, it is capacity which is being expanded. Future developments which impact this intersection area may not be allowed to
proceed until improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at the completion of this project. A Payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Griffin and 7th and Griffin and Rouse.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,500,000) and the Arterial & Collector District ($2,000,000). A development payback district or
SID may be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $2,000,000).
New
Replacement
Equipment
Project
FY21
$2,000,000
FY22 FY23
33
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF114
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler Connection (Huffine to Oak) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete the section of Fowler from Huffine to Oak. This project allows for extension of Fowler Avenue, which will directly
increase capacity, and it extends an important north-south corridor on the west side of the city. Future developments which
impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at
large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Conformance with the Transportation Master
Plan will be attained at the completion of this project. Other affected projects include intersection improvements on Fowler at
Huffine, Babcock, Durston and Oak.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Completes an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,750,000) and the Arterial & Collector District ($3,750,000). A Payback District or SID may be
created to reimburse the Arterial & Collector District for any local improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$3,750,000
34
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF116
DEPARTMENT
Arterial & Collector
PROJECT NAME
Bridger Dr & Story Mill Rd (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Bridger and Story Mill. Adding additional phases and improving geometry will increase
capacity for deficient movements at this intersection. Future developments which impact this intersection area may not be
allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at completion. Other
affected projects include Story Mill, Griffin to Bridger Drive.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000). An SID or payback district may
be created to recover the local share.
New
Replacement
Equipment
Project
FY21
$300,000
FY22 FY23
35
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF117
DEPARTMENT
Arterial & Collector
PROJECT NAME
Story Mill (Griffin to Bridger) - Construction*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve Story Mill from Griffin to Bridger. This project directly increases capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback District or SID
may be created to leverage other stakeholders. Other affected projects include intersection improvements to Story Mill and
Bridger Drive.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Improves an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($250,000) and the Arterial & Collector District ($250,000). An SID or payback district may be
created to recover the local share.
New
Replacement
Equipment
Project
FY21
$250,000
FY22 FY23
36
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF118
DEPARTMENT
Arterial & Collector
PROJECT NAME
Babcock (11th Ave to 19th Ave) - Construction*
FY19 FY20 Unscheduled
$750,000
DESCRIPTION OF PROJECT
Construct the Babcock (11th to 19th) street upgrade. This project increases capacity directly by adding additional lanes, dedicated
bike lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback
District or SID may be created to leverage other stakeholders.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($750,000) and the Arterial & Collector District ($750,000). An SID or payback district may be
created to pay for some local share improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
37
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF121
DEPARTMENT
Arterial & Collector
PROJECT NAME
Baxter & Davis (Intersection Improvements) - Roundabout Construction
FY19
$500,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Install a roundabout at Baxter & Davis. This intersection is currently 4-way stop controlled. Replacing it with a roundabout will
greatly increase its capacity. Future developments in this area may not be allowed to proceed until these improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan and Level of Service Standard will be attained at completion. Other affected projects include
Baxter Lane Corridor Improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network, improve safety for drivers and pedestrians and increase capacity at this
intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
38
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF134
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak (Cottonwood to Flanders Mill) - Construction
FY19 FY20
$433,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Cottonwood to Flanders Mill, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks, and it completes an important east-west link between Ferguson and
Cottonwood. Future developments in this area may not be allowed to proceed until these improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan will be attained at completion. A payback District or SID may be created to leverage other
stakeholders. Other affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak
and Ferguson, Oak Street New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($434,000) and $430,000 for the local share adjacent to the City park, and an additional $430,000
from School District #7.
New
Replacement
Equipment
Project
FY21 FY22 FY23
39
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF138
DEPARTMENT
Arterial & Collector
PROJECT NAME
Cottonwood Road, Oak to Baxter - Construction*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construction of a 5 lane Principal Arterial Street
ALTERNATIVES CONSIDERED
SID, Payback District, TOPS, incremental construction by adjacent developers.
ADVANTAGES OF APPROVAL
The project will expand the capacity and improve the connectivity of the city street network. It will improve safety for drivers and pedestrians
and improve access to the Sports Park. It will facilitate development currently occurring in this part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
The total project cost is $2.5M. $750k will come from Impact Fees, the remainder is the local share which will come from either TOPS money,
BSD 7 an SID or Payback of some sort or some combination of these.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$1,000,000
40
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF142
DEPARTMENT
Arterial & Collector
PROJECT NAME
Durston Road & N. 27th (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$300,000
DESCRIPTION OF PROJECT
Installation of a roundabout or signal at the intersection of Durston Road and North 27th Avenue
ALTERNATIVES CONSIDERED
Accept the current level of service
ADVANTAGES OF APPROVAL
Increased capacity at this intersection
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Incremental increase in sweeping, plowing, painting and general maintenance
FUNDING SOURCES
Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
41
42
Bu
i
l
d
i
n
g
I
n
s
p
e
c
t
i
o
n
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
n
s
c
h
e
d
u
l
e
d
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1
9
2
,
1
0
0
$
2
2
4
,
6
0
0
$
1
9
,
0
6
5
$
3
0
,
7
6
8
$
4
3
,
0
5
6
$
5
5
,
9
5
8
$
P
l
u
s
:
B
u
i
l
d
i
n
g
I
n
s
p
e
c
t
i
o
n
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
32
,
5
0
0
$
11
,
1
4
6
$
11
,
7
0
3
$
12
,
2
8
8
$
12
,
9
0
2
$
13,548 $ ‐$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
‐
$
(2
1
6
,
6
8
1
)
$
‐
$
‐
$
‐
$
‐ $ (325,000)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
22
4
,
6
0
0
$
1
9
,
0
6
5
$
3
0
,
7
6
8
$
4
3
,
0
5
6
$
5
5
,
9
5
8
$
6
9
,
5
0
6
$
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
:
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
B
u
i
l
d
i
n
g
I
n
s
p
e
c
t
i
o
n
R
e
v
e
n
u
e
s
1,
7
6
9
,
1
5
0
$
1,
7
6
9
,
1
5
0
$
1,
8
5
7
,
6
0
8
$
1,
9
5
0
,
4
8
8
$
2,
0
4
8
,
0
1
2
$
2,150,413
$
E
s
t
i
m
a
t
e
d
G
r
o
w
t
h
i
n
R
e
v
e
n
u
e
s
0%
5%
5%
5%
5%
5%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
1,
7
6
9
,
1
5
0
$
1,
8
5
7
,
6
0
8
$
1
,
9
5
0
,
4
8
8
$
2
,
0
4
8
,
0
1
2
$
2
,
1
5
0
,
4
1
3
$
2
,
2
5
7
,
9
3
4
$
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
0.
6
%
0.
6
%
0.
6
%
0
.
6
%
0
.
6
%
0
.
6
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
s
%
0.
0
%
0.
0
%
0.
0
%
0
.
0
%
0
.
0
%
0
.
0
%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
0.
6
%
0.
6
%
0.
6
%
0
.
6
%
0
.
6
%
0
.
6
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
32
,
5
0
0
$
11
,
1
4
6
$
11
,
7
0
3
$
12
,
2
8
8
$
12
,
9
0
2
$
13,548
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
2
1
6
,
6
8
1
)
$
‐
$
‐
$
‐
$
‐
$
(
3
2
5
,
0
0
0
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
BU
I
L
D
I
N
G
I
N
S
P
E
C
T
I
O
N
P
R
O
J
E
C
T
S
&
EQ
U
I
P
M
E
N
T
B
i
l
d
i
I
t
i
R
43
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Bu
i
l
d
i
n
g
In
s
p
e
c
t
i
o
n
BI
0
1
BU
I
L
D
I
N
G
I
N
S
P
E
ST
A
F
F
V
E
H
I
C
L
E
-
R
E
P
L
A
C
E
M
E
N
T
S
$325,000
GF
1
9
9
BU
I
L
D
I
N
G
IN
S
P
E
C
T
I
O
N
PR
O
F
E
S
S
I
O
N
A
L
B
U
I
L
D
I
N
G
RE
C
O
N
F
I
G
U
R
A
T
I
O
N
-
P
H
A
S
E
2
$2
1
6
,
6
8
1
$2
1
6
,
6
8
1
$325,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
B
u
i
l
d
i
n
g
In
s
p
e
c
t
i
o
n
(
2
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$2
1
6
,
6
8
1
$325,000FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
FY
2
1
44
CIP Project Fund
Building Inspection
PROJECT NUMBER
BI01
DEPARTMENT
BUILDING INSPECTION
PROJECT NAME
STAFF VEHICLE - REPLACEMENTS
FY19 FY20 Unscheduled
$325,000
DESCRIPTION OF PROJECT
This item is for the scheduled replacement of Building Inspection vehicles based on age and use of the vehicle. Vehicles will be
replaced according to the City's Vehicle Replacement policy; generally, 150,000 miles/20 years before replacement of non-
emergency vehicles. This program will address the long term vehicle needs of the Building Division by allowing careful
replacement of vehicles as vehicle conditions and department needs warrant. Right now, all vehicles are in use by Department
staff, averaging approximately 5,000 miles per year. Vehicle Mileage updated October 2015. There are no maintenance issues or
significant problems to report. We do regular maintenance and service all of our vehicles and always fix small stuff before it
becomes a big problem.
ALTERNATIVES CONSIDERED
Utilize vehicles beyond the recommendations of the vehicle use policy; consider replacements of different model of vehicle.
ADVANTAGES OF APPROVAL
Based on the age and use of the vehicle a new vehicle will be purchased as replacement. In the past, vehicles were replaced after 5 years. We are
stretching the useful life within the division to match the newly-revised vehicle purchase/replacement policy.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Generally, annual operating and maintenance costs are expected to decrease when older vehicles are replaced with newer ones. More fuel
efficiency and lower repair costs are financial benefits.
FUNDING SOURCES
100% Building Inspection Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
45
CIP Project Fund
Building Inspection
PROJECT NUMBER
GF199
DEPARTMENT
BUILDING INSPECTION
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$216,681
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this grow, we need to remodel the Stiff Building. In FY16 the City Commission
approved a Phase 1 of the remodel that will provide a better use of existing space by relocating certain functions to the basement
and reclaiming unused square footage. Approval of Phase II would allow the consolidation of Community Development (Planning
and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater) together
on another floor. This will allow better coordination of staff and better service to our public. Phase 1 is anticipated to be
completed late spring of 2016.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking.
New
Replacement
Equipment
Project
FY21 FY22 FY23
46
Building Inspection Vehicles - Details
Project Number Asset #Make Model Yr Current Mileage FY19 FY20 Unscheduled NotesFY21FY22FY23
BI01 3144 Jeep Liberty 2003 70,487 $32,500 Beyond FY20
3218 Grand Cherokee 2004 55,257 $32,500 Beyond FY20
3353 Jeep Liberty 2006 49,287 $32,500 Beyond FY20
3328 Dodge Durango 2006 72,608 $32,500 Beyond FY20
3354 Jeep Liberty 2006 62,990 $32,500 Beyond FY20
3404 Dodge Durango 2008 44,945 $32,500 Beyond FY20
3329 Dodge Durango 2008 67,382 $32,500 Beyond FY20
3723 Jeep Patriot 2014 11,321 $32,500 New in 2013
3674 Jeep Patriot 2014 14,405 $32,500 New in 2013
3968 Prius 2017 385 $32,500 New in 2017
3967 Prius 2017 3,961 $32,500 New in 2017
$357,500Total By Year for Vehicle Replacements
47
48
Co
m
m
u
n
i
t
y
D
e
v
e
l
o
p
m
e
n
t
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
n
s
c
h
e
d
u
l
e
d
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1
4
1
,
8
8
4
$
3
8
2
,
7
0
5
$
1
7
2
,
6
3
6
$
2
6
5
,
6
0
9
$
3
4
9
,
6
4
0
$
4
4
6
,
3
6
9
$
P
l
u
s
:
L
o
n
g
R
a
n
g
e
P
l
a
n
n
i
n
g
R
e
s
t
r
i
c
t
e
d
C
a
s
h
90
,
0
7
8
$
P
l
u
s
:
C
o
n
s
e
r
v
a
t
i
o
n
O
v
e
r
l
a
y
R
e
s
t
r
i
c
t
e
d
C
a
s
h
82
,
7
6
8
$
P
l
u
s
:
E
n
t
r
y
w
a
y
C
o
r
r
i
d
o
r
R
e
s
t
r
i
c
t
e
d
C
a
s
h
26
,
6
9
1
$
P
l
u
s
:
T
e
c
h
n
o
l
o
g
y
R
e
s
t
r
i
c
t
e
d
C
a
s
h
3
1
,
2
8
4
$
P
l
u
s
:
P
l
a
n
n
i
n
g
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
11
0
,
0
0
0
$
9
1
,
1
4
9
$
9
2
,
9
7
2
$
9
4
,
8
3
2
$
9
6
,
7
2
8
$
9
8
,
6
6
3
$
P
l
u
s
:
G
e
n
e
r
a
l
F
u
n
d
/
O
t
h
e
r
C
o
n
t
r
i
b
u
t
i
o
n
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(
1
0
0
,
0
0
0
)
$
(
3
0
1
,
2
1
8
)
$
‐
$
(
1
0
,
8
0
0
)
$
‐
$
‐
$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
38
2
,
7
0
5
$
17
2
,
6
3
6
$
26
5
,
6
0
9
$
34
9
,
6
4
0
$
44
6
,
3
6
9
$
54
5
,
0
3
2
$
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
:
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
C
o
m
m
u
n
i
t
y
D
e
v
e
l
o
p
m
e
n
t
R
e
v
e
n
u
e
s
1,
2
2
4
,
1
3
9
$
1,
2
2
4
,
1
3
9
$
1,
2
4
8
,
6
2
2
$
1,
2
7
3
,
5
9
4
$
1,
2
9
9
,
0
6
6
$
1,
3
2
5
,
0
4
7
$
(
E
x
c
l
u
d
e
s
i
n
t
e
r
f
u
n
d
t
r
a
n
s
f
e
r
s
)
E
s
t
i
m
a
t
e
d
G
r
o
w
t
h
i
n
R
e
v
e
n
u
e
s
‐
2%
2%
2%
2%
2%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
1,
2
2
4
,
1
3
9
$
1,
2
4
8
,
6
2
2
$
1,
2
7
3
,
5
9
4
$
1,
2
9
9
,
0
6
6
$
1,
3
2
5
,
0
4
7
$
1,
3
5
1
,
5
4
8
$
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
7.
3
%
7.
3
%
7
.
3
%
7
.
3
%
7
.
3
%
7
.
3
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
s
%
0.
0
%
0.
0
%
0
.
0
%
0
.
0
%
0
.
0
%
0
.
0
%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
7.
3
%
7.
3
%
7
.
3
%
7
.
3
%
7
.
3
%
7
.
3
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
11
0
,
0
0
0
$
91
,
1
4
9
$
92
,
9
7
2
$
94
,
8
3
2
$
96
,
7
2
8
$
98
,
6
6
3
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
3
0
1
,
2
1
8
)
$
‐
$
(
1
0
,
8
0
0
)
$
‐
$
‐
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
CO
M
M
U
N
I
T
Y
D
E
V
E
L
O
P
M
E
N
T
PR
O
J
E
C
T
S
&
E
Q
U
I
P
M
E
N
T
49
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Co
m
m
u
n
i
t
y
De
v
e
l
o
p
m
e
n
t
CD
0
3
CO
M
M
U
N
I
T
Y
D
CO
M
P
U
T
E
R
H
A
R
D
W
A
R
E
$1
0
,
8
0
0
CD
0
5
CO
M
M
U
N
I
T
Y
D
CO
P
I
E
R
R
E
P
L
A
C
E
M
E
N
T
$3
5
,
0
0
0
GF
1
9
9
CO
M
M
U
N
I
T
Y
DE
V
E
L
O
P
M
E
N
T
PR
O
F
E
S
S
I
O
N
A
L
B
U
I
L
D
I
N
G
RE
C
O
N
F
I
G
U
R
A
T
I
O
N
-
P
H
A
S
E
2
$2
6
6
,
2
1
8
$3
0
1
,
2
1
8
$1
0
,
8
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
C
o
m
m
u
n
i
t
y
D
e
v
e
l
o
p
m
e
n
t
(
3
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$3
0
1
,
2
1
8
FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$1
0
,
8
0
0
FY
2
1
50
CIP Project Fund
Community Development
PROJECT NUMBER
CD03
DEPARTMENT
COMMUNITY DEVELOPMENT
PROJECT NAME
COMPUTER HARDWARE
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace computer hardware; replacements planned for years FY18 and FY20 did not meet the CIP capital threshold and will be
included in budget requests for those years.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Keeping computer hardware current diminishes the need for service calls and also facilitates the production of planning review by ensuring
computers are able to run effective updated software.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
IT support, software updates
FUNDING SOURCES
Community Development Fund
New
Replacement
Equipment
Project
FY21
$10,800
FY22 FY23
51
CIP Project Fund
Community Development
PROJECT NUMBER
CD05
DEPARTMENT
COMMUNITY DEVELOPMENT
PROJECT NAME
Copier Replacement
FY19
$35,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace combination copier/scanner. This is an essential primary work tool for Community Development for production of staff
reports, intake of applications, and many other daily duties. The coper is shared with Public Works. The anticipated service life
for this type of equipment under the use conditions and loads is five years of less. Mechanical failure are becoming more common
with the existing machine.
ALTERNATIVES CONSIDERED
A lease may be an alternative. Experience with leasing has not been particularly positive. Efforts to continue with increasing maintenance may
extend service life some but there are associated costs financially and with lost productivity during breakdowns. Given the level of time sensitive
deadlines for the department substantial and frequent down times are not acceptable.
ADVANTAGES OF APPROVAL
Enable departments to continue to produce and process applications and materials.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional expenses are anticipated. Standard operating expenses are included in the annual budgets and are not anticipated to change
substantially.
FUNDING SOURCES
General fund, planning fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
52
CIP Project Fund
Community Development
PROJECT NUMBER
GF199
DEPARTMENT
COMMUNITY DEVELOPMENT
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$266,218
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this grow, we need to remodel the Stiff Building. In FY16 the City Commission
approved a Phase 1 of the remodel that will provide a better use of existing space by relocating certain functions to the basement
and reclaiming unused square footage. Approval of Phase II would allow the consolidation of Community Development (Planning
and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater) together
on another floor. This will allow better coordination of staff and better service to our public. Phase 1 is anticipated to be
completed late spring of 2016.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking.
New
Replacement
Equipment
Project
FY21 FY22 FY23
53
54
Fi
r
e
E
q
u
i
p
m
e
n
t
&
C
a
p
i
t
a
l
R
e
p
l
a
c
e
m
e
n
t
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
FY
2
2
FY23 Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
67
5
,
7
0
0
$
54
9
,
9
8
0
$
36
0
,
9
0
3
$
36
7
,
3
3
5
$
77
0
,
1
4
9
$
1,055,232 $
P
l
u
s
:
D
e
d
i
c
a
t
e
d
T
a
x
R
e
v
e
n
u
e
s
4
M
i
l
l
s
40
4
,
7
8
0
$
41
6
,
9
2
3
$
42
9
,
4
3
1
$
44
2
,
3
1
4
$
45
5
,
5
8
3
$
469,251 $ ‐$
P
l
u
s
:
A
n
t
i
c
i
p
a
t
e
d
G
r
a
n
t
R
e
v
e
n
u
e
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(
5
3
0
,
5
0
0
)
$
(
6
0
6
,
0
0
0
)
$
(
4
2
3
,
0
0
0
)
$
(
3
9
,
5
0
0
)
$
(
1
7
0
,
5
0
0
)
$
(
1
7
6
,
7
5
0
)
$ ‐$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
54
9
,
9
8
0
$
36
0
,
9
0
3
$
36
7
,
3
3
5
$
77
0
,
1
4
9
$
1,
0
5
5
,
2
3
2
$
1,347,733 $
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
:
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
T
a
x
R
e
v
e
n
u
e
s
40
4
,
7
8
0
$
4
0
4
,
7
8
0
$
41
6
,
9
2
3
$
42
9
,
4
3
1
$
44
2
,
3
1
4
$
455,583 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
0%
3%
3%
3%
3%
3%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
40
4
,
7
8
0
$
4
1
6
,
9
2
3
$
42
9
,
4
3
1
$
44
2
,
3
1
4
$
45
5
,
5
8
3
$
469,251 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
10
0
.
0
%
100.0%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
10
0
.
0
%
100.0%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
40
4
,
7
8
0
$
4
1
6
,
9
2
3
$
42
9
,
4
3
1
$
44
2
,
3
1
4
$
45
5
,
5
8
3
$
469,251 $
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
$
(
6
0
6
,
0
0
0
)
$
(
4
2
3
,
0
0
0
)
$
(
3
9
,
5
0
0
)
$
(
1
7
0
,
5
0
0
)
$
(
1
7
6
,
7
5
0
)
$
‐
FY
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
FI
R
E
E
Q
U
I
P
M
E
N
T
&
C
A
P
I
T
A
L
RE
P
L
A
C
E
M
E
N
T
S
55
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Fi
r
e
E
q
u
i
p
&
Ca
p
i
t
a
l
Re
p
l
a
c
e
m
e
n
t
FE
0
6
FI
R
E
RA
D
I
O
R
E
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
$2
5
0
,
0
0
0
$2
5
0
,
0
0
0
FE
1
2
FI
R
E
PE
R
S
O
N
A
L
P
R
O
T
E
C
T
I
V
E
E
Q
U
I
P
M
E
N
T
$41,750
$3
6
,
0
0
0
$3
8
,
0
0
0
$3
9
,
5
0
0
$4
0
,
5
0
0
FE
1
3
FI
R
E
ST
A
T
I
O
N
A
L
E
R
T
I
N
G
S
Y
S
T
E
M
$2
5
0
,
0
0
0
FE
1
4
FI
R
E
ST
R
U
C
T
U
R
A
L
C
O
L
L
A
P
S
E
E
Q
U
I
P
M
E
N
T
$7
0
,
0
0
0
FE
1
5
FI
R
E
CA
R
D
I
A
C
M
O
N
I
T
O
R
R
E
P
L
A
C
E
M
E
N
T
$1
3
5
,
0
0
0
FE
1
6
FI
R
E
EX
T
R
I
C
A
T
I
O
N
T
O
O
L
S
$1
3
0
,
0
0
0
FE
1
7
FI
R
E
WI
L
D
L
A
N
D
A
P
P
A
R
A
T
U
S
$135,000 $176,750
$6
0
6
,
0
0
0
$4
2
3
,
0
0
0
$3
9
,
5
0
0
$1
7
0
,
5
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
F
i
r
e
E
q
u
i
p
&
C
a
p
i
t
a
l
R
e
p
l
a
c
e
m
e
n
t
(
7
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$176,750
$6
0
6
,
0
0
0
$4
2
3
,
0
0
0
FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$1
7
0
,
5
0
0
$3
9
,
5
0
0
FY
2
1
56
CIP Project Fund
Fire Equip & Capital Replacement
PROJECT NUMBER
FE06
DEPARTMENT
FIRE
PROJECT NAME
Radio Replacement Program
FY19
$250,000
FY20
$250,000
Unscheduled
DESCRIPTION OF PROJECT
This plan allows for aging fire portable radios to be replaced, including all of the software, programming and peripheral accessories.
This is a planned replacement of radios at the end of their predicted usable life, estimated between eight and ten years. This will
provide for seamless communication and response capabilities as the radios become less reliable and repair is no longer a
financially prudent option. Radios are an essential item in the operation of the Bozeman Fire Department. Fire radios must be
available for fire use 24 hours a day, 365 days a year. These radios are assigned to the three stations, all apparatus, and
management staff and are used daily. The decision was made during FY-17 CIP discussions to postpone scheduled replacements
of Fire Department radios due to uncertain plans of the Gallatin County 911 Center. Since this decision one year ago, a test was
conducted with Bozeman Fire and Bozeman Police Department. The test utilized an 800 MHz radio system to evaluate its use as a
potential upgrade from the current radio system. The results of the test were extremely positive, with noted improvements
related to in-building coverage and city wide coverage. Since the test, the 911 advisory board has voted to move forward with a 4
phase plan to upgrade the radio system in Gallatin County. Phase 1 would call for the City of Bozeman to move to an 800 MHz
digital trunked radio system.
ALTERNATIVES CONSIDERED
We still have the option of backing out of the 800 MHz system, however in doing so we would need to re-visit with 911 and the 911 Advisory
Board about other potential solutions for Bozeman Fire. If Bozeman Fire were to back out and Bozeman Police still move forward, we would
lose the ability to communicate effectively with each other, something that creates a major safety concern for both parties. In order to maintain
consistency in public safety operations, both departments should remain on the same radio system.
ADVANTAGES OF APPROVAL
Clear and dependable communication allows for quick and efficient emergency deployment and the required level of firefighter safety. The
portable radio project addresses a planned replacement program that existed in the CIP prior to the decision to move to 800 MHz radios. The
purchase improves our ability to communicate within the city, particularly inside of larger buildings such as the high school, hospital, and big box
retailers. We potentially may see some trade in value or resale value for some of the replaced units depending on their condition.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
As these are replacement radios we anticipate very little increases operating costs.
FUNDING SOURCES
100% Fire Equipment & Capital Replacement Fund - with possible reimbursement by Gallatin County 911 System.
New
Replacement
Equipment
Project
FY21 FY22 FY23
57
CIP Project Fund
Fire Equip & Capital Replacement
PROJECT NUMBER
FE12
DEPARTMENT
Fire
PROJECT NAME
Personal Protective Equipment
FY19
$36,000
FY20
$38,000
Unscheduled
DESCRIPTION OF PROJECT
Today each member of the Bozeman Fire Department is issued two sets of personal protective equipment (PPE), a primary and a
backup set. By having two sets available members are ensured that if their primary set becomes contaminated or damaged on a
call that they have a backup set of gear to move over into to complete their shift while their primary set is cleaned or repaired.
The NFPA and manufacturer guidelines recommend that PPE used by firefighters, often referred to as turnout gear, be replaced
every 10 years due to the breakdown of the protective fibers that are used to make the gear. Presently the fire department
purchases gear on a rotating cycle so that a firefighter’s primary gear is 0-5 years old and their back-up gear is 6-10 years old. This
rotation is consistent with national best practice and is something the fire department plans to continue. To this point these
purchases have been made annually out of the general fund even though its meets the criteria for the Capital Equipment and
Replacement Fund. Starting in FY-19 the fire department will move this purchase form the general fund to the capital fund. This
will become an annual expense in the capital plan.
ALTERNATIVES CONSIDERED
Continue to purchase out of the general fund budget
ADVANTAGES OF APPROVAL
Moves purchase from general fund budget to capital budget
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Will be replaced in 10 years
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$39,500
FY22
$40,500
FY23
$41,750
58
CIP Project Fund
Fire Equip & Capital Replacement
PROJECT NUMBER
FE13
DEPARTMENT
Fire
PROJECT NAME
Station Alerting System
FY19
$250,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Presently the fire department receives primary notification of emergency calls via an alpha numeric pager. The use of alpha
numeric paging is an outdated method of notifying emergency responders of response request and is difficult to find technological
support for. The new 800 MHz radio system coupled with the installation of a new Computer Aided Dispatch (CAD) system
now gives the Fire Department the ability to utilize a station alerting system. The implementation of a station alerting system
allows for faster notification of responders as it eliminates the need for alpha numeric pagers which are slower, as they require
the use of multiple interfaces. Station alerting allows for both audible and visual notification of responders while not increasing the
workload on dispatchers. The moment that dispatchers have the basic information of an emergency call, a station alerting system
automatically notifies the appropriate response unit while the dispatcher continues to gather information. This improves the first
phase of a response which is commonly referred to as the call processing time, which by national standard is to be completed
within 60 – 80 seconds. Today the average call processing time is approximately 90 seconds. By improving call processing times
the overall response time to an emergency response is also reduced. This project also has a direct effect on the second phase of a
response which is referred to as turnout time. Turnout time is the time from when responders are notified until they begin their
actual driving response. Today with the alpha paging system the fire department routinely sees a 30-40 second delay in pager
activation which causes extended turnout times. The national standard for turnout times is 60-80 seconds depending on the type
of call, however today BFD times are closer to 90-105 seconds, primarily related to the alpha pager delay. Station alerting has the
potential to reduce overall response times by nearly a minute and solves the problem of using alpha numeric paging. This project
would require the installation of specific equipment in all of the fire stations, thus if a plan is implemented to address the current
station 1 and station 2 as suggested in the Fire Master Plan, this project may need to be postponed until that occurs.
ALTERNATIVES CONSIDERED
Continue to use existing alpha pagers / delay this project until decisions on existing fire stations are made.
ADVANTAGES OF APPROVAL
Improved response times / answers question about long term solution to emergency responder notification
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
59
CIP Project Fund
Fire Equip & Capital Replacement
PROJECT NUMBER
FE14
DEPARTMENT
Fire
PROJECT NAME
Structural Collapse Equipment
FY19
$70,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
A structural collapse can be defined as a car driving into a building causing part of the building to fall, up to a total building
collapsing due to a seismic event that occurs. Today the Fire Department has no structural collapse equipment in its cadre of
tools. In the event of structural collapse, the nearest capable response team would be dispatched from Idaho Falls, ID. The
department has spent the past two budget years improving our confined space and trench rescue response capabilities and is now
prepared to add structural collapse to our capabilities. The requested equipment includes tools that are capable of accessing
patients through concrete and steel, some of the more common obstacles encountered in a structural collapse. Also included in
the requested is a search camera which allows rescuers to evaluate areas of collapse both visually and audibly for potential victims
without having to access the area thus speeding up the search for potential victims.
ALTERNATIVES CONSIDERED
Do not purchase equipment / accept current level of risk / rely on out of state support for response if needed
ADVANTAGES OF APPROVAL
Provides city with equipment necessary to handle a structural collapse, most likely to occur with a seismic event. Minimizes need for out of
state response.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
60
CIP Project Fund
Fire Equip & Capital Replacement
PROJECT NUMBER
FE15
DEPARTMENT
Fire
PROJECT NAME
Cardiac Monitor Replacement
FY19 FY20
$135,000
Unscheduled
DESCRIPTION OF PROJECT
The Fire Department maintains 4 cardiac monitors that are on in-service apparatus. It is best practice to keep all of our cardiac
monitors the same across the board so that staff do not have to attempt to remain familiar with multiple models of monitors.
The next scheduled update to the cardiac monitoring is set for 2020. The department has the ability to receive trade in credit on
its existing monitors during this transition as well. By staying with the most current version of cardiac monitors the department
maintains interoperability with both AMR and Bozeman Health. These units would be expected to last until 2030 which is the
next scheduled update. The department also maintains an annual service contract on the monitors during their life span.
ALTERNATIVES CONSIDERED
Continue to use current model cardiac monitors and make replacements out of general fund as needed
ADVANTAGES OF APPROVAL
Helps maintain interoperability with Bozeman Health and AMR. Keeps monitors consistent across the board for all BFD paramedics
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Will be replaced in 10 years
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
61
CIP Project Fund
Fire Equip & Capital Replacement
PROJECT NUMBER
FE16
DEPARTMENT
Fire
PROJECT NAME
Extrication Tools
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
These are the tools that are used to access and remove patients from automobile accidents when they have become pinned or
trapped in a vehicle. Having up to date extrication equipment is important as auto manufacturers continue to come out with new
metals and materials that older equipment cannot cut. By replacing all three of the units at the same time we standardized our
fleet of tools, making use, training, and maintenance consistent across the board. The anticipated life span of this equipment is 10
years.
ALTERNATIVES CONSIDERED
Continue to use existing equipment and plan replacement out of general fund budget
ADVANTAGES OF APPROVAL
Moves purchase from general fund to capital fund. Ensures that extrication equipment is consistent across the department and up to current
standards related to automobile construction.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22
$130,000
FY23
62
CIP Project Fund
Fire Equip & Capital Replacement
PROJECT NUMBER
FE17
DEPARTMENT
Fire
PROJECT NAME
Wildland Apparatus
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The City of Bozeman continues to have several areas of undeveloped land within its corporate boundaries. Areas such as Story
Mill, the Gallatin Regional Park, MSU agricultural fields, Pete’s Hill, and others still pose a risk of wildland fire problems. Having a
wildland apparatus allows for the BFD to respond to these types of events in a vehicle that is equipped and designed for these
types of responses, which often require that we travel off road to address the fire problem. The City’s current wildland apparatus
will be approaching 30 years old during this fiscal year. While the vehicle may not have significant mileage other assessments such
as structural integrity of the vehicle will need to be done based on the use of the vehicle as well as an assessment of the fire pump
on the unit.
ALTERNATIVES CONSIDERED
Continue to use existing apparatus
ADVANTAGES OF APPROVAL
Provides department with reliable, up to date, wildland apparatus to address identified risk in the community.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
$135,000
63
Fire Department Light Vehicle Replacements
Asset #Current
Make/Features
Model
Yr
Current
Mileage
Replacement FY18 FY19 FY20 FY21 UnscheduledFY22Currently Assigned
to
Unit
#
3076 Chevy Surburban2002 149,347 Approved for replacement in FY-18
with Ford Interceptor SUV
$40,000Deputy Chief Fire
Marshall
F3
3247 Chevy Tahoe2004 147,932 Ford Interceptor SUV – in FY-25Emergency
Management Staff
Captain
F4
2764 Chevy Tahoe2000 134,519 Approved for replacement in FY-18
with Ford Interceptor SUV
$40,000Operations ChiefF2
3153 Chey Suburban2003 118,195 Approved for replacement in FY-18
with ½ ton 4x4 pickup
$50,000Batallion ChiefBC1
3332 Chevy Tahoe2007 77,365 Ford Interceptor SUVFire InspectorF6
3363 Dodge Durango2007 48,055 Ford Interceptor SUVFire InspectorF7
3275 Ford F1502005 46,159Plowing/Fire
Investigations/Preve
ntion Truck
U4
3158 Chevy Silverado -
Crew Cab
2003 35,760 3/4 or 1 ton pickup capable of
pulling fire department trailers
Training OfficerF5
1535 Ford Truck1993 18,197WildlandB1
3816 Ford Interceptor
SUV
2016 5,700Fire ChiefF1
3260 Trailer2004 HazmatHM T
$130,000Totals
64
Fi
r
e
I
m
p
a
c
t
F
e
e
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
5
4
6
,
5
0
1
$
1,
8
5
8
,
7
5
1
$
2,
2
3
9
,
1
1
4
$
2,
6
3
8
,
4
9
4
$
3,
0
5
7
,
8
4
4
$
3,498,161 $ ‐ $
P
l
u
s
:
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
36
2
,
2
5
0
$
38
0
,
3
6
3
$
39
9
,
3
8
1
$
41
9
,
3
5
0
$
440,317
$
462,333 $ ‐ $
P
l
u
s
:
F
I
F
0
7
E
n
g
i
n
e
#
4
‐
V
o
t
e
r
A
p
p
r
o
v
e
d
B
o
n
d
P
l
u
s
:
F
I
F
0
6
S
t
a
t
i
o
n
#
4
‐
V
o
t
e
r
A
p
p
r
o
v
e
d
B
o
n
d
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(
5
0
,
0
0
0
)
$
(4,600,000)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
8
5
8
,
7
5
1
$
2,
2
3
9
,
1
1
4
$
2,
6
3
8
,
4
9
4
$
3,
0
5
7
,
8
4
4
$
3,
4
9
8
,
1
6
1
$
3,960,494 $
A ss
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
:
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
F
Y
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
F
i
r
e
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
36
2
,
2
5
0
$
3
6
2
,
2
5
0
$
3
8
0
,
3
6
3
$
3
9
9
,
3
8
1
$
4
1
9
,
3
5
0
$
4
4
0
,
3
1
7
$
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
0.
0
%
5%
5%
5%
5%5%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
36
2
,
2
5
0
$
3
8
0
,
3
6
3
$
3
9
9
,
3
8
1
$
4
1
9
,
3
5
0
$
4
4
0
,
3
1
7
$
4
6
2
,
3
3
3
$
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
F
i
r
e
C
a
p
a
c
i
t
y
E
x
p
a
n
s
i
o
n
C
I
P
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0
.
0
%
0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
36
2
,
2
5
0
$
3
8
0
,
3
6
3
$
3
9
9
,
3
8
1
$
4
1
9
,
3
5
0
$
4
4
0
,
3
1
7
$
4
6
2
,
3
3
3
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
$
(
5
0
,
0
0
0
)
$
(
4
,
6
0
0
,
0
0
0
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
FI
R
E
I
M
P
A
C
T
F
E
E
P
R
O
J
E
C
T
S
65
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Im
p
a
c
t
F
e
e
s
F
i
r
e
FI
F
0
6
FI
R
E
I
F
FI
R
E
S
T
A
T
I
O
N
C
O
N
S
T
R
U
C
T
I
O
N
/
EX
P
A
N
S
I
O
N
/
R
E
L
O
C
A
T
I
O
N
$3,900,000
FI
F
0
7
FI
R
E
I
F
FI
R
E
D
E
P
A
R
T
M
E
N
T
R
E
S
P
O
N
S
E
A
P
P
A
R
A
T
U
S
$700,000 $4,600,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
I
m
p
a
c
t
F
e
e
s
F
i
r
e
(
2
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$4,600,000FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
FY
2
1
66
CIP Project Fund
Impact Fees Fire
PROJECT NUMBER
FIF06
DEPARTMENT
FIRE IF
PROJECT NAME
Fire Station Construction / Expansion / Relocation
FY19 FY20 Unscheduled
$3,900,000
DESCRIPTION OF PROJECT
The Fire Master Plan is completed and schedule for final adoption on November 6, 2017. The new Master Plan includes a
comprehensive review of current station locations and the capacity to meet the current needs of the city along with
recommendations for new fire stations. City staff will be evaluating the Master Plan recommendations during the next 12 months
and formulating a plan to rehab / relocate / construction new fire stations to address the growth in the City.
ALTERNATIVES CONSIDERED
As provided by Commission
ADVANTAGES OF APPROVAL
The completion of this project would enhance our ability to respond to growing parts of the community within a time frame that has been
historically acceptable to the citizens of Bozeman. The additional station /expansion / relocationalso has the potential to have a positive impact
on our ISO rating and encourage additional growth in areas of the city.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on operations and maintenance costs. The City’s General Fund will bear
the annual operating and maintenance expenses associated with this facility and staffing.
FUNDING SOURCES
Fire Impact Fees and possible voter approved bond
New
Replacement
Equipment
Project
FY21 FY22 FY23
67
CIP Project Fund
Impact Fees Fire
PROJECT NUMBER
FIF07
DEPARTMENT
FIRE IF
PROJECT NAME
Fire Department Response Apparatus
FY19 FY20 Unscheduled
$700,000
DESCRIPTION OF PROJECT
The Fire Master Plan is complete and scheduled for final adoption on November 6, 2017. The new Master Plan includes a review
of resource deployment, unit responses, and unit availability. The Fire Department will be evaluating these results to determine
future needs of the department from a response and deployment model. This could include potential outcomes of purchasing
additional apparatus, ranging from SUVs to Fire Engines to Ladder Trucks to handle the city’s emergency response load.
ALTERNATIVES CONSIDERED
As provided by the Commission
ADVANTAGES OF APPROVAL
Helps us maintain current response time standards.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be used for annual operating and maintenance costs. The City’s General Fund will
pay for the increased fuel, maintenance and insurance costs associated with this engine. In addition, this would add a possible FTE.
FUNDING SOURCES
Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
68
Tr
e
e
M
a
i
n
t
e
n
a
n
c
e
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
UNSCHEDULED
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
14
0
,
0
2
6
$
11
8
,
9
3
2
$
20
,
8
7
2
$
(4
4
,
1
8
0
)
$
19,994
$
(49,387)$ ‐ $
P
l
u
s
:
T
r
e
e
M
t
c
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
35
,
9
0
6
$
41
,
9
4
0
$
52
,
9
4
9
$
64
,
1
7
4
$
75,618
$
87,285 $ ‐ $
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(
5
7
,
0
0
0
)
$
(
1
4
0
,
0
0
0
)
$
(
1
1
8
,
0
0
0
)
$
‐
$
(
1
4
5
,
0
0
0
)
$
‐
$
(65,000)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
11
8
,
9
3
2
$
20
,
8
7
2
$
(4
4
,
1
8
0
)
$
19
,
9
9
4
$
(49,387)
$
37,898 $
A ss
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
T
r
e
e
M
t
c
R
e
v
e
n
u
e
s
69
2
,
0
7
3
$
6
9
2
,
0
7
3
$
6
9
8
,
9
9
4
$
7
0
5
,
9
8
4
$
7
1
3
,
0
4
4
$
7
2
0
,
1
7
4
$
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
‐
A
t
t
r
i
b
u
t
e
d
t
o
A
n
n
e
x
a
t
i
o
n
s
0
%
1
%
1
%
1
%
1% 1%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
6
9
2
,
0
7
3
$
6
9
8
,
9
9
4
$
7
0
5
,
9
8
4
$
7
1
3
,
0
4
4
$
7
2
0
,
1
7
4
$
7
2
7
,
3
7
6 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
3
.
2
%
4
.
5
%
6
.
0
%
7
.
5
%
9
.
0
%
1
0
.
5
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1
.
3
%
1
.
5
%
1
.
5
%
1
.
5
%
1
.
5
%
1
.
5
%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
4
.
5
%
6
.
0
%
7
.
5
%
9
.
0
%
1
0
.
5
%
1
2
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
3
1
,
1
4
3
$
4
1
,
9
4
0
$
5
2
,
9
4
9
$
6
4
,
1
7
4
$
7
5
,
6
1
8
$
8
7
,
2
8
5
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
1
4
0
,
0
0
0
)
$
(
1
1
8
,
0
0
0
)
$
‐
$
(
1
4
5
,
0
0
0
)
$
‐
$
(
6
5
,
0
0
0
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
TR
E
E
M
A
I
N
T
E
N
A
N
C
E
P
R
O
J
E
C
T
S
&
EQ
U
I
P
M
E
N
T
69
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Tr
e
e
Ma
i
n
t
e
n
a
n
c
e
Di
s
t
r
i
c
t
FO
R
0
7
FO
R
E
S
T
R
Y
FO
R
E
S
T
R
Y
V
E
H
I
C
L
E
R
E
P
L
A
C
E
M
E
N
T
S
$2
8
,
0
0
0
FO
R
1
0
FO
R
E
S
T
R
Y
ST
U
M
P
G
R
I
N
D
E
R
FO
R
1
1
FO
R
E
S
T
R
Y
LO
G
L
O
A
D
E
R
&
T
R
U
C
K
$1
4
0
,
0
0
0
FO
R
1
3
FO
R
E
S
T
R
Y
AE
R
I
A
L
L
I
F
T
/
B
U
C
K
E
T
T
R
U
C
K
$1
4
5
,
0
0
0
FO
R
1
4
FO
R
E
S
T
R
Y
FO
R
E
S
T
R
Y
C
H
I
P
T
R
U
C
K
$9
0
,
0
0
0
FO
R
1
5
FO
R
E
S
T
R
Y
TO
O
L
C
A
T
U
T
I
L
I
T
Y
M
A
C
H
I
N
E
$65,000
$1
4
0
,
0
0
0
$1
1
8
,
0
0
0
$1
4
5
,
0
0
0
$65,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
T
r
e
e
M
a
i
n
t
e
n
a
n
c
e
D
i
s
t
r
i
c
t
(
6
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$1
4
0
,
0
0
0
$1
1
8
,
0
0
0
$65,000FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$1
4
5
,
0
0
0
FY
2
1
70
CIP Project Fund
Tree Maintenance District
PROJECT NUMBER
FOR07
DEPARTMENT
FORESTRY
PROJECT NAME
Forestry Vehicle Replacements
FY19 FY20
$28,000
Unscheduled
DESCRIPTION OF PROJECT
This is a request to replace a 1999 Ford 1/2 ton pickup truck. #2728 has 95,000 miles and the clutch needs replacement.
ALTERNATIVES CONSIDERED
Continue to use and repair existing vehicle. As directed by Commission.
ADVANTAGES OF APPROVAL
Replacing this pickup will provide the Forestry division with more reliable truck, improve safety, lower exhaust emissions, tow trailers with its
tow package, and work as needed.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Operating costs (maintenance and fuel/oil) of a newer vehicle are expected to be lower.
FUNDING SOURCES
100% Tree Maintenance District Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
71
CIP Project Fund
Tree Maintenance District
PROJECT NUMBER
FOR10
DEPARTMENT
FORESTRY
PROJECT NAME
STUMP GRINDER
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This is a request to replace a 1996 Vermeer stump grinder. This would be a scheduled replacement of an department forestry
equipment that is nearing 20 years of age. Forestry needs a larger, and more modern stump grinder. Additional info: #2671 –
1996 Vermeer 630B Stump Grinder
350 Hours Replace All Wiring Replace Cutter Belts
ALTERNATIVES CONSIDERED
Continue to use existing equipment. As directed by Commission.
ADVANTAGES OF APPROVAL
Replacing this equipment will provide the Forestry division with an larger and more reliable piece of equipment. Also it will improve
productivity and will be safer for the operator. Trade in on new purchase or put in public auction.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal maintenance and upkeep.
FUNDING SOURCES
100% Tree Maintenance District Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
72
CIP Project Fund
Tree Maintenance District
PROJECT NUMBER
FOR11
DEPARTMENT
FORESTRY
PROJECT NAME
LOG LOADER & TRUCK
FY19
$140,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This a request to replace a 2001 Ford F650. Forestry is moving up an unscheduled request to FY19. This piece of Forestry
equipment is both unsafe and impractical. Additional info: #3125 – 2001 Ford F650, National Crane N50, Palift Hydraulic Dump,
10,000 miles/1100 hours. Hydroboost Brake System Repairs, Leaky Rear Seals, transmission slip, GVWR 26000 Max – 24500 lbs.
empty. Not True Forestry style Equipment.
ALTERNATIVES CONSIDERED
Continue to use existing vehicle. As directed by Commission.
ADVANTAGES OF APPROVAL
Replacing this Forestry equipment will provide better production and improved safety to the operator. This truck and crane was pieced
together and is over its safe gvwr nearly empty. Replace for a true urban Forestry log and brush loader. Trade in or public auction the whole
thing. No other City department can use it or any part of it.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Tree Maintenance District Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
73
CIP Project Fund
Tree Maintenance District
PROJECT NUMBER
FOR13
DEPARTMENT
FORESTRY
PROJECT NAME
Aerial Lift / Bucket Truck
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace 2001 #3069 C7500 HI-Ranger bucket truck. This Forestry equipment is nearing its 20 year anniversary. 11,000
miles/4,000 hours. This truck has been the main workhorse for the division and is showing its wear. Replacement would give us a
modern truck with a higher working height and new safety items.
ALTERNATIVES CONSIDERED
Continue to use existing vehicle. As directed by the commission.
ADVANTAGES OF APPROVAL
Replacement of this equipment provides the division with a more reliable bucket truck. Improves operator safety, lowers exhaust emissions, and
gives us the overall working height we need for the City's largest trees. Sell by public auction the existing bucket truck.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Tree Maintenance District Fund
New
Replacement
Equipment
Project
FY21 FY22
$145,000
FY23
74
CIP Project Fund
Tree Maintenance District
PROJECT NUMBER
FOR14
DEPARTMENT
Forestry
PROJECT NAME
FORESTRY CHIP TRUCK
FY19 FY20
$90,000
Unscheduled
DESCRIPTION OF PROJECT
This is a request to replace a 1991 International Forestry chip truck. This Forestry equipment is nearly 30 years old and has
reliability issues with the engine. Replacement with a modern truck would bring cleaner emission through Tier 4 Diesel standards.
A larger dump body of 20 cubic yards (25% increase) reduces trips to the landfill, saving both vehicle wear and time.
ALTERNATIVES CONSIDERED
Replace 1991 International Forestry with a new 15 cubic yard chip truck (Reduced cost).
ADVANTAGES OF APPROVAL
Improved efficiency and reduced man-hours spent dumping waste
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance and Diesel Exhaust Fluid
FUNDING SOURCES
100% Tree Maintenance District Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
75
CIP Project Fund
Tree Maintenance District
PROJECT NUMBER
FOR15
DEPARTMENT
FORESTRY
PROJECT NAME
TOOLCAT UTILITY MACHINE
FY19 FY20 Unscheduled
$65,000
DESCRIPTION OF PROJECT
This is a request for a multi-function, cabbed vehicle. This equipment would improve efficiency and capability related to snow
removal. Compared to hand-shoveling and ATV use, staff could maintain more plowing routes in less time.
ALTERNATIVES CONSIDERED
Rely on current hand-shoveling and ATV use.
ADVANTAGES OF APPROVAL
Increased staff efficiency related to snow removal
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance
FUNDING SOURCES
100% Tree Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
76
Ge
n
e
r
a
l
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
‐
$
23
6
,
0
0
0
$
(3
5
6
,
6
6
4
)
$
(7
5
5
,
5
6
8
)
$
(5
5
2
,
9
2
0
)
$
(11,771)$
Pl
u
s
:
G
e
n
e
r
a
l
F
u
n
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
2
8
4
,
9
9
6
$
91
9
,
4
1
2
$
1,
0
8
3
,
3
7
4
$
1,
0
9
4
,
2
0
7
$
1,
1
0
5
,
1
4
9
$
1,116,201 $ ‐ $
Pl
u
s
:
G
F
2
3
1
‐
C
e
m
.
I
r
r
i
g
a
t
i
o
n
P
r
o
j
e
c
t
‐
R
e
s
e
r
v
e
U
s
e
d
f
o
r
G
r
a
n
t
M
a
t
c
h
20
0
,
0
0
0
$
20
0
,
0
0
0
$
Pl
u
s
:
G
F
2
3
1
‐
C
e
m
.
I
r
r
i
g
a
t
i
o
n
P
r
o
j
e
c
t
‐
G
r
a
n
t
F
u
n
d
i
n
g
D
N
R
C
a
n
d
B
O
R
42
5
,
0
0
0
$
Pl
u
s
:
G
F
2
8
6
‐
V
e
t
e
r
a
n
s
C
e
m
e
t
e
r
y
P
r
o
j
e
c
t
‐
R
e
s
e
r
v
e
U
s
e
d
88
,
0
0
0
$
40
,
0
0
0
$
45
,
0
0
0
$
Pl
u
s
:
G
F
2
8
0
‐
S
t
o
r
y
M
a
n
s
i
o
n
S
e
w
e
r
R
e
p
a
i
r
,
f
r
o
m
S
t
o
r
y
M
a
n
s
i
o
n
F
u
n
d
18
,
0
0
0
$
Pl
u
s
:
G
F
0
5
2
‐
P
o
l
i
c
e
N
o
n
‐
P
a
t
r
o
l
V
e
h
i
c
l
e
,
f
r
o
m
D
o
n
a
t
i
o
n
18
,
0
0
0
$
Pl
u
s
:
I
n
t
e
r
c
a
p
L
o
a
n
‐
G
F
2
6
0
,
G
F
2
6
1
S
p
o
r
t
s
C
o
m
p
l
e
x
I
m
p
s
.
43
1
,
5
0
0
$
Pl
u
s
:
B
o
n
d
I
s
s
u
e
:
G
F
2
6
3
L
&
J
10
,
0
0
0
,
0
0
0
$
20
,
0
0
0
,
0
0
0
$
Pl
u
s
:
B
o
n
d
I
s
s
u
e
:
G
F
3
0
5
F
i
r
e
S
t
a
t
i
o
n
1
6,
5
0
0
,
0
0
0
$
Pl
u
s
:
B
o
n
d
I
s
s
u
e
:
G
F
3
0
6
F
i
r
e
S
t
a
t
i
o
n
2
4,500,000
Pl
u
s
:
B
o
n
d
I
s
s
u
e
:
G
F
0
5
6
I
n
d
o
o
r
/
O
u
t
d
o
o
r
A
q
u
a
t
i
c
s
F
a
c
i
l
i
t
y
16
,
5
0
0
,
0
0
0
$
Pl
u
s
:
G
F
1
3
7
S
w
i
m
C
e
n
t
e
r
/
G
F
2
3
8
B
o
g
e
r
t
B
o
n
d
I
s
s
u
e
(
w
i
t
h
A
q
u
a
t
i
c
s
F
a
c
i
l
i
t
y
q
u
e
s
t
i
o
n
)
1,
4
3
2
,
3
0
0
$
Le
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(1
,
2
8
4
,
9
9
6
)
$
(1
2
,
6
5
6
,
5
7
6
)
$
(8
,
5
2
2
,
2
7
7
)
$
(2
1
,
6
6
9
,
5
6
0
)
$
(1
9
,
1
5
4
,
3
0
0
)
$
(5,119,000)$ (11,346,933)$
Cr
e
a
t
i
o
n
o
f
C
i
t
y
w
i
d
e
P
a
r
k
M
a
i
n
t
D
i
s
t
.
C
I
P
p
r
o
j
e
c
t
s
m
o
v
e
d
t
o
o
w
n
f
u
n
d
Cr
e
a
t
i
o
n
50
0
,
0
0
0
$
73
3
,
0
0
0
$
65
8
,
0
0
0
$
203,00 0 $ 3,395,00 0 $
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
23
6
,
0
0
0
$
(3
5
6
,
6
6
4
)
$
(7
5
5
,
5
6
8
)
$
(5
5
2
,
9
2
0
)
$
(1
1
,
7
7
1
)
$
688,43 0 $
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
:
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
G
e
n
e
r
a
l
F
u
n
d
R
e
v
e
n
u
e
s
30
,
3
4
3
,
6
2
3
$
30
,
3
4
3
,
6
2
3
$
30
,
6
4
7
,
0
5
9
$
30
,
9
5
3
,
5
3
0
$
31
,
2
6
3
,
0
6
5
$
31,575,69 6 $
E
s
t
i
m
a
t
e
d
G
r
o
w
t
h
i
n
G
e
n
e
r
a
l
F
u
n
d
R
e
v
e
n
u
e
s
0%
1%
1%
1%
1%
1%
To
t
a
l
E
s
t
i
m
a
t
e
d
G
e
n
e
r
a
l
F
u
n
d
R
e
v
e
n
u
e
s
30
,
3
4
3
,
6
2
3
$
30
,
6
4
7
,
0
5
9
$
30
,
9
5
3
,
5
3
0
$
31
,
2
6
3
,
0
6
5
$
31
,
5
7
5
,
6
9
6
$
31,891,45 3 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
2.
6
%
2.
6
%
3.
0
%
3.
5
%
3.
5
%
3.5 %
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
s
%
0.
4
%
0.
4
%
0.
5
%
0.
0
%
0.
0
%
0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
3.
0
%
3.
0
%
3.
5
%
3.
5
%
3.
5
%
3.5%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
91
0
,
3
0
9
$
91
9
,
4
1
2
$
1,
0
8
3
,
3
7
4
$
1,
0
9
4
,
2
0
7
$
1,
1
0
5
,
1
4
9
$
1,116,201 $
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
1
2
,
6
5
6
,
5
7
6
)
$
(
8
,
5
2
2
,
2
7
7
)
$
(
2
1
,
6
6
9
,
5
6
0
)
$
(
1
9
,
1
5
4
,
3
0
0
)
$
(
5
,
1
1
9
,
0
0
0
)
$
(
1
1
,
3
4
6
,
9
3
3
)
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY
2
3
U
N
S
C
H
E
D
U
L
E
D
GE
N
E
R
A
L
F
U
N
D
P
R
O
J
E
C
T
S
&
E
Q
U
I
P
M
E
N
T
77
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Ge
n
e
r
a
l
F
u
n
d
GF
0
1
0
CE
M
E
T
E
R
Y
CE
M
E
T
E
R
Y
M
O
W
E
R
R
E
P
L
A
C
E
M
E
N
T
S
$18,000
$1
6
,
0
0
0
$1
6
,
0
0
0
$1
8
,
0
0
0
$1
8
,
0
0
0
GF
0
8
3
CE
M
E
T
E
R
Y
BA
C
K
H
O
E
$1
1
0
,
0
0
0
GF
1
1
6
CE
M
E
T
E
R
Y
CE
M
E
T
E
R
Y
V
E
H
I
C
L
E
R
E
P
L
A
C
E
M
E
N
T
S
$5
0
,
0
0
0
GF
2
3
1
CE
M
E
T
E
R
Y
CE
M
E
T
E
R
Y
I
R
R
I
G
A
T
I
O
N
P
R
O
J
E
C
T
$6
8
2
,
8
5
9
GF
2
5
2
CE
M
E
T
E
R
Y
CE
M
E
T
E
R
Y
C
O
L
U
M
B
A
R
I
U
M
$5
5
,
0
0
0
GF
2
6
8
CE
M
E
T
E
R
Y
SO
U
T
H
W
E
S
T
M
O
N
T
A
N
A
V
E
T
E
R
A
N
'
S
CE
M
E
T
E
R
Y
$8
8
,
0
0
0
$360,000
$4
0
,
0
0
0
$4
5
,
0
0
0
$18,000
$8
3
6
,
8
5
9
$1
6
6
,
0
0
0
$1
1
8
,
0
0
0
$1
8
,
0
0
0
$360,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
2
8
2
Ci
t
y
A
d
m
i
n
/
Su
s
t
a
i
n
a
b
i
l
i
t
y
C
I
T
Y
H
A
L
L
P
L
U
G
-
I
N
H
Y
B
R
I
D
E
L
E
C
T
R
I
C
VE
H
I
C
L
E
$3
3
,
0
0
0
$3
3
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
2
8
3
Ci
t
y
C
l
e
r
k
’
s
Of
f
i
c
e
/
CO
M
M
I
S
S
I
O
N
R
O
O
M
T
E
C
H
N
O
L
O
G
Y
UP
G
R
A
D
E
$8
0
,
0
0
0
GF
2
8
4
Ci
t
y
C
l
e
r
k
’
s
O
f
f
i
LA
S
E
R
F
I
C
H
E
S
O
F
T
W
A
R
E
U
P
G
R
A
D
E
$28,000 $28,000
$5
7
,
0
0
0
$2
8
,
0
0
0
$2
8
,
0
0
0
$28,000
$8
0
,
0
0
0
$5
7
,
0
0
0
$2
8
,
0
0
0
$2
8
,
0
0
0
$28,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
2
7
5
EC
O
N
O
M
I
C
D
E
V
FI
B
E
R
O
P
T
I
C
C
O
N
D
U
I
T
A
N
D
V
A
U
L
T
S
$25,000
$2
5
,
0
0
0
$25,000
$2
5
,
0
0
0
$2
5
,
0
0
0
$2
5
,
0
0
0
$25,000
$2
5
,
0
0
0
$2
5
,
0
0
0
$2
5
,
0
0
0
$2
5
,
0
0
0
$25,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
2
8
5
Fa
c
i
l
i
t
i
e
s
/
L
i
b
r
a
r
y
LI
B
R
A
R
Y
E
X
T
E
R
I
O
R
D
O
O
R
OP
E
R
A
T
O
R
S
/
C
L
O
S
U
R
E
S
R
E
P
L
A
C
E
M
E
N
T
$1
2
,
0
0
0
$1
2
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
1
0
3
FA
C
I
L
I
T
Y
-
C
H
AM
E
R
I
C
A
N
'
S
W
I
T
H
D
I
S
A
B
I
L
I
T
I
E
S
A
C
T
(A
D
A
)
C
O
M
P
L
I
A
N
C
E
I
M
P
R
O
V
E
M
E
N
T
S
$10,000
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
78
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
GF
2
1
9
FA
C
I
L
I
T
Y
-
C
H
AD
D
I
T
I
O
N
T
O
C
I
T
Y
H
A
L
L
,
C
O
N
S
O
L
I
D
A
T
I
O
N
OF
S
E
R
V
I
C
E
S
$5,500,000
GF
2
4
1
FA
C
I
L
I
T
Y
-
C
H
RE
P
L
A
C
E
M
E
N
T
O
F
C
I
T
Y
H
A
L
L
A
C
CO
N
D
E
N
S
I
N
G
U
N
I
T
–
R
O
O
F
T
O
P
$5
0
,
0
0
0
GF
2
4
5
FA
C
I
L
I
T
Y
-
C
H
EN
E
R
G
Y
P
R
O
J
E
C
T
S
–
C
I
T
Y
H
A
L
L
$7
5
,
0
0
0
GF
2
7
1
FA
C
I
L
I
T
Y
-
C
H
CI
T
Y
H
A
L
L
N
E
W
P
A
R
K
I
N
G
L
O
T
$250,000
GF
2
7
2
FA
C
I
L
I
T
Y
-
C
H
SI
T
E
S
E
C
U
R
I
T
Y
U
P
G
R
A
D
E
-
B
U
I
L
D
I
N
G
LO
C
K
S
$1
5
,
0
0
0
$1
5
,
0
0
0
$1
5
,
0
0
0
GF
3
0
3
FA
C
I
L
I
T
Y
-
C
H
CI
T
Y
H
A
L
L
E
X
P
A
N
S
I
O
N
R
E
M
O
D
E
L
O
F
ST
O
R
A
G
E
A
R
E
A
S
I
N
T
O
O
F
F
I
C
E
S
$2
5
,
0
0
0
GF
3
0
4
FA
C
I
L
I
T
Y
-
C
H
CI
T
Y
H
A
L
L
C
O
M
M
I
S
S
I
O
N
R
O
O
M
EX
P
A
N
S
I
O
N
/
R
E
M
O
D
E
L
$3
0
0
,
0
0
0
$10,000
$3
7
5
,
0
0
0
$2
5
,
0
0
0
$1
2
5
,
0
0
0
$1
0
,
0
0
0
$5,750,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
0
0
1
FA
C
I
L
I
T
Y
-
P
R
O
F
PR
O
F
E
S
S
I
O
N
A
L
B
U
I
L
D
I
N
G
E
L
E
V
A
T
O
R
RE
P
L
A
C
E
M
E
N
T
$66,600
GF
1
9
9
FA
C
I
L
I
T
Y
-
P
R
O
F
PR
O
F
E
S
S
I
O
N
A
L
B
U
I
L
D
I
N
G
RE
C
O
N
F
I
G
U
R
A
T
I
O
N
-
P
H
A
S
E
2
$3
7
,
0
3
1
$3
7
,
0
3
1
$66,600
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
1
5
7
FA
C
I
L
I
T
Y
-
S
C
SE
N
I
O
R
C
E
N
T
E
R
E
L
E
V
A
T
O
R
$6
8
,
0
0
0
$6
8
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
2
2
4
FI
N
A
N
C
E
SU
N
G
A
R
D
A
N
A
L
Y
T
I
C
S
N
O
W
C
O
G
N
O
S
B
I
(B
U
S
I
N
E
S
S
I
N
T
E
L
L
I
G
E
N
C
E
)
W
E
B
-
B
A
S
E
D
RE
P
O
R
T
I
N
G
S
U
I
T
E
$3
5
,
0
0
0
GF
2
2
7
FI
N
A
N
C
E
ER
P
R
E
P
L
A
C
E
M
E
N
T
/
U
P
G
R
A
D
E
"S
U
N
G
A
R
D
R
E
P
L
A
C
E
M
E
N
T
/
U
P
G
R
A
D
E
"
$333,333
$3
5
,
0
0
0
$333,333
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
3
0
5
Fi
r
e
FI
R
E
S
T
A
T
I
O
N
2
$4,500,000
GF
3
0
6
Fi
r
e
FI
R
E
S
T
A
T
I
O
N
1
$6
,
5
0
0
,
0
0
0
79
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
$4,500,000
$6
,
5
0
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
2
8
7
Hu
m
a
n
R
e
s
o
u
r
c
LE
A
R
N
I
N
G
M
A
N
A
G
E
M
E
N
T
S
Y
S
T
E
M
$2
5
,
0
0
0
GF
2
8
8
Hu
m
a
n
R
e
s
o
u
r
c
AP
P
L
I
C
A
N
T
T
R
A
C
K
I
N
G
S
Y
S
T
E
M
$3
0
,
0
0
0
$2
5
,
0
0
0
$3
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
0
6
2
I.
T
.
PE
R
S
O
N
A
L
C
O
M
P
U
T
E
R
(
P
C
)
R
E
P
L
A
C
E
M
E
N
T
$60,000
$5
0
,
0
0
0
$5
5
,
0
0
0
$6
5
,
0
0
0
$6
5
,
0
0
0
GF
0
8
0
I.
T
.
RE
M
O
T
E
C
L
O
S
E
T
S
W
I
T
C
H
E
S
,
R
O
U
T
E
R
A
N
D
WI
R
E
L
E
S
S
A
P
R
E
P
L
A
C
E
M
E
N
T
$50,000
$4
5
,
0
0
0
$4
5
,
0
0
0
$4
5
,
0
0
0
$5
0
,
0
0
0
GF
1
9
9
I.
T
.
PR
O
F
E
S
S
I
O
N
A
L
B
U
I
L
D
I
N
G
RE
C
O
N
F
I
G
U
R
A
T
I
O
N
-
P
H
A
S
E
2
$1
3
6
,
1
8
6
GF
2
2
9
I.
T
.
IS
C
S
I
S
T
O
R
A
G
E
R
E
P
L
A
C
E
M
E
N
T
$4
5
,
0
0
0
GF
2
3
3
I.
T
.
VE
H
I
C
L
E
R
E
P
L
A
C
E
M
E
N
T
$23,000 $83,000
GF
2
6
3
I.
T
.
PO
L
I
C
E
V
I
D
E
O
E
V
I
D
E
N
C
E
S
T
O
R
A
G
E
A
N
D
BA
C
K
U
P
$4
0
,
0
0
0
GF
2
6
5
I.
T
.
GE
N
E
R
A
L
F
U
N
D
S
E
R
V
E
R
R
E
P
L
A
C
E
M
E
N
T
$6
8
,
0
0
0
GF
2
8
9
I.
T
.
SE
R
V
E
R
F
A
R
M
S
O
F
T
W
A
R
E
U
P
G
R
A
D
E
S
$25,000
$1
0
,
0
0
0
$1
0
,
0
0
0
$2
5
,
0
0
0
$158,000
$2
7
6
,
1
8
6
$1
1
0
,
0
0
0
$1
8
8
,
0
0
0
$1
8
0
,
0
0
0
$83,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
0
3
1
PA
R
K
S
PA
R
K
I
M
P
R
O
V
E
M
E
N
T
G
R
A
N
T
S
$1
5
0
,
0
0
0
$1
5
0
,
0
0
0
GF
0
3
4
PA
R
K
S
LA
R
G
E
D
E
C
K
M
O
W
E
R
$60,000
$9
0
,
0
0
0
$110,000
$5
8
,
0
0
0
GF
0
8
4
PA
R
K
S
PA
R
K
S
R
E
S
T
R
O
O
M
U
P
G
R
A
D
E
S
$470,000
$8
0
,
0
0
0
GF
0
9
2
PA
R
K
S
PL
A
Y
G
R
O
U
N
D
E
Q
U
I
P
M
E
N
T
$120,000
$9
5
,
0
0
0
$9
5
,
0
0
0
$1
2
0
,
0
0
0
GF
1
0
8
PA
R
K
S
PA
R
K
S
I
D
E
W
A
L
K
R
E
P
L
A
C
E
M
E
N
T
S
$88,000
$1
2
0
,
0
0
0
GF
1
1
5
PA
R
K
S
PA
R
K
V
E
H
I
C
L
E
R
E
P
L
A
C
E
M
E
N
T
S
$55,000
$5
0
,
0
0
0
$180,000
$3
0
,
0
0
0
$3
0
,
0
0
0
$2
8
,
0
0
0
GF
1
4
8
PA
R
K
S
BM
X
P
A
R
K
I
N
G
L
O
T
$85,000
GF
1
9
0
PA
R
K
S
4-
W
H
E
E
L
E
R
A
T
V
R
E
P
L
A
C
E
M
E
N
T
$14,000
$1
6
,
0
0
0
GF
1
9
1
PA
R
K
S
UP
G
R
A
D
E
S
O
F
T
B
A
L
L
C
O
M
P
L
E
X
L
I
G
H
T
I
N
G
$1,000,000
80
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
GF
1
9
5
PA
R
K
S
TU
R
F
S
W
E
E
P
E
R
$3
2
,
0
0
0
$36,000
GF
2
0
5
PA
R
K
S
PR
O
S
T
P
L
A
N
U
P
D
A
T
E
$1
0
9
,
0
0
0
GF
2
5
0
PA
R
K
S
SP
L
A
S
H
P
A
D
S
$190,000
$2
2
5
,
0
0
0
$2
4
0
,
0
0
0
GF
2
6
0
PA
R
K
S
SP
O
R
T
S
C
O
M
P
L
E
X
-
C
O
N
S
T
R
U
C
T
I
O
N
O
F
'P
R
O
J
E
C
T
R
E
L
A
T
E
D
'
C
O
T
T
O
N
W
O
O
D
R
O
A
D
AR
E
A
W
A
T
E
R
&
W
A
S
T
E
W
A
T
E
R
IM
P
R
O
V
E
M
E
N
T
S
$3
6
4
,
0
0
0
GF
2
7
0
PA
R
K
S
SN
O
W
P
L
O
W
I
N
G
V
E
H
I
C
L
E
$6
5
,
0
0
0
$75,000
GF
2
7
8
PA
R
K
S
GR
I
F
F
I
N
A
T
S
T
O
R
Y
M
I
L
L
P
A
R
K
R
O
A
D
IM
P
R
O
V
E
M
E
N
T
-
.
2
6
M
I
L
E
$260,000
GF
2
7
9
PA
R
K
S
ST
O
R
Y
M
I
L
L
R
O
A
D
I
M
P
R
O
V
E
M
E
N
T
-
.
1
7
MI
L
E
$170,000
GF
2
8
1
PA
R
K
S
BO
Z
E
M
A
N
P
O
N
D
P
A
R
K
&
A
A
S
H
E
I
M
BA
L
L
F
I
E
L
D
S
R
O
A
D
E
X
P
A
N
S
I
O
N
-
.
1
7
M
I
L
E
&
.
0
9
M
I
L
E
$260,000
GF
2
9
0
PA
R
K
S
IR
R
I
G
A
T
I
O
N
S
Y
S
T
E
M
R
E
P
L
A
C
E
M
E
N
T
S
$425,000
GF
2
9
1
PA
R
K
S
PI
C
K
L
E
B
A
L
L
C
O
U
R
T
S
$9
0
,
0
0
0
$203,000
$3
4
6
,
0
0
0
$5
0
0
,
0
0
0
$7
3
3
,
0
0
0
$6
5
8
,
0
0
0
$3,395,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
PW
0
5
/
0
6
Pa
r
k
s
a
n
d
Fa
c
i
l
i
t
y
P
o
r
t
i
o
n
PU
B
L
I
C
W
O
R
K
S
S
H
O
P
S
F
A
C
I
L
I
T
Y
P
L
A
N
AN
D
C
O
N
S
T
R
U
C
T
I
O
N
$1
0
,
0
0
0
$5
0
,
0
0
0
$1
0
,
0
0
0
$5
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
0
5
2
PO
L
I
C
E
PO
L
I
C
E
N
O
N
-
P
A
T
R
O
L
V
E
H
I
C
L
E
RE
P
L
A
C
E
M
E
N
T
S
$30,000
$1
5
,
0
0
0
$377,000
$1
5
,
0
0
0
$1
5
,
0
0
0
GF
0
5
3
PO
L
I
C
E
PA
T
R
O
L
V
E
H
I
C
L
E
R
E
P
L
A
C
E
M
E
N
T
$132,000
$1
2
4
,
0
0
0
$680,000
$1
8
9
,
0
0
0
$1
2
8
,
0
0
0
$1
9
5
,
0
0
0
GF
1
6
5
PO
L
I
C
E
PA
T
R
O
L
M
O
T
O
R
C
Y
C
L
E
R
E
P
L
A
C
E
M
E
N
T
S
$60,000
GF
1
6
6
PO
L
I
C
E
PO
R
T
A
B
L
E
A
N
D
M
O
B
I
L
E
R
A
D
I
O
RE
P
L
A
C
E
M
E
N
T
S
$2
9
5
,
0
0
0
$2
9
5
,
0
0
0
GF
2
6
2
PO
L
I
C
E
PO
L
I
C
E
K
9
$19,000
$1
7
,
0
0
0
GF
2
6
3
PO
L
I
C
E
LA
W
&
J
U
S
T
I
C
E
C
E
N
T
E
R
$1
0
,
0
0
0
,
0
0
0
$2
0
,
0
0
0
,
0
0
0
GF
2
9
2
PO
L
I
C
E
PA
T
R
O
L
C
A
R
A
U
X
I
L
I
A
R
Y
E
Q
U
I
P
M
E
N
T
$15,000
$1
5
,
0
0
0
$10,000
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
81
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
GF
2
9
3
PO
L
I
C
E
NO
N
-
P
A
T
R
O
L
C
A
R
N
E
W
V
E
H
I
C
L
E
S
$1
5
,
0
0
0
$1
5
,
0
0
0
GF
2
9
4
PO
L
I
C
E
PA
T
R
O
L
C
A
R
-
A
D
D
I
T
I
O
N
A
L
$6
4
,
0
0
0
$177,000
$1
0
,
4
4
9
,
0
0
0
$5
0
9
,
0
0
0
$2
0
,
2
3
4
,
0
0
0
$2
3
5
,
0
0
0
$1,146,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Ge
n
e
r
a
l
F
u
n
d
GF
0
5
6
RE
C
R
E
A
T
I
O
N
DE
S
I
G
N
&
C
O
N
S
T
R
U
C
T
IN
D
O
O
R
/
O
U
T
D
O
O
R
F
A
M
I
L
Y
A
Q
U
A
T
I
C
S
CE
N
T
E
R
$1
0
0
,
0
0
0
$1
6
,
5
0
0
,
0
0
0
GF
1
3
7
RE
C
R
E
A
T
I
O
N
SW
I
M
C
E
N
T
E
R
-
F
A
C
I
L
I
T
Y
R
E
P
A
I
R
S
A
N
D
RE
P
L
A
C
E
M
E
N
T
S
$9
4
9
,
3
0
0
GF
1
4
0
RE
C
R
E
A
T
I
O
N
LI
N
D
L
E
Y
C
E
N
T
E
R
P
A
R
K
I
N
G
L
O
T
RE
N
O
V
A
T
I
O
N
$5
3
,
5
6
0
GF
2
0
9
RE
C
R
E
A
T
I
O
N
LI
N
D
L
E
Y
C
E
N
T
E
R
F
U
L
L
U
P
G
R
A
D
E
:
RE
S
T
R
O
O
M
S
,
W
I
N
D
O
W
S
,
S
I
D
I
N
G
,
KI
T
C
H
E
N
,
R
O
O
F
,
F
L
O
O
R
I
N
G
$2
2
4
,
2
7
7
GF
2
3
8
RE
C
R
E
A
T
I
O
N
BO
G
E
R
T
P
O
O
L
R
E
N
O
V
A
T
I
O
N
$4
8
3
,
0
0
0
GF
2
9
5
RE
C
R
E
A
T
I
O
N
SW
I
M
C
E
N
T
E
R
U
V
S
Y
S
T
E
M
R
E
P
L
A
C
E
M
E
N
T
$6
8
,
5
0
0
GF
2
9
6
RE
C
R
E
A
T
I
O
N
SW
I
M
C
E
N
T
E
R
–
F
R
O
N
T
F
U
R
N
A
C
E
RE
P
L
A
C
E
M
E
N
T
$3
6
,
0
0
0
GF
2
9
7
RE
C
R
E
A
T
I
O
N
SW
I
M
C
E
N
T
E
R
R
O
O
F
R
E
P
L
A
C
E
M
E
N
T
$2
6
,
0
0
0
GF
2
9
8
RE
C
R
E
A
T
I
O
N
SW
I
M
C
E
N
T
E
R
–
B
A
R
R
I
E
R
W
A
L
L
I
N
P
U
M
P
RO
O
M
$2
2
,
0
0
0
GF
2
9
9
RE
C
R
E
A
T
I
O
N
VE
H
I
C
L
E
R
E
P
L
A
C
E
M
E
N
T
$3
0
,
0
0
0
GF
3
0
0
RE
C
R
E
A
T
I
O
N
ST
O
R
Y
M
I
L
L
C
O
M
M
U
N
I
T
Y
C
E
N
T
E
R
GY
M
N
A
S
I
U
M
F
L
O
O
R
R
E
P
L
A
C
E
M
E
N
T
$110,000
GF
3
0
1
RE
C
R
E
A
T
I
O
N
ST
O
R
Y
M
A
N
S
I
O
N
E
X
T
E
R
I
O
R
P
A
I
N
T
$50,000
GF
3
0
2
RE
C
R
E
A
T
I
O
N
PA
S
S
E
N
G
E
R
V
A
N
$3
5
,
0
0
0
$1
1
6
,
5
0
0
$2
9
0
,
2
7
7
$1
8
8
,
5
6
0
$1
7
,
9
3
2
,
3
0
0
$160,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
G
e
n
e
r
a
l
F
u
n
d
(
7
8
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$5,119,000
$1
2
,
6
5
6
,
5
7
6
$8
,
2
3
2
,
2
7
7
$11,346,933FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$1
9
,
1
5
4
,
3
0
0
$2
1
,
6
6
9
,
5
6
0
FY
2
1
82
CIP Project Fund
General Fund
PROJECT NUMBER
GF001
DEPARTMENT
FACILITY - PROF
PROJECT NAME
PROFESSIONAL BUILDING ELEVATOR REPLACEMENT
FY19 FY20 Unscheduled
$66,600
DESCRIPTION OF PROJECT
The elevator in the Professional Building is a three stop Otis elevator. The elevator was installed when the second floor was
added in 1972. Since the City purchased the building we have remodeled several areas on both the main floor and second floor –
the elevator remains original and is approaching 44 years of continued use. The elevator is to the point where many technological
improvements have been made in elevator technology and a change out would yield both improved service and some reductions
in energy costs. The elevator is inspected annually and is still safe although there are some inherent problems with the operation
of the elevator. Of the four elevators owned by the City, this system experiences the most downtime. One big problem is the
leveling systems and the way the rails and tracks are mounted in the building. The elevator will malfunction and require resetting if
it loaded heavy to one side. A new car and track system would solve the nuisance trips associated with this aging elevator.
ALTERNATIVES CONSIDERED
Continue to maintain and adjust the elevator operating systems throughout the year.
ADVANTAGES OF APPROVAL
Increase reliability and reduced maintenance costs. Some electrical savings associated with improved electric motors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs
FUNDING SOURCES
General Fund and Building Inspection Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
83
CIP Project Fund
General Fund
PROJECT NUMBER
GF010
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY MOWER REPLACEMENTS
FY19
$16,000
FY20
$16,000
Unscheduled
DESCRIPTION OF PROJECT
Ongoing cemetery mower replacement program. Scheduled on a five year replacement program, with the oldest cemetery mower
now being 5 years old. Proposing to go back to the three replacement cycle, due to numerous breakdowns after the three year
mark. These mowers are used to complete the mowing 53+ acres of turf inside and outside the cemetery which include mowing
of the open space, trails, and the weekly mowing through the headstones.
ALTERNATIVES CONSIDERED
Keep older mowers for extended periods of time, which has been done as we moved to a 5 year replacement program instead of a 3 year
program.
ADVANTAGES OF APPROVAL
Less down time; Decreased repair /maintenance costs; High trade –in value; Increased productivity; Less emissions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Routine maintenance, oil changes, fuel.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$18,000
FY22
$18,000
FY23
$18,000
84
CIP Project Fund
General Fund
PROJECT NUMBER
GF031
DEPARTMENT
PARKS
PROJECT NAME
PARK IMPROVEMENT GRANTS
FY19 FY20
$150,000
Unscheduled
DESCRIPTION OF PROJECT
The General Fund contributes funds every other year towards improving park infrastructure through implementation of park
master plans. This grant program is a matching funds program in which the City receives a minimum 1 to 1 match from the
recipient. The Commission has established a formal grant policy by resolution. By switching to every other year, and also
increasing the allocation, bigger projects can be accomplished, though these projects will take more time to complete.
ALTERNATIVES CONSIDERED
Handle park equipment and improvement requests on an adhoc basis, as various donors or service groups bring them forward. Allocate more or
fewer dollars to the program.
ADVANTAGES OF APPROVAL
This matching funds program provides critical infrastructure to the park system by utilizing the talents of our community members through
matching funds, donations, labor in lieu of and numerous specialized services. All of the above can be used as a match in this program
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: New infrastructure and facilities bring on increased maintenance and labor costs. The nature of each
project funded will determine the continued costs. Some projects have very low ongoing costs, others have relatively higher costs.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22
$150,000
FY23
85
CIP Project Fund
General Fund
PROJECT NUMBER
GF034
DEPARTMENT
PARKS
PROJECT NAME
LARGE DECK MOWER
FY19
$90,000
FY20 Unscheduled
$110,000
DESCRIPTION OF PROJECT
The mower request in FY19 would be an addition of a large-deck sports turf mower, anticipated to be needed for additional
parkland used for athletics, such as: Enterprise Park (formerly Lerner Park), Oak Springs Park, Adam Bronken Sports Complex,
and the eventual 80 acre Bozeman Sports Complex. The City currently mows over 150 acres of irrigated turfgrass weekly.
ALTERNATIVES CONSIDERED
Continue to repair as break downs occur, Replace mowers as they breakdown, explore a lease program.
ADVANTAGES OF APPROVAL
Proper mowing of sports fields and formal parks are imperative to safety. Regular replacement will reduce maintenance costs and decrease the
number of breakdowns we have been experiencing. Well mowed parks are an important reflection on our City and how it is perceived by
visitors and citizens. New mowers will be more reliable, safer, productive, and will reduce the workload on the vehicle maintenance shop
personnel. Well maintained sports fields have proven to be a vital component to the economic growth of our community, by attracting regional
and state tournaments to Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Improve scheduling of mowing and increase crew efficiency because of reliable equipment.
FUNDING SOURCES
100% General Fund.
New
Replacement
Equipment
Project
FY21
$58,000
FY22 FY23
$60,000
86
CIP Project Fund
General Fund
PROJECT NUMBER
GF052
DEPARTMENT
POLICE
PROJECT NAME
POLICE NON-PATROL VEHICLE REPLACEMENTS
FY19
$15,000
FY20 Unscheduled
$377,000
DESCRIPTION OF PROJECT
The police department has unmarked vehicles used by command staff, detectives and some support positions. Some of these
vehicles are used for support operations, such as animal control, community resource officer, code compliance, etc…. Command
and detective vehicles are assigned and used to respond to emergency calls for command/control or investigations. Generally
vehicle replacement of these vehicles involves buying used, lower mileage vehicles with some trade-in done by higher mileage
vehicles nearing the end of time to operate safely. Decisions on when to rotate these vehicles is usually higher mileage than a
normal police car and dependent largely on track history for maintenance concerns. In FY19 and FY21 we have 2 detective
vehicles in need of replacement. Cost estimates involve buying a lower mileage or lease return vehicle, not a new vehicle. In
FY20 and FY22 we anticipate adding two School Resource Officer Positions to cover the new Bozeman High School and increased
demand for police services at all schools. In FY22 and FY23 we have identified 3 admin vehicles that will need replacement. These
are used by command officers for daily and on-call response throughout the city.
ALTERNATIVES CONSIDERED
Each year we assess each purchase decision. At times we may be able to convert a marked police car to a detective use, when the vehicle is no
longer trustworthy to the levels of immediate emergency response, but could be used for a year or two as an unmarked support vehicle.
ADVANTAGES OF APPROVAL
2 of these vehicles are new and essential. The replacements are also essential and continue to provide safe and reliable transportation. These
unmarked cars tend to last for at least 15 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$15,000
FY22
$15,000
FY23
$30,000
87
CIP Project Fund
General Fund
PROJECT NUMBER
GF053
DEPARTMENT
POLICE
PROJECT NAME
PATROL VEHICLE REPLACEMENT
FY19
$124,000
FY20
$189,000
Unscheduled
$680,000
DESCRIPTION OF PROJECT
This plan allows for a number of patrol cars to be replaced each year, including all of the necessary vehicle equipment (top lights,
sirens, radio, mobile data terminals, video cameras, electronic reporting / ticketing systems, etc.) Costs are based on actual costs
in FY18 of $61,000 per vehicle and anticipated increases in FY19 and beyond. Patrol vehicles are an essential item in the operation
of the Bozeman Police Department, being the primary tool used for over 50,000 Response to Calls each year. Police vehicles must
be available for police patrol and emergency call response 24 hours a day, 365 days a year. These vehicles are used to respond to
both emergency and non-emergency calls for service, investigate vehicle crashes, conduct traffic enforcement and for general
patrol duties. These patrol vehicles average approximately 20,000 miles annually. Vehicles earmarked for replacement will have a
minimum estimated 110,000 miles per vehicle, which with police emergency response tends to be the rough time when police
vehicles are no longer safe for emergency response. An additional 10 patrol vehicles will need replacement after FY23. A review
of mileage and estimated staffing increases in patrol by 2-3 officers over the next few years has also led to the identified need for
an additional patrol vehicle in FY21. This won’t replace a vehicle and brings the total patrol response vehicles to 23 (1 unmarked /
2 K9 vehicles / 20 fully marked)
ALTERNATIVES CONSIDERED
None.
ADVANTAGES OF APPROVAL
This helps us plan for safe and reliable emergency response vehicles for patrol use, as well as projected lower annual maintenance costs. This
program would allow for the replacement of older, higher mileage patrol cars that become less reliable and more costly to repair. Equipment
components mounted inside the car can sometimes be transferred from the old car to the new car, depending on the condition. These
replacements continue to bring the department closer to 100% matching Ford SUV patrol vehicles.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
These are replacement vehicles. Recurring costs frequently decline as newer cars replace older ones. Maintenance costs have stabilized due to
regularly scheduled service, even though calls for service have increased and additional officers have been hired.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$128,000
FY22
$195,000
FY23
$132,000
88
CIP Project Fund
General Fund
PROJECT NUMBER
GF056
DEPARTMENT
RECREATION
PROJECT NAME
DESIGN & CONSTRUCT INDOOR/OUTDOOR FAMILY AQUATICS CENTER
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Indoor/Outdoor Aquatics Center. This item was identified as a “Top Ten Capital Facility Recommendation” in the PROST plan,
adopted October 2007. The design phase in FY18 includes the preliminary design of the Family Aquatics Center. This project will
need to be approved by the voters. It is estimated that an election would be offered in the fall of 2021.
ALTERNATIVES CONSIDERED
Do not build a community aquatics center.
ADVANTAGES OF APPROVAL
Community Benefits of an Aquatics Center: safe and healthy place for families to play, connected families, strong vital involved community, and
increased community programs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs to include additional aquatic staff: Cost undetermined at this time.
FUNDING SOURCES
Bond and General Fund.
New
Replacement
Equipment
Project
FY21
$100,000
FY22
$16,500,000
FY23
89
CIP Project Fund
General Fund
PROJECT NUMBER
GF062
DEPARTMENT
I.T.
PROJECT NAME
PERSONAL COMPUTER (PC) REPLACEMENT
FY19
$50,000
FY20
$55,000
Unscheduled
DESCRIPTION OF PROJECT
This is a general item for replacement of personal computers for General Fund related jobs and services. (Enterprise and Special
Revenue fund services pay for their own pc’s.) As of FY17, Personal Computers moved to a 5 year rotation before replacement.
PC Replacements are one of the primary drivers of Help Desk Calls (PM01 & WL01) - aging computers can have more software
and technical conflicts, and replaced PC's often require user support for newer versions of software, etc.
ALTERNATIVES CONSIDERED
Not replace computer/server hardware as frequently.
ADVANTAGES OF APPROVAL
City technology needs will be better met and the IT department will be able to more efficiently support employees and citizens.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$65,000
FY22
$65,000
FY23
$60,000
90
CIP Project Fund
General Fund
PROJECT NUMBER
GF080
DEPARTMENT
I.T.
PROJECT NAME
REMOTE CLOSET SWITCHES, ROUTER AND WIRELESS AP REPLACEMENT
FY19
$45,000
FY20
$45,000
Unscheduled
DESCRIPTION OF PROJECT
Wan Site end of life replacements for switches and router throughout City to include City Hall, Professional Building, City Shops,
Landfill, L&J, Library, WWTP, WTP, Swim Center, Beall Park, Cemetery. Smaller sites will be consolidated in one year. FY 15 -
Prof-Building, Vehicle Maint. This equipment is critical to the City's technology network, supporting all of the department's
performance measures related to system "uptime" (PM02-PM06) and workload measures related to number of hours the network
and various software is "in service" (WL02-W06).
ALTERNATIVES CONSIDERED
Maintain current switches without critical support or maintenance.
ADVANTAGES OF APPROVAL
Maintain uptime for all WAN locations throughout the City to include phone services as well as data.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund – with costs shared with Enterprise, as location warrants.
New
Replacement
Equipment
Project
FY21
$45,000
FY22
$50,000
FY23
$50,000
91
CIP Project Fund
General Fund
PROJECT NUMBER
GF083
DEPARTMENT
CEMETERY
PROJECT NAME
BACKHOE
FY19 FY20
$110,000
Unscheduled
DESCRIPTION OF PROJECT
This piece of equipment would replace the current cemetery backhoe (2001- 3119 hours) that is used for burials an average of 2
times per week. This is the main piece of equipment utilized for cemetery burials.
ALTERNATIVES CONSIDERED
Continue to utilize the older backhoe and repair and maintain as necessary. Potentially, borrow from another department.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff and the families relying on cemetery services. The old cemetery backhoe could potentially be transitioned
to the Parks Division.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Operating and repair costs are expected to be lower than the existing vehicle.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
92
CIP Project Fund
General Fund
PROJECT NUMBER
GF084
DEPARTMENT
PARKS
PROJECT NAME
PARKS RESTROOM UPGRADES
FY19 FY20 Unscheduled
$470,000
DESCRIPTION OF PROJECT
This project is the general replacement and upgrading of the City Park’s public restroom facilities. Other restrooms that need to
be replaced- and/or built are: Rose Park $80,000 (FY 21), Beall Park $40,000 and the Softball Complex $300,000 –( Large Facility
plus Concession Stand), BMX- Westlake Park $130,000 are unscheduled.
ALTERNATIVES CONSIDERED
Continue to try to maintain existing facilities. The Rose and BMX Park projects will provide restroom facilities in areas where currently none
exist. The BMX project potentially could be part of the Midtown Urban Renewal District.
ADVANTAGES OF APPROVAL
Ease and efficiency of maintaining new restrooms; increased cleanliness of public facilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Operating and repair costs are expected to be lower than the existing facilities.
FUNDING SOURCES
100% General Fund, BMX Park funding possible from TIF
New
Replacement
Equipment
Project
FY21
$80,000
FY22 FY23
93
CIP Project Fund
General Fund
PROJECT NUMBER
GF092
DEPARTMENT
PARKS
PROJECT NAME
PLAYGROUND EQUIPMENT
FY19 FY20
$95,000
Unscheduled
$120,000
DESCRIPTION OF PROJECT
The following playground equipment will eventually need to be replaced due to its age and condition: Replacement will bring
equipment up to today’s standards and reduce safety and liability concerns. Jarrett Park (FY19) and Christie Park (FY20) are
identified as the playgrounds that need replacement, in that priority. New replacements include: Lindley Park (FY22) and Kirk
Park playgrounds. The majority of the city-maintained playgrounds were installed in the early 1990’s. In general, safety
recommendations for playgrounds address: playground site elements, sight lines, equipment features and materials, surfacing
materials, hardware, paints and finishes, and any other hazards that might be present. Playground repairs require same-day
response given their critical safety implication. Currently, the Parks Division inspects and maintains 21 playgrounds city-wide and
assists with another 19 HOA- maintained playgrounds with monthly inspections and recommendations.
ALTERNATIVES CONSIDERED
Keep existing equipment in place, maintain as we go
ADVANTAGES OF APPROVAL
Increased safety for community members.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
100% General Fund.
New
Replacement
Equipment
Project
FY21
$95,000
FY22
$120,000
FY23
94
CIP Project Fund
General Fund
PROJECT NUMBER
GF103
DEPARTMENT
FACILITY - CH
PROJECT NAME
AMERICAN'S WITH DISABILITIES ACT (ADA) COMPLIANCE IMPROVEMENTS
FY19
$10,000
FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
Replace or install ADA upgrades in various city-owned buildings. Work examples include: door hardware, handrails, parking
signage and stalls, building access, etc. The Facilities Superintendent has been working with the ADA advisory committee to
provide recommendations to the City on priority order for any upgrades or improvements that may be identified to make our
facilities and programs more accessible. This money has been used, and will continue to be used to improve accessibility as
demonstrates a commitment from the City to address ADA issues. Based on the initial review of the work to be done the dollar
amount should be increased in order to complete the improvements within the needed timeframe.
ALTERNATIVES CONSIDERED
When remodels are initiated on buildings they are brought up to current ADA requirements as per regulations. There are changes to the ADA
that took effect in March 2011. We will continue to make upgrades as changes are made to buildings but this budget item would accelerate the
compliance for city buildings.
ADVANTAGES OF APPROVAL
It has been the policy of the city to meet the full spirit of the law as outlined in the ADA regulations. By taking the initiative to bring all our
buildings up to current standards we can provide a positive example to the community in meeting the needs of people with restricted or limited
mobility.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No significant costs are anticipated with these improvements.
FUNDING SOURCES
100% General Fund.
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
$10,000
95
CIP Project Fund
General Fund
PROJECT NUMBER
GF108
DEPARTMENT
PARKS
PROJECT NAME
PARK SIDEWALK REPLACEMENTS
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Sidewalks Identified for replacement due to deteriorating cement, missing sections and heaving from weather and tree roots. New
sidewalks must meet or exceed city code. Replacing the old sidewalk will result in a safer sidewalk year round and enable the
sidewalk plows to better meet the snow removal municipal code. Costs of approximately $11.75 square foot for rip and replace.
Project 1: $120,000 - Southside Park - replace 730' of sidewalk along South 5th Avenue and along West Alderson Street with new
6' (six foot) wide concrete sidewalk, and the related retaining wall. Project 2: $88,000 - Cooper Park - replace the sidewalk
around the entire block approximately 1875' total. This sidewalk serves as a main route to and from the University.
ALTERNATIVES CONSIDERED
Maintain existing sidewalks and patch and repair as needed.
ADVANTAGES OF APPROVAL
Increased safety for community members and efficiency of operation (plowing)
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: no estimate at this time
FUNDING SOURCES
General Fund.
New
Replacement
Equipment
Project
FY21 FY22
$120,000
FY23
$88,000
96
CIP Project Fund
General Fund
PROJECT NUMBER
GF115
DEPARTMENT
PARKS
PROJECT NAME
PARK VEHICLE REPLACEMENTS
FY19
$50,000
FY20
$30,000
Unscheduled
$180,000
DESCRIPTION OF PROJECT
The Parks Division utilizes vehicles for mowing, fertilization, irrigation, inspections, snow plowing and repairs of the city parks.
City parkland now has grown to over 500 acres that the Parks Division is responsible for. All vehicles are utilized until service
related down-time for equipment and staff become problematic or safety is compromised. FY19 represents a one ton pick-up
replacement. Dodge has ceased making parts for 2001 1-ton that is currently in the Parks fleet. The two current 1-tons in the
Park fleet are used for plowing parking lots, ice rinks, hauling garbage, stone, and trail fines among other duties. The addition in
FY20 of $30,000 is for a ½ ton fleet vehicle to replace the 1991 Dodge with 5 year repair costs of $32124.00.That vehicle is
currently on the auction block. An incremental approach to replacing aging fleet vehicles which includes an additional hybrid car
(FY22)- and ½ ton pickups for the increase in FTE’s within the division. (FY20 and FY21) An additional 1-ton pickup was moved
into FY23. A more detailed list of the replacement plan, along with updated vehicle mileage, has been sent to Finance- Mileage
updated October 2, 2017.
ALTERNATIVES CONSIDERED
None.
ADVANTAGES OF APPROVAL
This insures safe and reliable vehicles for park use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: These are replacements; recurring costs frequently decline as newer cars replace older ones. 5 year
average on repairs to the Parks fleet - $3,550.00 per vehicle.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$30,000
FY22
$28,000
FY23
$55,000
97
CIP Project Fund
General Fund
PROJECT NUMBER
GF116
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY VEHICLE REPLACEMENTS
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Cemetery Vehicle Replacement Plan - the Cemetery Department utilizes 1-Ton trucks for operations and maintenance of the
Sunset Hills Cemetery. Asset# 1213 - 1989 1Ton 4x4, *41,360 miles - is critical to providing prompt burial services roughly twice
a week and sanding/plowing cemetery roads. While it has relatively low miles, it has extremely low fuel economy (460 engine)
which drives our recommendation to replace this 28 year old vehicle. *Mileage as of 11/2017.
ALTERNATIVES CONSIDERED
Keep maintaining #1213 until a new replacement is funded or replacement parts are no longer available.
ADVANTAGES OF APPROVAL
This insures safe and reliable vehicles for cemetery use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: These are replacements; recurring costs frequently decline as newer cars replace older ones
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
98
CIP Project Fund
General Fund
PROJECT NUMBER
GF137
DEPARTMENT
RECREATION
PROJECT NAME
SWIM CENTER - FACILITY REPAIRS AND REPLACEMENTS
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The Swim Center requires numerous repair and equipment replacements which would be added to the Bond initiative for the
Indoor/Outdoor Aquatics Center. These items include: gutter replacement $159,000; deck tile replacement $150,000; removal of
ceiling tiles and basic cosmetic improvements $127,000; HVAC unit replacement $365,000; pool re-plaster $148,000
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
These projects will help to ensure that we are able to maintain a safe and functional facility. The pool is extremely well utilized and repairs and
replacements are necessary over time in order to continue to serve the community.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional annual operating and maintenance costs
FUNDING SOURCES
Bond
New
Replacement
Equipment
Project
FY21 FY22
$949,300
FY23
99
CIP Project Fund
General Fund
PROJECT NUMBER
GF140
DEPARTMENT
RECREATION
PROJECT NAME
LINDLEY CENTER PARKING LOT RENOVATION
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Curb and overlay the parking lot at the Lindley Center and include ADA parking stalls. Install parking lot lights and bases, a
dumpster pad and dumpster enclosure fence. This project aligns with section 10.10.1 of the PROST plan (adopted October 2007)
that recommends that City parks, recreation facilities and trails are accessible to the greatest extent possible. Includes permit fees.
ALTERNATIVES CONSIDERED
Sealing and striping lot and not installing lights
ADVANTAGES OF APPROVAL
Comply with city codes, allow for more cars to be parked in the lot at a time, more organized parking which will make the lot safer and reduced
liability, lights will help with public safety and parking lot/facility security, ADA spots will be designated which will make the lot accessible, the
dumpster would be enclosed.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs to include stripping and periodic overlays.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$53,560
FY22 FY23
100
CIP Project Fund
General Fund
PROJECT NUMBER
GF148
DEPARTMENT
PARKS
PROJECT NAME
BMX PARKING LOT
FY19 FY20 Unscheduled
$85,000
DESCRIPTION OF PROJECT
Installation of parking lot at Westlake BMX park, left as unscheduled due to this potentially could be part of the Mid-Town Urban
Renewal project- as Westlake/BMX reside in this area.
ALTERNATIVES CONSIDERED
Do not install a parking lot
ADVANTAGES OF APPROVAL
Increased access to the Children’s Memorial Park and Christmas tree drop off area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Minimal. Clean-up, possible snow plowing, painting lines every few years
FUNDING SOURCES
100% General Fund, possible funding from TIF
New
Replacement
Equipment
Project
FY21 FY22 FY23
101
CIP Project Fund
General Fund
PROJECT NUMBER
GF157
DEPARTMENT
FACILITY - SC
PROJECT NAME
SENIOR CENTER ELEVATOR
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The elevator at the Bozeman Senior Social Center is a three stop Otis elevator. The elevator was installed in early 1980 and is at
the point where many technological improvements have been made in elevator technology. A change out would yield both
improved service and some reductions in energy costs. While the elevator is inspected annually and is safe, it is used heavily by the
members of the Senior Center. Planning ahead for the replacement of the elevator will be more cost effective and avoid
unnecessary down time during the replacement process. The elevator maintenance contractor has recommended this be the first
elevator replaced by the City.
ALTERNATIVES CONSIDERED
Continue to maintain and adjust the elevator operating systems as needed. Wait to replace the elevator until it physically breaks down or
continue to monitor the operation and hold off on the replacement until the routine repair and maintenance costs exceed acceptable limits
ADVANTAGES OF APPROVAL
Improved operations and reduced maintenance for the elevator most needed by a special population. Small reduction in annual energy costs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs.
FUNDING SOURCES
General Fund -
New
Replacement
Equipment
Project
FY21 FY22
$68,000
FY23
102
CIP Project Fund
General Fund
PROJECT NUMBER
GF165
DEPARTMENT
POLICE
PROJECT NAME
PATROL MOTORCYCLE REPLACEMENTS
FY19 FY20 Unscheduled
$60,000
DESCRIPTION OF PROJECT
Currently the Police Department has two police motorcycles and one used solely for training. Patrol motorcycles are an essential
item in the traffic enforcement division, used for a portion of the over 13,000 traffic stops, crashes, and citations each year. These
motorcycles are used from March to October each year and are responsible for a portion of the response to both emergency and
non-emergency calls for service, investigate accidents, conduct traffic enforcement and general patrol duties. In FY18 we did not
deploy the motorcycles because of staffing shortages and have plans to deploy in FY19. The current motorcycles will not need
replacement during the next 5 years.
ALTERNATIVES CONSIDERED
None.
ADVANTAGES OF APPROVAL
This ensures safe and reliable emergency response vehicles for patrol use, as well as lower annual maintenance costs. For the traffic division to
be effective, this equipment must be kept in top operating condition. Police motorcycles are available for police patrol use during the day and
when the city streets are clear enough to ride.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance costs are stable due to regularly scheduled service. Officers assigned to the motorcycle division are also assigned to their own
motorcycle.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
103
CIP Project Fund
General Fund
PROJECT NUMBER
GF166
DEPARTMENT
POLICE
PROJECT NAME
PORTABLE AND MOBILE RADIO REPLACEMENTS
FY19
$295,000
FY20
$295,000
Unscheduled
DESCRIPTION OF PROJECT
In FY18 the department and City has been in conversations and planning with Gallatin County 9-1-1 to improve radio
communication that has become an operational and safety concern. Regardless of the final improvements to infrastructure, one of
the identified needs for replacement is subscriber units (portable radios used by officers and mobile radios used in emergency
response vehicles).The replacement of these subscriber units (radios) are a major stop to improving communications and
responses capabilities. These radios are an essential item in the operation of the Bozeman Police Department, being a critical
communication tool used for over to 50,000 Response to Calls each year. Police radios must be available for police use 24 hours a
day, 365 days a year. These radios are individually assigned, allowing for greater longevity, and department-wide communication in
the event of a need for major response. The City Commission approved purchasing these units, which are currently purchased
with payments in FY19 and FY21. These radios will have at least a 10 year use for emergency response. This purchase included
70 Portable (handheld) radios and 27 mobile (vehicle) radios. This amount represents just the police department share of
purchases.
ALTERNATIVES CONSIDERED
No other alternatives at this time.
ADVANTAGES OF APPROVAL
This ensures safe and reliable emergency communication and response. Program allows for a planned and predictable need for equipment
replacement. Clear and dependable communication allows for quick and efficient deployment and the required level of officer safety.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
104
CIP Project Fund
General Fund
PROJECT NUMBER
GF190
DEPARTMENT
PARKS
PROJECT NAME
4-WHEELER ATV REPLACEMENT
FY19 FY20 Unscheduled
$14,000
DESCRIPTION OF PROJECT
Replace the ATV (2000 Yamaha Grizzly) used for sidewalk snow removal and is the main piece of equipment that is used to spray
approx 300 acres with herbicides and biostimulants for the Parks Division.
ALTERNATIVES CONSIDERED
Continue to use the 2000 Yamaha Grizzly and repair as needed.
ADVANTAGES OF APPROVAL
Maximize efficiency, minimize down time, proactive replacement of aging equipment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$16,000
FY22 FY23
105
CIP Project Fund
General Fund
PROJECT NUMBER
GF191
DEPARTMENT
PARKS
PROJECT NAME
UPGRADE SOFTBALL COMPLEX LIGHTING
FY19 FY20 Unscheduled
$1,000,000
DESCRIPTION OF PROJECT
Replace the current lights at the Softball Complex with appropriate stadium lights. Estimate provided by MUSCO, would be bid at
the time of construction. Existing lights have light spillage/pollution and cannot be “retro-fitted”.
ALTERNATIVES CONSIDERED
Keep existing lights
ADVANTAGES OF APPROVAL
The new lights can offer 50% less light spillage and glare and reduce energy costs by up to 50%. Additionally, upgraded lights could help to reduce
or eliminate complaints regarding light pollution.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Reduction in electrical use.
FUNDING SOURCES
100% General Fund, or fundraising by user groups - Cost estimates range from $750,000 to $825,000 in August 2012.
New
Replacement
Equipment
Project
FY21 FY22 FY23
106
CIP Project Fund
General Fund
PROJECT NUMBER
GF195
DEPARTMENT
PARKS
PROJECT NAME
TURF SWEEPER
FY19
$32,000
FY20 Unscheduled
$36,000
DESCRIPTION OF PROJECT
This would be used to maintain the 150+ acres of turf in the park inventory. This piece of equipment would be used extensively at
the new Sports Complex and other venues on the west side of town. ( Ex. Adam Bronken Sports Complex and Oak Springs
Park.) An efficient coring aerator is productive and coincides with water conservation efforts and safe playing athletic fields.
ALTERNATIVES CONSIDERED
Continue to operate with two aerators.
ADVANTAGES OF APPROVAL
Proactively and aggressively aerate parks and sports fields within the City to create safer and healthier turf that uses less water and attract
tournaments to Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
107
CIP Project Fund
General Fund
PROJECT NUMBER
GF199
DEPARTMENT
FACILITY - PROF
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$37,031
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this growth, we need to remodel the Stiff Building. In FY16 the City Commission
approved Phase 1 of the remodel which will provide better use of existing space by relocating certain functions to the basement
and repurposing unused square footage. Approval of Phase II would allow the consolidation of Community Development
(Planning and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater)
together on another floor. This will allow better coordination of staff and better service to our public.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking
New
Replacement
Equipment
Project
FY21 FY22 FY23
108
CIP Project Fund
General Fund
PROJECT NUMBER
GF199
DEPARTMENT
I.T.
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$136,186
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this grow, we need to remodel the Stiff Building. In FY16 the City Commission
approved a Phase 1 of the remodel that will provide a better use of existing space by relocating certain functions to the basement
and reclaiming unused square footage. Approval of Phase II would allow the consolidation of Community Development (Planning
and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater) together
on another floor. This will allow better coordination of staff and better service to our public. Phase 1 is anticipated to be
completed late spring of 2016.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking
New
Replacement
Equipment
Project
FY21 FY22 FY23
109
CIP Project Fund
General Fund
PROJECT NUMBER
GF205
DEPARTMENT
PARKS
PROJECT NAME
PROST PLAN UPDATE
FY19
$109,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Update the 2007 Parks Recreation Open Space Trail (PROST) Plan. The current plan is now 10 years old. Since adoption, the city
has grown in size, new park properties have come into the system, and local demographics have changed. This project anticipates
hiring an outside party to update the Plan that will take into consideration the updated Community Plan.
ALTERNATIVES CONSIDERED
Do not update the plan.
ADVANTAGES OF APPROVAL
The update would record and reference new and accurate information that has been developing over the last 10 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
110
CIP Project Fund
General Fund
PROJECT NUMBER
GF209
DEPARTMENT
RECREATION
PROJECT NAME
LINDLEY CENTER FULL UPGRADE: RESTROOMS, WINDOWS, SIDING, KITCHEN, ROOF, FLOOR
FY19 FY20
$224,277
Unscheduled
DESCRIPTION OF PROJECT
This project is the combination of requests for upgrade of the Restrooms ($56,650), Window Replacement ($24,926), Siding
Replacement ($27,192), Kitchen Upgrade ($56,650), East Roof Insulation ($27,192), Floor support ($14,389), Roof support
($17,278) . This is a heavily used community center that could benefit from substantial improvements.
ALTERNATIVES CONSIDERED
As suggested by the Commission
ADVANTAGES OF APPROVAL
1. Brings restroom up to current ADA requirements; 2. Brings restroom up to current City of Bozeman building codes; 3. Improves sanitation in
the restrooms and kitchen facilities; 4. Rehabs and secures the building envelope for years to come; 5. Reduced energy consumption from
improved windows and insulation. 6. Addresses deficiencies that were identified in the 2014 structural analysis and 2012 facility condition
inventory.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
111
CIP Project Fund
General Fund
PROJECT NUMBER
GF219
DEPARTMENT
FACILITY - CH
PROJECT NAME
ADDITION TO CITY HALL, CONSOLIDATION OF SERVICES
FY19 FY20 Unscheduled
$5,500,000
DESCRIPTION OF PROJECT
This project would relocate the functions currently housed in the Stiff Building (Community Development/Engineering/IT/Building
Inspection) into an expansion of City Hall on Lamme Street.
ALTERNATIVES CONSIDERED
Keep operations at the Stiff Building.
ADVANTAGES OF APPROVAL
Centralizing more services in one location at City Hall will improve efficiency of staff and make it easier for citizens to conduct business with the
City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The new facility should have lower operating costs than the Stiff Building.
FUNDING SOURCES
Potential Funding Sources include: General Fund, Enterprise Fund (for public works), Building Inspection Fund (Building Inspection Division), sale
of the Stiff Building. This is a very rough estimate, based on building square footage and current construction costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
112
CIP Project Fund
General Fund
PROJECT NUMBER
GF224
DEPARTMENT
FINANCE
PROJECT NAME
SUNGARD ANALYTICS NOW COGNOS BI (BUSINESS INTELLIGENCE) WEB-BASED REPORTING
FY19
$35,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Web-based report authoring tool used to build sophisticated, multi-page, multi-query reports using data from SunGard. Seamlessly
integrates Microsoft Excel, enabling users to explore and analyze data in a familiar environment using skills they already have.
Includes enhanced e-mailing and report publishing capabilities, in addition to access by mobile devices including iPads & iPhones.
ALTERNATIVES CONSIDERED
Continue to use SunGard QREP product, which requires a higher level of training and expertise for end-users. QREP is no longer being
developed/enhanced and IBM software support is scheduled to end on April 30, 2018
ADVANTAGES OF APPROVAL
An increased ability to push more big data out to a bigger audience and to empower novice users to collect and analyze the tremendous amount
of data in SunGard.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Ongoing annual maintenance cost = $3,280
FUNDING SOURCES
General Fund, although enterprise funds would continue to be big users, especially GIS
New
Replacement
Equipment
Project
FY21 FY22 FY23
113
CIP Project Fund
General Fund
PROJECT NUMBER
GF227
DEPARTMENT
FINANCE
PROJECT NAME
ERP REPLACEMENT / UPGRADE "SUNGARD REPLACEMENT / UPGRADE"
FY19 FY20 Unscheduled
$333,333
DESCRIPTION OF PROJECT
Replacing/upgrading the current system installed in 1999. This is the system that runs all the financial, community development,
land records, utility and business license applications. Although it is unscheduled we are currently looking into this with a
possibility of FY20.
ALTERNATIVES CONSIDERED
Continue running current SunGard package. Use SunGard.net (NaviLine EDGE) as an improvement to the current system, but not a full
replacement.
ADVANTAGES OF APPROVAL
Simplified package. Easier to integrate the various applications/programs. Easier to pull out information for end users. Easier compilation of
Commission reports and packets for Community Development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown. Dependent on the option chosen.
FUNDING SOURCES
General Fund 33%; Water Fund 33%; Wastewater Fund 33%
New
Replacement
Equipment
Project
FY21 FY22 FY23
114
CIP Project Fund
General Fund
PROJECT NUMBER
GF229
DEPARTMENT
I.T.
PROJECT NAME
ISCSI STORAGE REPLACEMENT
FY19
$45,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
All of the virtual servers that reside at these two buildings use these devices as their storage device. These are critical pieces of
infrastructure.
ALTERNATIVES CONSIDERED
Don't replace for one more year.
ADVANTAGES OF APPROVAL
Allows us to keep our critical pieces of infrastructure running well and under warranty.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
115
CIP Project Fund
General Fund
PROJECT NUMBER
GF231
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY IRRIGATION PROJECT
FY19
$682,859
FY20 Unscheduled
DESCRIPTION OF PROJECT
Phased Project to move irrigation of cemetery and park lands off treated municipal supply onto raw surface supply previously
decreed to irrigate cemetery lands from the Story Mill Ditch .The planned improvements dramatically reduces the amount of man
hours required to monitor watering during season. Improved irrigation system reduces/eliminates water loss and water is applied
in the most efficient manner maximizing the use of the resource. FY 17: Phase II Design for Irrigation of Cemetery Lands • Inlet
structure and piping • Pump house • Main and laterals • Electrical • Irrigation System Components. FY 18:* Phase III Installation of
Diversion Works Project to Cemetery Lands. FY 19:* Phase IV Extension to Haggerty Fields •Design •Installation.
ALTERNATIVES CONSIDERED
Continue to use treated water for cemetery land irrigation.
ADVANTAGES OF APPROVAL
The Parks & Rec Department would no longer pay for large quantities of treated water for irrigation. It protects and preserves the City’s most
valuable decreed surface water right and makes available for sale treated water that would otherwise have irrigated the cemetery. The treated
water that is no longer applied to the cemetery and parks irrigation would be available for sale to new water customers enabling future growth
and/or improving the reliability of the City’s water supplies for use in times of drought. Makes available approximately 258 AF of treated water,
valued at $1,548,000.00 available for retail sale for approximately 1,121 SF homes or 2,080 MF homes. increases the reliability of domestic water
supplies in times of drought.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Pump replacement. It is yet to be determined what additional operations and maintenance costs would be associated with the project during FY
19-21 at this time. This is due to the fact that the feasibility study that will be completed in FY 17 and will identify various alternatives and costs
of each alternative will inform future operations and maintenance costs during FY 19-21. Upon completion of the feasibility study, an alternative
will be selected and projected operations and maintenance costs can be included into the CIP for FY 19-21.
FUNDING SOURCES
General Fund. This project started in Fy18 with 200K. *If awarded, grant funding through the Bureau of Reclamation’s WaterSMART Program
would offset total project costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
116
CIP Project Fund
General Fund
PROJECT NUMBER
GF233
DEPARTMENT
I.T.
PROJECT NAME
VEHICLE REPLACEMENT
FY19 FY20 Unscheduled
$83,000
DESCRIPTION OF PROJECT
Replacement of IT Vehicles. If our current vehicle is still running well and maintenance costs are not high, we would keep them
beyond what is shown here. 2005 Chevy Colorado with 38K 1999 Dodge Truck with 107K 1999 Jeep Cherokee with 74K 1995
Dodge Truck with 67K
ALTERNATIVES CONSIDERED
Buy new or Do nothing.
ADVANTAGES OF APPROVAL
Provide functional transportation with reduced maintenance costs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
$23,000
117
CIP Project Fund
General Fund
PROJECT NUMBER
GF238
DEPARTMENT
RECREATION
PROJECT NAME
BOGERT POOL RENOVATION
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Bogert Pool is beginning to show its wear faster every year. This project would replace the coping around the pool that is
cracked in several areas and the pool gutters that are cracking, crumbling, and/or lifting from the pool edge. All of the leaks that
could be patched without digging up the bottom of the pool have been patched. There is minimal leaking in the return pipes to
the pool but we recommend repairing the leaks in the returning piping that were identified in May of 2015, before the pool is
blasted with sand or high pressure water, prepped, and resurfaced. The retaining wall is going to be replaced with a wrought iron
fence to allow more visibility to the facility at night and provide more structure, as the current wall is weakening. The sections of
the decking in front of the locker rooms have sunken over the years and will also be replaced. The Bogert Pool renovation or
replacement with an alternate water feature would be added to the Bond Initiative for the Indoor/Outdoor Aquatic Center.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
A new gutter system would mitigate entrapment issues caused by the current gutter system. The current gutters are disintegrating between the
gutter and the ledge of the pool where there gutter sits. Several gutter tiles need to be re-adhered to the pool ledge every spring and often
during the pool season. If a tile is still attached but loose, it can easily be pulled from the wall. Several of the gutter tiles have been replaced
through the years. In many places, a space was not left between the tiles. This doesn’t allow the water to flow into the gutter system for optimal
water circulation. The surface of the pool is currently being patched with hydraulic cement in areas where the plaster is coming up. A new
surface would work to protect the structure of the pool. Making these repairs to Bogert would extend the life of the pool for many years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional costs would be associated with these repairs.
FUNDING SOURCES
Bond
New
Replacement
Equipment
Project
FY21 FY22
$483,000
FY23
118
CIP Project Fund
General Fund
PROJECT NUMBER
GF241
DEPARTMENT
FACILITY - CH
PROJECT NAME
Replacement of City Hall AC Condensing Unit – Roof Top
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The roof-top air conditioning condensing unit at City Hall is original to the building (1980) and is reaching the end of its useful
service life. This unit is critical to the temperature control for all office and public areas at City Hall.
ALTERNATIVES CONSIDERED
Continue to maintain the current unit until parts and refrigerant are no longer available.
ADVANTAGES OF APPROVAL
Reduced maintenance, increased efficiency and improved operation.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
119
CIP Project Fund
General Fund
PROJECT NUMBER
GF245
DEPARTMENT
FACILITY - CH
PROJECT NAME
Energy Projects – City Hall
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
City Hall is a LEED-Silver certified building and is currently underperforming. A recent Energy Star Portfolio Manager review found
that City Hall scored a 30 on a scale of 1 to 100, indicating that the energy performance of the building has declined as equipment
has aged or been replaced, and spaces modified. Retro-commissioning improves efficiency of a building’s equipment and systems;
often resolving problems that occurred during design or construction, or those that develop over time. It is a system-wide
evaluation of opportunities to improve energy performance and occupant comfort. City Hall was first commissioned in 2008
following the remodel. Many issues were addressed at that time, but certain problems related to the heating hot water system
balance were not due to budget constraints. The commissioning report recommended replacement of 24 fin tube balancing valves
and control valves on unit heaters. These components are negatively impacting the operation and efficiency of heating and cooling
systems. Building Commissioning was again identified as a need in the 2014 McKinstry Investment Grade Audit. This project
addresses the mechanical upgrades first identified in the commissioning report from 2008 allowing for a retro-commission for the
building following the mechanical upgrades and AC Condensing Unit replacement.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Improved HVAC system operations and reduced utility costs, based on the known conditions, McKinstry estimates that commissioning would
save at least $2,400 per year. The occupants of the building should experience more even temperatures and improved building airflow and
ventilation. Additional savings may be possible, but not fully understood until all the recommended improvements are identified.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$75,000
FY22 FY23
120
CIP Project Fund
General Fund
PROJECT NUMBER
GF250
DEPARTMENT
PARKS
PROJECT NAME
Splash Pads
FY19 FY20
$225,000
Unscheduled
$190,000
DESCRIPTION OF PROJECT
There are two proposed Splash Pad Projects: 1, The installation Interactive Water Feature at the Story Mill Community Park 2.
The installation of a splash pad at the new sports complex.This plan will give the community two larger Splash Pads / Water
Features located in large Community Parks at different ends of the City. Story Mill Community Park in the East and Sports Park in
the West.
ALTERNATIVES CONSIDERED
Do not install splash pads.
ADVANTAGES OF APPROVAL
Can help reduce children’s fear of water. Adds community water features that have no admittance fee allowing people of all socio economic
status to enjoy a public aquatics amenity. Geographically separates two installations to best serve the entire community.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Some additional water costs and maintenance will be required. Additional maintenance is estimated at 0.2 FTE
FUNDING SOURCES
Numerous funding options include TOP Bond money, General Fund cash reserves, Park Improvement Grant money, or combining into an
Aquatics Bond vote.
New
Replacement
Equipment
Project
FY21 FY22
$240,000
FY23
121
CIP Project Fund
General Fund
PROJECT NUMBER
GF252
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY COLUMBARIUM
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Adding an additional eighty niche each columbarium to the Sunset Hills Cemetery with the first one scheduled FY18. These two
additional columbariums would be installed within the same area as the existing columbariums. Currently, the second
columbarium is approximately 96% sold.
ALTERNATIVES CONSIDERED
Do not add any columbariums to the cemetery and cease or put on hold the program once the second columbarium is full.
ADVANTAGES OF APPROVAL
Continuation on a long standing cemetery service, along with ease and minimal maintenance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal if any.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$55,000
FY22 FY23
122
CIP Project Fund
General Fund
PROJECT NUMBER
GF260
DEPARTMENT
PARKS
PROJECT NAME
SPORTS COMPLEX - CONSTRUCTION OF 'PROJECT RELATED' COTTONWOOD ROAD AREA
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
As owner of the Sports Park property, the City is required to construct a number of street, water, and sewer improvements. In
approval of the Sports Park purchase, $1,778,000 was approved in TOP Bond funding for these infrastructure improvements:
Baxter Lane, Cottonwood Road, Durston/Cottonwood Intersection, Flanders Mill Road (including ditch), and Oak Street. We
estimate that the Bond Funding will not be sufficient to cover the Cottonwood Road (or Oak Street) improvements. We
anticipate needing to build the project-related portions of the Cottonwood Road street-related improvements with Arterial
& Collector District dollars. The related water and sewer-line improvements will need to come from the General Fund. Our
original cost estimates from the Spring of 2014 have been increased by 15% to estimate construction inflation costs.
ALTERNATIVES CONSIDERED
Delay the improvements.
ADVANTAGES OF APPROVAL
Proper construction of the adjacent street, water, and sewer improvements, in concert with our development regulations. Better access and
amenities for the Sports Park.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The City's Street Maintenance Funds will maintain the street surface, once constructed. The utilities will maintain the pipes once installed.
FUNDING SOURCES
GENERAL FUND.
New
Replacement
Equipment
Project
FY21
$364,000
FY22 FY23
123
CIP Project Fund
General Fund
PROJECT NUMBER
GF262
DEPARTMENT
POLICE
PROJECT NAME
POLICE K9
FY19 FY20 Unscheduled
$19,000
DESCRIPTION OF PROJECT
Police K9 (Canine dogs) are an integral tool for police operations. The department has two trained K9teams (handler and dog) for
operations that provide assistance with drug interdiction, search ability for suspects committing crimes in buildings or helping
locate and identify suspects that have left or fled a crime-scene. A trained K9 generally has a maximum of 7-8years where the dog
is healthy and capable of serving. One of two dogs deployed is likely have reached its operational timeline by FY21, while the
remaining K9 has another 7 years+ of operational capability. This cost includes full purchase, training of the new K9
handler(officer) and shipping/transport of the K9 to Bozeman.
ALTERNATIVES CONSIDERED
Not purchasing or training a K9 dog/team is an option, but not recommended.
ADVANTAGES OF APPROVAL
Continued ability to have K9 on-duty or available to investigate and secure prosecution of criminal activity in Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The operational costs of a K9 each year are part of existing budget considerations.
FUNDING SOURCES
Other funding sources may be available as FY23 gets closer.
New
Replacement
Equipment
Project
FY21
$17,000
FY22 FY23
124
CIP Project Fund
General Fund
PROJECT NUMBER
GF263
DEPARTMENT
POLICE
PROJECT NAME
LAW & JUSTICE CENTER
FY19
$10,000,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
GF050 for City only Justice Center did not pass and the original GF263 joint City and County Justice Center did not pass. This
project is still needed and the project is being placed in the plan as options are explored.
ALTERNATIVES CONSIDERED
Non-joint project with county but other City Department joint projects could be planned
ADVANTAGES OF APPROVAL
This has been a priority since 2008 and the issues noted in the past are still present and have increased.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance of an additional building
FUNDING SOURCES
Voter approved general obligation bond and other fundig will be explored
New
Replacement
Equipment
Project
FY21
$20,000,000
FY22 FY23
125
CIP Project Fund
General Fund
PROJECT NUMBER
GF263
DEPARTMENT
I.T.
PROJECT NAME
Police Video Evidence Storage and Backup
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
We are currently generating around 1 Terabyte of data per month with the in car video systems and will be out of space for
storage in the next 12-18 months. It is critical information that grows rapidly. We are trying to get ahead of the growth by
purchasing a 5 year solution out of the gate that can be expanded as needed into the future for growth and the possibility of body
cameras. The FY 22 amount relates to the increased storage needed related to body camera files.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Will allow us to continue to safely store, access and backup crucial evidentiary data without concern of running out of storage space.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund or Grant Money
New
Replacement
Equipment
Project
FY21 FY22
$40,000
FY23
126
CIP Project Fund
General Fund
PROJECT NUMBER
GF265
DEPARTMENT
I.T.
PROJECT NAME
GENERAL FUND SERVER REPLACEMENT
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Replacement of physical servers.
ALTERNATIVES CONSIDERED
Virtualize if possible instead of buying physical servers
ADVANTAGES OF APPROVAL
Keep our server infrastructure under warranty and in good working condition for required performance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$68,000
FY22 FY23
127
CIP Project Fund
General Fund
PROJECT NUMBER
GF268
DEPARTMENT
CEMETERY
PROJECT NAME
Southwest Montana Veteran's Cemetery
FY19
$88,000
FY20
$40,000
Unscheduled
$360,000
DESCRIPTION OF PROJECT
First phase of the Southwest Montana Veteran's Cemetery which includes design, earth work, sidewalks and retaining walls to
form the 'backbone' for the Veteran group to start fundraising. Phase two potentially could be the 5500 square foot stamped
concrete plaza and phase three could be the installation of the first columbarium. Phases 2 and 3 potentially be funded with a 50%
match from the veteran's groups for the concrete and the first columbarium.
ALTERNATIVES CONSIDERED
Reduce the City's capital input and rely on the various Veteran groups for the funding.
ADVANTAGES OF APPROVAL
A true veteran's cemetery will help the veteran's realize their benefits upon their death. Currently, there are over 70,000 veterans in southwest
Montana, who upon their death, would have to be interred in Helena or Laurel to realize the benefit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Future phasing might be required, depending on the fundraising capabilities of the various veteran group in southwest Montana.
FUNDING SOURCES
50% General Fund and funds from various veteran's groups.
New
Replacement
Equipment
Project
FY21
$45,000
FY22 FY23
128
CIP Project Fund
General Fund
PROJECT NUMBER
GF270
DEPARTMENT
PARKS
PROJECT NAME
Snow Plowing Vehicle
FY19
$65,000
FY20 Unscheduled
$75,000
DESCRIPTION OF PROJECT
The eventual replacement of the 1992 MT articulating tractor, which does the bulk of the sidewalk snow removal for the Parks
Division, encompassing over 20 miles of sidewalks and four routes to plow. The newest cost saving measure is to share the cost
of a vehicle with Streets. The advantage of the co-op is that Parks needs the vehicle in the winter for plowing and Streets in the
summer for right of way mowing. The Parks and Cemetery divisions are responsible for snow removal on the majority of
sidewalks, paths, accesses and trails that the City is responsible for. The addition of Oak Spring Park, Adam Bronken sidewalk and
the Bozeman Pond expansion has necessitated moving up the request for an additional snow removal vehicle into FY19 instead of
FY20.
ALTERNATIVES CONSIDERED
Repair and maintain the 1992 MT as needed.
ADVANTAGES OF APPROVAL
Less down time and maintenance/repair costs. A new MT tractor will be able to support more implements, less emissions and better fuel
economy, faster more efficient use of time which will be a factor with the expanding sidewalk and trail snow removal routes as more parks come
on board such as Bozeman Pond expansion, sports Complex and Story Mill Community Park.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs: better fuel economy and less emissions = less maintenance and operating costs.
FUNDING SOURCES
100% General Fund for Parks but cost share with Street Maintenance District
New
Replacement
Equipment
Project
FY21 FY22 FY23
129
CIP Project Fund
General Fund
PROJECT NUMBER
GF271
DEPARTMENT
FACILITY - CH
PROJECT NAME
City Hall New Parking Lot
FY19 FY20 Unscheduled
$250,000
DESCRIPTION OF PROJECT
Convert existing lot west of City Hall into a new parking lot.
ALTERNATIVES CONSIDERED
Continue to use the underutilized lot West of City Hall as a community garden.
ADVANTAGES OF APPROVAL
Parking at City Hall is very limited due to space constraints, this has an impact on City staff, the general public, and visiting guests. Additional
parking spaces in the West lot should take pressure off of street parking around City Hall as well as allow staff to parking in the same lot. This
will free up the East side parking lot for general public during normal business hours. A new lot will also provide a safer parking environment to
the public during large meetings that take place at City Hall after hours.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General annual cost for items such as: lamp replacement, line stripping, asphalt reseal, snow removal, and landscaping.
FUNDING SOURCES
General Fund or Downtown TIF District Funding
New
Replacement
Equipment
Project
FY21 FY22 FY23
130
CIP Project Fund
General Fund
PROJECT NUMBER
GF272
DEPARTMENT
FACILITY - CH
PROJECT NAME
Site Security upgrade - Building Locks
FY19
$15,000
FY20
$15,000
Unscheduled
DESCRIPTION OF PROJECT
Currently the City has approximately 64 Trilogy keyless access locks. Of the 64 units, 18 are wireless units. The remaining 46
hardwired units require physical access with a cable & laptop to make updates for staffing access changes. This project will upgrade
the hardwire units to wireless over a period of time.
ALTERNATIVES CONSIDERED
Continue as we currently operate.
ADVANTAGES OF APPROVAL
Moving to a wireless system means all updates can be performed using the City wide network. The advantages to this system is the better
utilization of staff hours by reducing the required man hours per access update. Depending on the access level required for a staff member, it
could mean accessing 50 individual locks for a single access change.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General maintenance cost, battery change-outs.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$15,000
FY22 FY23
131
CIP Project Fund
General Fund
PROJECT NUMBER
GF275
DEPARTMENT
ECONOMIC DEVELOPMENT
PROJECT NAME
Fiber Optic Conduit and Vaults
FY19
$25,000
FY20
$25,000
Unscheduled
$25,000
DESCRIPTION OF PROJECT
Future City conduit policy will drive the future investment in city owned conduit.
ALTERNATIVES CONSIDERED
Do nothing, reduce or increase CIP investment.
ADVANTAGES OF APPROVAL
Provides funding for the purchase of fiber conduit and vaults in furtherance of a future conduit policy
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Cost of design and installation
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$25,000
FY22
$25,000
FY23
$25,000
132
CIP Project Fund
General Fund
PROJECT NUMBER
GF278
DEPARTMENT
PARKS
PROJECT NAME
Griffin at Story Mill Park road improvement - .26 mile
FY19 FY20 Unscheduled
$260,000
DESCRIPTION OF PROJECT
This represents funding the City's 1/2 portion of the East Griffin Road construction as it abuts to Story Mill Community Park.
ALTERNATIVES CONSIDERED
Construction of a woonerf type road section (or alternative park type road). More accomodating to pedestrian traffic depending on future
development by the property owners adjacent south side E Griffin.
ADVANTAGES OF APPROVAL
Safe vehiclular an dpedestrian access to municpal facilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
133
CIP Project Fund
General Fund
PROJECT NUMBER
GF279
DEPARTMENT
PARKS
PROJECT NAME
Story Mill Road Improvement - .17 mile
FY19 FY20 Unscheduled
$170,000
DESCRIPTION OF PROJECT
This represents funding the City's 1/2 portion of the Story Mill Road construction as it abuts to Story Mill Community Park.
ALTERNATIVES CONSIDERED
No alternatives considered.
ADVANTAGES OF APPROVAL
Safe vehicular and pedestrian access to municipal facilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
134
CIP Project Fund
General Fund
PROJECT NUMBER
GF281
DEPARTMENT
PARKS
PROJECT NAME
Bozeman Pond Park & Aasheim ballfields road expansion - .17 mile & .09 mile
FY19 FY20 Unscheduled
$260,000
DESCRIPTION OF PROJECT
This represents funding the City's required portion of 1/2 necessary to build Fowler Road adjacent to Bozeman Pond Park
Expansion and Aasheim ballfields.
ALTERNATIVES CONSIDERED
Waiting to acquire the ROW at the intersection of Fowler and Babcock before constructing these road sections.
ADVANTAGES OF APPROVAL
Safe vehicular and pedestrian access to municipal parks.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
135
CIP Project Fund
General Fund
PROJECT NUMBER
GF282
DEPARTMENT
City Admin/ Sustainability
PROJECT NAME
City Hall Plug-in Hybrid Electric Vehicle
FY19
$33,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Bozeman City Hall is in need of an efficient vehicle for staff to conduct daily errands and to attend local and regional meetings. As
part of City Hall’s LEED certification, the building is equipped with a 120v outlet adjacent to the west parking lot for the purpose
of charging an electric vehicle. To demonstrate our commitment to efficiency and to lead by example, we would like to
incorporate Plug-in Hybrid Electric Vehicle (PHEV) technology into our fleet. PHEVs combine a gasoline with an electric motor
and a rechargeable battery. Unlike conventional hybrids, PHEVs can be plugged-in and recharged from an outlet, allowing them to
drive extended distances using just electricity before transitioning to gasoline. PHEVs offer an exceptional range and offer
enhanced reliability by operating on either electricity or gasoline. Currently, City Hall has a Chevy Tahoe with 124,658 and gets 15
MPG compared to an estimated 133 MPGe for a PHEV and a 640 mile driving range. City Hall staff generally borrow a hybrid
vehicle from Public Works for long distance travel, however, this has become increasingly challenging as our staff grows and the
hybrids are often unavailable. The budget includes $2,000 to designate a parking space at City Hall for EV charging.
ALTERNATIVES CONSIDERED
Leasing for $300 to $380 per month for three years instead of purchasing.
ADVANTAGES OF APPROVAL
Improved operational efficiency. Most days the vehicle would operate on electricity only, but offers the flexibility to travel long distances.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Periodic tire replacements and maintenance.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
136
CIP Project Fund
General Fund
PROJECT NUMBER
GF283
DEPARTMENT
City Clerk’s Office / Informational Technology
PROJECT NAME
Commission Room Technology Upgrade
FY19
$80,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This request is to replace the majority of outdated/broken/breaking technology and structurally-related elements including but not
limited to built-in microphones, live-streaming equipment, computer display equipment, audio/amps, equipment housing, City-
responsibility audio/visual room technology/equipment, etc.
ALTERNATIVES CONSIDERED
This will require substantial in-room activity and a number of elements depend on room/dais layout, if a larger remodel of the room is planned,
this should happen concurrently.
ADVANTAGES OF APPROVAL
The Commission Room is already outdated and many elements already do not work. This will increase technological options for both meetings
and general use, as well as prevent more significant issues are larger elements inherently break over time.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No substantial operating costs, only small changes/fixes when necessary.
FUNDING SOURCES
General Fund capital?
New
Replacement
Equipment
Project
FY21 FY22 FY23
137
CIP Project Fund
General Fund
PROJECT NUMBER
GF284
DEPARTMENT
City Clerk’s Office / Informational Technology
PROJECT NAME
Laserfiche Software Upgrade
FY19 FY20
$57,000
Unscheduled
$28,000
DESCRIPTION OF PROJECT
The FY19 request is to replace the majority of outdated/broken/breaking technology and structural-related elements including but
not limited to built-in microphones, live-streaming equipment, computer display equipment, audio/amps, equipment housing, City-
responsibility audio/visual room technology/equipment, etc. | The FY20 request is an upgrade to Laserfiche Avante, which is
needed to bring our digital records software to a more recent version, as well as incorporate in functionality including workflow
and forms, which can increase efficiencies across departments. The following years request is the estimated annual fee for the
software.
ALTERNATIVES CONSIDERED
The FY19 Commission Room technology upgrade will require substantial in-room activity and a number of elements depend on room/dais
layout, if a larger remodel of the room is planned, this should happen concurrently. | The FY20 Laserfiche upgrade could potentially happen a
year prior or later, depending on workload and City priorities and staff resources. A number of departments are anxious for the increased use
of the product.
ADVANTAGES OF APPROVAL
Regarding the FY19 tech upgrade, the Commission Room is already outdated and many elements already do not work. This will increase
technological options for both meetings and general use, as well as prevent more significant issues are larger elements inherently break over
time. | The FY20+ Laserfiche upgrade is a needed improvement, and while it will be a process to bring departments on board, it will both
increase staff efficiencies in record management (across all departments) but also citizen ease of access for public information.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No substantial operating costs for the FY19 Commission Room upgrade, only small changes/fixes when necessary. | The FY20+ Laserfiche
upgrade will require an annual software fee, estimated at $28,000 (incorporated in the above schedule).
FUNDING SOURCES
General Fund capital
New
Replacement
Equipment
Project
FY21
$28,000
FY22
$28,000
FY23
$28,000
138
CIP Project Fund
General Fund
PROJECT NUMBER
GF285
DEPARTMENT
Facilities/Library
PROJECT NAME
Library Exterior Door Operators/Closures Replacement
FY19
$12,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The automatic door operators at the library have been in operation for over ten years, due to the heavy traffic load on these door
they are showing wear. Issues with the operators can impact ADA performance and also not close fully when seals are in place.
Normal door closure will also be replaced at the same time.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increases the reliability of the building system
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$1200 per year, preventative maintenance cost General Fund
FUNDING SOURCES
Library has stated they have funds in Library depreciation fund that can be used for this project
New
Replacement
Equipment
Project
FY21 FY22 FY23
139
CIP Project Fund
General Fund
PROJECT NUMBER
GF287
DEPARTMENT
Human Resources
PROJECT NAME
Learning Management System
FY19
$25,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Enterprise solution for housing and administering employee training
ALTERNATIVES CONSIDERED
none
ADVANTAGES OF APPROVAL
Efficient and manageable training for employees in a variety of formats, improved training records
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$5,000 annual maintenance estimate
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
140
CIP Project Fund
General Fund
PROJECT NUMBER
GF288
DEPARTMENT
Human Resources
PROJECT NAME
Applicant Tracking System
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
System to electronically manage the recruitment process – from application to hire.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increased efficiency, accuracy, and applicant experience
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$5,000 estimate
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$30,000
FY22 FY23
141
CIP Project Fund
General Fund
PROJECT NUMBER
GF289
DEPARTMENT
I.T.
PROJECT NAME
Server Farm Software Upgrades
FY19 FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
Upgrading our VM farm and SQL Cluster to the newest versions for current and future compatibility
ALTERNATIVES CONSIDERED
Stay on our current versions until forced to upgrade
ADVANTAGES OF APPROVAL
Will keep the City current with supported versions of the operating systems and will allow us to support software that requires the newer
versions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund-Perhaps some enterprise funds to cover their use.
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$25,000
FY23
$25,000
142
CIP Project Fund
General Fund
PROJECT NUMBER
GF290
DEPARTMENT
Parks
PROJECT NAME
Irrigation System Replacements
FY19 FY20 Unscheduled
$425,000
DESCRIPTION OF PROJECT
Replacement of irrigation systems that are past their life cycle estimates. 40 years is the average life cycle of an irrigation system.
ALTERNATIVES CONSIDERED
Not replace the systems and fix on an “as needed” basis.
ADVANTAGES OF APPROVAL
Efficient water use, lower repair costs, compatibility with the new Centralized systems. Potentially coincide with transitioning the Softball
Complex and Lindley Park off of treated water (Complex) and on to surface water.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
143
CIP Project Fund
General Fund
PROJECT NUMBER
GF291
DEPARTMENT
Parks
PROJECT NAME
Pickleball Courts
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Install Pickleball courts in one of our city parks. One potential site would be Bogert Park Tennis Courts.
ALTERNATIVES CONSIDERED
Do not install Pickleball courts and continue to utilize Southside tennis courts.
ADVANTAGES OF APPROVAL
Separate the increasing number of Pickleball players from the tennis players. Dedicated space for a fast growing sport
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Resurfacing or re-painting in future years.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$90,000
FY22 FY23
144
CIP Project Fund
General Fund
PROJECT NUMBER
GF292
DEPARTMENT
POLICE
PROJECT NAME
PATROL CAR AUXILIARY EQUIPMENT
FY19
$15,000
FY20
$10,000
Unscheduled
$10,000
DESCRIPTION OF PROJECT
Within a patrol car is a significant amount of technology related auxiliary equipment. This includes a radar unit, Arbitrator Video
Recorder, Electronic ticketing printer, Mobile Data Computer amongst other items. Most of these items are part of a normal
replacement schedule as new patrol vehicles are purchased and old patrol vehicles retired. However, we are finding the need to
address several areas in this category separate from this rotation schedule. First, in FY19, we need to replace all electronic
ticketing printers, which were installed over 5 years ago, with full sized printers. This will allow for integration with our new
Records management system and will allow for the printing of tickets in the field that are easier to read, printing of forms or
“Marsy rights” notifications, etc… Secondly, we are finding that a Mobile Data Computer needs replacement about every 5 years,
and many of our vehicles are rotated at 6 or 7 years, meaning some additional MDC will be needed beyond what is part of a
vehicle rotation. And 3rd, we will be moving to a more portable MDC and docking stations over a 5 year period that makes the
ability for an officer to use the MDC outside of the vehicle, on calls and bringing it into buildings or our station to complete
reports. This direction will also lead to less desktop computers being purchased and increase officer efficiency.
ALTERNATIVES CONSIDERED
Alternatives are to continue to use existing MDC
ADVANTAGES OF APPROVAL
Less costs for desktop computers, less duplication of maintenance, more efficiency for officers, meaning officers more available for emergency
call response.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
$15,000
145
CIP Project Fund
General Fund
PROJECT NUMBER
GF293
DEPARTMENT
POLICE
PROJECT NAME
NON-PATROL CAR NEW VEHICLES
FY19 FY20
$15,000
Unscheduled
DESCRIPTION OF PROJECT
In FY20 and FY22 we anticipate adding two School Resource Officer Positions to cover the new Bozeman High School and
increased demand for police services at all schools.
ALTERNATIVES CONSIDERED
Alternatives may include use of older patrol cars that can’t be used for patrol response, or the use of existing marked units which will add
mileage to those vehicles and effect that rotation schedule.
ADVANTAGES OF APPROVAL
These vehicles tend to be used for more than 10 years and provide SRO ability to respond to the schools, other emergency and on-call
response after hours.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22
$15,000
FY23
146
CIP Project Fund
General Fund
PROJECT NUMBER
GF294
DEPARTMENT
POLICE
PROJECT NAME
PATROL CAR - ADDITIONAL
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
A review of mileage and estimated staffing increases in patrol by 2-3 officers over the next few years has also led to the identified
need for an additional patrol vehicle in FY21. This won’t replace a vehicle and brings the total patrol response vehicles to 23 (1
unmarked / 2 K9 vehicles / 20 fully marked)
ALTERNATIVES CONSIDERED
Continue patrol response with existing patrol cars, resulting in higher mileage/annum for each vehicle and difficulty at times to have sufficient
vehicles available for # of officers hired and deployed by FY21+)
ADVANTAGES OF APPROVAL
This is an essential vehicle for safe and reliable emergency response vehicles for patrol use, as well as projected lower annual maintenance costs.
This additional vehicle provides sufficient marked patrol cars for 24/7 response.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$64,000
FY22 FY23
147
CIP Project Fund
General Fund
PROJECT NUMBER
GF295
DEPARTMENT
Recreation
PROJECT NAME
SWIM CENTER UV SYSTEM REPLACEMENT
FY19
$68,500
FY20 Unscheduled
DESCRIPTION OF PROJECT
A functioning UV system is critical when dealing with the high bather load that the swim center accommodates. The UV system
was installed in 2010. We are in line for a replacement considering the environment the electrical components are exposed to. If
we were able to construct a wall between the humid, corrosive environment and our electronics it is estimated that a UV unit
would last twice that long. Annually we are spending approximately four times the amount in repairs and maintenance compared
to units that are stored separately from an open water source and units that are more advanced since this unit was put it. The
Swim Center currently has such a high bather load that when the UV goes out in the winter months it is difficult and sometimes
impossible to keep our combined chlorine levels within the range outlined by the MT Health Code. It is a safety issue for the
swimmers. Parts for this unit are not readily available. Control panels have a 6 week lead time to be replaced and the electrical
components have to be shipped from Germany.
ALTERNATIVES CONSIDERED
Do not replace the current system.
ADVANTAGES OF APPROVAL
In addition to maintaining air quality, UV systems act as a secondary disinfectant to the chlorine, making the water cleaner and safer for
swimmers. A modern UV unit would be more energy efficient, and it would be easier to obtain parts for since UV systems are now standard
practice for pool sanitization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
148
CIP Project Fund
General Fund
PROJECT NUMBER
GF296
DEPARTMENT
Recreation
PROJECT NAME
SWIM CENTER – FRONT FURNACE REPLACEMENT
FY19 FY20
$36,000
Unscheduled
DESCRIPTION OF PROJECT
The front furnace supplies air to the lobby, locker rooms, and lifeguard room. The unit is deteriorating due to the humid
environment. Getting parts for the furnace is becoming increasingly difficult due to its age. The unit would be replaced with a unit
which are designed for aquatic environments or be placed outside. The current unit was installed in 2008.
ALTERNATIVES CONSIDERED
Continue to repair the unit.
ADVANTAGES OF APPROVAL
Replacing the current unit would cut down on costs to repair and service the unit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
149
CIP Project Fund
General Fund
PROJECT NUMBER
GF297
DEPARTMENT
RECREATION
PROJECT NAME
SWIM CENTER ROOF REPLACEMENT
FY19
$26,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The roof over the locker rooms/lobby area needs to be reroofed. The recommendation it to remove the existing Hypalon roof
membrane and Gypsum cover board. Replace any damaged insulation. Attach ½ inch layer of HD Polylso cover board on top of
the existing poly roof insulation on the entire surface that is being reroofed. Install a fully adhered Firestone 60 mil EPDM roof
system. Flash all walls, pipes, and penetrations with Firestone flashing material. Install new prefinished metal drip edge on the
outer perimeter and seal with a 5” flashing membrane.
ALTERNATIVES CONSIDERED
Do not replace the roof.
ADVANTAGES OF APPROVAL
Fix the roof before it becomes problematic.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
150
CIP Project Fund
General Fund
PROJECT NUMBER
GF298
DEPARTMENT
Recreation
PROJECT NAME
SWIM CENTER – BARRIER WALL IN PUMP ROOM
FY19
$22,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The pump room at the swim center contains an open filtration pit. The pump room also houses all of the equipment necessary to
operate the pool. The constant exposure to the chlorine and humidity from the open pit leads to accelerated deterioration of the
electrical and mechanical components on the boilers, UV system and programmable logic controller.
ALTERNATIVES CONSIDERED
Do not build the wall.
ADVANTAGES OF APPROVAL
Thousands of dollars are spent each year replacing parts due to rust and corrosion. It has been recommended to us by those who service our
equipment to build a barrier between the open water source and our equipment in order to help extend the life of the equipment and cut down
on money spent on parts and service.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund.
New
Replacement
Equipment
Project
FY21 FY22 FY23
151
CIP Project Fund
General Fund
PROJECT NUMBER
GF299
DEPARTMENT
RECREATION
PROJECT NAME
Vehicle Replacement
FY19 FY20
$30,000
Unscheduled
DESCRIPTION OF PROJECT
Replacement of a 1989 truck with a more dependable vehicle for Recreation Division staff.
ALTERNATIVES CONSIDERED
Not replacing the 1989 truck
ADVANTAGES OF APPROVAL
Having a reliable and safer vehicle for Recreation Division staff to utilize.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
152
CIP Project Fund
General Fund
PROJECT NUMBER
GF300
DEPARTMENT
RECREATION
PROJECT NAME
Story Mill Community Center gymnasium floor replacement
FY19 FY20 Unscheduled
$110,000
DESCRIPTION OF PROJECT
Replacing the existing gymnasium floor with a wood floor that is more durable and conducive to multiple uses.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The current floor is made of brightly colored plastic tiles that include a large Boys and Girls Club logo in the middle. The former Boys and Girls
Club was used primarily for youth programs. The Story Mill Community Center will be home to Parks and Recreation Department programs for
people of all ages, large special events, and will also be utilized by community groups for sports leagues and events. There will be a significant
increase in use of the space and existing floor is not conducive to many of those uses, including pickleball, one of our most popular adult
programs. A wood gymnasium floor is the most durable and long lasting option.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Refinishing when needed
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
153
CIP Project Fund
General Fund
PROJECT NUMBER
GF301
DEPARTMENT
RECREATION
PROJECT NAME
Story Mansion Exterior Paint
FY19 FY20 Unscheduled
$50,000
DESCRIPTION OF PROJECT
Repainting the exterior of the Story Mansion
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The exterior paint at the Story Mansion has started to fade and peel. As this continues, we risk compromising the siding which could need
replacement due to damage and would be a significantly more expensive project.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Repainting as needed
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
154
CIP Project Fund
General Fund
PROJECT NUMBER
GF302
DEPARTMENT
RECREATION
PROJECT NAME
Passenger Van
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The purchase of a 12-15 passenger van for Parks and Recreation Department programs as well as other city departments use as
needed.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Our current passenger van can accommodate 13 children and 2 staff when used for programs. The majority of our programs have a max
capacity of 20 or more, which means multiple trips and additional staff support is required when transporting participants, or a lower max
number put on the program. Another van would better meet current needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine Maintenance
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$35,000
FY22 FY23
155
CIP Project Fund
General Fund
PROJECT NUMBER
GF303
DEPARTMENT
FACILITY - CH
PROJECT NAME
City Hall Expansion Remodel of Storage areas into Offices
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
With the additional planned FTE as the City grows City Hall's current storage areas can be remodeled into office spaces. The
space could potentially provide 2-3 offices spaces downstairs.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Any additional FTE in any of the Department in City Hall do not currently have space. This would provide space that is permenant.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine Maintenance and cleaning.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$25,000
FY22 FY23
156
CIP Project Fund
General Fund
PROJECT NUMBER
GF304
DEPARTMENT
FACILITY - CH
PROJECT NAME
City Hall Commission Room Expansion/Remodel
FY19
$300,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This will address security issues and provide an additional meeting room.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases safety and provides the needed additional meeting room.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine Maintenance and cleaning.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
157
CIP Project Fund
General Fund
PROJECT NUMBER
GF305
DEPARTMENT
Fire
PROJECT NAME
Fire Station 2
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Fire Station 2, located at 410 S. 19th Ave, is a 1-story building that was constructed in 1974 to serve as the West end fire station
for the City of Bozeman. Due to growth of the city, this station now primarily serves what is the South side and Central parts of
the city. The station serves as the primary response station for all areas west of N. 7th Ave to the City limits that are South of
Durston Ave. This station is the primary response station for all of MSU campus and Bozeman High School and is the secondary
response to areas in the downtown core. General maintenance and repairs have been the majority of work completed on this
station since it’s opening. The department has continued to deal with a sewage problem on a reoccurring basis where the sewage
backs up into the living area of the station. Multiple plans have been implemented to addressed this but to date the problem still
occurs. Size and location are two factors that impede the service delivery of this station. Based on it’s location in relation to
campus and the downtown core this is the station where the fire department ladder truck should be housed, however the station
is too small to accommodate the ladder truck. In terms of location when station 2 was built N. 19th was a two lane road whereas
today it is a 4 lane major thoroughfare for the city. Leaving from and returning to the fire station can be an extremely difficult task
for fire crews during peak traffic hours. In September 2017 the Fire Master Plan update was presented with the
recommendation to relocate Fire Station 2 somewhere on MSU campus to improve response capabilities. This would require a
partnership with MSU but could have multiple benefits from an emergency planning standpoint. If a plan were to be developed
that relocated Fire Station 2 to MSU campus additional funds and planning should be evaluated for relocating the fire department
training facility to the same site, an additional recommendation from the recent Fire Master Plan.
ALTERNATIVES CONSIDERED
As recommended by Commission
ADVANTAGES OF APPROVAL
Addresses health and safety, space, and long term needs of fire station 2 for the next 25-30 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General operating cost which are currently budgeted in the fire department general fund budget.
FUNDING SOURCES
TBD
New
Replacement
Equipment
Project
FY21 FY22 FY23
$4,500,000
158
CIP Project Fund
General Fund
PROJECT NUMBER
GF306
DEPARTMENT
Fire
PROJECT NAME
Fire Station 1
FY19 FY20
$6,500,000
Unscheduled
DESCRIPTION OF PROJECT
Fire Station 1, located at 34 N. Rouse Ave, is a 2-story building with an ancillary fire tower attached to the building that was
constructed in 1965 to serve as the downtown fire station for the City of Bozeman as well as the administrative offices for the
Fire Department. The station serves as the primary response station for all areas east of N. 7th Ave to the City limits and is the
secondary response to areas primarily east of 19th Ave included all of MSU campus. Since its opening the station has been a
shared facility between police and fire with the police presences fluctuating over that period of time. Today the station houses
the support services functions of BPD which is comprised of a staff of 5 personnel and 1 Administrative Assistant. The station
also serves as an East annex for patrol officers who need to access a computer, paperwork, or restroom. A remodel was done in
1996 on the main level portions of the building currently used by the Police Department which added some exterior windows and
moved some of the interior walls. An addition to North Side of Fire Station 1 was completed in 2003, adding an additional office,
locker space for firefighter’s personal protective equipment, and a clean room were members could decontaminate themselves
and their equipment after returning from an emergency call. In 2011 a Heating Plan Replacement Assessment was conducted by
CTA Architects & Engineers to assess three different heating plant replacement options. The following is from the executive
summary of the report, the entire report can be found in Appendix A of this report. “The existing heating plant contains the
original steam boiler that currently serves the existing fire station. The boiler’s chemical treatment history has been erratic at
best. Consequently the boiler and steam piping has corroded severely over time and its overall condition can be considered as
poor. The boiler was originally sized to serve the fire station and the adjacent old City Hall building which included an intended
future addition. In 2010 the connection of the steam system to the old city hall was severed as a result of the building being sold.
With the extreme reduction of the steam load the existing steam boiler has experienced severe cycling. The continued short
cycling will inevitably lead to boiler failure”. To date now action has been taken on this study.In 2012 the Bozeman Facilities
Department partnered with Bechtle Architects to conduct a facilities condition inventory, Appendix B. In this report the
ALTERNATIVES CONSIDERED
As recommended by Commission
ADVANTAGES OF APPROVAL
Addresses structural, mechanically, health and safety, and space needs of fire station 1 for the next 25-30 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General operating cost which are currently budgeting in the fire department general fund budget.
FUNDING SOURCES
TBD
New
Replacement
Equipment
Project
FY21 FY22 FY23
159
CIP Project Fund
General Fund
PROJECT NUMBER
PW05/06
DEPARTMENT
Parks and Facility Portion
PROJECT NAME
Public Works Shops Facility Plan and Construction
FY19
$10,000
FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
Develop a long term master plan for Public Works shop facilities, equipment, and personnel. This includes conducting a needs
assessment of space for existing and future employees, equipment, machinery, and rolling stock. There is a severe shortage of
enclosed storage for equipment, vehicles, and machinery, resulting in extra wear and tear, additional maintenance costs, and time
preparing the equipment on cold mornings.
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
Provide an accurate analysis of the City of Bozeman Public Works space needs for both equipment as well as people.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Depending on the results of the plan, the likely result will be the construction of additional storage and office space.
FUNDING SOURCES
his project will be split 3 ways between Water Fund ($20,000), Wastewater Fund ($20,000), and Street Maintenance Fund ($20,000). With a
portion from the General Fund for Parks and Facility vehicle uses.
New
Replacement
Equipment
Project
FY21 FY22 FY23
160
Police Vehicle Details
Project
Number
Current
Mileage
Asset #Make FY19 FY20 Unscheduled NotesFY21FY22FY23
GF052 126,0003138Detective Vehicle -$15,000 $20,000 Mileage Oct16
116,0003274General Use Vehic $0 Mileage Oct16
41,0003480General Use Vehic $0 Mileage Oct16
136,0003230General Use Vehic $0 Mileage Oct16
41,0003680Detective Vehicle $15,000 Mileage Oct16
68,0003680Captain Vehicle – $15,000 Mileage Oct16
62,0003445Deputy Chief Vehi $15,000 Mileage Oct16
70,0003368Detective Vehicle $15,000 Mileage Oct16
63,0003384Detective Vehicle $15,000 Mileage Oct16
59,0003383Detective Vehicle $15,000 Mileage Oct16
51,0003678Detective Vehicle $15,000 Mileage Oct16
45,0003381Detective Vehicle $15,000 Mileage Oct16
45,0003971Detective Vehicle $15,000 Mileage Oct16
41,0003680Detective Vehicle $15,000 Mileage Oct16
40,0003679Detective Vehicle $15,000 Mileage Oct16
40,0003739Detective Vehicle $15,000 Mileage Oct16
45,0003677Detective Vehicle -$15,000 Mileage Oct16
47,0003681Community Resou $20,000 Mileage Oct16
88,0003374Code Compliance $20,000 Mileage Oct16
100,0003976Evidence Vehicle -$20,000 Mileage Oct16
69,0003438Chief Vehicle – 08 $20,000 Mileage Oct16$15,000
69,0003443Captain Vehicle – $20,000 Mileage Oct16$15,000
28,0003790Animal Control Of $45,000 Mileage Oct16
4,0004042Crash Investigatio $62,000 Mileage Oct16
79,0003140Captain Vehicle - $20,000 Mileage Oct16$15,000
94,0003382Detective Vehicle -$20,000 Mileage Oct16$15,000161
Project
Number
Current
Mileage
Asset #Make FY19 FY20 Unscheduled NotesFY21FY22FY23
GF053 85,0003627Marked Patrol Ve $62,000 Mileage Oct 16
78,0003499Marked Patrol Ve $63,000 Mileage Oct 16
74,0003630Marked Patrol Ve $62,000 $63,000 Mileage Oct 16
73,0003595Marked Patrol Ve $62,000 $63,000 Mileage Oct 16
100,0003590Marked Patrol Ve $62,000 Mileage Oct 16
57,0003699Marked Patrol Ve $63,000 Mileage Oct 16$65,000
63,0003698Marked Patrol Ve $63,000 Mileage Oct 16$64,000
70,0003628Marked Patrol Ve $63,000 Mileage Oct 16$64,000
24,0004037Marked Patrol Ve $67,000 Mileage Oct 16
36,0003740Marked Patrol Ve $67,000 Mileage Oct 16
23,0004038Marked Patrol Ve $67,000 Mileage Oct 16
18,0004039Marked Patrol Ve $67,000 Mileage Oct 16
3,0004040Marked Patrol Ve $67,000 Mileage Oct16
1,0004041Marked Patrol Ve $67,000 Mileage Oct16
34,0003741Marked Patrol Ve $67,000 Mileage Oct 16
52,0003631Marked Patrol Ve $72,000 Mileage Oct 16
49,0003661Marked Patrol Ve Mileage Oct 16$65,000
47,0003697Marked Patrol Ve Mileage Oct 16$65,000.00 $66,000
42,0003660Marked Patrol Ve $72,000 Mileage Oct 16$65,000.00
56,0003695Marked Patrol Ve Mileage Oct 16$64,000 $66,000
43,0003742Marked Patrol Ve $67,000 Mileage Oct 16$64,000
55,0003659Marked Patrol Ve Mileage Oct 16$64,000 $65,000
GF165 22,000311202 Harley Davidso $30,000 Mileage Oct16
5,000374415 Harley Davidso $30,000 Mileage Oct16
18,000311102 Harley Davidso Mileage Oct16 – Trai$20,000.00
$263,000 $378,000 $335,000 $360,000 $1,202,000Totals$162,000
162
Li
b
r
a
r
y
D
e
p
r
e
c
i
a
t
i
o
n
R
e
s
e
r
v
e
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
3
5
2
,
5
0
3
$
2
7
0
,
8
6
0
$
2
7
8
,
3
6
8
$
8
8
,
6
6
6
$
5
4
,
7
7
0
$
9
6
,
6
9
6
$
P
l
u
s
:
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
U
n
s
p
e
n
t
A
p
p
r
o
p
r
i
a
t
i
o
n
s
38
,
3
5
7
$
39
,
5
0
8
$
40
,
2
9
8
$
41
,
1
0
4
$
41,926
$
42,765 $ ‐$
L
e
s
s
:
C
a
r
r
y
o
v
e
r
F
Y
1
7
C
a
p
i
t
a
l
P
r
o
j
e
c
t
s
(5
0
,
0
0
0
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(7
0
,
0
0
0
)
$
(3
2
,
0
0
0
)
$
(2
3
0
,
0
0
0
)
$
(7
5
,
0
0
0
)
$
‐ $ ‐ $ ‐$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
27
0
,
8
6
0
$
27
8
,
3
6
8
$
88
,
6
6
6
$
54
,
7
7
0
$
96,696
$
139,461 $
A ss
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
:
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
L
i
b
r
a
r
y
B
u
d
g
e
t
2,
0
1
8
,
8
0
0
$
2,
0
7
9
,
3
6
4
$
2,
1
2
0
,
9
5
1
$
2,
1
6
3
,
3
7
0
$
2,
2
0
6
,
6
3
8
$
2,250,770 $
Es
t
i
m
a
t
e
d
A
m
o
u
n
t
o
f
B
u
d
g
e
t
l
e
f
t
U
n
u
s
e
d
1.
9
%
1.
9
%
1.
9
%
1.
9
%
1.9%1.9%
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
U
n
s
p
e
n
t
A
p
p
r
o
p
r
i
a
t
i
o
n
s
38
,
3
5
7
$
39
,
5
0
8
$
40
,
2
9
8
$
41
,
1
0
4
$
41,926
$
42,765 $
Cu
r
r
e
n
t
B
u
d
g
e
t
A
m
o
u
n
t
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
s
%
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.0%0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
38
,
3
5
7
$
3
9
,
5
0
8
$
4
0
,
2
9
8
$
4
1
,
1
0
4
$
4
1
,
9
2
6
$
4
2
,
7
6
5
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
3
2
,
0
0
0
)
$
(
2
3
0
,
0
0
0
)
$
(
7
5
,
0
0
0
)
$
‐
$
‐
$
‐
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
LI
B
R
A
R
Y
D
E
P
R
E
C
I
A
T
I
O
N
F
U
N
D
P
R
O
J
E
C
T
S
&
E
Q
U
I
P
M
E
N
T
16
3
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Li
b
r
a
r
y
De
p
r
e
c
i
a
t
i
o
n
Re
s
e
r
v
e
LI
B
2
2
LI
B
R
A
R
Y
NE
W
C
A
R
P
E
T
F
O
R
T
H
E
P
U
B
L
I
C
A
R
E
A
O
F
TH
E
L
I
B
R
A
R
Y
.
$2
3
0
,
0
0
0
LI
B
2
3
LI
B
R
A
R
Y
1
C
O
L
O
R
C
O
P
I
E
R
$1
0
,
0
0
0
LI
B
2
5
LI
B
R
A
R
Y
AU
T
O
M
A
T
E
D
B
L
I
N
D
S
,
1
S
T
F
L
O
O
R
WI
N
D
O
W
S
$2
2
,
0
0
0
LI
B
2
6
LI
B
R
A
R
Y
MA
T
E
R
I
A
L
S
C
O
N
V
E
Y
O
R
S
Y
S
T
E
M
F
O
R
CI
R
C
U
L
A
T
I
O
N
D
E
P
A
R
T
M
E
N
T
$7
5
,
0
0
0
$3
2
,
0
0
0
$2
3
0
,
0
0
0
$7
5
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
L
i
b
r
a
r
y
D
e
p
r
e
c
i
a
t
i
o
n
R
e
s
e
r
v
e
(
4
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$3
2
,
0
0
0
$2
3
0
,
0
0
0
FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$7
5
,
0
0
0
FY
2
1
16
4
CIP Project Fund
Library Depreciation Reserve
PROJECT NUMBER
LIB22
DEPARTMENT
LIBRARY
PROJECT NAME
New carpet for the public area of the Library.
FY19 FY20
$230,000
Unscheduled
DESCRIPTION OF PROJECT
Replace worn carpeting in Library on both floors, in public areas.
ALTERNATIVES CONSIDERED
Library patrons and staff will continue to walk on worn carpet.
ADVANTAGES OF APPROVAL
The 10-yr. old carpet is beginning to show a great deal of wear from the 1000-1500 people a day who come through the library. It will have to
be replace at some point for both aesthetic reasons and as a safety precaution.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Library Depreciation Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
165
CIP Project Fund
Library Depreciation Reserve
PROJECT NUMBER
LIB23
DEPARTMENT
LIBRARY
PROJECT NAME
1 Color copier
FY19
$10,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Obtain a new small color copier
ALTERNATIVES CONSIDERED
Place a small color copier in the Children's Department and replace the aging black & white printer in the staff workroom until it quits.
Continue to provide only black & white copies to public in Children’s; use the existing black & white printer in the staff workroom until it quits.
According to the service rep, we will not be able to get parts for the machine after the next year.
ADVANTAGES OF APPROVAL
Patrons of the Children’s department have asked for color printing for some time and will be pleased to have this service.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Library Depreciation Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
166
CIP Project Fund
Library Depreciation Reserve
PROJECT NUMBER
LIB25
DEPARTMENT
LIBRARY
PROJECT NAME
Automated Blinds, 1st floor windows
FY19
$22,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace the automated window blinds on the 1st floor windows in the Library. They are ten years old and are malfunctioning on
a regular basis.
ALTERNATIVES CONSIDERED
Leave the existing ones in place.
ADVANTAGES OF APPROVAL
We will not have broken, non-functional blinds in the windows facing our beautiful Library grounds and Lindley Park.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Library Depreciation Reserve Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
167
CIP Project Fund
Library Depreciation Reserve
PROJECT NUMBER
LIB26
DEPARTMENT
LIBRARY
PROJECT NAME
Materials conveyor system for Circulation Department
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Automated conveyor system for returned books and materials will pre-sort materials for staff and save on staff time
ALTERNATIVES CONSIDERED
Continue to handle returned materials manually
ADVANTAGES OF APPROVAL
Greater efficiency in circulation department, save staff time
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Library Depreciation Reserve Fund
New
Replacement
Equipment
Project
FY21
$75,000
FY22 FY23
168
Pa
r
k
i
n
g
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
71
0
,
7
0
2
$
32
3
,
3
7
3
$
64
2
,
6
9
7
$
7
0
1
,
7
7
1
$
6
7
5
,
7
9
8
$
4
9
7
,
6
8
4
$
Pl
u
s
:
P
a
r
k
i
n
g
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
43
,
8
3
5
$
4
6
,
0
2
7
$
4
8
,
3
2
9
$
5
0
,
7
4
5
$
5
3
,
2
8
2
$
5
5
,
9
4
6
$
C
a
s
h
I
n
L
i
e
u
o
f
P
a
r
k
i
n
g
P
l
u
s
:
P
a
r
k
i
n
g
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
4
3
,
8
3
5
$
4
8
,
3
2
9
$
5
0
,
7
4
5
$
5
3
,
2
8
2
$
5
3
,
6
0
4
$
5
3
,
6
0
4
$
‐$
P
l
u
s
:
D
o
w
n
t
o
w
n
T
I
F
I
n
t
e
r
e
s
t
C
o
n
t
r
i
b
u
t
i
o
n
10
,
0
0
0
$
1
0
,
0
0
0
$
1
0
,
0
0
0
$
1
0
,
0
0
0
$
1
0
,
0
0
0
$
1
0
,
0
0
0
$
P
l
u
s
:
T
I
F
C
o
n
t
r
i
b
u
t
i
o
n
f
o
r
p
a
r
k
i
n
g
l
o
t
r
e
d
e
s
i
g
n
a
n
d
i
m
p
r
o
v
.
2
5
0
,
0
0
0
$
3
0
0
,
0
0
0
$
2
8
0
,
0
0
0
$
1
7
0
,
0
0
0
$
‐
$
‐ $
P
l
u
s
:
G
r
a
n
t
f
u
n
d
i
n
g
f
o
r
P
0
2
4
27
,
0
0
0
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
C
o
s
t
s
(
a
d
j
u
s
t
e
d
)
(7
3
5
,
0
0
0
)
$
(1
1
2
,
0
3
1
)
$
(3
3
0
,
0
0
0
)
$
(3
1
0
,
0
0
0
)
$
(2
9
5
,
0
0
0
)
$
(30,000)
$
(1,900,000)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
32
3
,
3
7
3
$
64
2
,
6
9
7
$
70
1
,
7
7
1
$
67
5
,
7
9
8
$
49
7
,
6
8
4
$
587,235
$
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
:
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
P
a
r
k
i
n
g
F
u
n
d
R
e
v
e
n
u
e
s
73
0
,
5
9
0
$
7
3
0
,
5
9
0
$
7
6
7
,
1
2
0
$
8
0
5
,
4
7
5
$
8
4
5
,
7
4
9
$
8
8
8
,
0
3
7
$
E
s
t
i
m
a
t
e
d
G
r
o
w
t
h
i
n
R
e
v
e
n
u
e
s
0%
5%
5%
5%
5%
5%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
73
0
,
5
9
0
$
7
6
7
,
1
2
0
$
8
0
5
,
4
7
5
$
8
4
5
,
7
4
9
$
8
8
8
,
0
3
7
$
9
3
2
,
4
3
9
$
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
0.
0
%
6.
0
%
6.
0
%
6.
0
%
6
.
0
%
6
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
s
%
6.
0
%
0.
0
%
0.
0
%
0.
0
%
0
.
0
%
0
.
0
%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
6.
0
%
6.
0
%
6.
0
%
6.
0
%
6
.
0
%
6
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
43
,
8
3
5
$
4
6
,
0
2
7
$
4
8
,
3
2
9
$
5
0
,
7
4
5
$
5
3
,
2
8
2
$
5
5
,
9
4
6
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
1
1
2
,
0
3
1
)
$
(
3
3
0
,
0
0
0
)
$
(
3
1
0
,
0
0
0
)
$
(
2
9
5
,
0
0
0
)
$
(
3
0
,
0
0
0
)
$
(
1
,
9
0
0
,
0
0
0
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
PA
R
K
I
N
G
F
U
N
D
C
A
P
I
T
A
L
P
R
O
J
E
C
T
S
16
9
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Pa
r
k
i
n
g
F
u
n
d
GF
1
9
9
PA
R
K
I
N
G
PR
O
F
E
S
S
I
O
N
A
L
B
U
I
L
D
I
N
G
RE
C
O
N
F
I
G
U
R
A
T
I
O
N
-
P
H
A
S
E
2
$3
7
,
0
3
1
P0
0
1
PA
R
K
I
N
G
WI
L
L
S
O
N
L
O
T
R
E
D
E
S
I
G
N
$3
0
0
,
0
0
0
P0
0
4
PA
R
K
I
N
G
SU
R
F
A
C
E
P
A
R
K
I
N
G
L
O
T
H
A
R
D
W
A
R
E
&
SO
F
T
W
A
R
E
S
Y
S
T
E
M
S
$15,000
$1
5
,
0
0
0
$1
5
,
0
0
0
$1
5
,
0
0
0
$1
5
,
0
0
0
P0
1
2
PA
R
K
I
N
G
AR
M
O
R
Y
L
O
T
R
E
D
E
S
I
G
N
A
N
D
IM
P
R
O
V
E
M
E
N
T
S
$2
5
0
,
0
0
0
P0
1
4
PA
R
K
I
N
G
PA
R
K
I
N
G
G
A
R
A
G
E
C
R
A
C
K
M
A
I
N
T
E
N
A
N
C
E
AN
D
R
E
P
A
I
R
$5,000
$2
0
,
0
0
0
$5
,
0
0
0
$5
,
0
0
0
$2
0
,
0
0
0
P0
1
5
PA
R
K
I
N
G
PA
R
K
I
N
G
G
A
R
A
G
E
R
O
O
F
P
R
O
J
E
C
T
$400,000
P0
1
6
PA
R
K
I
N
G
PU
R
C
H
A
S
E
O
F
P
R
O
P
E
R
T
Y
F
O
R
F
U
T
U
R
E
PA
R
K
I
N
G
F
A
C
I
L
I
T
I
E
S
I
N
T
H
E
D
O
W
N
T
O
W
N
PA
R
K
I
N
G
D
I
S
T
R
I
C
T
.
$1,500,000
P0
1
7
PA
R
K
I
N
G
RO
U
S
E
P
A
R
K
I
N
G
L
O
T
R
E
-
D
E
S
I
G
N
A
N
D
IM
P
R
O
V
E
M
E
N
T
S
$2
8
0
,
0
0
0
P0
2
0
PA
R
K
I
N
G
PA
R
K
I
N
G
V
E
H
I
C
L
E
L
E
A
S
E
S
$10,000
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
P0
2
4
PA
R
K
I
N
G
EL
E
C
T
R
I
C
V
E
H
I
C
L
E
C
H
A
R
G
I
N
G
S
T
A
T
I
O
N
$3
0
,
0
0
0
$30,000
$1
1
2
,
0
3
1
$3
3
0
,
0
0
0
$3
1
0
,
0
0
0
$2
9
5
,
0
0
0
$1,900,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
P
a
r
k
i
n
g
F
u
n
d
(
1
0
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$30,000
$1
1
2
,
0
3
1
$3
3
0
,
0
0
0
$1,900,000FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$2
9
5
,
0
0
0
$3
1
0
,
0
0
0
FY
2
1
17
0
CIP Project Fund
Parking Fund
PROJECT NUMBER
GF199
DEPARTMENT
PARKING
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$37,031
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this growth, we need to remodel the Stiff Building. In FY16 the City Commission
approved a Phase 1 of the remodel that will provide a better use of existing space by relocating certain functions to the basement
and reclaiming unused square footage. Approval of Phase II would allow the consolidation of Community Development (Planning
and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater) together
on another floor. This will allow better coordination of staff and better service to our public. Phase 1 is anticipated to be
completed late spring of 2016.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking
New
Replacement
Equipment
Project
FY21 FY22 FY23
171
CIP Project Fund
Parking Fund
PROJECT NUMBER
P001
DEPARTMENT
PARKING
PROJECT NAME
Willson Lot Redesign
FY19 FY20
$300,000
Unscheduled
DESCRIPTION OF PROJECT
Improve the parking lot layout, set-backs, landscaping, signage, lighting, required storm water treatment infrastructure
requirements and parking kiosk.
ALTERNATIVES CONSIDERED
Keep lot as is
ADVANTAGES OF APPROVAL
Improved functioning of parking lot
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
Parking Fund and TIF Contribution
New
Replacement
Equipment
Project
FY21 FY22 FY23
172
CIP Project Fund
Parking Fund
PROJECT NUMBER
P004
DEPARTMENT
PARKING
PROJECT NAME
Surface Parking Lot Hardware & Software Systems
FY19
$15,000
FY20
$15,000
Unscheduled
DESCRIPTION OF PROJECT
It is highly likely the Downtown Parking Lots will be transitioned to a fee lots. This will require the purchase and installation of
pay-and-display kiosks for each parking lot estimated to cost $60,000. The pads and vehicle protection will be installed as a part of
each surface lot’s redesign.
ALTERNATIVES CONSIDERED
Do not convert lots to pay lots; continue the current practice of permit holders and free 2-hour parking.
ADVANTAGES OF APPROVAL
Citizens using the surface lots will pay for the actual time they use the facilities. Revenue from parking charges can be used to support the
parking operations and fund additional parking assets. This equipment will improve the efficiency of parking officers monitoring parking rules in
the downtown.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minor operational costs.
FUNDING SOURCES
Parking Fund and TIF Contributions
New
Replacement
Equipment
Project
FY21
$15,000
FY22
$15,000
FY23
173
CIP Project Fund
Parking Fund
PROJECT NUMBER
P012
DEPARTMENT
PARKING
PROJECT NAME
Armory Lot Redesign and Improvements
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project is scheduled after the completion of the Etha Hotel construction project. Layout, set-backs, landscaping, signage,
lighting, sidewalks, and storm water treatment facilities are being planned.
ALTERNATIVES CONSIDERED
Keep the lot as is.
ADVANTAGES OF APPROVAL
Better functioning and safer parking lot layout. Will reduce a significant amount of untreated stormwater runoff. Increased revenue and parking
asset coordination through the implementation of pay kiosks.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
New asphalt will require less maintenance, but plantings and landscaping will require additional maintenance.
FUNDING SOURCES
Parking Fund and TIF Contributions - the Etha Hotel may also help fund these improvements.
New
Replacement
Equipment
Project
FY21 FY22
$250,000
FY23
174
CIP Project Fund
Parking Fund
PROJECT NUMBER
P014
DEPARTMENT
PARKING
PROJECT NAME
Parking Garage Crack Maintenance and Repair
FY19
$20,000
FY20
$5,000
Unscheduled
DESCRIPTION OF PROJECT
Includes laser measuring of deck gaps and routine repairs and patching of concrete deck surfaces. Structural gap repair is
anticipated every 3 years with routine caulking in between.
ALTERNATIVES CONSIDERED
Moving to an every other year gap maintenance or reducing the frequency of structural gap filling (not advised).
ADVANTAGES OF APPROVAL
Will extend the life of the parking garage deck surfaces.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Parking Fund
New
Replacement
Equipment
Project
FY21
$5,000
FY22
$20,000
FY23
175
CIP Project Fund
Parking Fund
PROJECT NUMBER
P015
DEPARTMENT
PARKING
PROJECT NAME
Parking Garage Roof Project
FY19 FY20 Unscheduled
$400,000
DESCRIPTION OF PROJECT
Construction in the downtown core has increased demand for parking space in the Garage. The demand for additional space is
anticipated with construction projects both planned and underway. The top floor of the garage has limited use during the winter
months as snow removal is difficult due to limited clearances. Installing a roof on the top floor would allow for maximum
utilization of the garage year around.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased utilization of the Parking Garage in all weather conditions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Parking Fund and TIF Contributions
New
Replacement
Equipment
Project
FY21 FY22 FY23
176
CIP Project Fund
Parking Fund
PROJECT NUMBER
P016
DEPARTMENT
PARKING
PROJECT NAME
Purchase of property for future parking facilities in the Downtown Parking District.
FY19 FY20 Unscheduled
$1,500,000
DESCRIPTION OF PROJECT
The Downtown Strategic Parking Management Plan was adopted by the Parking omission and City Commission in July 2016. The
plan outlines 26 strategies to address current and future parking issue in the Downtown. Over the next year, the Parking
Commission will be working with city staff, downtown stakeholders and the community at large on next steps based on the
adopted plan. The acquisition and construction of future parking assets (surface and structured) is a fundamental component.
Costs and locations of those needed assets are not know, but our current Black (Carnegie) Parking lot was appraised at $1.5 M in
2011.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Adequate parking resources are critical for the economic health and vibrancy of the Downtown Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Additional lot maintenance each year/season.
FUNDING SOURCES
Parking Fund, Bonds, TIF, Loans, SID
New
Replacement
Equipment
Project
FY21 FY22 FY23
177
CIP Project Fund
Parking Fund
PROJECT NUMBER
P017
DEPARTMENT
PARKING
PROJECT NAME
Rouse Parking Lot Re-design and Improvements
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Rouse Lot Improvements – Layout, set-backs, landscaping, signage, lighting, sidewalks, and stormwater treatment facilities. These
improvements are separate from any creek restoration project and will only involve the surface lot.
ALTERNATIVES CONSIDERED
Maintain current configuration.
ADVANTAGES OF APPROVAL
Better functioning and safer parking lot layout. Increased revenue and parking asset coordination through the implementation of pay kiosks.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
New asphalt will require less maintenance, but plantings and landscaping will require additional maintenance.
FUNDING SOURCES
Parking Fund, TIF contribution for lot improvements.
New
Replacement
Equipment
Project
FY21
$280,000
FY22 FY23
178
CIP Project Fund
Parking Fund
PROJECT NUMBER
P020
DEPARTMENT
PARKING
PROJECT NAME
Parking Vehicle Leases
FY19
$10,000
FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
In the fall of 2016, the Parking Division transitioned from utilizing old Police vehicles to leased Prius hybrids. Initial indications are
that these vehicles will work exceptionally well for parking enforcement duties and will reduce the fuel consumption and
maintenance costs when compared to the retired patrol vehicles.
ALTERNATIVES CONSIDERED
Continue to use retired patrol vehicles, lease hybrid vehicles at $280/pm. 12,000 mile annual usage. Purchase new cars.
ADVANTAGES OF APPROVAL
Low cost vehicles that are suitable for the Parking Enforcement function; re-use of police vehicles once they are no longer suitable for first-
responder use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Anticipating maintenance requirements for used police vehicles is difficult at best as their age and condition were the primary reasons they were
replaced in the PD. Maintenance and operations for leased vehicles would be limited to oil changes and fuel costs and would be significantly
lower than the current fleet.
FUNDING SOURCES
Parking Fund
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
179
CIP Project Fund
Parking Fund
PROJECT NUMBER
P024
DEPARTMENT
Parking
PROJECT NAME
Electric Vehicle Charging Station
FY19
$30,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The Sustainability Coordinator is preparing a grant application to the Montana Department of Environmental Quality for federal
pass-thru grant funding, derived from the Volkswagen settlement, for the purchase and installation of one electric vehicle charging
station (EVCS) at the Bridger Park Downtown Garage. The EVCS will be positioned directly outside the parking office, inside the
parking garage, and will have the capability to charge two EV’s at once. The amount budgeted ($3,000) is a required 10% match
on the project.
ALTERNATIVES CONSIDERED
N/A
ADVANTAGES OF APPROVAL
Installation and operation of the EVCS will enhance the City of Bozeman’s ability to service multi-modal forms of transportation, and provide
additional support to local sustainability efforts.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Increased electric power costs for the parking garage, level of which is unknown at this time.
FUNDING SOURCES
Parking Services Fund (Operating). It is the intention of Majority of the funding is grant related with a 10% match. Thee parking fund will only be
required to contribute $3,000 of the $30,000 total cost.
New
Replacement
Equipment
Project
FY21 FY22 FY23
180
So
l
i
d
W
a
s
t
e
C
o
l
l
e
c
t
i
o
n
&
R
e
c
y
c
l
i
n
g
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
46
8
,
4
9
5
$
13
5
,
8
6
2
$
45
2
,
8
4
8
$
43
5
,
6
8
3
$
667,660
$
1,016,135 $ ‐ $
P
l
u
s
:
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
49
2
,
3
6
7
$
5
1
6
,
9
8
6
$
5
4
2
,
8
3
5
$
5
6
9
,
9
7
7
$
598,476
$
628,399 $ ‐ $
L
e
s
s
:
F
Y
1
7
C
a
r
r
y
o
v
e
r
C
a
p
i
t
a
l
(9
5
,
0
0
0
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(7
3
0
,
0
0
0
)
$
(2
0
0
,
0
0
0
)
$
(5
6
0
,
0
0
0
)
$
(3
3
8
,
0
0
0
)
$
(250,000)
$
(600,000)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
13
5
,
8
6
2
$
45
2
,
8
4
8
$
43
5
,
6
8
3
$
66
7
,
6
6
0
$
1,016,135
$
1,044,535 $ ‐ $
A ss
u
m
p
t
i
o
n
s
a
r
e
m
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
R
e
v
e
n
u
e
s
3,
7
8
7
,
4
4
1
$
3,
7
8
7
,
4
4
1
$
3,
9
7
6
,
8
1
3
$
4,
1
7
5
,
6
5
4
$
4,384,436
$
4,603,658 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
i
n
R
e
v
e
n
u
e
s
0.
0
%
5.
0
%
5.
0
%
5
.
0
%
5
.
0
%
5
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
3,
7
8
7
,
4
4
1
$
3,
9
7
6
,
8
1
3
$
4,
1
7
5
,
6
5
4
$
4,
3
8
4
,
4
3
6
$
4,603,658
$
4,833,841 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
13
.
0
%
13
.
0
%
1
3
.
0
%
1
3
.
0
%
1
3
.
0
%
1
3
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
0.
0
%
0.
0
%
0.
0
%
0
.
0
%
0
.
0
%
0
.
0
%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1
3
.
0
%
1
3
.
0
%
1
3
.
0
%
1
3
.
0
%
1
3
.
0
%
1
3
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
49
2
,
3
6
7
$
5
1
6
,
9
8
6
$
5
4
2
,
8
3
5
$
5
6
9
,
9
7
7
$
5
9
8
,
4
7
6
$
6
2
8
,
3
9
9
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
2
0
0
,
0
0
0
)
$
(
5
6
0
,
0
0
0
)
$
(
3
3
8
,
0
0
0
)
$
(
2
5
0
,
0
0
0
)
$
(
6
0
0
,
0
0
0
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
SO
L
I
D
W
A
S
T
E
P
R
O
J
E
C
T
S
&
E
Q
U
I
P
M
E
N
T
18
1
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
So
l
i
d
W
a
s
t
e
Fu
n
d
SW
3
2
Co
l
l
e
c
t
i
o
n
FR
O
N
T
L
O
A
D
T
R
U
C
K
R
E
P
L
A
C
E
M
E
N
T
$2
7
0
,
0
0
0
SW
3
6
Co
l
l
e
c
t
i
o
n
SI
D
E
L
O
A
D
T
R
U
C
K
-
N
E
W
(
A
D
D
I
T
I
O
N
A
L
RO
U
T
E
)
$2
9
0
,
0
0
0
SW
4
5
Co
l
l
e
c
t
i
o
n
TO
T
E
D
E
L
I
V
E
R
Y
T
R
U
C
K
$3
8
,
0
0
0
SW
4
6
Co
l
l
e
c
t
i
o
n
GR
A
P
P
L
E
T
R
U
C
K
$2
0
0
,
0
0
0
$2
0
0
,
0
0
0
$5
6
0
,
0
0
0
$3
8
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
So
l
i
d
W
a
s
t
e
Fu
n
d
SW
4
7
So
l
i
d
W
a
s
t
e
SO
L
I
D
W
A
S
T
E
R
A
T
E
S
T
U
D
Y
$5
0
,
0
0
0
SW
4
8
So
l
i
d
W
a
s
t
e
TR
O
M
M
E
L
S
C
R
E
E
N
$2
0
0
,
0
0
0
SW
5
0
So
l
i
d
W
a
s
t
e
SI
D
E
L
O
A
D
T
R
U
C
K
$300,000
SW
5
1
So
l
i
d
W
a
s
t
e
SI
D
E
L
O
A
D
T
R
U
C
K
-
R
E
C
Y
C
L
I
N
G
$300,000
SW
5
2
So
l
i
d
W
a
s
t
e
SI
D
E
L
O
A
D
T
R
U
C
K
R
E
P
L
A
C
E
M
E
N
T
$3
0
0
,
0
0
0
$600,000
$3
0
0
,
0
0
0
$2
5
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
S
o
l
i
d
W
a
s
t
e
F
u
n
d
(
9
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$600,000
$2
0
0
,
0
0
0
$5
6
0
,
0
0
0
FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$2
5
0
,
0
0
0
$3
3
8
,
0
0
0
FY
2
1
18
2
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW32
DEPARTMENT
Collection
PROJECT NAME
Front Load Truck Replacement
FY19 FY20
$270,000
Unscheduled
DESCRIPTION OF PROJECT
This truck is a replacement for an existing front-load truck currently collecting residential and commercial refuse. This equipment
is critical to the operation of the Solid Waste Division. Customer depend on refuse removal on their collection day. Efficiency is
improved with this equipment on the chassis side with increased fuel efficiency and emission reductions.
ALTERNATIVES CONSIDERED
Leasing a front-load truck.
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Average maintenance costs: $10,000/year
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
183
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW36
DEPARTMENT
Collection
PROJECT NAME
Side Load Truck - New (Additional Route)
FY19 FY20
$290,000
Unscheduled
DESCRIPTION OF PROJECT
This is a new side load truck to be used for additional routes. This equipment is critical to the operation of the Solid Waste
Division. Customers depend on refuse removal on their collection day. Efficiency is improved with this equipment on the chassis
side with increased fuel efficiency and emission reductions. The packer mounted on the chassis also see improvements thru
better operator agronomics with joystick controls and better packer function options.
ALTERNATIVES CONSIDERED
Leasing a side-load truck
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs = $30,000
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
184
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW45
DEPARTMENT
Collection
PROJECT NAME
Tote Delivery Truck
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This truck is a replacement for an existing tote delivery truck. This truck is critical in the execution of container management.
Totes need to be delivered to new customers, exchange of totes for customers and removal of totes.
ALTERNATIVES CONSIDERED
Leasing a truck
ADVANTAGES OF APPROVAL
The Solid Waste Divison can continue to deliver,exchange and remove customer tote requests.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance costs $1,000/year
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY21
$38,000
FY22 FY23
185
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW46
DEPARTMENT
Collection
PROJECT NAME
Grapple Truck
FY19
$200,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Truck with articulating arm with clam shells that will pick up large, bulky items (including brush removal) and place into dump
box. While work can still be done by hand, manual work increases risk of back injury. Efficiency is accomplished thru our work
comp rates.
ALTERNATIVES CONSIDERED
Leasing a grapple truck
ADVANTAGES OF APPROVAL
Equipment would be used to pick up large bulky items and brush. Currently we manually load these items by hand.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance cost: $6,000 per year
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
186
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW47
DEPARTMENT
Solid Waste
PROJECT NAME
Solid Waste Rate Study
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Solid Waste Rate Study - including an analysis of revenue requirements, funding depreciation, and cost recovery by customer
class. The most recent rate study was completed in 2013 and should be updated.
ALTERNATIVES CONSIDERED
Continue with current rates.
ADVANTAGES OF APPROVAL
Full cost accounting, rates based on cost of services.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY21 FY22
$50,000
FY23
187
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW48
DEPARTMENT
Solid Waste
PROJECT NAME
Trommel Screen
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
A screen that can separate out garbage from finished compost and separate the size of compost. This is the final stage of the
composting process that we are currently unable to accomplish using existing equipment.
ALTERNATIVES CONSIDERED
Rental of this equipment is not avaiable
ADVANTAGES OF APPROVAL
The Solid Waste Divison can market the finished compost product
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY21 FY22
$200,000
FY23
188
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW50
DEPARTMENT
Solid Waste
PROJECT NAME
Side Load Truck
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This side load truck is critical to complete residential garbage collection service. As per the approved 6 year replacement
schedule, garbage truck, asset # 3839, will be placed as backup truck for the division.
ALTERNATIVES CONSIDERED
Leasing a side load truck
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs $30,000
FUNDING SOURCES
100% Solid Waste Enterprise Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
$300,000
189
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW51
DEPARTMENT
Solid Waste
PROJECT NAME
Side Load Truck - Recycling
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This side load truck is critical to complete residential and commercial recycling collection service. As per the approved 6 year
replacement schedule, recycling truck, asset #3838, will be placed as a backup truck for the division.
ALTERNATIVES CONSIDERED
Leasing a side load truck
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs $30,000
FUNDING SOURCES
100% Solid Waste Enterprise Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
$300,000
190
CIP Project Fund
Solid Waste Fund
PROJECT NUMBER
SW52
DEPARTMENT
Solid Waste
PROJECT NAME
Side Load Truck Replacement
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This side load truck is critical to complete residential garbage collection service. As per the approved 6 year replacement
schedule, garbage truck, asset #3746, will be placed as a backup truck for the division.
ALTERNATIVES CONSIDERED
Leasing a side load truck
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of newer equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs $30,000
FUNDING SOURCES
100% Solid Waste Enterprise Fund
New
Replacement
Equipment
Project
FY21
$300,000
FY22 FY23
191
192
St
o
r
m
W
a
t
e
r
U
t
i
l
i
t
y
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
79
7
,
3
8
9
$
44
6
,
4
3
7
$
42
0
,
7
7
7
$
41
3
,
8
4
8
$
42
6
,
2
1
1
$
458,445 $
P
l
u
s
:
S
t
o
r
m
W
a
t
e
r
U
t
i
l
i
t
y
F
e
e
s
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
60
6
,
1
5
6
$
62
4
,
3
4
1
$
64
3
,
0
7
1
$
66
2
,
3
6
3
$
68
2
,
2
3
4
$
702,701 $
L
e
s
s
:
F
Y
1
7
C
a
r
r
y
o
v
e
r
C
a
p
i
t
a
l
(3
0
7
,
1
0
8
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(6
5
0
,
0
0
0
)
$
(6
5
0
,
0
0
0
)
$
(6
5
0
,
0
0
0
)
$
(6
5
0
,
0
0
0
)
$
(6
5
0
,
0
0
0
)
$
(650,000)$ (125,000)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
44
6
,
4
3
7
$
42
0
,
7
7
7
$
41
3
,
8
4
8
$
42
6
,
2
1
1
$
45
8
,
4
4
5
$
511,146 $
A ss
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
F
Y
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
S
t
o
r
m
W
a
t
e
r
U
t
i
l
i
t
y
R
e
v
e
n
u
e
1,
3
4
7
,
0
1
3
$
1
,
3
4
7
,
0
1
3
$
1
,
3
8
7
,
4
2
3
$
1,
4
2
9
,
0
4
6
$
1,
4
7
1
,
9
1
7
$
1,516,075 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
‐
A
t
t
r
i
b
u
t
e
d
t
o
G
r
o
w
t
h
0%
3%
3%
3%
3%3%
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
‐
R
a
t
e
I
n
c
r
e
a
s
e
0%
0%
0%
0%
0%0%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
1,
3
4
7
,
0
1
3
$
1
,
3
8
7
,
4
2
3
$
1
,
4
2
9
,
0
4
6
$
1,
4
7
1
,
9
1
7
$
1,
5
1
6
,
0
7
5
$
1,561,557 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
45
.
0
%
45
.
0
%
4
5
.
0
%
4
5
.
0
%
4
5
.
0
%
4
5
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
a
p
i
t
a
l
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0
.
0
%
0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
45
.
0
%
45
.
0
%
4
5
.
0
%
4
5
.
0
%
4
5
.
0
%
4
5
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
60
6
,
1
5
6
$
6
2
4
,
3
4
1
$
6
4
3
,
0
7
1
$
6
6
2
,
3
6
3
$
6
8
2
,
2
3
4
$
7
0
2
,
7
0
1
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
$
(
6
5
0
,
0
0
0
)
$
(
6
5
0
,
0
0
0
)
$
(
6
5
0
,
0
0
0
)
$
(
6
5
0
,
0
0
0
)
$
(
6
5
0
,
0
0
0
)
$
(
6
5
0
,
0
0
0
)
$
(
1
2
5
,
0
0
0
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
ST
O
R
M
W
A
T
E
R
P
R
O
J
E
C
T
S
19
3
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
St
o
r
m
w
a
t
e
r
Fu
n
d
ST
R
M
4
8
En
g
i
n
e
e
r
i
n
g
AN
N
U
A
L
I
N
L
E
T
R
E
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
$100,000
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
ST
R
M
5
7
En
g
i
n
e
e
r
i
n
g
DO
W
N
T
O
W
N
B
O
Z
E
M
A
N
C
R
E
E
K
C
U
L
V
E
R
T
AS
S
E
S
S
M
E
N
T
$1
5
,
0
0
0
$100,000
$1
1
5
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
St
o
r
m
w
a
t
e
r
Fu
n
d
ST
R
M
1
3
St
o
r
m
w
a
t
e
r
AN
N
U
A
L
P
I
P
E
R
E
H
A
B
I
L
I
T
A
T
I
O
N
A
N
D
DR
A
I
N
A
G
E
P
R
O
J
E
C
T
S
$200,000
$5
0
,
0
0
0
$5
0
,
0
0
0
$2
0
0
,
0
0
0
$2
0
0
,
0
0
0
ST
R
M
2
6
St
o
r
m
w
a
t
e
r
ST
O
R
M
W
A
T
E
R
T
V
V
A
N
R
E
F
U
R
B
I
S
H
M
E
N
T
$125,000
ST
R
M
3
1
St
o
r
m
w
a
t
e
r
ME
C
H
A
N
I
C
A
L
S
E
P
A
R
A
T
I
O
N
U
N
I
T
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
4
$3
0
0
,
0
0
0
ST
R
M
3
4
St
o
r
m
w
a
t
e
r
ME
C
H
A
N
I
C
A
L
S
E
P
A
R
A
T
I
O
N
U
N
I
T
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
3
$3
0
0
,
0
0
0
ST
R
M
3
6
St
o
r
m
w
a
t
e
r
BO
U
L
E
V
A
R
D
I
N
F
I
L
T
R
A
T
I
O
N
S
T
R
U
C
T
U
R
E
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
2
$5
0
,
0
0
0
ST
R
M
3
8
St
o
r
m
w
a
t
e
r
ME
C
H
A
N
I
C
A
L
S
E
P
A
R
A
T
I
O
N
U
N
I
T
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
5
$3
0
0
,
0
0
0
ST
R
M
3
9
St
o
r
m
w
a
t
e
r
ME
C
H
A
N
I
C
A
L
S
E
P
A
R
A
T
I
O
N
U
N
I
T
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
2
$3
5
0
,
0
0
0
ST
R
M
4
9
St
o
r
m
w
a
t
e
r
BO
U
L
E
V
A
R
D
I
N
F
I
L
T
R
A
T
I
O
N
S
T
R
U
C
T
U
R
E
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
3
$5
0
,
0
0
0
ST
R
M
5
0
St
o
r
m
w
a
t
e
r
ST
O
R
M
W
A
T
E
R
F
A
C
I
L
I
T
Y
P
L
A
N
U
P
D
A
T
E
$1
5
0
,
0
0
0
ST
R
M
5
1
St
o
r
m
w
a
t
e
r
PI
P
E
R
E
P
L
A
C
E
M
E
N
T
–
N
.
4
T
H
(
W
.
CO
T
T
O
N
W
O
O
D
T
O
W
.
P
E
A
C
H
)
$5
0
,
0
0
0
ST
R
M
5
2
St
o
r
m
w
a
t
e
r
ME
C
H
A
N
I
C
A
L
S
E
P
A
R
A
T
I
O
N
U
N
I
T
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
6
$300,000
19
4
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
ST
R
M
5
3
St
o
r
m
w
a
t
e
r
BO
U
L
E
V
A
R
D
I
N
F
I
L
T
R
A
T
I
O
N
S
T
R
U
C
T
U
R
E
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
6
$50,000
ST
R
M
5
4
St
o
r
m
w
a
t
e
r
AD
M
I
N
I
S
T
R
A
T
I
O
N
S
T
A
F
F
V
E
H
I
C
L
E
$3
5
,
0
0
0
ST
R
M
5
5
St
o
r
m
w
a
t
e
r
BO
U
L
E
V
A
R
D
I
N
F
I
L
T
R
A
T
I
O
N
S
T
R
U
C
T
U
R
E
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
5
$5
0
,
0
0
0
ST
R
M
5
6
St
o
r
m
w
a
t
e
r
BO
U
L
E
V
A
R
D
I
N
F
I
L
T
R
A
T
I
O
N
S
T
R
U
C
T
U
R
E
S
-
DO
W
N
T
O
W
N
S
T
O
R
M
W
A
T
E
R
T
R
E
A
T
M
E
N
T
PH
A
S
E
4
$5
0
,
0
0
0
$550,000
$5
3
5
,
0
0
0
$5
5
0
,
0
0
0
$5
5
0
,
0
0
0
$5
5
0
,
0
0
0
$125,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
S
t
o
r
m
w
a
t
e
r
F
u
n
d
(
1
7
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$650,000
$6
5
0
,
0
0
0
$6
5
0
,
0
0
0
$125,000FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$6
5
0
,
0
0
0
$6
5
0
,
0
0
0
FY
2
1
19
5
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM13
DEPARTMENT
Stormwater
PROJECT NAME
Annual Pipe Rehabilitation and Drainage Projects
FY19
$50,000
FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
An annual program that provides funding for the design and construction of various pipe rehabilitation, drainage, and treatment
projects that improve the structural integrity and conveyance capacity of the City’s stormwater infrastructure network.
Unplanned funds allow Staff to respond to infrastructure needs that arise from reoccurring system inspection and partner with
other Public Works’ projects, such as local SID street reconstructions when approved.
ALTERNATIVES CONSIDERED
Staff assessed the potential of Stormwater Operations Personnel completing all pipe rehabilitation and drainage projects; however, this approach
would significantly reduce resources applied towards critical reoccurring infrastructure maintenance.
ADVANTAGES OF APPROVAL
The allocation of unplanned funds allows Staff to be proactive in the repair and replacement of stormwater infrastructure that has or is likely to
fail, increasing system efficiency and reducing City liability.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance of projects as required.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21
$200,000
FY22
$200,000
FY23
$200,000
196
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM26
DEPARTMENT
Stormwater
PROJECT NAME
Stormwater TV Van Refurbishment
FY19 FY20 Unscheduled
$125,000
DESCRIPTION OF PROJECT
Refurbishment of existing Stormwater TV van routinely completed every 5 years to replace worn parts and remain consistent
with new technology. This equipment is critical in assessing structural failures in the City's underground stormwater system, and
allows the City to identify troubled areas and allocate resources to fix. This process significantly improves operation efficiency,
budget allocation, and project planning. Deferring this purchase would result in existing equipment to exceed their effective
lifespans, resulting in unexpected breakdowns and inefficiencies.
ALTERNATIVES CONSIDERED
Purchase a new TV Van at an estimated cost of $250,000.
ADVANTAGES OF APPROVAL
Provides for the timely replacement of critical maintenance equipment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Decrease in maintenance costs
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
197
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM31
DEPARTMENT
Stormwater
PROJECT NAME
Mechanical Separation Units - Downtown Stormwater Treatment Phase 4
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of three (3) stormwater mechanical separation units near the following intersections: N.
Rouse and E. Tamarack, S. Black and E. Cleveland, and S. Bozeman and E. Cleveland. Staff proposes to target these locations
because the roads, parking lots, yards, driveways, and drainage systems contained within their urban watersheds have a direct
connection to Bozeman and Matthew Bird Creeks, meaning no removal of stormwater pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the large size of the drainage basins targeted.
ADVANTAGES OF APPROVAL
The three (3) units will treat stormwater flowing from 278 urban acres and collect over 17 tons of sediment, litter, oil, and metals annually.
Pollutant removal will improve public safety, help restore Bozeman and Matthew Bird Creeks’ aquatic habitat, decrease infrastructure
degradation, and provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21
$300,000
FY22 FY23
198
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM34
DEPARTMENT
Stormwater
PROJECT NAME
Mechanical Separation Units - Downtown Stormwater Treatment Phase 3
FY19 FY20
$300,000
Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of three (3) stormwater mechanical separation units near the following intersections: N.
Rouse and E. Peach, N. Tracy and W. Main, and Langhor and Westridge. Staff proposes to target these locations because the
roads, parking lots, yards, driveways, and drainage systems contained within their urban watersheds have a direct connection to
Bozeman and Matthew Bird Creeks, meaning no removal of stormwater pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the large size of the drainage basins targeted.
ADVANTAGES OF APPROVAL
The three (3) units will treat stormwater flowing from 258 urban acres, and collect over 16 tons of sediment, litter, oil, and metals annually.
Pollutant removal will improve public safety, help restore Bozeman and Matthew Bird Creeks’ aquatic habitat, decrease infrastructure
degradation, and provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
199
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM36
DEPARTMENT
Stormwater
PROJECT NAME
Boulevard Infiltration Structures - Downtown Stormwater Treatment Phase 2
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of two (2) stormwater boulevard infiltration structures near the intersection of N. 11th and
W. Dickerson. Staff proposes to target this location because the roads, parking lots, yards, driveways, and drainage systems
contained within its urban watershed have a direct connection to Mandeville Creek, meaning no removal of stormwater
pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the small size of the drainage basin targeted.
ADVANTAGES OF APPROVAL
The two (2) structures will divert, capture, and infiltrate stormwater flowing from seven (7) urban acres, collecting over two (2) tons of
sediment, litter, oil, and metals annually. Pollutant removal will improve public safety, help restore Mandeville Creek’s aquatic habitat, decrease
infrastructure degradation, and provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
200
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM38
DEPARTMENT
Stormwater
PROJECT NAME
Mechanical Separation Units - Downtown Stormwater Treatment Phase 5
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of three (3) stormwater mechanical separation units near the following intersections: N. 4th
and W. Peach, N. 11th and W. Koch, and N. 9th and W. Villard. Staff proposes to target these locations because the roads,
parking lots, yards, driveways, and drainage systems contained within their urban watersheds have a direct connection to
Mandeville Creek, meaning no removal of stormwater pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the large size of the drainage basins targeted.
ADVANTAGES OF APPROVAL
The three (3) units will treat stormwater flowing from 255 urban acres and collect over 15 tons of sediment, litter, oil, and metals annually.
Pollutant removal will improve public safety, help restore aquatic habitat, decrease infrastructure degradation, and provide the City a measurable
step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22
$300,000
FY23
201
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM39
DEPARTMENT
Stormwater
PROJECT NAME
Mechanical Separation Units - Downtown Stormwater Treatment Phase 2
FY19
$350,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of four (4) stormwater mechanical separation units near the following intersections: N. Black
and E. Main, N. Bozeman and E. Main, N. Rouse and E. Main, and Westridge and Overbrook. Staff proposes to target these
locations because the roads, parking lots, yards, driveways, and drainage systems contained within their urban watersheds have a
direct connection to Bozeman and Matthew Bird Creeks, meaning no removal of stormwater pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the large size of the drainage basins targeted.
ADVANTAGES OF APPROVAL
The four (4) units will treat stormwater flowing from 162 urban acres, collecting over 12 tons of sediment, litter, oil, and metals annually.
Pollutant removal will improve public safety, help restore Bozeman and Matthew Bird Creeks’ aquatic habitat, decrease infrastructure
degradation, and provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
202
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM48
DEPARTMENT
Engineering
PROJECT NAME
Annual Inlet Replacement Program
FY19
$100,000
FY20
$100,000
Unscheduled
DESCRIPTION OF PROJECT
An annual program that provides funding for the replacement of under sized and degraded stormwater inlets throughout the
downtown core in coordination with the Street and Engineering Divisions’ Annual Pedestrian Ramp Replacement Program.
ALTERNATIVES CONSIDERED
Staff assessed the potential of Stormwater Operations Personnel completing inlet replacements; however, this approach would significantly
reduce resources applied towards critical reoccurring system maintenance.
ADVANTAGES OF APPROVAL
Upgrading the inlets to the City’s current standard will reduce localized flooding and improve stormwater treatment through increased sump
depth.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance annually, including the removal of collected debris using existing inlet vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21
$100,000
FY22
$100,000
FY23
$100,000
203
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM49
DEPARTMENT
Stormwater
PROJECT NAME
Boulevard Infiltration Structures - Downtown Stormwater Treatment Phase 3
FY19 FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of two (2) stormwater boulevard infiltration structures near the intersection of N. 11th and
W. Alderson. Staff proposes to target this location because the roads, parking lots, yards, driveways, and drainage systems
contained within its urban watershed have a direct connection to Mandeville Creek, meaning no removal of stormwater
pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the small size of the drainage basin targeted.
ADVANTAGES OF APPROVAL
The two (2) structures will divert, capture, and infiltrate stormwater flowing from eight (8) urban acres and collect over two (2) tons of
sediment, litter, oil, and metals annually. Pollutant removal will improve public safety, help restore Mandeville Creek’s aquatic habitat, decrease
infrastructure degradation, and provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
204
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM50
DEPARTMENT
Stormwater
PROJECT NAME
Stormwater Facility Plan Update
FY19 FY20
$150,000
Unscheduled
DESCRIPTION OF PROJECT
This project includes the hiring of a contractor to update the City of Bozeman’s Stormwater Facility Plan, which was last revised
in 2007. The City has made significant programmatic, operational, and administrative changes over the past ten years in response
to evolving environmental regulations, growth, and aging infrastructure. An updated Stormwater Facility Plan will assist Staff in
identifying high-priority infrastructure deficiencies, future needs, and determine the City’s regulatory standing with MS4 Permit
regulations.
ALTERNATIVES CONSIDERED
Staff will continue implementing recommendations provided in the 2007 Stormwater Facility Plan.
ADVANTAGES OF APPROVAL
A Stormwater Facility Plan will provide Staff a framework, action plan, and third party professional oversight that will assist the City in achieving
its programmatic goals, which include complying with environmental regulations, improving waterway health, protecting public safety, and
managing infrastructure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
205
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM51
DEPARTMENT
Stormwater
PROJECT NAME
Pipe Replacement – N. 4th (W. Cottonwood to W. Peach)
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the construction of 150’ of 30” reinforced concrete pipe near the intersection of N. 4th and W. Peach,
replacing a conveyance ditch and linking two existing pipe sections. Staff proposes to target this location because the ditch is
clogged and reverse graded due to significant degradation. Staff secured an easement from the property owner in FY17 to
facilitate the construction of this project and improve land records.
ALTERNATIVES CONSIDERED
Staff assessed the potential of rehabbing the conveyance ditch currently in place; however, decided to proceed with a pipe project after
reviewing long-term maintenance cost and private property concerns.
ADVANTAGES OF APPROVAL
The pipe will convey stormwater originating from a 58-acre urban watershed, reducing flood risk for adjacent properties and improving water
quality by mitigating past issues stemming from erosion and illegal dumping.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance annually, including the removal of collected debris using existing pipe flushing
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
206
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM52
DEPARTMENT
Stormwater
PROJECT NAME
Mechanical Separation Units - Downtown Stormwater Treatment Phase 6
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of three (3) stormwater mechanical separation units near the following intersections: S. 17th
and W. Babcock, Blackmore and Terrace, and S. Tracy and E. Kagy. Staff proposes to target these locations because the roads,
parking lots, yards, driveways, and drainage systems contained within their urban watersheds have a direct connection to
Mandeville and Matthew Bird Creeks, meaning no removal of stormwater pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the large size of the drainage basins targeted.
ADVANTAGES OF APPROVAL
The three (3) units will treat stormwater flowing from 100 urban acres and collect over 6 tons of sediment, litter, oil, and metals annually.
Pollutant removal will improve public safety, help restore aquatic habitat, decrease infrastructure degradation, and provide the City a measurable
step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
$300,000
207
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM53
DEPARTMENT
Stormwater
PROJECT NAME
Boulevard Infiltration Structures - Downtown Stormwater Treatment Phase 6
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of two stormwater boulevard infiltration structures near the intersection of N. Broadway
and E. Mendenhall. Staff proposes to target this location because the roads, parking lots, yards, driveways, and drainage systems
contained within its urban watershed have a direct connection to the East Gallatin River, meaning no removal of stormwater
pollutants currently occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the small size of the drainage basin targeted.
ADVANTAGES OF APPROVAL
The two (2) structures will divert, capture, and infiltrate stormwater flowing from four (4) urban acres and collect over one (1) ton of sediment,
litter, oil, and metals annually. Pollutant removal will improve public safety, help restore aquatic habitat, decrease infrastructure degradation, and
provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
$50,000
208
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM54
DEPARTMENT
Stormwater
PROJECT NAME
Administration Staff Vehicle
FY19
$35,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the purchase of a new field work and inspection vehicle for Stormwater Division Administrative Staff,
accommodating transportation needs for a new Specialist Position hired in FY18. The Stormwater Division has three
administrative personnel who currently have one truck, and access to two cars shared between multiple Public Works' Divisions.
An additional truck is necessary for Staff to complete pollution event mitigation activities, sampling equipment transport, work
within the public-right-of way, and field inspections.
ALTERNATIVES CONSIDERED
Staff assessed the potential of sharing existing vehicles; however, determined that scheduling conflicts would present themselves frequently,
affecting the Division’s ability to achieve level of service goals.
ADVANTAGES OF APPROVAL
The purchase of an additional vehicle will allow Stormwater Division Staff to complete daily work activities timely, effectively, and safely.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Staff will budget for annual preventative maintenance completed by a mix of internal and external services, ensuring the vehicle stays in good
working order.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
209
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM55
DEPARTMENT
Stormwater
PROJECT NAME
Boulevard Infiltration Structures - Downtown Stormwater Treatment Phase 5
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of two stormwater boulevard infiltration structures near the intersection of N. Montana and
E. Beall. Staff proposes to target this location because the roads, parking lots, yards, driveways, and drainage systems contained
within its urban watershed have a direct connection to Bozeman Creek, meaning no removal of stormwater pollutants currently
occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the small size of the drainage basin targeted.
ADVANTAGES OF APPROVAL
The two (2) structures will divert, capture, and infiltrate stormwater flowing from eight (8) urban acres and collect over two (2) tons of
sediment, litter, oil, and metals annually. Pollutant removal will improve public safety, help restore aquatic habitat, decrease infrastructure
degradation, and provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22
$50,000
FY23
210
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM56
DEPARTMENT
Stormwater
PROJECT NAME
Boulevard Infiltration Structures - Downtown Stormwater Treatment Phase 4
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project includes the installation of two stormwater boulevard infiltration structures near the intersection of S. Black and E.
Garfield. Staff proposes to target this location because the roads, parking lots, yards, driveways, and drainage systems contained
within its urban watershed have a direct connection to Mandeville Creek, meaning no removal of stormwater pollutants currently
occurs.
ALTERNATIVES CONSIDERED
Staff has not identified any alternative stormwater treatment approaches with comparable maintenance requirements, construction footprints,
and/or pollutant removal efficiencies, especially considering the small size of the drainage basin targeted.
ADVANTAGES OF APPROVAL
The two (2) structures will divert, capture, and infiltrate stormwater flowing from 14 urban acres and collect over two (2) tons of sediment,
litter, oil, and metals annually. Pollutant removal will improve public safety, help restore Mandeville Creek’s aquatic habitat, decrease
infrastructure degradation, and provide the City a measurable step towards municipal stormwater discharge permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Stormwater Operations Personnel will complete maintenance quarterly, including the removal of collected debris using existing vacuuming
equipment. Once collected, Staff will temporarily store and dry debris at the City’s Stormwater Waste Management Facility before hauling to
the landfill for final disposal.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21
$50,000
FY22 FY23
211
CIP Project Fund
Stormwater Fund
PROJECT NUMBER
STRM57
DEPARTMENT
Engineering
PROJECT NAME
Downtown Bozeman Creek Culvert Assessment
FY19
$15,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Assess the condition of the downtown Bozeman Creek culverts crossing Lamme St, Mendenhall St, Main St, Babcock St, Olive St,
and Rouse Ave. These are high risk assets that in the event of a failure, could result in extensive road and business closures
throughout the downtown corridor. This project is split between Stormwater ($15,000) and Street Maintenance ($15,000).
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Identifies susceptibility of downtown culverts to critical failure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
$15,000 Stormwater, $15,000 Street Maintenance
New
Replacement
Equipment
Project
FY21 FY22 FY23
212
St
r
e
e
t
a
n
d
C
u
r
b
R
e
c
o
n
s
t
r
u
c
t
i
o
n
s
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
46
9
,
8
6
3
$
(
2
0
6
,
1
3
7
)
$
3
7
5
,
5
4
1
$
8
5
6
,
1
0
3
$
1
,
2
3
0
,
5
4
2
$
1
,
7
0
4
,
9
1
5
$
P
l
u
s
:
S
t
r
e
e
t
M
a
i
n
t
e
n
a
n
c
e
A
s
s
e
s
s
m
e
n
t
s
D
e
d
i
c
a
t
e
d
68
4
,
0
0
0
$
69
7
,
6
8
0
$
71
1
,
6
3
4
$
72
5
,
8
6
6
$
74
0
,
3
8
4
$
755,191 $
P
l
u
s
:
S
I
D
f
o
r
W
e
s
t
L
i
n
c
o
l
n
‐
S
C
R
2
0
‐
75
%
16
8
,
0
0
8
$
P
l
u
s
:
S
I
D
f
o
r
S
o
u
t
h
T
r
a
c
y
‐
S
C
R
0
9
‐
50
%
24
0
,
0
0
0
$
P
l
u
s
:
S
I
D
f
o
r
S
o
u
t
h
B
l
a
c
k
‐
S
C
R
0
8
‐
75
%
51
3
,
2
1
3
$
P
l
u
s
:
S
I
D
f
o
r
N
o
r
t
h
T
r
a
c
y
‐
S
C
R
1
0
‐
50
%
29
1
,
4
2
8
$
P
l
u
s
:
S
I
D
f
o
r
N
o
r
t
h
1
7
t
h
‐
S
C
R
1
6
‐ 7
5
%
61
8
,
0
3
2
$
P
l
u
s
:
S
I
D
f
o
r
W
K
o
c
h
h
‐
S
C
R
1
2
‐ 5
0
%
867,070 $
P
l
u
s
:
S
I
D
f
o
r
S
5
t
h
‐
S
C
R
1
4
‐ 5
0
%
1,277,873 $
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(1
,
6
0
0
,
0
0
0
)
$
(
2
8
4
,
0
1
1
)
$
(
7
4
4
,
2
8
4
)
$
(
6
4
2
,
8
5
6
)
$
(
8
8
4
,
0
4
2
)
$
(
4
,
3
4
9
,
8
8
6
)
$ (12,610,559)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
(2
0
6
,
1
3
7
)
$
37
5
,
5
4
1
$
85
6
,
1
0
3
$
1,
2
3
0
,
5
4
2
$
1,
7
0
4
,
9
1
5
$
255,164 $
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
To
t
a
l
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
S
t
r
e
e
t
A
s
s
e
s
s
m
e
n
t
R
e
v
e
n
u
e
68
4
,
0
0
0
$
68
4
,
0
0
0
$
69
7
,
6
8
0
$
71
1
,
6
3
4
$
72
5
,
8
6
6
$
740,384 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
‐
A
t
t
r
i
b
u
t
e
d
t
o
A
n
n
e
x
a
t
i
o
n
s
0.
0
%
2%
2%
2%
2%
2%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
68
4
,
0
0
0
$
69
7
,
6
8
0
$
71
1
,
6
3
4
$
72
5
,
8
6
6
$
74
0
,
3
8
4
$
755,191 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
S
t
r
e
e
t
&
C
u
r
b
C
I
P
%
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
R
e
c
o
n
s
t
r
u
c
t
i
o
n
&
C
u
r
b
s
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0
.
0
%
0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
68
4
,
0
0
0
$
69
7
,
6
8
0
$
71
1
,
6
3
4
$
72
5
,
8
6
6
$
74
0
,
3
8
4
$
755,191 $
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
2
8
4
,
0
1
1
)
$
(
7
4
4
,
2
8
4
)
$
(
6
4
2
,
8
5
6
)
$
(
8
8
4
,
0
4
2
)
$
(
4
,
3
4
9
,
8
8
6
)
$
(
1
2
,
6
1
0
,
5
5
9
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
ST
R
E
E
T
R
E
C
O
N
S
T
R
U
C
T
I
O
N
P
R
O
J
E
C
T
S
21
3
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
St
r
e
e
t
&
C
u
r
b
Re
c
o
n
s
t
r
u
c
t
i
o
n
Fu
n
d
SC
R
0
1
En
g
i
n
e
e
r
i
n
g
AN
N
U
A
L
C
U
R
B
R
E
P
L
A
C
E
M
E
N
T
&
CO
N
C
R
E
T
E
R
E
P
A
I
R
P
R
O
G
R
A
M
$60,000
$6
0
,
0
0
0
$6
0
,
0
0
0
$6
0
,
0
0
0
$6
0
,
0
0
0
SC
R
0
3
En
g
i
n
e
e
r
i
n
g
W
O
L
I
V
E
(
8
T
H
T
O
T
R
A
C
Y
)
-
D
E
S
I
G
N
A
N
D
CO
N
S
T
R
U
C
T
I
O
N
$1,736,555
SC
R
0
4
En
g
i
n
e
e
r
i
n
g
S
G
R
A
N
D
(
O
L
I
V
E
T
O
H
A
Y
E
S
)
–
D
E
S
I
G
N
A
N
D
CO
N
S
T
R
U
C
T
I
O
N
$2,118,375
SC
R
0
5
En
g
i
n
e
e
r
i
n
g
N
G
R
A
N
D
(
M
E
N
D
E
N
H
A
L
T
O
P
E
A
C
H
)
-
DE
S
I
G
N
A
N
D
C
O
N
S
T
R
U
C
T
I
O
N
$1,191,119
SC
R
0
7
En
g
i
n
e
e
r
i
n
g
S
3
R
D
(
O
L
I
V
E
T
O
C
L
E
V
E
L
A
N
D
)
-
D
E
S
I
G
N
AN
D
C
O
N
S
T
R
U
C
T
I
O
N
$1,866,113
SC
R
0
8
En
g
i
n
e
e
r
i
n
g
S
B
L
A
C
K
(
C
O
L
L
E
G
E
T
O
S
C
U
L
-
D
E
-
S
A
C
)
-
DE
S
I
G
N
A
N
D
C
O
N
S
T
R
U
C
T
I
O
N
$6
8
4
,
2
8
4
SC
R
1
0
En
g
i
n
e
e
r
i
n
g
N
T
R
A
C
Y
(
V
I
L
L
A
R
D
T
O
P
E
A
C
H
)
-
D
E
S
I
G
N
AN
D
C
O
N
S
T
R
U
C
T
I
O
N
$5
8
2
,
8
5
6
SC
R
1
1
En
g
i
n
e
e
r
i
n
g
S
4
T
H
A
V
E
(
C
O
L
L
E
G
E
T
O
B
A
B
C
O
C
K
)
-
DE
S
I
G
N
A
N
D
C
O
N
S
T
R
U
C
T
I
O
N
$1,637,967
SC
R
1
2
En
g
i
n
e
e
r
i
n
g
W
K
O
C
H
(
8
T
H
T
O
T
R
A
C
Y
)
-
D
E
S
I
G
N
A
N
D
CO
N
S
T
R
U
C
T
I
O
N
$1,734,140
SC
R
1
3
En
g
i
n
e
e
r
i
n
g
S
6
T
H
(
B
A
B
C
O
C
K
T
O
C
L
E
V
E
L
A
N
D
)
-
D
E
S
I
G
N
AN
D
C
O
N
S
T
R
U
C
T
I
O
N
$2,117,189
SC
R
1
4
En
g
i
n
e
e
r
i
n
g
S
5
T
H
(
O
L
I
V
E
T
O
H
A
Y
E
S
)
-
D
E
S
I
G
N
A
N
D
CO
N
S
T
R
U
C
T
I
O
N
$2,555,746
SC
R
1
5
En
g
i
n
e
e
r
i
n
g
W
H
A
R
R
I
S
O
N
(
T
R
A
C
Y
T
O
6
T
H
)
-
D
E
S
I
G
N
AN
D
C
O
N
S
T
R
U
C
T
I
O
N
$1,305,886
SC
R
1
6
En
g
i
n
e
e
r
i
n
g
N
1
7
T
H
(
D
U
R
S
T
O
N
T
O
E
N
D
)
-
D
E
S
I
G
N
A
N
D
CO
N
S
T
R
U
C
T
I
O
N
$8
2
4
,
0
4
2
SC
R
1
9
En
g
i
n
e
e
r
i
n
g
DA
V
I
S
(
C
H
U
R
C
H
T
O
P
L
U
M
)
-
D
E
S
I
G
N
A
N
D
CO
N
S
T
R
U
C
T
I
O
N
$637,355
SC
R
2
0
En
g
i
n
e
e
r
i
n
g
W
L
I
N
C
O
L
N
(
G
R
A
N
D
T
O
W
I
L
S
O
N
)
-
DE
S
I
G
N
A
N
D
C
O
N
S
T
R
U
C
T
I
O
N
$2
2
4
,
0
1
1
$4,349,886
$2
8
4
,
0
1
1
$7
4
4
,
2
8
4
$6
4
2
,
8
5
6
$8
8
4
,
0
4
2
$12,610,559
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
21
4
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Su
m
m
a
r
y
f
o
r
S
t
r
e
e
t
&
C
u
r
b
R
e
co
n
s
t
r
u
c
t
i
o
n
F
u
n
d
(
1
5
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$4,349,886
$2
8
4
,
0
1
1
$7
4
4
,
2
8
4
$12,610,559FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$8
8
4
,
0
4
2
$6
4
2
,
8
5
6
FY
2
1
21
5
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR01
DEPARTMENT
Engineering
PROJECT NAME
Annual Curb Replacement & Concrete Repair Program
FY19
$60,000
FY20
$60,000
Unscheduled
DESCRIPTION OF PROJECT
When a pedestrian ramp is installed, many times the adjacent curbs need to be replaced in order to get drainage to not stop at
the new ramp. Smaller curb repairs can be necessary rather than replacing a whole block. These repairs result in improved
stormwater control, and facilitates better street sweeping. Additionally, broken curbs can be hazardous to vehicle tires. These
improvements can be combined with ADA ramp replacement work and inlet replacement work.
ALTERNATIVES CONSIDERED
Continue current operations
ADVANTAGES OF APPROVAL
This will allow completion of smaller projects instead of waiting for an entire block to be repaired
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Cost of Materials
FUNDING SOURCES
Street & Curb Replacement Fund
New
Replacement
Equipment
Project
FY21
$60,000
FY22
$60,000
FY23
$60,000
216
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR03
DEPARTMENT
Engineering
PROJECT NAME
W Olive (8th to Tracy) - Design and Construction
FY19 FY20 Unscheduled
$1,736,555
DESCRIPTION OF PROJECT
Reconstruction of West Olive St from 8th to Tracy, including repairs to failed curbs and gutters. The street is already in a failing
condition and continues to function; however, eventually the street will become deteriorated to a point where it is unfeasible to
maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant pedestrian
ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will
eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion. This project
will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For planning purposes, project
estimates West Olive to function as a Major Collector, which would require a 15% contribution from property owners via a
Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 85%. Local SID - 15%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
217
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR04
DEPARTMENT
Engineering
PROJECT NAME
S Grand (Olive to Hayes) – Design and Construction
FY19 FY20 Unscheduled
$2,118,375
DESCRIPTION OF PROJECT
Reconstruction of S Grand, from Olive to Hayes, including repairs to failed curbs and gutters. The street is already in a failing
condition and continues to function; however, eventually the street will become deteriorated to a point where it is unfeasible to
maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant pedestrian
ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will
eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion. This project
will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For planning purposes, project
estimates Lincoln to function as a Local Street, which would re quire a 75% contribution from property owners via a Special
Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
218
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR05
DEPARTMENT
Engineering
PROJECT NAME
N Grand (Mendenhal to Peach) - Design and Construction
FY19 FY20 Unscheduled
$1,191,119
DESCRIPTION OF PROJECT
Reconstruction of North Grand from Mendenhal to Peach, including repairs to failed curbs and gutters. The street is already in a
failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates North Grand will function as a Local Street, which would re quire a 75% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
219
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR07
DEPARTMENT
Engineering
PROJECT NAME
S 3rd (Olive to Cleveland) - Design and Construction
FY19 FY20 Unscheduled
$1,866,113
DESCRIPTION OF PROJECT
Reconstruction of South 3rd Ave from Olive to Cleveland, including repairs to failed curbs and gutters. The street is already in a
failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates S 3rd to function as a Minor Collector, which would require a 50% contribution from
property owners via a Special District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 50%. Local SID - 50%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
220
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR08
DEPARTMENT
Engineering
PROJECT NAME
S Black (College to S Cul-De-Sac) - Design and Construction
FY19 FY20
$684,284
Unscheduled
DESCRIPTION OF PROJECT
Reconstruction of South Black from College to the Cul-de-Sac, including repairs to failed curb and gutters. The street is already in
a failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates South Black to function as a Local Street, which would re quire a 75% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
221
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR10
DEPARTMENT
Engineering
PROJECT NAME
N Tracy (Villard to Peach) - Design and Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Reconstruction of North Tracy Street from Villard to Peach, including repairs to failed curbs and gutters. The street is already in
a failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates North Tracy to function as a Minor Collector, which would require a 50% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 50%. Local SID - 50%.
New
Replacement
Equipment
Project
FY21
$582,856
FY22 FY23
222
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR11
DEPARTMENT
Engineering
PROJECT NAME
S 4th Ave (College to Babcock) - Design and Construction
FY19 FY20 Unscheduled
$1,637,967
DESCRIPTION OF PROJECT
Reconstruction of South 4th Ave from College to Babcock, including re pairs to failed curbs and gutters. The street is already in a
failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates South 4th to function as a Local Street, which would re quire a 75% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
223
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR12
DEPARTMENT
Engineering
PROJECT NAME
W Koch (8th to Tracy) - Design and Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Reconstruction of West Koch Street from 8th to Tracy, including repairs to failed curbs and gutters. The street is already in a
failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates West Koch to function as a Minor Collector, which would require a 50% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 50%. Local SID - 50%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$1,734,140
224
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR13
DEPARTMENT
Engineering
PROJECT NAME
S 6th (Babcock to Cleveland) - Design and Construction
FY19 FY20 Unscheduled
$2,117,189
DESCRIPTION OF PROJECT
Reconstruction of South 6th Ave from Babcock to Cleveland, including repairs to failed curbs and gutters. The street is already in
a failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates South 6th to function as a Local Street, which would re quire a 75% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
225
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR14
DEPARTMENT
Engineering
PROJECT NAME
S 5th (Olive to Hayes) - Design and Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Reconstruction of South 5th Ave from Olive to Hayes, including repairs to failed curbs and gutters. The street is already in a
failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates South 5th to function as a Minor Collector, which would require a 50% contribution from
property owners via a Special District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 50%. Local SID - 50%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$2,555,746
226
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR15
DEPARTMENT
Engineering
PROJECT NAME
W Harrison (Tracy to 6th) - Design and Construction
FY19 FY20 Unscheduled
$1,305,886
DESCRIPTION OF PROJECT
Reconstruction of West Harrison from Tracy to 6th, including repairs to failed curbs and gutters. The street is already in a failing
condition and continues to function; however, eventually the street will become deteriorated to a point where it is unfeasible to
maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant pedestrian
ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will
eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion. This project
will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For planning purposes, project
estimates West Harrison to function as a Local Street, which would re quire a 75% contribution from property owners via a
Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
227
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR16
DEPARTMENT
Engineering
PROJECT NAME
N 17th (Durston to End) - Design and Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Reconstruction of North 17th Ave from Durston to Waggon Wheel Trailer Park, including repairs to failed curbs and gutters.
The street is already in a failing condition and continues to function; however, eventually the street will become deteriorated to a
point where it is unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with
ADA compliant pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and
drainage improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met
at completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates North 17th to function as a Local Street, which would re quire a 75% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22
$824,042
FY23
228
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR19
DEPARTMENT
Engineering
PROJECT NAME
Davis (Church to Plum) - Design and Construction
FY19 FY20 Unscheduled
$637,355
DESCRIPTION OF PROJECT
Reconstruction of Davis from Church to Plum, including repairs to failed curbs and gutters. The street is already in a failing
condition and continues to function; however, eventually the street will become deteriorated to a point where it is unfeasible to
maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant pedestrian
ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will
eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion. This project
will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For planning purposes, project
estimates Davis to function as a Local Street, which would require a 75% contribution from property owners via a Special
Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
229
CIP Project Fund
Street & Curb Reconstruction Fund
PROJECT NUMBER
SCR20
DEPARTMENT
Engineering
PROJECT NAME
W Lincoln (Grand to Wilson) - Design and Construction
FY19
$224,011
FY20 Unscheduled
DESCRIPTION OF PROJECT
Reconstruction of West Lincoln, from Grand to Wilson, including repairs to failed curbs and gutters. The street is already in a
failing condition and continues to function; however, eventually the street will become deteriorated to a point where it is
unfeasible to maintain and keep open to public use. This project will provide a city standard street section, with ADA compliant
pedestrian ramps, pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage
improvements will eliminate potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at
completion. This project will trigger water, sewer, and storm drain improvement projects within the reconstruction area. For
planning purposes, project estimates Lincoln to function as a Local Street, which would re quire a 75% contribution from
property owners via a Special Improvement District Assessment.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Street and Curb Replacement Fund - 25%. Local SID - 75%.
New
Replacement
Equipment
Project
FY21 FY22 FY23
230
St
r
e
e
t
I
m
p
a
c
t
F
e
e
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23 Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
11
,
6
3
6
,
0
5
8
$
3,
1
3
3
,
5
6
9
$
98
6
,
8
1
9
$
(1
,
4
5
1
,
6
1
9
)
$
(2
,
4
9
2
,
1
7
8
)
$
2,150,23 5 $
P
l
u
s
:
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
4
,
0
2
5
,
0
0
0
$
4,
2
2
6
,
2
5
0
$
4,
4
3
7
,
5
6
3
$
4,
6
5
9
,
4
4
1
$
4,
8
9
2
,
4
1
3
$
5,137,03 3 $ ‐$
P
l
u
s
:
U
r
b
a
n
F
u
n
d
s
:
L
e
s
s
:
C
a
r
r
y
o
v
e
r
F
Y
1
7
C
a
p
i
t
a
l
P
r
o
j
e
c
t
s
(
4
,
8
2
6
,
2
4
4
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
*
(
7
,
7
0
1
,
2
4
5
)
$
(6
,
3
7
3
,
0
0
0
)
$
(6
,
8
7
6
,
0
0
0
)
$
(5
,
7
0
0
,
0
0
0
)
$
(2
5
0
,
0
0
0
)
$
(7,250,000 )$ (26,816,000 )$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
3
,
1
3
3
,
5
6
9
$
98
6
,
8
1
9
$
(1
,
4
5
1
,
6
1
9
)
$
(2
,
4
9
2
,
1
7
8
)
$
2,
1
5
0
,
2
3
5
$
37,268 $
A ss
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
S
t
r
e
e
t
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
*
*
4,
0
2
5
,
0
0
0
$
4,0
2
5
,
0
0
0
$
4,
2
2
6
,
2
5
0
$
4,
4
3
7
,
5
6
3
$
4,
6
5
9
,
4
4
1
$
4,892,41 3 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
0
.
0
%
5
%
5
%
5
%
5
%
5
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
4
,
0
2
5
,
0
0
0
$
4,2
2
6
,
2
5
0
$
4,
4
3
7
,
5
6
3
$
4,
6
5
9
,
4
4
1
$
4,
8
9
2
,
4
1
3
$
5,137,03 3 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
1
0
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
100.0 %100.0 %
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
S
t
r
e
e
t
C
a
p
a
c
i
t
y
E
x
p
a
n
s
i
o
n
C
I
P
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.0%0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
10
0
.
0
%
100.0 %100.0 %
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
4,
0
2
5
,
0
0
0
$
4,2
2
6
,
2
5
0
$
4,
4
3
7
,
5
6
3
$
4,
6
5
9
,
4
4
1
$
4,
8
9
2
,
4
1
3
$
5,137,03 3 $
*N
o
t
e
:
T
h
i
s
s
c
h
e
d
u
l
e
n
o
l
o
n
g
e
r
c
o
n
t
a
i
n
s
t
h
e
p
o
r
t
i
o
n
s
o
f
p
r
o
j
e
c
t
c
o
s
t
s
th
a
t
w
i
l
l
b
e
p
a
i
d
b
y
o
t
h
e
r
s
o
u
r
c
e
s
,
w
i
t
h
t
h
e
e
x
c
e
p
t
i
o
n
o
f
F
e
d
e
r
a
l
Ur
b
a
n
F
u
n
d
s
.
S
e
e
t
h
e
"
F
u
n
d
i
n
g
S
o
u
r
c
e
s
"
d
i
s
c
u
s
s
i
o
n
a
t
t
h
e
b
o
t
t
o
m
o
f
ea
c
h
p
r
o
j
e
c
t
i
t
e
m
s
h
e
e
t
.
**
U
s
i
n
g
t
h
r
e
e
y
e
a
r
a
v
e
r
a
g
e
f
o
r
e
s
t
i
m
a
t
e
s
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
6
,
3
7
3
,
0
0
0
)
$
(
6
,
8
7
6
,
0
0
0
)
$
(
5
,
7
0
0
,
0
0
0
)
$
(
2
5
0
,
0
0
0
)
$
(
7
,
2
5
0
,
0
0
0
)
$
(
2
6
,
8
1
6
,
0
0
0
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
ST
R
E
E
T
I
M
P
A
C
T
F
E
E
P
R
O
J
E
C
T
S
23
1
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Im
p
a
c
t
F
e
e
s
St
r
e
e
t
s
SI
F
0
0
1
St
r
e
e
t
I
m
p
a
c
t
F
AN
N
U
A
L
R
I
G
H
T
O
F
W
A
Y
A
C
Q
U
I
S
I
T
I
O
N
$250,000
$2
5
0
,
0
0
0
$2
5
0
,
0
0
0
$2
5
0
,
0
0
0
$2
5
0
,
0
0
0
SI
F
0
0
9
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
KA
G
Y
(
W
I
L
L
S
O
N
T
O
1
9
T
H
)
-
CO
N
S
T
R
U
C
T
I
O
N
$8,000,000
SI
F
0
5
7
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
OA
K
(
F
L
A
N
D
E
R
S
M
I
L
L
T
O
R
Y
U
N
S
U
N
WA
Y
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$1
,
0
0
0
,
0
0
0
SI
F
0
5
8
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
OA
K
&
N
2
7
T
H
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
D
E
S
I
G
N
&
CO
N
S
T
R
U
C
T
I
O
N
$8
0
0
,
0
0
0
SI
F
0
6
2
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
DU
R
S
T
O
N
(
F
O
W
L
E
R
T
O
F
E
R
G
U
S
O
N
)
-
CO
N
S
T
R
U
C
T
I
O
N
$7
6
0
,
0
0
0
SI
F
0
6
3
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
FO
W
L
E
R
&
B
A
B
C
O
C
K
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$1,600,000
SI
F
0
7
3
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
FO
W
L
E
R
&
D
U
R
S
T
O
N
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$1,616,000
SI
F
0
7
6
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
FO
W
L
E
R
C
O
N
N
E
C
T
I
O
N
(
H
U
F
F
I
N
E
T
O
OA
K
)
-
D
E
S
I
G
N
(
I
N
C
L
U
D
E
S
3
IN
T
E
R
S
E
C
T
I
O
N
S
)
$5
0
0
,
0
0
0
SI
F
0
8
6
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BA
X
T
E
R
&
C
O
T
T
O
N
W
O
O
D
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$2,000,000
SI
F
0
9
8
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
OA
K
&
C
O
T
T
O
N
W
O
O
D
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
R
O
U
N
D
A
B
O
U
T
CO
N
S
T
R
U
C
T
I
O
N
$2
,
1
9
2
,
0
0
0
SI
F
1
0
5
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
CO
T
T
O
N
W
O
O
D
(
D
U
R
S
T
O
N
T
O
O
A
K
)
-
CO
N
S
T
R
U
C
T
I
O
N
$1
,
2
5
0
,
0
0
0
SI
F
1
0
8
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
S
3
R
D
A
N
D
G
R
A
F
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$1
,
2
0
0
,
0
0
0
SI
F
1
0
9
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
OA
K
(
R
O
U
S
E
T
H
R
O
U
G
H
C
A
N
N
E
R
Y
DI
S
T
R
I
C
T
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$1
3
3
,
0
0
0
SI
F
1
1
0
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
MA
N
L
E
Y
&
G
R
I
F
F
I
N
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$1
,
6
0
0
,
0
0
0
SI
F
1
1
1
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
HI
G
H
L
A
N
D
(
M
A
I
N
T
O
K
A
G
Y
)
-
CO
N
S
T
R
U
C
T
I
O
N
&
D
E
S
I
G
N
$5,000,000
SI
F
1
1
3
St
r
e
e
t
I
m
p
a
c
t
F
GR
I
F
F
I
N
(
7
T
H
T
O
R
O
U
S
E
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$3
,
5
0
0
,
0
0
0
SI
F
1
1
4
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
FO
W
L
E
R
C
O
N
N
E
C
T
I
O
N
(
H
U
F
F
I
N
E
T
O
OA
K
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$3,750,000
23
2
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
SI
F
1
1
6
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BR
I
D
G
E
R
D
R
&
S
T
O
R
Y
M
I
L
L
R
D
(I
N
T
E
R
S
E
C
T
I
O
N
I
M
P
R
O
V
E
M
E
N
T
S
)
-
CO
N
S
T
R
U
C
T
I
O
N
$1
,
2
0
0
,
0
0
0
SI
F
1
1
7
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
ST
O
R
Y
M
I
L
L
(
G
R
I
F
F
I
N
T
O
B
R
I
D
G
E
R
)
-
CO
N
S
T
R
U
C
T
I
O
N
$2
5
0
,
0
0
0
SI
F
1
1
8
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BA
B
C
O
C
K
(
1
1
T
H
A
V
E
T
O
1
9
T
H
A
V
E
)
-
CO
N
S
T
R
U
C
T
I
O
N
$750,000
SI
F
1
1
8
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BA
B
C
O
C
K
(
1
1
T
H
A
V
E
T
O
1
9
T
H
A
V
E
)
-
DE
S
I
G
N
$250,000
SI
F
1
2
1
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BA
X
T
E
R
&
D
A
V
I
S
(
I
N
T
E
R
S
E
C
T
I
O
N
IM
P
R
O
V
E
M
E
N
T
S
)
-
R
O
U
N
D
A
B
O
U
T
CO
N
S
T
R
U
C
T
I
O
N
$2
,
0
0
0
,
0
0
0
SI
F
1
2
3
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BR
I
D
G
E
R
D
R
&
S
T
O
R
Y
M
I
L
L
R
D
(I
N
T
E
R
S
E
C
T
I
O
N
I
M
P
R
O
V
E
M
E
N
T
S
)
-
D
E
S
I
G
N
$1
0
0
,
0
0
0
SI
F
1
2
7
St
r
e
e
t
I
m
p
a
c
t
F
FO
W
L
E
R
R
I
G
H
T
O
F
W
A
Y
P
U
R
C
H
A
S
E
$1,000,000
SI
F
1
2
8
St
r
e
e
t
I
m
p
a
c
t
F
KA
G
Y
(
W
I
L
L
S
O
N
T
O
H
I
G
H
L
A
N
D
)
-
D
E
S
I
G
N
$500,000
SI
F
1
2
9
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
KA
G
Y
(
W
I
L
L
S
O
N
T
O
H
I
G
H
L
A
N
D
)
-
CO
N
S
T
R
U
C
T
I
O
N
$6,000,000
SI
F
1
3
2
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
ST
O
R
Y
M
I
L
L
(
G
R
I
F
F
I
N
T
O
B
R
I
D
G
E
R
)
-
DE
S
I
G
N
$5
0
,
0
0
0
SI
F
1
3
3
St
r
e
e
t
I
m
p
a
c
t
F
GR
I
F
F
I
N
(
7
T
H
T
O
R
O
U
S
E
)
-
D
E
S
I
G
N
$4
0
0
,
0
0
0
SI
F
1
3
4
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
OA
K
(
C
O
T
T
O
N
W
O
O
D
T
O
F
L
A
N
D
E
R
S
MI
L
L
)
-
C
O
N
S
T
R
U
C
T
I
O
N
$4
3
4
,
0
0
0
SI
F
1
3
6
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BA
B
C
O
C
K
W
I
D
E
N
I
N
G
F
E
R
G
U
S
O
N
T
O
CO
T
T
O
N
W
O
O
D
$900,000
SI
F
1
3
7
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
CO
T
T
O
N
W
O
O
D
(
D
U
R
S
T
O
N
T
O
O
A
K
)
-
DE
S
I
G
N
$2
5
0
,
0
0
0
SI
F
1
3
8
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
CO
T
T
O
N
W
O
O
D
R
O
A
D
,
O
A
K
T
O
B
A
X
T
E
R
-
CO
N
S
T
R
U
C
T
I
O
N
$500,000
SI
F
1
3
9
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
OA
K
(
F
L
A
N
D
E
R
S
M
I
L
L
T
O
R
Y
U
N
S
U
N
WA
Y
)
-
D
E
S
I
G
N
$1
5
0
,
0
0
0
SI
F
1
4
0
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
OA
K
(
C
O
T
T
O
N
W
O
O
D
T
O
F
L
A
N
D
E
R
S
MI
L
L
)
-
D
E
S
I
G
N
$1
8
0
,
0
0
0
SI
F
1
4
1
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
CO
T
T
O
N
W
O
O
D
R
O
A
D
,
O
A
K
T
O
B
A
X
T
E
R
-
DE
S
I
G
N
$2
5
0
,
0
0
0
23
3
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
SI
F
1
4
2
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
DU
R
S
T
O
N
R
O
A
D
&
N
.
2
7
T
H
(I
N
T
E
R
S
E
C
T
I
O
N
I
M
P
R
O
V
E
M
E
N
T
S
)
-
CO
N
S
T
R
U
C
T
I
O
N
$1,200,000
SI
F
1
4
3
St
r
e
e
t
I
m
p
a
c
t
Fe
e
s
BA
X
T
E
R
&
C
O
T
T
O
N
W
O
O
D
IN
T
E
R
S
E
C
T
I
O
N
-
R
I
G
H
T
O
F
W
A
Y
$750,000 $7,250,000
$6
,
3
7
3
,
0
0
0
$6
,
8
7
6
,
0
0
0
$5
,
7
0
0
,
0
0
0
$2
5
0
,
0
0
0
$26,816,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
I
m
p
a
c
t
F
e
es
S
t
r
e
e
t
s
(
3
7
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$7,250,000
$6
,
3
7
3
,
0
0
0
$6
,
8
7
6
,
0
0
0
$26,816,000FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$2
5
0
,
0
0
0
$5
,
7
0
0
,
0
0
0
FY
2
1
23
4
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF001
DEPARTMENT
Street Impact Fees
PROJECT NAME
Annual Right Of Way Acquisition
FY19
$250,000
FY20
$250,000
Unscheduled
DESCRIPTION OF PROJECT
Annual allocation available for right-of-way purchases as they become available. In all cases, the only reason additional R/W is
required is that the existing roadway is being expanded and capacity will be increased. Purchasing additional right-of-way may be
critical to connecting elements of the transportation network, and in doing so, conformance with the City Transportation Master
Plan can be obtained. Purchase of R/W is often a prerequisite for construction of the critical elements of the transportation
network. Other affected projects include all of the other street impact fee projects could potentially be affected by R/W
acquisition.
ALTERNATIVES CONSIDERED
Condemn property for right-of-way; pay court costs as well as appraised value of property. Time consuming for city staff and a relatively
expensive process. Wait for adjacent property owners to dedicate R/W as part of the annexation/development process.
ADVANTAGES OF APPROVAL
Provides dollars for the purchase of necessary right-of-way as it becomes available on the market. Avoids the expensive, antagonistic
condemnation process where possible or having to wait for voluntary dedications.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Street Impact Fees can not be spent on operating and maintaining facilities. There is expected to be a
very minimal, incremental cost to the Street Maintenance District from this expenditure.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21
$250,000
FY22
$250,000
FY23
$250,000
235
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF009
DEPARTMENT
Street Impact Fees
PROJECT NAME
Kagy (Willson to 19th) - Construction
FY19 FY20 Unscheduled
$8,000,000
DESCRIPTION OF PROJECT
This project consists of reconstructing Kagy Boulevard from the intersection of S 19th Ave to Willson Ave to a 4 lane urban
arterial standard. This project directly increase capacity by adding additional travel lanes, dedicated bike lanes and sidewalks and
making improvements to the intersections. Future developments which impact this intersection area may not be allowed to
proceed until improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. Kagy serves as an important element of Bozeman's perimeter street system connecting Highland Blvd.,
Willson Ave, and S. 19th. It also serves as the primary access to Montana State University and the University's major athletic
facilities. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained with
this project. Other affected projects include intersection Improvements at Kagy & 19th, Kagy & 7th, Kagy & 11th, Kagy & Willson.
ALTERNATIVES CONSIDERED
SID, Urban funds, incremental construction by adjacent development.
ADVANTAGES OF APPROVAL
Kagy is a State Urban Route and is eligible for expenditure of State urban funds designated annually for the City of Bozeman; however, the
availability of urban funds cannot match the pace of the City's transportation improvement needs. The need for this project comes from
increased traffic due to growth in the Bozeman area and the project is eligible for Impact Fee Funds. Use of Street Impact Funds enables the
community to leverage the available State Urban transportation funds to complete projects and address more of its pressing transportation
needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($8,000,000) and Urban Funds ($8,000,000). A Payback District or SID may be able to created to
leverage other stakeholders.
New
Replacement
Equipment
Project
FY21 FY22 FY23
236
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF057
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Flanders Mill to Ryun Sun Way) - Construction
FY19 FY20
$1,000,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Flanders Mill to Ryun Sun Way, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to proceed until these
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. This project will complete an important east-west link between Ferguson and Cottonwood, and conformance with
the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak and Ferguson, Oak
Street - New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,300,000) the Arterial & Collector District ($500.000) and local participation. The Flander's Mill
development is expected to be a partner in the construction of the segments adjacent to their development.
New
Replacement
Equipment
Project
FY21 FY22 FY23
237
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF058
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak & N 27th (Intersection Improvements) - Design & Construction
FY19
$800,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Oak and N 27th. This intersection is currently 2-way stop controlled.
Replacing it with a signal will greatly increase its capacity. The level of service at this intersection has degraded to unacceptable
levels. Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. Other affected projects include Oak
Street corridor projects and North 27th Street improvements project.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Secure additional financing by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
238
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF062
DEPARTMENT
Street Impact Fees
PROJECT NAME
Durston (Fowler to Ferguson) - Construction
FY19
$760,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete Durston Rd, from Cottonwood to Fowler, to a three-lane urban minor arterial standard. This project directly increase
capacity by adding additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. Connectivity already exists at this location, it is capacity that is affected. With completion, conformance
with the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders.
Other affected projects include intersection improvements at Durston & Ferguson, Durston & Fowler, Durston & Flanders Mill.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($757,421) and the Arterial & Collector District ($757,421). A payback district may be created to
reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
239
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF063
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler & Babcock (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$1,600,000
DESCRIPTION OF PROJECT
Install a traffic signal, roundabout, or other adequate traffic control device at the intersection of Fowler and Babcock. This
intersection is currently 1-way stop controlled. Replacing it with a signal or roundabout will greatly increase its capacity. East-
west connectivity already exists at this location. North-south connectivity is still lacking. Peak hour level of service for
northbound traffic is degrading due to lack of north-south connectivity in the network. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. A Payback District or SID may be
created to leverage other stakeholders. Other affected projects include Fowler corridor improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,600,000) and the Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
240
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF073
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler & Durston (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$1,616,000
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Fowler and Durston. This intersection is currently 1- way stop controlled.
Replacing it with a signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location.
North-south connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation
Master Plan will be attained at completion. Other affected projects include Fowler corridor street improvements.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Improves an imporant connecting element in the network.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,616,000) and the Arterial & Collector District ($404,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $404,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
241
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF076
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler Connection (Huffine to Oak) - Design (Includes 3 Intersections)
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Design Fowler from Huffine to Oak to an urban minor arterial standard, including three intersections. This project directly
increase capacity by adding additional travel lanes, dedicated bike lanes and sidewalks and making improvements to the
intersections. Future developments which impact this intersection area may not be allowed to proceed until improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. This project
completes an important north-south connection on the west side of town. With its completion, the Level of Service (LOS)
Standard (BMC) and conformance with the Transportation Master Plan will be attained. A Payback District or SID may be created
to leverage other stakeholders. Other affected projects include intersection improvements at Fowler and Durston and Fowler
and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will complete an important north-south connection, expand the capacity of our street network and improve safety for drivers and
pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($500,000) and the Arterial & Collector District ($500,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $500,000).
New
Replacement
Equipment
Project
FY21
$500,000
FY22 FY23
242
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF086
DEPARTMENT
Street Impact Fees
PROJECT NAME
Baxter & Cottonwood (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection at Baxter and Cottonwood. This intersection is currently 1-way stop controlled. Replacing it with a
signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location. North-south
connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at completion. Other affected projects include Cottonwood corridor improvements and Baxter corridor
improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
$2,000,000
243
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF098
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak & Cottonwood (Intersection Improvements) - Roundabout Construction
FY19 FY20
$2,192,000
Unscheduled
DESCRIPTION OF PROJECT
Installation of a roundabout at the intersection of Oak and Cottonwood. Capacity will be greatly increased on the network as a
whole as this intersection is currently 3-legged, rural and stop controlled on Cottonwood (Harper Puckett). This improvement
will complete an important north-south connection on Cottonwood. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place. The Level of Service (LOS) Standard (BMC) and conformance with the
Transportation Master Plan will be attained at completion. Other affected projects include Cottonwood Road Improvements and
Oak Street Improvements.
ALTERNATIVES CONSIDERED
Not installing the intersection improvement at the same time as the construction of the intersecting streets. Secure additional financing by
creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,192,000) and a local share ($548,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
244
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF105
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood (Durston to Oak) - Construction
FY19 FY20
$1,250,000
Unscheduled
DESCRIPTION OF PROJECT
Complete the construction of Cottonwood Road from Durston Road to Oak Street to a five-lane urban arterial standard. This
project increases capacity directly by adding additional lanes, dedicated bike lanes and sidewalks. Future developments which
impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at
large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Cottonwood Rd serves as an important element
in Bozeman's west side street system and serves as a primary north-south corridor on the west side of the city, and conformance
with the Transportation Master Plan will be attained with its completion. A Payback District or SID may be created to leverage
other stakeholders. Other affected projects include Cottonwood corridor street improvements, intersection improvements at
Cottonwood and Durston and Cottonwood and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
The total project cost is $2.5M. $1.5M will come from Impact Fees, the remainder is the local share which will come from either BSD 7, an SID
or Payback of some sort or some combination of these.
New
Replacement
Equipment
Project
FY21 FY22 FY23
245
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF108
DEPARTMENT
Street Impact Fees
PROJECT NAME
S 3rd and Graf (Intersection Improvements) - Construction
FY19
$1,200,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at S 3rd and Graf. This is currently a stop controlled intersection. Installation of a roundabout
will directly increase capacity. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) will be attained at completion.
ALTERNATIVES CONSIDERED
Accept the existing level of service, create an SID for financing.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
246
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF109
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Rouse through Cannery District) - Construction
FY19
$133,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of improving Oak from Rouse through the Cannery District to include curb, gutter, sidewalks, and a turning
lane to provide a complete arterial street standard. The Cannery District will be responsible for the cost of curb, gutter, and
sidewalk along their property frontage as well as the turn lane to access two drive accesses that allow a left turn movement from
Oak Street into the Cannery District. Future developments in this area may not be allowed to proceed until these improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Left turn traffic safety will be improved upon installation of left turn lanes. Pedestrian safety will be improved. Conformance with
the Transportation Master Plan will be attained with its completion. A payback District or SID may be created to leverage other
stakeholders. Cash-in-lieu of infrastructure is anticipated to be contributed from the Cannery District developer to cover the
cost of the left turn lanes needed for their drive accesses as well as the cost of curb, gutter, and sidewalk adjacent to their
property. Other affected projects include Oak Street Corridor improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians. There will be substantial
pedestrian traffic between the Fairgrounds and the Cannery District. Additionally, the traffic impact study for the Cannery District indicated the
need for left turn lanes for their drive accesses. As the City's transportation master plan identifies the need to upgrade the Oak Street Corridor
to an arterial standard, this is an opportunity to partner with the Cannery District developer to complete a portion of the Oak Street
improvements.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($133,000), the Arterial & Collector District ($133,000), and Developer share ($133,000). A
development payback district or SID may be created to reimburse the Arterial & Collector District for the County’s (project related) costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
247
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF110
DEPARTMENT
Street Impact Fees
PROJECT NAME
Manley & Griffin (Intersection Improvements) - Construction
FY19 FY20
$1,600,000
Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Manley & Griffin. This intersection is currently 1-way stop controlled. Replacing it with a
signal will greatly increase its capacity. Future developments which impact this intersection area may not be allowed to proceed
until improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained at
completion. A Payback District or SID may be created to leverage other stakeholders. Other affected projects include Griffin
corridor improvements.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Street Impact Fees ($1,600,000) and Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
248
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF111
DEPARTMENT
Street Impact Fees
PROJECT NAME
Highland (Main to Kagy) - Construction & Design
FY19 FY20 Unscheduled
$5,000,000
DESCRIPTION OF PROJECT
Upgrade Highland, from Main to Kagy. Future developments in this area may not be allowed to proceed until these improvements
are in place. This project directly increase capacity by adding additional lanes, dedicated bike lanes and sidewalks. Connectivity
already exists at this location, it is capacity that is affected. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at the completion of
the project. A payback District or SID may be created to leverage other stakeholders. Other affected projects include
Intersection improvements at Highland and Kagy, Highland and Ellis and Highland and Main Street.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs
FUNDING SOURCES
This project is funded by Street Impact Fees ($5,000,000) and the Arterial & Collector District ($5,000,000). A payback district may be
created to reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
249
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF113
DEPARTMENT
Street Impact Fees
PROJECT NAME
Griffin (7th to Rouse) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construct W Griffin corridor improvements from N. 7th to Rouse to an urban minor arterial standard. Designed improvements
will improve LOS at the key intersections and will increase capacity in the corridor as a whole. Connectivity already exists at this
location, it is capacity which is being expanded. Future developments which impact this intersection area may not be allowed to
proceed until improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at the completion of this project. A Payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Griffin and 7th and Griffin and Rouse.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,500,000) and the Arterial & Collector District ($2,000,000). A development payback district or
SID may be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $2,000,000).
New
Replacement
Equipment
Project
FY21
$3,500,000
FY22 FY23
250
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF114
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler Connection (Huffine to Oak) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete the section of Fowler from Huffine to Oak. This project allows for extension of Fowler Avenue, which will directly
increase capacity, and it extends an important north-south corridor on the west side of the city. Future developments which
impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at
large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Conformance with the Transportation Master
Plan will be attained at the completion of this project. Other affected projects include intersection improvements on Fowler at
Huffine, Babcock, Durston and Oak.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Completes an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,750,000) and the Arterial & Collector District ($3,750,000). A Payback District or SID may be
created to reimburse the Arterial & Collector District for any local improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$3,750,000
251
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF116
DEPARTMENT
Street Impact Fees
PROJECT NAME
Bridger Dr & Story Mill Rd (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Bridger and Story Mill. Adding additional phases and improving geometry will increase
capacity for deficient movements at this intersection. Future developments which impact this intersection area may not be
allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at completion. Other
affected projects include Story Mill, Griffin to Bridger Drive.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000). An SID or payback district may
be created to recover the local share.
New
Replacement
Equipment
Project
FY21
$1,200,000
FY22 FY23
252
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF117
DEPARTMENT
Street Impact Fees
PROJECT NAME
Story Mill (Griffin to Bridger) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve Story Mill from Griffin to Bridger. This project directly increases capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback District or SID
may be created to leverage other stakeholders. Other affected projects include intersection improvements to Story Mill and
Bridger Drive.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Improves an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($250,000) and the Arterial & Collector District ($250,000). An SID or payback district may be
created to recover the local share.
New
Replacement
Equipment
Project
FY21
$250,000
FY22 FY23
253
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF118
DEPARTMENT
Street Impact Fees
PROJECT NAME
Babcock (11th Ave to 19th Ave) - Construction
FY19 FY20 Unscheduled
$750,000
DESCRIPTION OF PROJECT
Construct the Babcock (11th to 19th) street upgrade. This project increases capacity directly by adding additional lanes, dedicated
bike lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback
District or SID may be created to leverage other stakeholders.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($750,000) and the Arterial & Collector District ($750,000). An SID or payback district may be
created to pay for some local share improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
254
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF118
DEPARTMENT
Street Impact Fees
PROJECT NAME
Babcock (11th Ave to 19th Ave) - Design
FY19 FY20 Unscheduled
$250,000
DESCRIPTION OF PROJECT
Design the Babcock (11th to 19th) street upgrade. This project increases capacity directly by adding additional lanes, dedicated
bike lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback
District or SID may be created to leverage other stakeholders.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
100% Street Impact Fees. A payback district may be able to reimburse for design costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
255
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF121
DEPARTMENT
Street Impact Fees
PROJECT NAME
Baxter & Davis (Intersection Improvements) - Roundabout Construction
FY19
$2,000,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Install a roundabout at Baxter & Davis. This intersection is currently 4-way stop controlled. Replacing it with a roundabout will
greatly increase its capacity. Future developments in this area may not be allowed to proceed until these improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan and Level of Service Standard will be attained at completion. Other affected projects include
Baxter Lane Corridor Improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network, improve safety for drivers and pedestrians and increase capacity at this
intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
256
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF123
DEPARTMENT
Street Impact Fees
PROJECT NAME
Bridger Dr & Story Mill Rd (Intersection Improvements) - Design
FY19 FY20
$100,000
Unscheduled
DESCRIPTION OF PROJECT
Design of Intersection improvements at the intersection of Story Mill and Bridger Drive.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitate development already occurring in this area
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
257
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF127
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler Right of Way Purchase
FY19 FY20 Unscheduled
$1,000,000
DESCRIPTION OF PROJECT
Purchase the right of way on Fowler (Durston to Annie). This purchase allows for extension of Fowler Avenue, which will
directly increase capacity, and it extends an important north-south corridor on the west side of the City. Future developments
which impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network
at large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Other affected projects include Fowler corridor
improvements.
ALTERNATIVES CONSIDERED
Do nothing, wait for adjacent development to dedicate the R/W
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
100% Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
258
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF128
DEPARTMENT
Street Impact Fees
PROJECT NAME
Kagy (Willson to Highland) - Design
FY19 FY20 Unscheduled
$500,000
DESCRIPTION OF PROJECT
Design Kagy, from Willson to Highland, including the intersections at Sourdough & Kagy and Highland & Kagy. This project
increases capacity directly by adding additional lanes, dedicated bike lanes and sidewalks and by improving intersection LOS.
Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. A Payback
District or SID may be created to leverage other stakeholders. Other affected projects include intersections at
Sourdough/Church and Highland.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Design is 100% impact fee eligible.
New
Replacement
Equipment
Project
FY21 FY22 FY23
259
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF129
DEPARTMENT
Street Impact Fees
PROJECT NAME
Kagy (Willson to Highland) - Construction
FY19 FY20 Unscheduled
$6,000,000
DESCRIPTION OF PROJECT
Complete Kagy, from Willson to Highland, including the intersections at Sourdough & Kagy and Highland & Kagy. This project
increases capacity directly by adding additional lanes, dedicated bike lanes and sidewalks and by improving intersection LOS.
Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. The Level of
Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained at completion. A Payback
District or SID may be created to leverage other stakeholders. Other affected projects include intersections at
Sourdough/Church and Highland.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is eligible for Urban funds. A payback district or SID could be created to recover a portion of the local share.
New
Replacement
Equipment
Project
FY21 FY22 FY23
260
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF132
DEPARTMENT
Street Impact Fees
PROJECT NAME
Story Mill (Griffin to Bridger) - Design
FY19 FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
Story Mill design from Griffin to Bridger. This project directly increases capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Conformance with the Transportation Master Plan will be attained at completion. A Payback District or SID may be created to
leverage other stakeholders. Other affected projects include intersection improvements to Story Mill and Bridger Drive.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Improves an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
Design is 100% impact fee eligible.
New
Replacement
Equipment
Project
FY21 FY22 FY23
261
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF133
DEPARTMENT
Street Impact Fees
PROJECT NAME
Griffin (7th to Rouse) - Design
FY19
$400,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design W Griffin corridor improvements from N. 7th to Rouse to an urban minor arterial standard. Designed improvements will
improve LOS at the key intersections and will increase capacity in the corridor as a whole. Future developments which impact
this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at large is
dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary
demand on those elements of the street network that are in place. The Level of Service (LOS) Standard (BMC) and conformance
with the Transportation Master Plan will be attained at completion. A Payback District or SID may be created to leverage other
stakeholders. Other affected projects include intersection improvements at Griffin and 7th and Griffin and Rouse.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Design is 100% impact fee eligible.
New
Replacement
Equipment
Project
FY21 FY22 FY23
262
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF134
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Cottonwood to Flanders Mill) - Construction
FY19 FY20
$434,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Cottonwood to Flanders Mill, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks, and it completes an important east-west link between Ferguson and
Cottonwood. Future developments in this area may not be allowed to proceed until these improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan will be attained at completion. A payback District or SID may be created to leverage other
stakeholders. Other affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak
and Ferguson, Oak Street New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($434,000) and $430,000 for the local share adjacent to the City park, and an additional $430,000
from School District #7.
New
Replacement
Equipment
Project
FY21 FY22 FY23
263
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF136
DEPARTMENT
Street Impact Fees
PROJECT NAME
Babcock Widening Ferguson to Cottonwood
FY19 FY20 Unscheduled
$900,000
DESCRIPTION OF PROJECT
Widen Babcock to a 3-lane collector standard per the section defined in the 2017 Transportation Master Plan.
ALTERNATIVES CONSIDERED
Developer funded street expansion per the former streets policy where the developers on the south side of Babcock will upgrade the street as
development proceeds.
ADVANTAGES OF APPROVAL
Coordinate upgrade of the entire street segment with development along the south side of Babcock and use a payback district to recover costs
from development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The street already exists, and the street will be widened to add a center turn lane. Therefore additional striping and pavement maintenance will
be required for approximately 2,600 feet.
FUNDING SOURCES
Development funded improvement of the southern half of the street per the former streets policy under which the northern half of the street
improvement was constructed.
New
Replacement
Equipment
Project
FY21 FY22 FY23
264
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF137
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood (Durston to Oak) - Design
FY19
$250,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design of 5 lane arterial in FY 19 to allow construction in FY20
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city as well as network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
265
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF138
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood Road, Oak to Baxter - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construction of a 5 lane Principal Arterial Street
ALTERNATIVES CONSIDERED
SID, Payback District, TOPS, incremental construction by adjacent developers.
ADVANTAGES OF APPROVAL
The project will expand the capacity and improve the connectivity of the city street network. It will improve safety for drivers and pedestrians
and improve access to the Sports Park. It will facilitate development currently occurring in this part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
The total project cost is $2.5M. $750K will come from Impact Fees, the remainder is the local share which will come from either TOPS money,
BSD 7 an SID or Payback of some sort or some combination of these.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$500,000
266
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF139
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Flanders Mill to Ryun Sun Way) - Design
FY19
$150,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design of 5 lane arterial in FY 19 to allow construction in FY20.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city as well as network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
267
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF140
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Cottonwood to Flanders Mill) - Design
FY19
$180,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project is to design the street segment of Oak St, from Cottonwood to Flanders Mill, to a five-lane urban principal arterial
standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding additional lanes,
dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to proceed until these improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
This project completes an important east-west link between Ferguson and Cottonwood, and conformance with the
Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak and Ferguson, Oak
Street New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
268
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF141
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood Road, Oak to Baxter - Design
FY19
$250,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design a 5 lane Principal Arterial Street
ALTERNATIVES CONSIDERED
SID, Payback District, TOPS, incremental construction by adjacent developers.
ADVANTAGES OF APPROVAL
The project will expand the capacity and improve the connectivity of the city street network. It will improve safety for drivers and pedestrians
and improve access to the Sports Park. It will facilitate development currently occurring in this part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
269
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF142
DEPARTMENT
Street Impact Fees
PROJECT NAME
Durston Road & N. 27th (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$1,200,000
DESCRIPTION OF PROJECT
Installation of a roundabout or signal at the intersection of Durston Road and N. 27th
ALTERNATIVES CONSIDERED
Accept the current level of service
ADVANTAGES OF APPROVAL
Increased capacity at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Incremental increases in sweeping, plowing, painting and general maintenance costs
FUNDING SOURCES
Arterial and Collector funds
New
Replacement
Equipment
Project
FY21 FY22 FY23
270
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF143
DEPARTMENT
Street Impact Fees
PROJECT NAME
Baxter & Cottonwood Intersection - Right of Way
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Purchase of the right of way necessary for the construction of the Baxter & Cottonwood intersection improvments
ALTERNATIVES CONSIDERED
Do not construct intersection until ROW obtained
ADVANTAGES OF APPROVAL
This project will allow an intersection to built
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
100% Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
$750,000
271
272
St
r
e
e
t
M
a
i
n
t
e
n
a
n
c
e
D
i
s
t
r
i
c
t
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
17
0
,
0
3
9
$
52
2
,
8
0
2
$
37
7
,
1
6
3
$
(4
6
6
,
7
3
8
)
$
(509,234)
$
(427,437)$
P
l
u
s
:
S
t
r
e
e
t
M
t
c
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
7
7
3
,
5
0
0
$
1,
6
6
1
,
9
6
1
$
1,
6
9
5
,
2
0
0
$
1,
7
2
9
,
1
0
4
$
1,
7
6
3
,
6
8
6
$
1,798,960 $ ‐ $
P
l
u
s
:
G
a
s
T
a
x
69
3
,
9
3
6
$
6
9
3
,
9
0
0
$
6
9
3
,
9
0
0
$
6
9
3
,
9
0
0
$
6
9
3
,
9
0
0
$
6
9
3
,
9
0
0
$
L
e
s
s
:
C
a
r
r
y
o
v
e
r
F
Y
1
7
C
a
p
i
t
a
l
P
r
o
j
e
c
t
s
(
4
5
2
,
6
7
3
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(
1
,
6
6
2
,
0
0
0
)
$
(
2
,
5
0
1
,
5
0
0
)
$
(
3
,
2
3
3
,
0
0
0
)
$
(
2
,
4
6
5
,
5
0
0
)
$
(
2
,
3
7
5
,
7
8
9
)
$
(
1
,
9
8
5
,
0
0
0
)
$ (3,581,210)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
52
2
,
8
0
2
$
3
7
7
,
1
6
3
$
(
4
6
6
,
7
3
8
)
$
(
5
0
9
,
2
3
4
)
$
(
4
2
7
,
4
3
7
)
$
8
0
,
4
2
3
$
As
s
u
m
p
t
i
o
n
s
a
r
e
m
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY22 FY23
Es
t
i
m
a
t
e
d
U
n
d
e
s
i
g
n
a
t
e
d
A
n
n
u
a
l
S
t
r
e
e
t
M
t
c
R
e
v
e
n
u
e
s
4,
5
4
7
,
4
3
6
$
4,
1
7
7
,
8
8
0
$
4,
2
6
1
,
4
3
7
$
4,
3
4
6
,
6
6
6
$
4,433,599
$
4,522,271 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
‐
A
t
t
r
i
b
u
t
e
d
t
o
A
n
n
e
x
a
t
i
o
n
s
2%
2%
2%
2%2%
A
n
n
u
a
l
I
n
c
r
e
a
s
e
i
n
P
a
v
e
m
e
n
t
M
a
i
n
t
e
n
a
n
c
e
0%
0%
0%
0%0%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
4,
5
4
7
,
4
3
6
$
4,
2
6
1
,
4
3
7
$
4,
3
4
6
,
6
6
6
$
4,
4
3
3
,
5
9
9
$
4,522,271
$
4,612,71 7 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
30
.
0
%
39
.
0
%
3
9
.
0
%
3
9
.
0
%
3
9
.
0
%
3
9
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
9.
0
%
0.
0
%
0.
0
%
0
.
0
%
0.0% 0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
39
.
0
%
39
.
0
%
3
9
.
0
%
3
9
.
0
%
3
9
.
0
%
3
9
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
7
7
3
,
5
0
0
$
1,
6
6
1
,
9
6
1
$
1,
6
9
5
,
2
0
0
$
1,
7
2
9
,
1
0
4
$
1,763,68 6
$
1,798,96 0 $
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
3
,
2
3
3
,
0
0
0
)
$
(
2
,
4
6
5
,
5
0
0
)
$
(
2
,
3
7
5
,
7
8
9
)
$
(
1
,
9
8
5
,
0
0
0
)
$
(
3
,
5
8
1
,
2
1
0
)
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY
2
3
ST
R
E
E
T
M
A
I
N
T
E
N
A
N
C
E
P
R
O
J
E
C
T
S
&
EQ
U
I
P
M
E
N
T
27
3
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
St
r
e
e
t
Ma
i
n
t
e
n
a
n
c
e
Fu
n
d
ST
R
7
1
-
1
9
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
M
I
L
L
&
O
V
E
R
L
A
Y
)
-
FY
1
9
$5
5
4
,
5
0
0
ST
R
7
1
-
2
0
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
M
I
L
L
&
O
V
E
R
L
A
Y
)
-
FY
2
0
$9
8
6
,
0
0
0
ST
R
7
1
-
2
1
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
M
I
L
L
&
O
V
E
R
L
A
Y
)
-
FY
2
1
$9
6
4
,
0
0
0
ST
R
7
1
-
2
2
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
M
I
L
L
&
O
V
E
R
L
A
Y
)
-
FY
2
2
$9
1
3
,
3
2
9
ST
R
7
1
-
2
3
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
M
I
L
L
&
O
V
E
R
L
A
Y
)
-
FY
2
3
$1,014,000
ST
R
7
2
-
1
9
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
C
H
I
P
S
E
A
L
)
-
F
Y
1
9
$8
2
7
,
0
0
0
ST
R
7
2
-
2
0
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
C
H
I
P
S
E
A
L
)
-
F
Y
2
0
$9
1
3
,
0
0
0
ST
R
7
2
-
2
1
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
C
H
I
P
S
E
A
L
)
-
F
Y
2
1
$9
0
2
,
5
0
0
ST
R
7
2
-
2
2
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
C
H
I
P
S
E
A
L
)
-
F
Y
2
2
$7
2
7
,
4
6
0
ST
R
7
2
-
2
3
En
g
i
n
e
e
r
i
n
g
ST
R
E
E
T
I
M
P
R
O
V
E
M
E
N
T
S
-
M
A
I
N
T
E
N
A
N
C
E
&
R
E
H
A
B
I
L
I
T
A
T
I
O
N
(
C
H
I
P
S
E
A
L
)
-
F
Y
2
3
$316,000
ST
R
7
5
En
g
i
n
e
e
r
i
n
g
AN
N
U
A
L
P
E
D
E
S
T
R
I
A
N
R
A
M
P
RE
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
$100,000
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
ST
R
7
6
En
g
i
n
e
e
r
i
n
g
DO
W
N
T
O
W
N
B
O
Z
E
M
A
N
C
R
E
E
K
C
U
L
V
E
R
T
AS
S
E
S
S
M
E
N
T
$1
5
,
0
0
0
ST
R
7
7
En
g
i
n
e
e
r
i
n
g
OA
K
A
N
D
7
T
H
I
N
T
E
R
S
E
C
T
I
O
N
U
P
G
R
A
D
E
$6
0
,
0
0
0
$1,430,000
$1
,
5
5
6
,
5
0
0
$1
,
9
9
9
,
0
0
0
$1
,
9
6
6
,
5
0
0
$1
,
7
4
0
,
7
8
9
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
St
r
e
e
t
Ma
i
n
t
e
n
a
n
c
e
Fu
n
d
27
4
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
PW
0
5
Pu
b
l
i
c
W
o
r
k
s
PU
B
L
I
C
W
O
R
K
S
S
H
O
P
S
M
A
S
T
E
R
P
L
A
N
$2
0
,
0
0
0
PW
0
6
Pu
b
l
i
c
W
o
r
k
s
PU
B
L
I
C
W
O
R
K
S
S
H
O
P
S
F
A
C
I
L
I
T
Y
CO
N
S
T
R
U
C
T
I
O
N
$6
7
0
,
0
0
0
ST
R
5
3
Pu
b
l
i
c
W
o
r
k
s
ME
N
D
E
N
H
A
L
L
&
B
A
B
C
O
C
K
S
T
R
E
E
T
S
C
A
P
E
$2,076,210
$2
0
,
0
0
0
$6
7
0
,
0
0
0
$2,076,210
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
St
r
e
e
t
Ma
i
n
t
e
n
a
n
c
e
Fu
n
d
ST
R
6
8
Si
g
n
s
&
S
i
g
n
a
l
s
RE
C
T
A
N
G
U
L
A
R
R
A
P
I
D
F
L
A
S
H
I
N
G
B
E
A
C
O
N
$10,000
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
ST
R
7
8
Si
g
n
s
&
S
i
g
n
a
l
s
RE
P
L
A
C
E
#
2
7
4
8
-
1
9
9
9
S
E
R
V
I
C
E
T
R
U
C
K
WI
T
H
A
M
I
D
S
I
Z
E
P
I
C
K
U
P
.
$35,000
ST
R
7
9
Si
g
n
s
&
S
i
g
n
a
l
s
SI
G
N
M
A
K
I
N
G
M
A
C
H
I
N
E
$6
0
,
0
0
0
ST
R
8
0
Si
g
n
s
&
S
i
g
n
a
l
s
UT
I
L
I
T
Y
T
E
R
R
A
IN
V
E
H
I
C
L
E
$5
5
,
0
0
0
$45,000
$1
2
5
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
St
r
e
e
t
Ma
i
n
t
e
n
a
n
c
e
Fu
n
d
ST
R
0
1
St
r
e
e
t
O
p
e
r
a
t
i
o
RE
P
L
A
C
E
#
1
5
3
9
-
2
W
D
1
9
9
0
F
O
R
D
R
A
N
G
E
R
$1
6
,
0
0
0
ST
R
0
1
St
r
e
e
t
Op
e
r
a
t
i
o
n
s
RE
P
L
A
C
E
#
2
7
4
9
-
1
9
9
7
F
O
R
D
1
T
O
N
MA
N
U
A
L
T
R
A
N
S
M
I
S
S
I
O
N
F
3
5
0
$4
5
,
0
0
0
ST
R
2
0
St
r
e
e
t
O
p
e
r
a
t
i
o
AN
N
U
A
L
B
I
K
E
P
A
T
H
I
M
P
R
O
V
E
M
E
N
T
S
$25,000
$2
5
,
0
0
0
$2
5
,
0
0
0
$2
5
,
0
0
0
$2
5
,
0
0
0
ST
R
2
2
St
r
e
e
t
O
p
e
r
a
t
i
o
GR
A
D
E
R
L
E
A
S
E
$60,000
$6
0
,
0
0
0
$6
0
,
0
0
0
$6
0
,
0
0
0
$6
0
,
0
0
0
ST
R
3
0
St
r
e
e
t
Op
e
r
a
t
i
o
n
s
AN
N
U
A
L
M
E
D
I
A
N
&
B
O
U
L
E
V
A
R
D
MA
I
N
T
E
N
A
N
C
E
$75,000
$5
5
,
0
0
0
$6
0
,
0
0
0
$6
5
,
0
0
0
$7
0
,
0
0
0
ST
R
3
4
St
r
e
e
t
O
p
e
r
a
t
i
o
SW
E
E
P
E
R
S
$100,000
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
ST
R
3
5
St
r
e
e
t
O
p
e
r
a
t
i
o
RE
G
E
N
E
R
A
T
I
V
E
A
I
R
S
W
E
E
P
E
R
$250,000
ST
R
4
0
St
r
e
e
t
O
p
e
r
a
t
i
o
DU
M
P
T
R
U
C
K
W
I
T
H
P
L
O
W
&
S
A
N
D
E
R
-
2
$210,000
$2
0
0
,
0
0
0
ST
R
4
9
St
r
e
e
t
O
p
e
r
a
t
i
o
SA
N
D
E
R
S
$27,000
$2
7
,
0
0
0
$2
7
,
0
0
0
$2
7
,
0
0
0
$2
7
,
0
0
0
ST
R
5
0
St
r
e
e
t
O
p
e
r
a
t
i
o
PL
O
W
S
$13,000
$1
2
,
0
0
0
$1
2
,
0
0
0
$1
2
,
0
0
0
$1
3
,
0
0
0
ST
R
5
8
St
r
e
e
t
Op
e
r
a
t
i
o
n
s
TA
N
D
E
M
A
X
L
E
D
U
M
P
T
R
U
C
K
W
I
T
H
P
L
O
W
&
S
A
N
D
E
R
$2
5
0
,
0
0
0
27
5
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
ST
R
6
3
St
r
e
e
t
O
p
e
r
a
t
i
o
RE
P
L
A
C
E
S
I
G
N
A
L
A
T
B
A
B
C
O
C
K
&
W
I
L
S
O
N
$750,000
ST
R
7
3
St
r
e
e
t
O
p
e
r
a
t
i
o
RE
P
L
A
C
E
S
K
I
D
S
T
E
E
R
$9
0
,
0
0
0
ST
R
7
4
St
r
e
e
t
O
p
e
r
a
t
i
o
PA
I
N
T
T
R
U
C
K
$225,000
ST
R
8
1
St
r
e
e
t
O
p
e
r
a
t
i
o
BR
I
N
E
M
A
K
I
N
G
M
A
C
H
I
N
E
W
I
T
H
B
U
I
L
D
I
N
G
$200,000
ST
R
8
2
St
r
e
e
t
O
p
e
r
a
t
i
o
MO
T
O
R
G
R
A
D
E
R
L
E
A
S
E
P
A
Y
O
F
F
$1
7
0
,
0
0
0
ST
R
8
3
St
r
e
e
t
Op
e
r
a
t
i
o
n
s
N.
2
7
T
H
M
E
D
I
A
N
L
A
N
D
S
C
A
P
I
N
G
A
N
D
IR
R
I
G
A
T
I
O
N
F
R
O
M
O
A
K
T
O
B
A
X
T
E
R
$4
0
,
0
0
0
ST
R
8
4
St
r
e
e
t
O
p
e
r
a
t
i
o
PL
U
G
I
N
E
L
E
C
T
R
I
C
W
O
R
K
T
R
U
C
K
.
$6
0
,
0
0
0
ST
R
8
5
St
r
e
e
t
O
p
e
r
a
t
i
o
RE
P
L
A
C
E
1
9
9
2
W
H
E
E
L
L
O
A
D
E
R
$1
8
0
,
0
0
0
ST
R
8
6
St
r
e
e
t
Op
e
r
a
t
i
o
n
s
S.
2
7
T
H
M
E
D
I
A
N
L
A
N
D
S
C
A
P
I
N
G
A
N
D
IR
R
I
G
A
T
I
O
N
F
R
O
M
K
U
R
K
T
O
B
L
A
C
K
W
O
O
D
.
$2
0
,
0
0
0
ST
R
8
7
St
r
e
e
t
Op
e
r
a
t
i
o
n
s
SP
O
T
P
R
O
J
E
C
T
S
A
S
R
E
C
O
M
M
E
N
D
E
D
B
Y
TH
E
B
O
Z
E
M
A
N
A
R
E
A
B
I
C
Y
C
L
E
A
D
V
I
S
O
R
Y
BO
A
R
D
(
B
A
B
A
B
)
.
$50,000
ST
R
8
8
St
r
e
e
t
Op
e
r
a
t
i
o
n
s
SP
O
T
P
R
O
J
E
C
T
S
A
S
R
E
C
O
M
M
E
N
D
E
D
B
Y
TH
E
P
E
D
E
S
T
R
I
A
N
T
R
A
F
F
I
C
A
N
D
S
A
F
E
T
Y
CO
M
M
I
T
T
E
E
.
$30,000
ST
R
8
9
St
r
e
e
t
O
p
e
r
a
t
i
o
SP
R
A
Y
P
A
T
C
H
T
R
U
C
K
$2
5
0
,
0
0
0
$510,000
$8
0
0
,
0
0
0
$5
5
4
,
0
0
0
$4
8
9
,
0
0
0
$6
2
5
,
0
0
0
$1,505,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
S
t
r
e
e
t
M
a
i
n
t
e
n
a
n
c
e
F
u
n
d
(
4
3
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$1,985,000
$2
,
5
0
1
,
5
0
0
$3
,
2
3
3
,
0
0
0
$3,581,210FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$2
,
3
7
5
,
7
8
9
$2
,
4
6
5
,
5
0
0
FY
2
1
27
6
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
PW05
DEPARTMENT
Public Works
PROJECT NAME
Public Works Shops Master Plan
FY19
$20,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Develop a long term master plan for Public Works shop facilities, equipment, and personnel. This includes conducting a needs
assessment of space for existing and future employees, equipment, machinery, and rolling stock. There is a severe shortage of
enclosed storage for equipment, vehicles, and machinery, resulting in extra wear and tear, additional maintenance costs, and time
preparing the equipment on cold mornings. Additionally, there is a lack of space available for existing as well as future staff. This
will be split three ways between water ($20,000), wastewater ($20,000), and streets ($20,000).
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
Provide an accurate analysis of the City of Bozeman Public Works space needs for both equipment as well as people.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Depending on the results of the plan, the likely result will be the construction of additional storage and office space.
FUNDING SOURCES
This project will be split 3 ways between Water Fund ($20,000), Wastewater Fund ($20,000), and Street Maintenance Fund ($20,000)
New
Replacement
Equipment
Project
FY21 FY22 FY23
277
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
PW06
DEPARTMENT
Public Works
PROJECT NAME
Public Works Shops Facility Construction
FY19 FY20
$670,000
Unscheduled
DESCRIPTION OF PROJECT
Construct additional facilities recommended in the result of the Public Works Shops Master Plan. This will be split three ways
between water ($670,000), wastewater ($670,000), and streets ($670,000).
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
The construction of a new Public Works facility will provide indoor storage for millions of dollars of equipment, machinery, vehicles, etc. This
will both reduce wear and tear and maintenance costs, as well as reduce time spent on preparing equipment on cold mornings.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal building maintenance and utility costs.
FUNDING SOURCES
This project will be split 3 ways between Water Fund ($670,000), Wastewater Fund ($670,000), and Street Maintenance Fund ($670,000)
New
Replacement
Equipment
Project
FY21 FY22 FY23
278
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR01
DEPARTMENT
Street Operations
PROJECT NAME
Replace #2749 - 1997 Ford 1 Ton Manual Transmission F350
FY19
$45,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace #2749 - 1997 Ford 1 Ton Manual Transmission F350. Setting up and mobilizing to the job site is done with this truck and
a trailer. Being able to leave the truck hooked up to the trailer during the project helps with transporting and also utilizing the
smallest work area in neighborhoods. Single pieces of equipment scattered over blocks in the core not only inconveniences the
residents where we are working but affects the surrounding blocks as well. Without this truck operating reliably, we have to
drive equipment to the site which can take a paver or skid steer more than an hour to travel through town.
ALTERNATIVES CONSIDERED
Run to failure.
ADVANTAGES OF APPROVAL
A much more useable year round truck. Better fuel mileage and lower emissions. We are spending about $.90 per mile on maintenance and
repairs. A new vehicle spends about $.05 per mile on M&R. Anytime M&R exceed $.50 per mile, it is time to consider removing the truck from
the fleet.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal routine maintenance.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21 FY22 FY23
279
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR01
DEPARTMENT
Street Operations
PROJECT NAME
Replace #1539 - 2WD 1990 Ford Ranger
FY19
$16,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace #1539 - 2WD 1990 Ford Ranger with Hybrid Sedan. We would buy one of the Public Works lease hybrids. Their lease
ends in. Currently when we need to do inspections, inventories, GIS, training trips or take several people on route training, we
use several vehicles or make several trips. A hybrid sedan to replace the truck would be much more useful. This vehicle will be
able to carry up to 4 people at a time, and would be available to other departments as needed.
ALTERNATIVES CONSIDERED
Run to failure.
ADVANTAGES OF APPROVAL
A much more useable year round vehicle. Better fuel mileage and lower emissions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal routine maintenance.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21 FY22 FY23
280
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR20
DEPARTMENT
Street Operations
PROJECT NAME
Annual Bike Path Improvements
FY19
$25,000
FY20
$25,000
Unscheduled
DESCRIPTION OF PROJECT
This item would provide for bike-related infrastructure including (but, not limited to) racks, signs, striping, curb-cuts, and
separated pathways. The Greater Bozeman Area Transportation Plan (2007 Update) Section 5.4 Recommended Bicycle Facility
Improvements outlines many facilities. The Bozeman Area Bicycle Advisory Board (BABAB) gave the City their top 2 priorities:
They are listed with City Engineering cost estimates: North 11th Ave - Mendenhall to Durston, $14,500: Willson Ave - Main
Street to Kagy Blvd, $54,300. This money can be combined with street re-surfacing projects.
ALTERNATIVES CONSIDERED
Continue with existing infrastructure.
ADVANTAGES OF APPROVAL
Safety will likely be improved.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs.
FUNDING SOURCES
100% Street Maintenance Fund
New
Replacement
Equipment
Project
FY21
$25,000
FY22
$25,000
FY23
$25,000
281
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR22
DEPARTMENT
Street Operations
PROJECT NAME
Grader Lease
FY19
$60,000
FY20
$60,000
Unscheduled
DESCRIPTION OF PROJECT
This is a request to establish at a minimum a 20 year replacement schedule for our graders. Currently our fleet is comprised of a
1994, 1998, 2003, 2007, and 2014. Grading the residential streets is critical to safe travel of our citizens. Pulling the snow out
from the curb so it can be blown into trucks and hauled away is important to parking in the downtown and other business areas.
These graders will be all-wheel drive, which increases our productivity. Newer equipment has fewer breakdowns and better fuel
economy which means less time in the shop and fueling during a shift. The old grader would be traded in or auctioned.
ALTERNATIVES CONSIDERED
Budget 250k every 5 years to purchase. Cut back on our use of graders in the residential areas. Continue to use what we have and replace when
we have complete failure.
ADVANTAGES OF APPROVAL
Much more reliable and fuel efficient equipment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Decrease in costs due to newer equipment.
FUNDING SOURCES
100% Street Maintenance Revenue
New
Replacement
Equipment
Project
FY21
$60,000
FY22
$60,000
FY23
$60,000
282
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR30
DEPARTMENT
Street Operations
PROJECT NAME
Annual Median & Boulevard Maintenance
FY19
$55,000
FY20
$60,000
Unscheduled
DESCRIPTION OF PROJECT
This provides funding for the annual maintenance of Bozeman’s medians. This includes sprinkler installation and maintenance,
landscaping, mowing, and general maintenance of Bozeman’s medians and boulevards. Annual increases are due to expected
growth.
ALTERNATIVES CONSIDERED
None.
ADVANTAGES OF APPROVAL
Making our currently unmaintained medians into weed free low maintenance show pieces. We are partnering internally with the Water
Conservation Manager and externally with MSU to design and install low water easily maintained medians. Also contract out the maintenance on
our established medians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None. Lower water use means lower utility costs.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21
$65,000
FY22
$70,000
FY23
$75,000
283
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR34
DEPARTMENT
Street Operations
PROJECT NAME
Sweepers
FY19
$100,000
FY20
$100,000
Unscheduled
DESCRIPTION OF PROJECT
This is for leasing or purchasing sweepers through the MACI (Montana Air and Congestion Initiative) equipment purchase
program. These are mechanical sweepers that if necessary can be operated without using water. The next sweeper we would
replace is our 2005 model with 59,000 miles and 9372 hours. It is scheduled for an elevator replacement next year and we would
like to replace rather than repair at a cost of $15,000. Industry standards show it is best to replace municipal sweepers at 5 years.
We are able to get about 10 years due to our excellent maintenance program. The City's MS4 Stormwater Permitting requires
sweeping up sand and dirt before it can enter waterways. Clean streets/ bike lanes are a quality of life issue. We are required to
meet the goal of sweeping all local streets twice per year, monthly sweeping of all arterial and collector roadways and weekly
sweeping of Main Street, most bike lanes weekly during the summer. Heavy development activity requires additional sweeping in
construction areas. Sweepers are very high maintenance as they age. Leases terms for sweepers are a maximum of 5 years due to
life expectancy. We are currently in the 3rd year of one lease. This additional sweeper lease would replace our oldest sweeper a
2006. We submit every year to the Montana Department of Transportation's (MDT) Montana Air and Congestion Initiative
(MACI) equipment purchase program for sweepers. With this program, MACI pays for 87% and we pay 13% for a sweeper. If we
are chosen, we would use our lease payment to fund our share of the cost which would be ~$34,000.
ALTERNATIVES CONSIDERED
Budget 250k every year until all sweepers are replaced. Cut back on our sweeping There are no local contractors at this time. Continue to use
what we have.
ADVANTAGES OF APPROVAL
Much improved operations. Better air quality. Improved storm water discharge.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21
$100,000
FY22
$100,000
FY23
$100,000
284
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR35
DEPARTMENT
Street Operations
PROJECT NAME
Regenerative Air Sweeper
FY19 FY20 Unscheduled
$250,000
DESCRIPTION OF PROJECT
We have had demonstrations of these sweepers and their ability to get the fine particles off of the pavement is noticeable. As air
quality and Stormwater discharge regulations tighten, we may be forced to use regenerative type sweepers or at the very least
have one in our fleet to do the final sweeping pass to get the <1 micron particles that can become airborne. Rather than make
several passes with our mechanical sweepers, an RA sweeper could get it done in one pass. The one drawback is that RA
sweepers cannot be used below freezing. They need water at all times.
ALTERNATIVES CONSIDERED
Only use mechanical sweepers which discharge dust when sweeping.
ADVANTAGES OF APPROVAL
We could improve our discharge into the storm water system. Spring sweeping of the winter sand would generate less dust therefore
eliminating complaints from citizens and DEQ.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal sweeper maintenance costs.
FUNDING SOURCES
100% Street Maintenance District
New
Replacement
Equipment
Project
FY21 FY22 FY23
285
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR40
DEPARTMENT
Street Operations
PROJECT NAME
Dump Truck With Plow & Sander - 2
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The 1990 Dump truck will be 28 years old with 82,000 in town miles and over 10,000 hours. Parts have been discontinued. We
have had to patch the leaking gas tank because a replacement is not available. When the other rusted spots start leaking we will
be forced to park the truck. The motor is so tired that we are removing the plow this winter because it doesn’t have the power
to plow and sand uphill. We average about $1,200 per year in repairs and maintenance. The running and floor boards are rusted
through but we are able to cover them with old mud flaps to make it drivable. Parts availability will be what stops this truck.
Single axle dump trucks are used on smaller projects in the summer including alley maintenance, asphalt patching and debris
pickup. In the winter these trucks are the only equipment we can safely and efficiently plow the narrow streets. We are able to
haul snow in tight quarters also. Additionally, the 1990 underpowered gasoline engine dump truck that averages about 3 MPG
when used for plowing operations. The FY21 request will replace a 1993 underpowered gasoline engine dump truck. The new
truck could be fueled with alternative fuels such as Biodiesel. Estimates show that the 1990 spews over 30 tons of CO2 into the
air per year and by removing this from our fleet will help us reach our goal of reducing municipal greenhouse emissions 15%
below 2000 levels by 2020. This truck will also be available for use by other departments.
ALTERNATIVES CONSIDERED
Continue with 1993 model.
ADVANTAGES OF APPROVAL
Efficiency, less emissions, safety, fuel savings and more reliable equipment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Less than current model.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21
$200,000
FY22 FY23
$210,000
286
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR49
DEPARTMENT
Street Operations
PROJECT NAME
Sanders
FY19
$27,000
FY20
$27,000
Unscheduled
DESCRIPTION OF PROJECT
Sanders are used in a very corrosive and abrasive environments. We rebuild the conveyor and hydraulic system in the first 4
years. If we don’t have a have a catastrophic failure in the next 2-3 years, the V box and structural components start to fail in the
7th year. By replacing the sander every 8 years (we now have 8 sanders), we can avoid having a season ending failure. Sanders are
about 6 months out when ordering so we would never get a new one in the same season that we needed a replacement. We
have two different sizes so we could run them until they fail during a major storm and then have one of each size sitting here. The
problem with that is the new sanders would be aging without being used. Using this method we could have two failures in one
year and be short one sander. If we can't put down sand or deicer during the winter, we fail to service our citizens. Not being
able to control the quantity, means we are either putting down too much or too little product. Too much sand and we increase
our spring sweeping and too little sand and the crashes increase.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
More reliable sanders. Less failures in the middle of a storm.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Decrease in maintenance costs.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21
$27,000
FY22
$27,000
FY23
$27,000
287
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR50
DEPARTMENT
Street Operations
PROJECT NAME
Plows
FY19
$12,000
FY20
$12,000
Unscheduled
DESCRIPTION OF PROJECT
This is to replace the worn plow blades. With as much as a 90 day delivery time to replace a plow, it is important to replace them
before they fail. When the moldboard of the plow gets bent after several years of use, it is very difficult to bolt on a replacement
cutting edge. If they are not tight to the cutting edge surface they face early failure and require replacement at inopportune times.
We have 7 large plows so they will be on a 7 year replacement schedule.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
A much more efficient plow operation. Less time spent replacing cutting edges that prematurely break.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21
$12,000
FY22
$13,000
FY23
$13,000
288
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR53
DEPARTMENT
Public Works
PROJECT NAME
Mendenhall & Babcock Streetscape
FY19 FY20 Unscheduled
$2,076,210
DESCRIPTION OF PROJECT
Conduct Streetscape Improvements Along Mendenhall & Babcock (On Hold For SID Development)
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
289
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR58
DEPARTMENT
Street Operations
PROJECT NAME
Tandem Axle Dump Truck With Plow & Sander
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This is a request to replace a 1994 tandem axle truck with 128,000 miles and over 11,000 hours. It is very important that we get
the arterials and collectors plowed and sanded before 8 AM. When a tandem axle 10 yard truck is down for any period of time,
the backup is a 1990 gas engine single axle 4 yard truck which takes twice as long to finish a route if it stays in operation for the
entire shift. Not acceptable to our customers. With the widening of multiple collectors and arterials, the continued need for a
larger capacity truck to finish plow and sanding routines is critical to maintaining our service to the traveling public. During paving
operations, being able to haul twice as much asphalt cuts down on the number of trips to the asphalt plant. This makes the paving
crew more efficient and uses less fuel. The 1994 truck would be used as a backup in the winter and still be used for paving instead
of a single-axle truck.
ALTERNATIVES CONSIDERED
Continue with no tandem back up in the winter. Run single axle 4 yard dump trucks with asphalt operations
ADVANTAGES OF APPROVAL
Reliability, efficiency, less emissions and safety.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Less than the current model.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21 FY22
$250,000
FY23
290
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR63
DEPARTMENT
Street Operations
PROJECT NAME
Replace Signal At Babcock & Wilson
FY19 FY20 Unscheduled
$750,000
DESCRIPTION OF PROJECT
Upgrade Signal at Babcock & Wilson. Underground conduit is full and failing. Pedestrian functions should be upgraded to new type
such as count down and vibratory tactile. Additionally, the existing signal can't have Opticom for fire trucks.
ALTERNATIVES CONSIDERED
Leave as is until failure.
ADVANTAGES OF APPROVAL
Fire department can use Opticom to pass through the light. ADA requirements would be met. Room for future expansion in the conduit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance.
FUNDING SOURCES
Arterial and Collector Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
291
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR68
DEPARTMENT
Signs & Signals
PROJECT NAME
Rectangular Rapid Flashing Beacon
FY19
$10,000
FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
This request is for a rectangular rapid flashing beacon. We get several requests a year for these and would like to have one ready
to install. These would be similar to the unit installed on Kagy at 7th avenue. RRFB's have shown to increase visibility of
pedestrians in crosswalks which in turn increases safety of the pedestrian. In the past we have had the Bozeman School District
and the Bozeman Police Foundation contribute to the cost of these.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
By having one on hand, we are able to install it in the same construction season it is requested without waiting for a budget cycle.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
$10,000
292
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR71-19
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Mill & Overlay) - FY19
FY19
$554,500
FY20 Unscheduled
DESCRIPTION OF PROJECT
Mill and Overlays are a critical component to our pavement preservation program. We plan to mill and overlay 2.4 miles in FY19.
This includes W Babcock from Main to 11th, Koch from S 23rd to 11th, S 23rd from Main to College, and S 20th from Babcock
to Koch. There is potential for bike lane striping enhancements with some projects, and they will be coordinated with any
necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
293
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR71-20
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Mill & Overlay) - FY20
FY19 FY20
$986,000
Unscheduled
DESCRIPTION OF PROJECT
Mill and Overlays are a critical component to our pavement preservation program. We plan to mill and overlay 3.6 miles in FY20.
This includes Story Mill Rd from Bridger north to City Limits, Tamarack from N 7th to Rouse, N 5th from Peach to Tamarack, W
Aspen from N 7th to N 5th, N 3rd from Peach to Tamarack, Willson from Main to Cottonwood, and W Lincoln from 19th to
11th. There is potential for bike lane striping enhancements with some projects, and they will be coordinated with any necessary
utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
294
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR71-21
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Mill & Overlay) - FY21
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Mill and Overlays are a critical component to our pavement preservation program. We plan to mill and overlay 1.9 miles in FY21.
This includes Simmental Way from Baxter north, and Durston from Hanson to 19th. There is potential for bike lane striping
enhancements with some projects, and they will be coordinated with any necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21
$964,000
FY22 FY23
295
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR71-22
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Mill & Overlay) - FY22
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Mill and Overlays are a critical component to our pavement preservation program. We plan to mill and overlay 2.3 miles in FY22.
This includes N Church from Lamme to Peach, S 3rd from Kagy to Graf, W Graf from S 3rd to S 3rd, and S 3rd from Graf to
Goldenstein. There is potential for bike lane striping enhancements with some projects, and they will be coordinated with any
necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22
$913,329
FY23
296
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR71-23
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Mill & Overlay) - FY23
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Mill and Overlays are a critical component to our pavement preservation program. We plan to mill and overlay 5.7 miles in FY23.
This includes, Westglen Subdivision, Michaels Grove from Babcock to Durston, Hunters Way from Babcock to Durston,
Greenway Subdivision, N 25th from Babcock to Durston, N 24th from Babcock to Beall, Church from Main to Babcock, Church
from Olive to Kagy, N 11th from main to Durston, S 10th from Main to Olive, S 9th from Main to Olive, and W Olive from 11th
to 8th. There is potential for bike lane striping enhancements with some projects, and they will be coordinated with any
necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
$1,014,000
297
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR72-19
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Chip Seal) - FY19
FY19
$827,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Chip seals are a critical component to our pavement preservation program. We plan to chip seal 15.6 miles in FY19. This
includes Oak Springs Subdivision, Diamond Estates Subdivision, Ferguson Meadows Subdivision, Valley Unit Subdivision, Bridger
Peaks Estates Subdivision, Cascade Subdivision, Garden Valley Estates Subdivision, Valley Creek Subdivision, Parkway Plaza
Subdivision, Babcock from Meagher to main, Fowler from Babcock to Garfield and Garfield from Fowler to 19th. There is
potential for bike lane striping enhancements with some projects, and they will be coordinated with any necessary utility
replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
298
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR72-20
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Chip Seal) - FY20
FY19 FY20
$913,000
Unscheduled
DESCRIPTION OF PROJECT
Chip seals are a critical component to our pavement preservation program. We plan to chip seal 13.5 miles in FY20. This
includes Meadow Creek Subdivision, Alder Creek Subdivision, Woodridge Addition, Westridge Subdivision, Thompson Addition,
Kagy Crossroads Subdivision, S 11th from Kagy to University Way, West Park Manor Subdivision, Kirk Subdivision, and 15th from
Main north. There is potential for bike lane striping enhancements with some projects, and they will be coordinated with any
necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
299
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR72-21
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Chip Seal) - FY21
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Chip seals are a critical component to our pavement preservation program. We plan to chip seal 19.3 miles in FY21. This
includes Laurel Glen Subdivision, Baxter Meadows Subdivision, Cattail Creek Subdivision, Crossing 2 Subdivision, West Winds
Subdivision, and N 27th Ave from Oak north. There is potential for bike lane striping enhancements with some projects, and they
will be coordinated with any necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21
$902,500
FY22 FY23
300
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR72-22
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Chip Seal) - FY22
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Chip seals are a critical component to our pavement preservation program. We plan to chip seal 13.7 miles in FY22. This
includes Bridger Creek Subdivision, Legends at Bridger Creek, Traditions Subdivision, Flanders Creek Subdivision, Norton East
Ranch Subdivision, J & D Family Subdivision, Valley West Subdivision, and Babcock from Cottonwood west. There is potential for
bike lane striping enhancements with some projects, and they will be coordinated with any necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22
$727,460
FY23
301
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR72-23
DEPARTMENT
Engineering
PROJECT NAME
Street Improvements - Maintenance & Rehabilitation (Chip Seal) - FY23
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Chip seals are a critical component to our pavement preservation program. We plan to chip seal 6.2 miles in FY23. This includes
Loyal Garden Subdivision, Southbridge Subdivision, and Westfield South Subdivision. There is potential for bike lane striping
enhancements with some projects, and they will be coordinated with any necessary utility replacement projects.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases the lifespan of streets within the City of Bozeman
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pavements.
FUNDING SOURCES
Street Maintenance Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
$316,000
302
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR73
DEPARTMENT
Street Operations
PROJECT NAME
Replace Skid Steer
FY19 FY20
$90,000
Unscheduled
DESCRIPTION OF PROJECT
This to replace our 2003 Skid Steer with 1750 hours. Used mainly in paving operations with the cold planer attached. This is very
important in our operation but is also very hard on the equipment. In the last 5 years we have spent over $26,000 in repairs.
Down time during these repairs has been weeks and that interferes with our ability to finish asphalt repairs in a timely manner.
Streets uses the skid steer in all aspects of milling, paving and gravel work. When we don't have the skid steer up and running, we
are using larger equipment using more fuel. Working in tight spaces is more difficult with a full size loader.
ALTERNATIVES CONSIDERED
Keep running the one we have.
ADVANTAGES OF APPROVAL
Less downtime
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21 FY22 FY23
303
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR74
DEPARTMENT
Street Operations
PROJECT NAME
Paint Truck
FY19 FY20 Unscheduled
$225,000
DESCRIPTION OF PROJECT
Pavement marking renewal is a yearly operation because we use environmentally friendly water borne paint. The disadvantage to
latex paint is that it has to be renewed at least annually. Currently we have MDT paint for us and due to their busy schedule it is
not always done as early in the season as we would like. We are now waiting until mid to late summer to get the double yellow
center lines, bike lane lines, skip lines and fog lines painted. MDT's crew is not as dialed in to the needs and wants of our citizens
so we are not getting the quality that we and our city is used to. Our crews would get it done in a timelier manner with fewer
mistakes. Fresh pavement markings are critical to the traveling public.
ALTERNATIVES CONSIDERED
Continue to have MDT paint for us when it is convenient for their schedule and weather permitting. Contract out the painting.
ADVANTAGES OF APPROVAL
Producing a quality product that we don't always get with our current MOU with MDT. Being able to paint when we want and as often as we
want.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This will need to be stored inside and we will have to make room for that in our current buildings.
FUNDING SOURCES
100% Street Maintenance District Revenue
New
Replacement
Equipment
Project
FY21 FY22 FY23
304
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR75
DEPARTMENT
Engineering
PROJECT NAME
Annual Pedestrian Ramp Replacement Program
FY19
$100,000
FY20
$100,000
Unscheduled
DESCRIPTION OF PROJECT
This annual program provides funding to continue upgrading pedestrain ramps to ADA compliance. A curb/pedestrain ramp
provides an accessible route that people with disabilities can use to safely transition from a roadway to a curbed sidewalk and vice
versa. Without access to properly developed ramps onto sidewalks, people with dissabilities are forced to risk their personal
safety by traveling in the street. Upgrading CoB pedestrain ramps will allow the City to be in compliance with Title II of the ADA
and Section 504 of the Rehabilitation Act of 1973 (Section 504). This project will be completed in coordination with the
Stormwater Divisions Annual Inlet Replacement Program (STRM48).
ALTERNATIVES CONSIDERED
Continue with existing infrastructure, and not meet current ADA regulatory standards
ADVANTAGES OF APPROVAL
Upgrading the curb ramps will increase safety for community members and visitors with disabilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs.
FUNDING SOURCES
50% Street Maintenance Fund & 50% Stormwater Fund
New
Replacement
Equipment
Project
FY21
$100,000
FY22
$100,000
FY23
$100,000
305
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR76
DEPARTMENT
Engineering
PROJECT NAME
Downtown Bozeman Creek Culvert Assessment
FY19
$15,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Assess the condition of the downtown Bozeman Creek culverts crossing Lamme St, Mendenhall St, Main St, Babcock St, Olive St,
and Rouse Ave. These are high risk assets that in the event of a failure, could result in extensive road and business closures
throughout the downtown corridor. This project is split between Stormwater ($15,000) and Street Maintenance ($15,000).
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Identifies susceptibility of downtown culverts to critical failure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
$15,000 Stormwater, $15,000 Street Maintenance
New
Replacement
Equipment
Project
FY21 FY22 FY23
306
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR77
DEPARTMENT
Engineering
PROJECT NAME
Oak and 7th Intersection Upgrade
FY19
$60,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of lane restriping on the westbound leg of the intersection to add a right-hand turn lane. To accommodate
the additional lane, a new signal head must also be added to the existing mast arm.
ALTERNATIVES CONSIDERED
Wait until Montana Department of Transportation completes upgrades to this intersection, which is still a viable option as this improvement is
tentatively being planned by MDT.
ADVANTAGES OF APPROVAL
Improve intersection operations as this intersection currently operates at a level-of-service of "D" in the PM peak hour. Upon addition of the
right-hand turn lane, the intersection will be constructed to its maximum turning and movement capacity.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Additional operating costs will be minimal due to the addition of a lane at the intersection.
FUNDING SOURCES
The Midtown Urban Renewal District is anticipated to fund this intersection upgrade.
New
Replacement
Equipment
Project
FY21 FY22 FY23
307
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR78
DEPARTMENT
Signs & Signals
PROJECT NAME
Replace #2748 - 1999 service truck with a mid size pick up.
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This is a request to replace a 1999, asset #2748, pick-up with over 140,000 miles. It will be 24 years old at time of replacement.
The truck would be traded in or auctioned.
ALTERNATIVES CONSIDERED
Keep using 1999 model until failure. Lease.
ADVANTAGES OF APPROVAL
Increased safety and reliability.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
None.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$35,000
308
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR79
DEPARTMENT
Signs & Signals
PROJECT NAME
Sign Making Machine
FY19
$60,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Our 13-year-old machine is no longer reliable. It gets stuck in Chinese font when we try to make street name signs and when IT
can get it back to English, it does not function as it should. We can no longer add special symbols like arrows, which we need
often. The new machine will print signs ready to go rather than as we do it now where we have to manually cut out the letters by
hand. Very time consuming.
ALTERNATIVES CONSIDERED
Order signs as needed from vendors. 2-4 week turn around time.
ADVANTAGES OF APPROVAL
Make signs as needed same day. Make specialty signs as needed.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
309
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR80
DEPARTMENT
Signs & Signals
PROJECT NAME
Utility Terrain Vehicle
FY19
$55,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Utility Terrain Vehicle (UTV) for use by the Sign and Signal Crew. These have been used in the Parks and Street Departments and
have found that they are very versatile. It would be used for curb painting, pavement markings, weed trimming, auguring
postholes, sign installation and work where tight spaces make it easier using the smaller UTV. We would be able to use all the
skid steer attachments that the City currently has as well as any hydraulically powered attachment.
ALTERNATIVES CONSIDERED
Continue to borrow when Toolcats are available from other departments.
ADVANTAGES OF APPROVAL
Efficiency in operations. Maneuverability in tight spaces. Versatility as many attachments can be used for different jobs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
310
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR81
DEPARTMENT
Street Operations
PROJECT NAME
Brine Making Machine With Building
FY19 FY20 Unscheduled
$200,000
DESCRIPTION OF PROJECT
This is a request for a brine-making machine to replace the use of Magnesium Chloride in the pre wetting of our sand. By wetting
the sand as it is applied, it cuts down on the amount of bounce when the sand hits the ground and gives some melting action. In
some communities, salt brine is used pre storm to keep the initial snow from bonding to the pavement. This could be used on
our known early freeze areas such as roundabouts and shaded areas.
ALTERNATIVES CONSIDERED
Keep using Mag.
ADVANTAGES OF APPROVAL
Less cost per gallon. Mag has a tendency to migrate into wiring looms on the truck. Brine does not.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Less cost after initial investment.
FUNDING SOURCES
None.
New
Replacement
Equipment
Project
FY21 FY22 FY23
311
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR82
DEPARTMENT
Street Operations
PROJECT NAME
Motor Grader Lease Payoff
FY19
$170,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Our 5-year lease will be up in FY19. This grader has been trouble free during the lease and the operators are efficient in its
operation. A used grader with the low hours, all preventative maintenance performed and the M Series with joystick controls
would be over $200,000 to purchase. Purchasing for $170,000 is a good buy and will give us years of service.
ALTERNATIVES CONSIDERED
Turn lease unit back in. Lease another new grader and turn this one back in.
ADVANTAGES OF APPROVAL
Keeping a grader that we know operationally and mechanically is good. Snow gate stays with the grader where a new one would need a new
snow gate.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal maintenance.
FUNDING SOURCES
None.
New
Replacement
Equipment
Project
FY21 FY22 FY23
312
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR83
DEPARTMENT
Street Operations
PROJECT NAME
N. 27th Median Landscaping and Irrigation from Oak to Baxter
FY19
$40,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Install irrigation, trees and turf where none exists on N 27th from Oak to Baxter.
ALTERNATIVES CONSIDERED
Concrete, paving or continue to mow and spray weeds.
ADVANTAGES OF APPROVAL
Aesthetics. A landscaped median has shown to calm traffic. Less maintenance than weeds.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
We would add this to our median maintenance contract. $4,000 per year for mowing and trimming per year.
FUNDING SOURCES
None.
New
Replacement
Equipment
Project
FY21 FY22 FY23
313
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR84
DEPARTMENT
Street Operations
PROJECT NAME
Plug In Electric Work Truck.
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This is a request to add to our fleet an electric work pickup. It would be a ½-ton four-wheel drive. Production is expected to
start in 2018 with preference given to fleets. With an estimated range of 80 miles between charges, it would be ideal in our
operations. Cost per day to charge would be about $4.00.
ALTERNATIVES CONSIDERED
Continue with gas powered trucks.
ADVANTAGES OF APPROVAL
Lower operating costs. Less emissions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Less than gasoline. 240 volt charging station would be needed at the Shops.
FUNDING SOURCES
Possible grants.
New
Replacement
Equipment
Project
FY21 FY22
$60,000
FY23
314
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR85
DEPARTMENT
Street Operations
PROJECT NAME
Replace 1992 Wheel Loader
FY19 FY20
$180,000
Unscheduled
DESCRIPTION OF PROJECT
This is a request to replace our 1992 CAT Wheel Loader that will be 28 years old at time of replacement. It currently has 11,839
hours. We are spending over $10,000 per year on maintenance and repairs. We will trade in this loader on the new unit. Since
this loader was built, improvements on wheel loaders include 50% reduction in fuel usage per hour, more than 50% emission
reduction of Oxides of Nitrogen (NOx) and Particulate Matter (PM), increased operator efficiency, wireless maintenance
reminders and better roll over protection (ROPS).
ALTERNATIVES CONSIDERED
Keep loader. Budget for repair costs.
ADVANTAGES OF APPROVAL
Reliability. Lower maintenance costs, increased productivity.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
None.
New
Replacement
Equipment
Project
FY21 FY22 FY23
315
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR86
DEPARTMENT
Street Operations
PROJECT NAME
S. 27th Median Landscaping and Irrigation from Kurk to Blackwood.
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Currently only one median has irrigation. This would extend the irrigation to all three and add turf and trees.
ALTERNATIVES CONSIDERED
Continue to mow and spray weeds. Concrete or pave.
ADVANTAGES OF APPROVAL
Aesthetics. Landscaped medians have shown to calm traffic. Not letting weeds go to seed.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This would be added to our Median Maintenance contract. $2,500 yearly.
FUNDING SOURCES
None.
New
Replacement
Equipment
Project
FY21 FY22
$20,000
FY23
316
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR87
DEPARTMENT
Street Operations
PROJECT NAME
Spot Projects as Recommended by the Bozeman Area Bicycle Advisory Board (BABAB).
FY19 FY20 Unscheduled
$50,000
DESCRIPTION OF PROJECT
This board would like to be able to recommend projects that might be outside the TMP. Project lists will be submitted to
Engineering and Streets.
ALTERNATIVES CONSIDERED
Only do projects that are part of a larger project.
ADVANTAGES OF APPROVAL
When an opportunity arises and the board can prioritize a list, money would be available.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Repainting of markings.
FUNDING SOURCES
Transportation Alternatives (TA).
New
Replacement
Equipment
Project
FY21 FY22 FY23
317
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR88
DEPARTMENT
Street Operations
PROJECT NAME
Spot Projects as Recommended by the Pedestrian Traffic and Safety Committee.
FY19 FY20 Unscheduled
$30,000
DESCRIPTION OF PROJECT
This committee would like to be able to recommend projects that might be outside the TMP. Project list will be submitted to
Engineering and Streets.
ALTERNATIVES CONSIDERED
Only do projects that are part of a larger project.
ADVANTAGES OF APPROVAL
When an opportunity arises and the committee can prioritize a list, money would be available.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Repainting of markings.
FUNDING SOURCES
Transportation Alternatives (TA).
New
Replacement
Equipment
Project
FY21 FY22 FY23
318
CIP Project Fund
Street Maintenance Fund
PROJECT NUMBER
STR89
DEPARTMENT
Street Operations
PROJECT NAME
Spray Patch Truck
FY19
$250,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Our pavement preservation program includes several types of patching from a simple patch to a mill and overlay. We have found
spray patching, where oil and aggregate is used to fill the pothole to be very efficient and effective. Spray patching allows pothole
patching during a wider range of temperatures and conditions. Currently we are using a trailer-mounted unit that takes at least
two operators with one working directly in traffic. It also ties up one dump truck making it unavailable for our mill and overlays
when we need all the trucks available. While this always gives us the patch we want, getting set up and then working around and
in traffic is not ideal. Traffic control and positioning the truck and trailer often take longer than the patching process. A truck-
mounted unit is a much quieter operation and could be used on our 3AM crew by just one operator. We have found spray
patches to be a permanent repair that has saved many streets from going over the cliff to reconstruction. Sealing alligator cracking
and low spots have prevented failures during the spring that lead to tire breaking potholes that are difficult to patch during wet
weather. Spray patching is the main reason we have not had a pothole claim in 3 years. We would trade in or sell our trailer
mounted unit.
ALTERNATIVES CONSIDERED
Keep using current method with trailer mounted unit.
ADVANTAGES OF APPROVAL
One operator operation vs. two. Greater temperature range we can operate. Quicker process so we can get more done.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal maintenance costs.
FUNDING SOURCES
None.
New
Replacement
Equipment
Project
FY21 FY22 FY23
319
320
Wa
s
t
e
w
a
t
e
r
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1
,
5
4
8
,
4
1
4
$
1
,
7
3
0
,
7
5
5
$
5
7
2
,
7
1
8
$
8
7
2
,
3
1
5
$
1
,
5
3
1
,
5
7
6
$
2
,
3
4
2
,
5
8
9
$ ‐ $
P
l
u
s
:
W
a
s
t
e
w
a
t
e
r
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
2,
1
8
8
,
8
0
0
$
2,
2
5
4
,
4
6
3
$
2,
3
2
2
,
0
9
7
$
2,
3
9
1
,
7
6
0
$
2,
4
6
3
,
5
1
3
$
2,537,419 $ ‐ $
L
e
s
s
:
F
Y
1
7
C
a
r
r
y
o
v
e
r
C
a
p
i
t
a
l
(1
9
3
,
9
5
9
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(1
,
8
1
2
,
5
0
0
)
$
(3
,
4
1
2
,
5
0
0
)
$
(2
,
0
2
2
,
5
0
0
)
$
(1
,
7
3
2
,
5
0
0
)
$
(1
,
6
5
2
,
5
0
0
)
$
(1,232,500)$ (12,484,333)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
7
3
0
,
7
5
5
$
57
2
,
7
1
8
$
87
2
,
3
1
5
$
1,
5
3
1
,
5
7
6
$
2,
3
4
2
,
5
8
9
$
3,647,507 $
A ss
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
W
a
s
t
e
w
a
t
e
r
R
e
v
e
n
u
e
s
8,
7
5
5
,
1
9
8
$
8,
7
5
5
,
1
9
8
$
9,
0
1
7
,
8
5
4
$
9,
2
8
8
,
3
9
0
$
9,567,041
$
9,854,052 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
0.
0
%
3%
3%
3%
3%3%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
8,
7
5
5
,
1
9
8
$
9,
0
1
7
,
8
5
4
$
9,
2
8
8
,
3
9
0
$
9,
5
6
7
,
0
4
1
$
9,854,052
$
10,149,674 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
25
.
0
%
25
.
0
%
2
5
.
0
%
2
5
.
0
%
2
5
.
0
%
2
5
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.0%0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
25
.
0
%
25
.
0
%
2
5
.
0
%
2
5
.
0
%
2
5
.
0
%
2
5
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
2,
1
8
8
,
8
0
0
$
2,
2
5
4
,
4
6
3
$
2,
3
2
2
,
0
9
7
$
2,
3
9
1
,
7
6
0
$
2,463,513
$
2,537,419 $
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
3
,
4
1
2
,
5
0
0
)
$
(
2
,
0
2
2
,
5
0
0
)
$
(
1
,
7
3
2
,
5
0
0
)
$
(
1
,
6
5
2
,
5
0
0
)
$
(
1
,
2
3
2
,
5
0
0
)
$
(
1
2
,
4
8
4
,
3
3
3
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
WA
S
T
E
W
A
T
E
R
F
U
N
D
P
R
O
J
E
C
T
S
&
EQ
U
I
P
M
E
N
T
32
1
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Wa
s
t
e
w
a
t
e
r
Fu
n
d
WW
0
7
En
g
i
n
e
e
r
i
n
g
AN
N
U
A
L
W
A
S
T
E
W
A
T
E
R
P
I
P
E
RE
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
-
D
E
S
I
G
N
$22,500
$2
2
,
5
0
0
$2
2
,
5
0
0
$2
2
,
5
0
0
$2
2
,
5
0
0
WW
0
8
-
1
9
En
g
i
n
e
e
r
i
n
g
WA
S
T
E
W
A
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
PR
O
G
R
A
M
-
C
O
N
S
T
R
U
C
T
I
O
N
I
N
2
0
1
9
$1
,
0
0
0
,
0
0
0
WW
0
8
-
2
0
En
g
i
n
e
e
r
i
n
g
WA
S
T
E
W
A
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
PR
O
G
R
A
M
-
C
O
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
0
$1
,
0
0
0
,
0
0
0
WW
0
8
-
2
1
En
g
i
n
e
e
r
i
n
g
WA
S
T
E
W
A
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
PR
O
G
R
A
M
-
C
O
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
1
$1
,
0
0
0
,
0
0
0
WW
0
8
-
2
2
En
g
i
n
e
e
r
i
n
g
WA
S
T
E
W
A
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
PR
O
G
R
A
M
-
C
O
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
2
$1
,
0
0
0
,
0
0
0
WW
0
8
-
2
3
En
g
i
n
e
e
r
i
n
g
WA
S
T
E
W
A
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
PR
O
G
R
A
M
-
C
O
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
3
$1,000,000
WW
2
7
En
g
i
n
e
e
r
i
n
g
AN
N
U
A
L
W
A
T
E
R
S
H
E
D
S
T
U
D
Y
&
S
T
R
E
A
M
MO
D
E
L
I
N
G
$60,000
$6
0
,
0
0
0
$6
0
,
0
0
0
$6
0
,
0
0
0
$6
0
,
0
0
0
$1,082,500
$1
,
0
8
2
,
5
0
0
$1
,
0
8
2
,
5
0
0
$1
,
0
8
2
,
5
0
0
$1
,
0
8
2
,
5
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
s
t
e
w
a
t
e
r
Fu
n
d
GF
2
2
7
Fi
n
a
n
c
e
ER
P
R
E
P
L
A
C
E
M
E
N
T
"
S
U
N
G
A
R
D
RE
P
L
A
C
E
M
E
N
T
/
U
P
G
R
A
D
E
"
$333,333 $333,333
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
s
t
e
w
a
t
e
r
Fu
n
d
PW
0
5
Pu
b
l
i
c
W
o
r
k
s
PU
B
L
I
C
W
O
R
K
S
S
H
O
P
S
M
A
S
T
E
R
P
L
A
N
$2
0
,
0
0
0
PW
0
6
Pu
b
l
i
c
W
o
r
k
s
PU
B
L
I
C
W
O
R
K
S
S
H
O
P
S
F
A
C
I
L
I
T
Y
CO
N
S
T
R
U
C
T
I
O
N
$6
7
0
,
0
0
0
$2
0
,
0
0
0
$6
7
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
s
t
e
w
a
t
e
r
Fu
n
d
WW
5
4
Wa
s
t
e
w
a
t
e
r
O
p
RE
P
L
A
C
E
#
1
7
8
3
-
1
9
9
5
F
O
R
D
D
U
M
P
T
R
U
C
K
$9
5
,
0
0
0
WW
8
6
Wa
s
t
e
w
a
t
e
r
O
p
WH
E
E
L
E
D
E
X
C
A
V
A
T
O
R
$151,000
WW
8
6
Wa
s
t
e
w
a
t
e
r
O
p
ST
E
E
R
A
B
L
E
S
E
W
E
R
T
V
T
R
A
C
T
O
R
$2
5
,
0
0
0
32
2
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
WW
8
7
Wa
s
t
e
w
a
t
e
r
O
p
SE
W
E
R
F
L
O
W
M
E
T
E
R
S
$3
5
,
0
0
0
$6
0
,
0
0
0
$9
5
,
0
0
0
$151,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
s
t
e
w
a
t
e
r
Fu
n
d
WW
3
9
WR
F
RE
S
U
R
F
A
C
E
A
N
D
R
E
P
A
I
N
T
C
L
A
R
I
F
I
E
R
S
$3
2
0
,
0
0
0
WW
4
9
WR
F
RO
L
L
-
O
F
F
S
T
O
R
A
G
E
B
U
I
L
D
I
N
G
CO
N
S
T
R
U
C
T
I
O
N
&
P
O
S
S
I
B
L
E
2
N
D
S
C
R
E
W
PR
E
S
S
E
N
C
L
O
S
U
R
E
$1
,
5
0
0
,
0
0
0
WW
5
8
WR
F
CH
I
P
S
E
A
L
A
N
D
T
O
P
C
O
A
T
W
R
F
A
S
P
H
A
L
T
$5
5
,
0
0
0
WW
6
9
WR
F
WR
F
F
A
C
I
L
I
T
Y
R
&
R
$100,000
$7
5
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
WW
7
0
WR
F
WR
F
F
A
C
I
L
I
T
Y
E
N
G
I
N
E
E
R
I
N
G
&
OP
T
I
M
I
Z
A
T
I
O
N
$50,000
$5
0
,
0
0
0
$5
0
,
0
0
0
$5
0
,
0
0
0
$5
0
,
0
0
0
WW
7
6
WR
F
TH
I
R
D
P
R
E
T
R
E
A
T
M
E
N
T
S
C
R
E
E
N
$5
0
0
,
0
0
0
WW
7
8
WR
F
SE
R
V
E
R
R
E
P
L
A
C
E
M
E
N
T
A
T
W
R
F
(W
R
F
C
T
R
L
B
A
K
)
$1
0
,
0
0
0
WW
8
3
WR
F
UF
A
T
G
R
A
V
I
T
Y
T
H
I
C
K
E
N
E
R
D
R
I
V
E
A
N
D
AR
M
S
R
E
P
L
A
C
E
M
E
N
T
$4
0
0
,
0
0
0
WW
8
4
WR
F
SE
R
V
E
R
R
E
P
L
A
C
E
M
E
N
T
A
T
W
R
F
(W
R
F
C
T
R
L
P
R
I
)
$1
0
,
0
0
0
WW
8
5
WR
F
WR
F
P
R
O
C
E
S
S
U
P
G
R
A
D
E
S
T
O
I
M
P
R
O
V
E
NU
T
R
I
E
N
T
R
E
C
O
V
E
R
Y
&
C
A
P
A
C
I
T
Y
$12,000,000
WW
8
8
WR
F
RE
-
T
U
B
E
B
O
I
L
E
R
$2
5
,
0
0
0
WW
8
9
WR
F
HV
A
C
H
E
A
T
L
O
O
P
O
P
T
I
M
I
Z
A
T
I
O
N
$2
5
0
,
0
0
0
$150,000
$2
,
2
5
0
,
0
0
0
$1
7
5
,
0
0
0
$6
5
0
,
0
0
0
$5
7
0
,
0
0
0
$12,000,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
W
a
s
t
e
w
a
t
e
r
F
u
n
d
(
2
6
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$1,232,500
$3
,
4
1
2
,
5
0
0
$2
,
0
2
2
,
5
0
0
$12,484,333FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$1
,
6
5
2
,
5
0
0
$1
,
7
3
2
,
5
0
0
FY
2
1
32
3
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
GF227
DEPARTMENT
Finance
PROJECT NAME
ERP Replacement "Sungard Replacement/Upgrade"
FY19 FY20 Unscheduled
$333,333
DESCRIPTION OF PROJECT
Replacing/upgrading the current system installed in 1999. This is the system that runs all the financial, community development,
land records, utility and business license applications. Although it is unscheduled we are currently looking into this with a
possibility of FY20.
ALTERNATIVES CONSIDERED
Continue running current SunGard package. Use SunGard.net (NaviLine EDGE) as an improvement to the current system, but not a full
replacement.
ADVANTAGES OF APPROVAL
Simplified package. Easier to integrate the various applications/programs. Easier to pull out information for end users. Easier compiliation of
Commission reports and packets for Community Development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown. Dependent on the option chosen.
FUNDING SOURCES
General Fund 33%; Water Fund 33%; Wastewater Fund 33%
New
Replacement
Equipment
Project
FY21 FY22 FY23
324
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
PW05
DEPARTMENT
Public Works
PROJECT NAME
Public Works Shops Master Plan
FY19
$20,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Develop a long term master plan for Public Works shop facilities, equipment, and personnel. This includes conducting a needs
assessment of space for existing and future employees, equipment, machinery, and rolling stock. There is a severe shortage of
enclosed storage for equipment, vehicles, and machinery, resulting in extra wear and tear, additional maintenance costs, and time
preparing the equipment on cold mornings. Additionally, there is a lack of space available for existing as well as future staff. This
will be split three ways between water ($20,000), wastewater ($20,000), and streets ($20,000).
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
Provide an accurate analysis of the City of Bozeman Public Works space needs for both equipment as well as people.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Depending on the results of the plan, the likely result will be the construction of additional storage and office space.
FUNDING SOURCES
This project will be split 3 ways between Water Fund ($20,000), Wastewater Fund ($20,000), and Street Maintenance Fund ($20,000)
New
Replacement
Equipment
Project
FY21 FY22 FY23
325
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
PW06
DEPARTMENT
Public Works
PROJECT NAME
Public Works Shops Facility Construction
FY19 FY20
$670,000
Unscheduled
DESCRIPTION OF PROJECT
Construct additional facilities recommended in the result of the Public Works Shops Master Plan. This will be split three ways
between water ($670,000), wastewater ($670,000), and streets ($670,000).
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
The construction of a new Public Works facility will provide indoor storage for millions of dollars of equipment, machinery, vehicles, etc. This
will both reduce wear and tear and maintenance costs, as well as reduce time spent on preparing equipment on cold mornings.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal building maintenance and utility costs.
FUNDING SOURCES
This project will be split 3 ways between Water Fund ($670,000), Wastewater Fund ($670,000), and Street Maintenance Fund ($670,000)
New
Replacement
Equipment
Project
FY21 FY22 FY23
326
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW07
DEPARTMENT
Engineering
PROJECT NAME
Annual Wastewater Pipe Replacement Program - Design
FY19
$22,500
FY20
$22,500
Unscheduled
DESCRIPTION OF PROJECT
This item provides for design work to be completed every-other year, in anticipation of the Annual System Upgrades. Annual
wastewater pipe replacement projects minimize service interruptions or main breaks attributable to aging infrastructure. Annual
Wastewater Pipe Replacement Program project would be delayed if not done.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides survey work needed for design of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY21
$22,500
FY22
$22,500
FY23
$22,500
327
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-19
DEPARTMENT
Engineering
PROJECT NAME
Wastewater Pipe Replacement Program - Construction in 2019
FY19
$1,000,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2019. Priority will will be places on the
sewer segment on S Tracy from College to Babcock to coincide with the S Tracy street reconstructions scheduled for FY19. The
remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the
sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary wastewater system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
328
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-20
DEPARTMENT
Engineering
PROJECT NAME
Wastewater Pipe Replacement Program - Construction in 2020
FY19 FY20
$1,000,000
Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2020. Priority will will be places on the
sewer segment on S Black from College to the Cul-De-Sac to coincide with the S Black street reconstructions scheduled for
FY20. The remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The
condition of the sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary wastewater system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
329
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-21
DEPARTMENT
Engineering
PROJECT NAME
Wastewater Pipe Replacement Program - Construction in 2021
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2021. Priority will will be places on the
sewer segment on N Tracy from Villard to Peach to coincide with the N Tracy street reconstructions scheduled for FY21. The
remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the
sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary wastewater system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21
$1,000,000
FY22 FY23
330
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-22
DEPARTMENT
Engineering
PROJECT NAME
Wastewater Pipe Replacement Program - Construction in 2022
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2022. Priority will will be places on the
sewer segment on N 17th from Durston to the end to coincide with the N 17th street reconstructions scheduled for FY22. The
remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The condition of the
sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary wastewater system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22
$1,000,000
FY23
331
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-23
DEPARTMENT
Engineering
PROJECT NAME
Wastewater Pipe Replacement Program - Construction in 2023
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2023. Priority will will be places on the
sewer segment on West Koch Street from 8th to Tracy to coincide with the West Koch Street reconstructions scheduled for
FY23. The remaining balance will be used to continue sewer replacements on segments identified as needing repairs. The
condition of the sewer system is analyzed nightly to account for daily updates from the Wastewater Operations Department.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary wastewater system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
$1,000,000
332
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW27
DEPARTMENT
Engineering
PROJECT NAME
Annual Watershed Study & Stream Modeling
FY19
$60,000
FY20
$60,000
Unscheduled
DESCRIPTION OF PROJECT
Develop a comprehensive, multi-year watershed study and computer model for the East Gallatin River, which would enable the
City and DEQ to better determine stream load allocations and develop a more scientifically valid TMDL for the river segment we
discharge to. This will require annual field sample collection, laboratory analytic al work, and detailed computer modeling using
calibrated and validated datasets. It is a crucial tool to inform MPDES discharge permit negotiations and compliance with MT
numeric nutrient regulations. This project leverages cooperative relationship with Gallatin Local Water Quality District in the
performance of field sampling activities, and it has significant potential to affect scope of future upgrades to WRF to meet numeric
nutrient limitations imposed by DEQ Circular 12A and implemented through future MPDES discharge permits. Stream modeling
may reduce or eliminate the need for future upgrades dependent upon the results of ongoing data collection and model
calibrations. Modeling could identify that assimilative capacity is available in the East Gallatin River or that the EGR is nutrient
limited. Model also essential to identify nutrient trade opportunities which could be a significant MPDES compliance tool.
ALTERNATIVES CONSIDERED
Not undertake this work and risk having to accept the TMDL and waste load allocations the DEQ has proposed in their original draft
documents. This decision could greatly limit our ability to appeal future nutrient limitations and could result in non-compliance.
ADVANTAGES OF APPROVAL
This watershed study will greatly enhance the City’s understand of our impact on the East Gallatin River and enable us to more successfully
negotiate future permit limits with the DEQ.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None, unless additional stream sampling is desired in subsequent years.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21
$60,000
FY22
$60,000
FY23
$60,000
333
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW39
DEPARTMENT
WRF
PROJECT NAME
Resurface and Repaint Clarifiers
FY19
$320,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Sandblast and paint clarifier drives on primary 1 and secondary 3. Beaches and weirs also need replaced on Primary 1 and 2, and
on Secondary 1, 2, and 3. The old final clarifiers were installed in the late 1980's and need to be painted and resurfaced to extend
their useful life. Painting and resurfacing the clarifier drives and replacing beaches and weirs will preserve the infrastructure and
delay the cost of replacement.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Replace lost & chipping paint on old clarifiers to prevent further deterioration of existing infrastructure. These clarifiers have not been painted
since they were installed in 1985.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No new operating costs.
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY21 FY22 FY23
334
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW49
DEPARTMENT
WRF
PROJECT NAME
Roll-Off Storage Building Construction & Possible 2nd Screw Press Enclosure
FY19
$1,500,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Engineering and construction of a roll-off building and 2nd screw press enclosure. Currently, an enclosed area consisting of
concrete blankets is suspended by cables and heated with portable propane heaters which keeps the roll-offs from freezing in the
truck storage building. The trucks are stored overnight during the winter so the solids inside them do not freeze. The addition
would return the needed space in the truck storage building and would reduce heating costs by using the exhaust air from the
solids handling building. Less energy would be used if an extension to the roll-off loading area was built. It could use exhaust air
from the solids dewatering building to heat it. Also, not using the portable propane heaters would be a cost savings. Installing this
screw press will allow not only redundancy but allows for the additional solids handling that the growing community will need.
This project will allow for additional storage of roll-offs, polymer totes and the housing of a new screw press.
ALTERNATIVES CONSIDERED
Construction of an addition not to include the purchase of a new screw press.
ADVANTAGES OF APPROVAL
Installing this screw press will allow not only redundancy but allows for the additional solids handling that the growing community will need. This
project will allow for additional storage of roll-offs, polymer totes and the housing of a new screw press.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This addition could be heated with exhaust air from the Solids Handling Building, reducing costs. If a screw press was also housed in this
addition, electrical costs for pumping and press operation would be additional.
FUNDING SOURCES
Digester 3 settlement money, amount TBD but estimated at $1,500,000.
New
Replacement
Equipment
Project
FY21 FY22 FY23
335
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW54
DEPARTMENT
Wastewater Operations
PROJECT NAME
Replace #1783 - 1995 Ford Dump Truck
FY19 FY20
$95,000
Unscheduled
DESCRIPTION OF PROJECT
Vehicle maintenance is requesting that the vehicle be replaced due to age. It has a leaking brake booster that needs replaced, and
they can’t get parts to get it repaired because the parts aren’t available for this vehicle anymore. The parts will continue to get
harder to purchase in the future to keep this vehicle in service.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Will be a more fuel efficient and lower emissions vehicle. The new vehicle will improve safety of the crews, there would be lower repair costs
and it would help maintain current operations levels.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Using an older piece of equipment that becomes more unreliable.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
336
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW58
DEPARTMENT
WRF
PROJECT NAME
Chip Seal and Topcoat WRF Asphalt
FY19
$55,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Chip Seal and topcoat WRF Asphalt to keep it from deteriorating. The 4.894 acres of asphalt at the WRF facility needs to be
protected to extend its useful life. Chip seal 0.402 acres and topcoat 4.492 acres.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
Chip seal and topcoat will extend the useful life of the existing City infrastructure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY21 FY22 FY23
337
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW69
DEPARTMENT
WRF
PROJECT NAME
WRF Facility R&R
FY19
$75,000
FY20
$100,000
Unscheduled
DESCRIPTION OF PROJECT
Repair and replacement of equipment is an ongoing job at the Bozeman WRF. These funds would be used to repair or replace
equipment that fails unexpectedly in an emergency situation. An unforeseen mechanical failure needs to be remedied quickly to
protect the quality of facility effluent discharged into the East Gallatin.
ALTERNATIVES CONSIDERED
Not having this fund would defer other needed maintenance.
ADVANTAGES OF APPROVAL
Most processes run 24/7 and have backup systems but when the first system fails there is no backup system and repairs need to be made
immediately. Not all repairs or equipment failures can be predicted and budgeted as a capital improvement project.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY21
$100,000
FY22
$100,000
FY23
$100,000
338
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW70
DEPARTMENT
WRF
PROJECT NAME
WRF Facility Engineering & Optimization
FY19
$50,000
FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
This will allow engineering to be completed on needed projects and to study plant optimization options before spending money
on equipment that might not be needed or the proper type. Additionally, this will allow studies to be conducted to make sure the
proposed plant optimizations will actually improve the effluent quality at a reasonable expense.
ALTERNATIVES CONSIDERED
Order replacement or upgrades to equipment that may not be sized correctly or made of the proper materials. Proceed with optimization
projects without knowing if the project will actually improve plant performance.
ADVANTAGES OF APPROVAL
The advantage of having funds available to do engineering studies before any project is started will make sure that the right equipment is
purchased and that it will perform properly. Optimization studies will predict actual cost/benefit over time to make sure the city is spending its
money efficiently.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Currently unknown
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY21
$50,000
FY22
$50,000
FY23
$50,000
339
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW76
DEPARTMENT
WRF
PROJECT NAME
Third Pretreatment Screen
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Purchase a third pretreatment screen and the engineering to properly install it. The two installed pretreatment screens are
running 24/7 so there is no redundancy to the system. Adding a third screen will increase the capacity of pretreatment to handle
increased flows from growth without bypassing the screens. This screen will prevent the clogging of pipes and pumps will preserve
the effluent quality of the facility, and all equipment downstream of the screens will be better protected. Pipes and pumps that are
not plugged run more efficiently and require less energy to run.
ALTERNATIVES CONSIDERED
Do nothing and run the risk of having to bypass the existing screens because they cannot handle the load coming into the plant.
ADVANTAGES OF APPROVAL
Protecting downstream infrastructure by not having to bypass the screens.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Additional cost of electricity for the motors on the screen.
FUNDING SOURCES
Wastewater Funds and possibly Impact Funds
New
Replacement
Equipment
Project
FY21
$500,000
FY22 FY23
340
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW78
DEPARTMENT
WRF
PROJECT NAME
Server Replacement at WRF (WRFCTRLBAK)
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace the WRF server WRFCTRLBAK
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY21 FY22
$10,000
FY23
341
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW83
DEPARTMENT
WRF
PROJECT NAME
UFAT Gravity Thickener Drive and Arms Replacement
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Replacement of the gravity thickener deteriorating mechanism. The UFAT gravity Thickener thickens elutriated fermented sludge
before it is sent to the digester thus increasing detention time in the digesters. It is the second stage of the UFAT system that
generates Volatile Fatty Acids that are an energy source for the Phosphorus Accumulating Organisms. These POA's are what
remove the phosphorus from the wastewater. The gravity Thickener thickens elutriated fermented sludge before it is sent to the
digester thus increasing detention time in the digesters.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Installation planning and purchase of the drive and arms will allow a scheduled shutdown rather than a quick fix when the drive fails.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional costs.
FUNDING SOURCES
Not known at this time.
New
Replacement
Equipment
Project
FY21 FY22
$400,000
FY23
342
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW84
DEPARTMENT
WRF
PROJECT NAME
Server Replacement at WRF (WRFCTRLPRI)
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Replace the WRF server WRFCTRLPRI
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY21 FY22
$10,000
FY23
343
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW85
DEPARTMENT
WRF
PROJECT NAME
WRF Process Upgrades to Improve Nutrient Recovery & Capacity
FY19 FY20 Unscheduled
$12,000,000
DESCRIPTION OF PROJECT
This project will increase WRF capacity to meet facility plan recommendations and future discharge permit requirements.
ALTERNATIVES CONSIDERED
Do nothing and loose a commodity that is a bi-product of anaerobic digestion
ADVANTAGES OF APPROVAL
The production of magnesium ammonium phosphate to be sold as a slow release fertilizer will recycle limited nutrients back into the ecosystem.
This process will reduce the nitrogen and phosphorus in our sidestream returning to the head of the plant which will in turn reduce the loading
on the process.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance and operating costs that will be offset by income from the sale of the slow release fertilizer.
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY21 FY22 FY23
344
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW86
DEPARTMENT
Wastewater Operations
PROJECT NAME
Steerable sewer TV tractor
FY19
$25,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This tractor carries our TV camera in our sanitary and storm sewers. This tractor is the only tractor that can carry our new larger
digital cameras. Currently, we only have one steerable tractor, so using both sewer trucks at the same time is not possible.
ALTERNATIVES CONSIDERED
Use one truck at a time with the larger camera.
ADVANTAGES OF APPROVAL
Using both digital cameras at the same time which televise the sewer mains much faster than our older cameras.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
345
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW86
DEPARTMENT
Wastewater Operations
PROJECT NAME
Wheeled Excavator
FY19 FY20 Unscheduled
$151,000
DESCRIPTION OF PROJECT
This would be a trackhoe excavator with wheels instead of tracks. It is a critical piece of machinery in our departments, and it is
used to maintain water, sewer, and stormwater infrastructure. The excavator will be split 50/50 with the water fund (W68).
ALTERNATIVES CONSIDERED
Continue to use smaller equipment.
ADVANTAGES OF APPROVAL
Increased productivity with larger excavator.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
$151,000 Water Fund, $151,000 Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
346
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW87
DEPARTMENT
Wastewater Operations
PROJECT NAME
Sewer Flow Meters
FY19
$35,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Two flow meters can record sewer flows in the sewer mains, which is critical for planning for new mains. These meters will be
used along with the one we purchased in FY 17. We need multiple flow meters to monitor wet weather events to calibrate our
sewer model. With growth, there is also a need to monitor available sewer capacity for new subdivisions.
ALTERNATIVES CONSIDERED
Renting additional meters.
ADVANTAGES OF APPROVAL
The ability to do in house monitoring of sewer flows.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$600 / year for software. $80 / month for cellular data. (For both meters)
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
347
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW88
DEPARTMENT
WRF
PROJECT NAME
Re-Tube Boiler
FY19 FY20
$25,000
Unscheduled
DESCRIPTION OF PROJECT
Current boiler in de-watering building continually has wear on internal components that causes deterioration. Rebuilding will
ensure operation, as well as, extend life of boiler and is more economical than replacing the entire boiler.
ALTERNATIVES CONSIDERED
Replace and repair tubes individually as they fail.
ADVANTAGES OF APPROVAL
The cost of replacing 4 tubes is about the same as what replacing all 20+ would cost.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
348
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW89
DEPARTMENT
WRF
PROJECT NAME
HVAC heat loop optimization
FY19
$250,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Modify heating system to provide for facility needs. The current HVAC system is not adequately heating the digester and buildings.
This poses some operational problems that range from inadequate sludge digestion to not being able to provide enough heat to
buildings and keep utilities from freezing.
ALTERNATIVES CONSIDERED
Some alterations have already been made to the system to maximize the current setup. There is not an easy or cost effective alternative solution
that would solve this problem.
ADVANTAGES OF APPROVAL
This project would improve the digester operation as well as keep buildings properly heated.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
There will be some increase the energy usage, but this has not been calculated yet.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
349
350
Wa
s
t
e
w
a
t
e
r
I
m
p
a
c
t
F
e
e
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
7
6
7
,
4
6
0
$
(3
1
5
,
1
3
6
)
$
32
7
,
0
7
2
$
56
8
,
5
9
2
$
1,
2
6
0
,
4
6
9
$
2,023,028
$
‐ $
P
l
u
s
:
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
2
2
1
,
1
5
0
$
1
,
2
8
2
,
2
0
8
$
1
,
3
4
6
,
3
1
8
$
1
,
4
1
3
,
6
3
4
$
1
,
4
8
4
,
3
1
5
$
1
,
5
5
8
,
5
3
1
$
‐ $
P
l
u
s
:
F
i
n
a
n
c
i
n
g
W
W
I
F
1
1
2,
1
8
5
,
0
0
0
$
P
l
u
s
:
F
i
n
a
n
c
i
n
g
W
W
I
F
2
4
5,
8
0
0
,
0
0
0
$
P
l
u
s
:
F
i
n
a
n
c
i
n
g
W
W
I
F
3
8
3,
3
2
0
,
0
0
0
$
P
l
u
s
:
F
i
n
a
n
c
i
n
g
W
W
I
F
2
0
(
$
5
,
2
9
0
,
0
0
0
)
3,000,000
$
L
e
s
s
:
C
a
r
r
y
o
v
e
r
F
Y
1
7
C
a
p
i
t
a
l
P
r
o
j
e
c
t
s
(1
,
8
6
3
,
7
4
6
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(1
,
4
4
0
,
0
0
0
)
$
(8
,
6
2
5
,
0
0
0
)
$
(4
,
4
2
4
,
7
9
7
)
$
(7
2
1
,
7
5
7
)
$
(7
2
1
,
7
5
7
)
$
(6
,
0
1
1
,
7
5
7
)
$
(7,005,792)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
(3
1
5
,
1
3
6
)
$
32
7
,
0
7
2
$
56
8
,
5
9
2
$
1,
2
6
0
,
4
6
9
$
2,
0
2
3
,
0
2
8
$
569,802
$
Be
g
i
n
n
i
n
g
B
a
l
a
n
c
e
o
f
P
a
y
b
a
c
k
I
m
p
r
o
v
e
m
e
n
t
s
:
‐
$
‐
$
39
7
,
5
0
0
$
1,
0
5
3
,
1
5
6
$
2,
6
4
0
,
1
5
6
$
2,640,156
$
Pa
y
b
a
c
k
D
i
s
t
r
i
c
t
‐
W
W
I
F
1
1
65
5
,
6
5
6
$
Pa
y
b
a
c
k
D
i
s
t
r
i
c
t
‐
W
W
I
F
2
0
1,
5
8
7
,
0
0
0
$
Pa
y
b
a
c
k
D
i
s
t
r
i
c
t
‐
W
W
I
F
2
7
39
7
,
5
0
0
$
Pa
y
b
a
c
k
D
i
s
t
r
i
c
t
‐
W
W
I
F
2
3
En
d
i
n
g
B
a
l
a
n
c
e
o
f
P
a
y
b
a
c
k
I
m
p
r
o
v
e
m
e
n
t
s
:
‐
$
39
7
,
5
0
0
$
1,0
5
3
,
1
5
6
$
2,
6
4
0
,
1
5
6
$
2,
6
4
0
,
1
5
6
$
2,640,156
$
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
W
a
s
t
e
w
a
t
e
r
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
1,
2
2
1
,
1
5
0
$
1
,
2
2
1
,
1
5
0
$
1
,
2
8
2
,
2
0
8
$
1
,
3
4
6
,
3
1
8
$
1
,
4
1
3
,
6
3
4
$
1
,
4
8
4
,
3
1
5
$
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
0.
0
%
5%
5%
5%
5%
5%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
1,
2
2
1
,
1
5
0
$
1
,
2
8
2
,
2
0
8
$
1
,
3
4
6
,
3
1
8
$
1
,
4
1
3
,
6
3
4
$
1
,
4
8
4
,
3
1
5
$
1
,
5
5
8
,
5
3
1
$
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
W
a
s
t
e
w
a
t
e
r
C
a
p
a
c
i
t
y
E
x
p
a
n
s
i
o
n
C
I
P
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
2
2
1
,
1
5
0
$
1
,
2
8
2
,
2
0
8
$
1
,
3
4
6
,
3
1
8
$
1
,
4
1
3
,
6
3
4
$
1
,
4
8
4
,
3
1
5
$
1
,
5
5
8
,
5
3
1
$
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
8
,
6
2
5
,
0
0
0
)
$
(
4
,
4
2
4
,
7
9
7
)
$
(
7
2
1
,
7
5
7
)
$
(
7
2
1
,
7
5
7
)
$
(
6
,
0
1
1
,
7
5
7
)
$
(
7
,
0
0
5
,
7
9
2
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
WA
S
T
E
W
A
T
E
R
I
M
P
A
C
T
F
E
E
P
R
O
J
E
C
T
S
35
1
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Im
p
a
c
t
F
e
e
s
Wa
s
t
e
w
a
t
e
r
WW
I
F
1
1
Wa
s
t
e
w
a
t
e
r
I
m
FR
O
N
T
S
T
R
E
E
T
I
N
T
E
R
C
E
P
T
O
R
$2
,
1
8
5
,
0
0
0
WW
I
F
2
0
Wa
s
t
e
w
a
t
e
r
I
m
N
F
R
O
N
T
A
G
E
R
D
I
N
T
E
R
C
E
P
T
O
R
$5,290,000
WW
I
F
2
2
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
DA
V
I
S
-
F
O
W
L
E
R
I
N
T
E
R
C
E
P
T
O
R
(
D
U
R
S
T
O
N
RD
T
O
W
O
A
K
S
T
)
$778,035
WW
I
F
2
4
Wa
s
t
e
w
a
t
e
r
I
m
DA
V
I
S
L
A
N
E
(
L
I
F
T
S
T
A
T
I
O
N
)
$5
,
8
0
0
,
0
0
0
WW
I
F
3
2
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
HI
D
D
E
N
V
A
L
L
E
Y
(
L
I
F
T
S
T
A
T
I
O
N
A
N
D
F
O
R
C
E
MA
I
N
)
$5,190,000
WW
I
F
3
3
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
DA
V
I
S
L
N
L
I
F
T
S
T
A
T
I
O
N
D
E
B
T
S
E
R
V
I
C
E
(W
W
I
F
2
4
)
$370,300 $370,300
$3
7
0
,
3
0
0
$3
7
0
,
3
0
0
$3
7
0
,
3
0
0
WW
I
F
3
4
Wa
s
t
e
w
a
t
e
r
I
m
AN
N
I
E
S
T
R
E
E
T
S
A
N
I
T
A
R
Y
S
E
W
E
R
U
P
G
R
A
D
E
$300,000
WW
I
F
3
5
Wa
s
t
e
w
a
t
e
r
I
m
BA
B
C
O
C
K
S
A
N
I
T
A
R
Y
S
E
W
E
R
U
P
G
R
A
D
E
$2
4
5
,
0
0
0
WW
I
F
3
6
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
BA
X
T
E
R
C
R
E
E
K
B
A
S
I
N
-
C
O
T
T
O
N
W
O
O
D
RO
A
D
1
8
"
S
A
N
I
T
A
R
Y
S
E
W
E
R
E
X
T
E
N
S
I
O
N
$6
4
0
,
0
0
0
WW
I
F
3
7
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
HU
N
T
E
R
S
W
A
Y
S
E
W
E
R
C
A
P
A
C
I
T
Y
UP
G
R
A
D
E
$3
5
0
,
0
0
0
WW
I
F
3
8
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
NO
R
T
O
N
E
A
S
T
R
A
N
C
H
O
U
T
F
A
L
L
DI
V
E
R
S
I
O
N
$3
,
3
2
0
,
0
0
0
WW
I
F
3
9
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
RE
N
O
V
A
S
T
R
E
E
T
S
A
N
I
T
A
R
Y
S
E
W
E
R
M
A
I
N
UP
G
R
A
D
E
$16,000
WW
I
F
4
0
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
FR
O
N
T
S
T
R
E
E
T
I
N
T
E
R
C
E
P
T
O
R
D
E
B
T
SE
R
V
I
C
E
(
W
W
I
F
1
1
)
$139,497 $139,497
$1
3
9
,
4
9
7
$1
3
9
,
4
9
7
$1
3
9
,
4
9
7
WW
I
F
4
1
Wa
s
t
e
w
a
t
e
r
Im
p
a
c
t
F
e
e
s
NO
R
T
O
N
E
A
S
T
R
A
N
C
H
O
U
T
F
A
L
L
DI
V
E
R
S
I
O
N
D
E
B
T
S
E
R
V
I
C
E
(
W
W
I
F
3
8
)
$211,960 $211,960
$2
1
1
,
9
6
0
$2
1
1
,
9
6
0
$6,011,757
$8
,
6
2
5
,
0
0
0
$4
,
4
2
4
,
7
9
7
$7
2
1
,
7
5
7
$7
2
1
,
7
5
7
$7,005,792
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
I
m
p
a
c
t
F
e
e
s
W
a
s
t
e
w
a
t
e
r
(
1
4
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$6,011,757
$8
,
6
2
5
,
0
0
0
$4
,
4
2
4
,
7
9
7
$7,005,792FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$7
2
1
,
7
5
7
$7
2
1
,
7
5
7
FY
2
1
35
2
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF11
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Front Street Interceptor
FY19
$2,185,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of construction of ~8,500 LF 18", 21", 24" sewer pipe from manhole E0304 to C0524. Without this
wastewater interceptor development in the vicinity of Bozeman Deaconess Health Services, Blackmore Bend Development (new
Heebs store), development on E. Main Street, and development along Haggery Lane will not be able to occur. The downstream
portion of the existing sewer is already at capacity. Additional capacity is needed to serve future development in the vicinity of
Bozeman Deaconess Hospital and lands to the south. This project will conform to the City's Wastewater Master Plan. It is
estimated that 70% of this project costs will be due to capacity expansion and will be eligible for Wastewater Impact Fees. The
remaining 30% of the project costs will need to be provided by a "local share" contribution or other source.
ALTERNATIVES CONSIDERED
No action.
ADVANTAGES OF APPROVAL
This project will significantly increase the capacity of the trunk sewer, allow for infill and new development along East Main Street, Haggerty
Lane, and Bozeman Deaconess Health.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $1,529,864 30% Wastewater Impact Fees for Local Share = $655,656, recovered via payback district(s).
New
Replacement
Equipment
Project
FY21 FY22 FY23
353
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF20
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
N Frontage Rd Interceptor
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project will replace or parallel 11,500' of the North Frontage Road interceptor between Springhill Rd and Bridger Dr.
Portions of the interceptor are at or very near capacity and unless improvements are made it will be at or over capacity when the
tributary obligated areas are developed. This project will directly increase collection capacity in the southeast and east parts of
the city. Development in the southeast part of town within the Community Plan Boundary as well as the east part of town will
be tributary to this North Frontage Road Interceptor. There are potentially a great number of private development projects
which will not be able to proceed due to the lack of wastewater collection capacity. This project will conform to the City's
Wastewater Master Plan. It is estimated that 70% of this project costs will be du e to capacity expansion and will be eligible for
Wastewater Impact Fees. The remaining 30 % of the project costs will need to be provided by a "local share" contribution or
other source.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for future growth tributary to
this main.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Wastewater Impact Fees, with local share recovered via payback district(s)
New
Replacement
Equipment
Project
FY21 FY22 FY23
$5,290,000
354
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF22
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Davis-Fowler Interceptor (Durston Rd to W Oak St)
FY19 FY20 Unscheduled
$778,035
DESCRIPTION OF PROJECT
This project will replace or parallel 2700' of the Davis-Fowler Interceptor between Durston and Oak. The interceptor between
Durston Rd and W Oak will eventually exceed capacity as the Baxter Creek drainage basin develops. In order to convey the
ultimate build-out flow, the interceptor will need to be increased from an 18-inch diameter to a 24-inch diameter pipe.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating the long-term
future growth in this area
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Wastewater Impact Fees, with local share recovered via payback district
New
Replacement
Equipment
Project
FY21 FY22 FY23
355
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF24
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Davis Lane (Lift Station)
FY19
$5,800,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete the buildout of the Davis Ln Lift Station.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating the long-term
future growth in this area
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Wastewater Impact Fees, with local share recovered via payback district
New
Replacement
Equipment
Project
FY21 FY22 FY23
356
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF32
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Hidden Valley (Lift Stationand Force Main)
FY19 FY20 Unscheduled
$5,190,000
DESCRIPTION OF PROJECT
Design and Construct Hidden Valley Lift Station and Force Main. This project will conform to the City's Wastewater Collection
Facilities Plan. The Davis Lane Lift Station must be upgraded to accommodate flows from the Hidden Valley Lift Station when the
Hidden Valley Lift Station is constructed.
ALTERNATIVES CONSIDERED
Limit development on the northwestern edge of of the City due to no sanitary sewer availability.
ADVANTAGES OF APPROVAL
Increased service area of the City's sanitary sewer system.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Operating costs will be paid from the City's sewer enterprise fund.
FUNDING SOURCES
Payback district or other local share contribution from development at the time of construction.
New
Replacement
Equipment
Project
FY21 FY22 FY23
357
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF33
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Davis Ln Lift Station Debt Service (WWIF24)
FY19 FY20
$370,300
Unscheduled
$370,300
DESCRIPTION OF PROJECT
This project will provide a debt service payment for the City's portion of the Davis Ln Lift Station. If we do not fund this debit
service, the City will be in default of our loan. This lift station serves development north of the Cattail Lake Lift Station, and it will
conform to the City's Wastewater Master Plan. The Billings Clinic will finance the lift station, and the City will reimburse the
Billings Clinic for the City's portion over 5 years. The Billings Clinic will not be reimbursed for their portion of the lift station
capacity, which is estimates as 8% of the capacity of the initial lift station construction. The Norton East Ranch Diversion would
reduce early operational challenges in the Davis Lane Lift Station due to odors associated with minimal flows.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
This will pay off the City's portion of the Davis Ln Lift Station
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater utility will pay for
these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
Billings Clinic is constructing the Lift Station and will provide a payback district for the City's portion of the financing.
New
Replacement
Equipment
Project
FY21
$370,300
FY22
$370,300
FY23
$370,300
358
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF34
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Annie Street Sanitary Sewer Upgrade
FY19 FY20 Unscheduled
$300,000
DESCRIPTION OF PROJECT
This project consists of upgrading approximately 1,200 feet of an existing 18-inch sanitary sewer main in the Annie Street
alignment to a 21-inch main. Given the current planned development projects, this main will be at capacity in 5-10 years upon
buildout of multiple projects.
ALTERNATIVES CONSIDERED
No action, but this will limit infill development when the capacity of the sewer main is reached.
ADVANTAGES OF APPROVAL
Allows future infill development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The additional operating costs will be minimal as this is an upgrade of an existing line.
FUNDING SOURCES
Payback district.
New
Replacement
Equipment
Project
FY21 FY22 FY23
359
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF35
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Babcock Sanitary Sewer Upgrade
FY19 FY20
$245,000
Unscheduled
DESCRIPTION OF PROJECT
To accommodate flows from Phase 2 of the Icon Apartments project, Ferguson Farm, and Lupine Village as well as future in-fill
development, the existing 10-inch sanitary sewer main in W. Babcock must be upgraded to a 15-inch sanitary sewer main from
Manhole L0408 at the intersection of Resort Drive and Babcock to L0412 at the intersection of Babcock and Cottonwood.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
Allows infill development to proceed as this sanitary sewer main will be at capacity after development of Phase I of Icon Apartments and various
site plan applications at Ferguson Farms.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal as this will be a capacity upgrade of an existing sanitary sewer main.
FUNDING SOURCES
Development that depends on this line upgrade will be required to upgrade this main as necessary to serve their projects. However, an upsizing
fee from the City is anticipated to support this upgrade.
New
Replacement
Equipment
Project
FY21 FY22 FY23
360
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF36
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Baxter Creek Basin - Cottonwood Road 18" Sanitary Sewer Extension
FY19
$640,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of constructing an 18-inch sanitary sewer main from the intersection of Babcock and Cottonwood to the
intersection of Cottonwood and Durston per the Wastewater Collection Facilities Plan Update (2015). This section of
Cottonwood Road is currently being designed and will be constructed in the summer of 2018, and the sewer improvement must
be constructed with the road upgrade, so the road will not need to be excavated for new sewer main construction within the
next 2-3 years. The sanitary sewer main identified in the facilities plan is also required to serve any new development upstream
of this section of sanitary sewer. The existing 12-inch main capacity is completely dedicated for approved, new development.
Any new development served by this line including current site plan applications are dependent on an upgrade of the sanitary
sewer at this location (Icon Apartments, Lupine Village, and multiple smaller site plans at Ferguson Farms will require this upgrade
in the immediate short term). Also, there will be substantial cost savings to complete the sewer improvement with the
Cottonwood Road upgrade. The cost of the project in this item reflects the cost listed in the facility plan, but the cost will be less
expensive if completed with the street upgrade.
ALTERNATIVES CONSIDERED
The line is at capacity and must be upgraded now, or infill property served by this pipe will not be allowed to proceed.
ADVANTAGES OF APPROVAL
Allows immediate use by development as multiple development applications are dependent on this upgrade (Icon Apartments, site plan
applications in Ferguson Farms, Lupine Village)
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Additional operating costs are minimal as the proposed upgrade is a replacement of an existing 12-inch main that is at capacity.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
361
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF37
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Hunters Way Sewer Capacity Upgrade
FY19 FY20
$350,000
Unscheduled
DESCRIPTION OF PROJECT
Approximately 1,600 feet of sanitary sewer main requires an upgrade from a 12-inch main to a 15-inch main to accommodate
infill development including buildout of the MSU Innovation Campus and other infill areas immediately west of S. 19th.
ALTERNATIVES CONSIDERED
No action. This option would not allow buildout of the MSU Innovation Campus and other infill development immediately west of S. 19th.
ADVANTAGES OF APPROVAL
Allows buildout of the MSU Innovation Campus and other infill projects immediately west of S. 19th including a potential student housing project.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Operational costs would remain the same as the existing 12-inch main would be upgraded to a 15-inch main.
FUNDING SOURCES
In-fill development contributions through a direct contribution or a payback district.
New
Replacement
Equipment
Project
FY21 FY22 FY23
362
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF38
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Norton East Ranch Outfall Diversion
FY19 FY20
$3,320,000
Unscheduled
DESCRIPTION OF PROJECT
The existing system does not have enough capacity to collect all of the flows from the full development of the Aajker Creek and
Baxter Creek Drainage Basins. Most of the flow is proposed to be collected by a new extension in the Aajker Creek drainage
basin and enter the system at the Norton East Ranch Outfall Interceptor. The Norton East Ranch Outfall Interceptor will be
constructed from the intersection of Baxter Lane and Flanders Mill Road to the proposed Davis Lane Lift Station north of
Interstate 90 and will be a 27-inch sanitary sewer pipe. The project will take pressure off the Baxter Meadows Lift Station which
has limited capacity. This project will only be constructed if the Davis Lane Lift Station is constructed. If the Davis Lane Lift
Station is not constructed, we will need to divert funds from the Norton East Ranch Outfall to upgrade the existing Baxter
Meadows Lift station and sewer interceptor to the lift station.
ALTERNATIVES CONSIDERED
1) Upgrade the existing sanitary sewer interceptor and Baxter Meadows Lift Station that serve the Aajker Creek and Baxter Creek Drainage
Basins, or 2) do nothing.
ADVANTAGES OF APPROVAL
Frees capacity in existing infrastructure to serve infill development while simultaneously opening new areas for development that currently do
not have access to the City sanitary sewer system.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance of sanitary sewer mains including flushing and long-term maintenance.
FUNDING SOURCES
Local share contributions from development. New development that connects to the interceptor sewer would be required to pay the
assessment associated with a payback district.
New
Replacement
Equipment
Project
FY21 FY22 FY23
363
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF39
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Renova Street Sanitary Sewer Main Upgrade
FY19 FY20 Unscheduled
$16,000
DESCRIPTION OF PROJECT
A small section, 40-feet, of 21-inch sanitary sewer main in Renova Street must be upgraded to a minimum 24-inch main due to
the flat slope of this segment of pipe. Upon buildout of the currently planned development projects, this segment of sanitary
sewer main will be at capacity in approximately 5-10 years. Further evaluation of this pipe segment is required prior to an
upgrade including a survey of the actual grade of the pipe and flow monitoring to verify the need for the upgrade and the results
of the City's hydraulic model.
ALTERNATIVES CONSIDERED
Additional flow monitoring and survey data needed to verify the timing and need for this upgrade.
ADVANTAGES OF APPROVAL
Accommodate future development demands on this segment of interceptor sewer.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal due to replacement of an existing, smaller main.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
364
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF40
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Front Street Interceptor Debt Service (WWIF11)
FY19 FY20
$139,497
Unscheduled
$139,497
DESCRIPTION OF PROJECT
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$139,497
FY22
$139,497
FY23
$139,497
365
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF41
DEPARTMENT
Wastewater Impact Fees
PROJECT NAME
Norton East Ranch Outfall Diversion Debt service (WWIF38)
FY19 FY20 Unscheduled
$211,960
DESCRIPTION OF PROJECT
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$211,960
FY22
$211,960
FY23
$211,960
366
Wa
t
e
r
F
u
n
d
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
2,
2
1
9
,
4
9
2
$
39
,
0
3
5
$
(2
9
7
,
1
7
1
)
$
(3
1
6
,
7
5
1
)
$
132,443
$
557,526 $ ‐$
P
l
u
s
:
W
a
t
e
r
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
2,
2
3
3
,
6
4
4
$
2,
7
9
6
,
3
5
1
$
2,
9
3
6
,
1
6
9
$
3,
9
9
9
,
8
1
9
$
4,119,814
$
4,243,408 $ ‐$
P
l
u
s
:
L
o
a
n
o
r
F
i
n
a
n
c
i
n
g
f
o
r
H
y
a
l
i
t
e
D
a
m
I
m
p
r
o
v
e
m
e
n
t
s
W
7
9
2,
0
0
0
,
0
0
0
$
P
l
u
s
:
L
o
a
n
o
r
F
i
n
a
n
c
i
n
g
f
o
r
A
u
t
o
m
a
t
i
o
n
U
p
g
r
a
d
e
s
W
7
1
6,710,000
$
P
l
u
s
:
L
o
a
n
f
o
r
M
e
c
h
a
n
i
c
a
l
U
p
g
r
a
d
e
s
W
7
2
1,
7
5
0
,
0
0
0
$
P
l
u
s
:
L
o
a
n
o
r
F
i
n
a
n
c
i
n
g
f
o
r
L
y
m
a
n
T
a
n
k
C
o
n
s
t
r
u
c
t
i
o
n
10
,
0
0
0
,
0
0
0
$
P
l
u
s
:
L
o
a
n
f
o
r
w
a
t
e
r
f
u
n
d
p
o
r
t
i
o
n
o
f
W
I
F
4
0
48
0
,
0
0
0
$
L
e
s
s
:
F
Y
1
7
C
a
r
r
y
o
v
e
r
C
a
p
i
t
a
l
(1
,
6
0
5
,
7
0
1
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(2
,
8
0
8
,
4
0
0
)
$
(4
,
8
8
2
,
5
5
7
)
$
(3
,
4
3
5
,
7
4
9
)
$
(1
5
,
5
5
0
,
6
2
5
)
$
(1
0
,
4
0
4
,
7
3
1
)
$
(1,460,791)$ (3,479,439)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
39
,
0
3
5
$
(2
9
7
,
1
7
1
)
$
(3
1
6
,
7
5
1
)
$
13
2
,
4
4
3
$
557,526
$
3,340,143 $ (3,479,439)$
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
W
a
t
e
r
R
e
v
e
n
u
e
s
8,
5
9
0
,
9
4
0
$
8,
5
9
0
,
9
4
0
$
9,
0
2
0
,
4
8
7
$
9,
4
7
1
,
5
1
1
$
9,755,657
$
10,048,326 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
5.
0
%
5.
0
%
3.
0
%
3.0%3.0%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
8,
5
9
0
,
9
4
0
$
9,
0
2
0
,
4
8
7
$
9,
4
7
1
,
5
1
1
$
9,
7
5
5
,
6
5
7
$
10
,
0
4
8
,
3
2
6
$
10,349,776 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
21
.
0
%
26
.
0
%
3
1
.
0
%
31
.
0
%
41.0% 41.0%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
5.
0
%
5.
0
%
0.
0
%
10
.
0
%
0.0%0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
26
.
0
%
31
.
0
%
3
1
.
0
%
41
.
0
%
41.0% 41.0%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
2,
2
3
3
,
6
4
4
$
2,
7
9
6
,
3
5
1
$
2,
9
3
6
,
1
6
9
$
3,
9
9
9
,
8
1
9
$
4,119,814
$
4,243,408 $
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
4
,
8
8
2
,
5
5
7
)
$
(
3
,
4
3
5
,
7
4
9
)
$
(
1
5
,
5
5
0
,
6
2
5
)
$
(
1
0
,
4
0
4
,
7
3
1
)
$
(
1
,
4
6
0
,
7
9
1
)
$
(
3
,
4
7
9
,
4
3
9
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
WA
T
E
R
F
U
N
D
P
R
O
J
E
C
T
S
&
E
Q
U
I
P
M
E
N
T
36
7
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Wa
t
e
r
F
u
n
d
W0
3
En
g
i
n
e
e
r
i
n
g
AN
N
U
A
L
W
A
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
PR
O
G
R
A
M
-
D
E
S
I
G
N
$22,500
$2
2
,
5
0
0
$2
2
,
5
0
0
$2
2
,
5
0
0
$2
2
,
5
0
0
W0
4
-
1
9
En
g
i
n
e
e
r
i
n
g
WA
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
-
CO
N
S
T
R
U
C
T
I
O
N
I
N
2
0
1
9
$1
,
2
0
0
,
0
0
0
W0
4
-
2
0
En
g
i
n
e
e
r
i
n
g
WA
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
-
CO
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
0
$1
,
2
0
0
,
0
0
0
W0
4
-
2
1
En
g
i
n
e
e
r
i
n
g
WA
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
-
CO
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
1
$1
,
2
0
0
,
0
0
0
W0
4
-
2
2
En
g
i
n
e
e
r
i
n
g
WA
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
-
CO
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
2
$1
,
2
0
0
,
0
0
0
W0
4
-
2
3
En
g
i
n
e
e
r
i
n
g
WA
T
E
R
P
I
P
E
R
E
P
L
A
C
E
M
E
N
T
P
R
O
G
R
A
M
-
CO
N
S
T
R
U
C
T
I
O
N
I
N
2
0
2
3
$1,200,000 $1,222,500
$1
,
2
2
2
,
5
0
0
$1
,
2
2
2
,
5
0
0
$1
,
2
2
2
,
5
0
0
$1
,
2
2
2
,
5
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
GF
2
2
7
Fi
n
a
n
c
e
ER
P
R
E
P
L
A
C
E
M
E
N
T
"
S
U
N
G
A
R
D
RE
P
L
A
C
E
M
E
N
T
/
U
P
G
R
A
D
E
"
$333,333 $333,333
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
GI
S
0
3
GI
S
AS
S
E
T
M
A
N
A
G
E
M
E
N
T
S
O
F
T
W
A
R
E
$5
0
,
0
0
0
GI
S
0
4
GI
S
AE
R
I
A
L
P
H
O
T
O
G
R
A
P
H
Y
$8
5
,
0
0
0
GI
S
0
6
GI
S
GP
S
S
Y
S
T
E
M
R
E
P
L
A
C
E
M
E
N
T
$1
7
,
5
0
0
GI
S
0
8
GI
S
LA
R
G
E
F
O
R
M
A
T
P
L
O
T
T
E
R
-
R
E
P
L
A
C
E
M
E
N
T
$2
0
,
0
0
0
GI
S
1
2
GI
S
FM
E
S
E
R
V
E
R
$2
0
,
0
0
0
GI
S
1
3
GI
S
VE
R
T
I
C
A
L
A
S
S
E
T
R
I
S
K
A
S
S
E
S
S
M
E
N
T
(P
H
A
S
E
2
)
$85,000
GI
S
1
4
GI
S
VE
R
T
I
C
A
L
A
S
S
E
T
R
I
S
K
A
S
S
E
S
S
M
E
N
T
(P
H
A
S
E
1
)
$20,000
GI
S
1
5
GI
S
GI
S
F
I
E
L
D
V
E
H
I
C
L
E
R
E
P
L
A
C
E
M
E
N
T
$2
6
,
0
0
0
$8
3
,
5
0
0
$5
0
,
0
0
0
$8
5
,
0
0
0
$105,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
GI
S
1
1
Pu
b
l
i
c
W
o
r
k
s
CO
M
P
U
T
E
R
R
E
P
L
A
C
E
M
E
N
T
S
$52,291
$4
9
,
0
4
8
$4
5
,
3
6
9
$3
0
,
1
2
5
$5
9
,
2
3
1
36
8
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
PW
0
5
Pu
b
l
i
c
W
o
r
k
s
PU
B
L
I
C
W
O
R
K
S
S
H
O
P
S
M
A
S
T
E
R
P
L
A
N
$2
0
,
0
0
0
PW
0
6
Pu
b
l
i
c
W
o
r
k
s
PU
B
L
I
C
W
O
R
K
S
S
H
O
P
S
F
A
C
I
L
I
T
Y
CO
N
S
T
R
U
C
T
I
O
N
$6
7
0
,
0
0
0
$52,291
$6
9
,
0
4
8
$7
1
5
,
3
6
9
$3
0
,
1
2
5
$5
9
,
2
3
1
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
GI
S
1
4
SC
A
D
A
SC
A
D
A
U
P
G
R
A
D
E
S
&
I
M
P
R
O
V
E
M
E
N
T
S
$2
,
1
0
0
,
0
0
0
W6
6
SC
A
D
A
ME
T
E
R
S
,
T
R
A
N
S
D
U
C
E
R
S
&
CO
M
M
U
N
I
C
A
T
I
O
N
S
(
R
E
P
L
A
C
E
M
E
N
T
SC
A
D
A
R
A
D
I
O
&
S
T
R
A
P
O
N
F
L
O
W
M
E
T
E
R
)
$10,000
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
$10,000
$1
0
,
0
0
0
$1
0
,
0
0
0
$1
0
,
0
0
0
$2
,
1
1
0
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
WC
0
2
Wa
t
e
r
C
o
n
s
e
r
v
a
ME
T
E
R
S
O
F
T
W
A
R
E
S
U
B
S
C
R
I
P
T
I
O
N
$36,000
$3
6
,
0
0
0
$3
6
,
0
0
0
$3
6
,
0
0
0
$3
6
,
0
0
0
WC
0
3
Wa
t
e
r
Co
n
s
e
r
v
a
t
i
o
n
MU
N
I
C
I
P
A
L
W
A
T
E
R
S
H
E
D
D
A
T
A
CO
L
L
E
C
T
I
O
N
$5
0
,
0
0
0
$36,000
$8
6
,
0
0
0
$3
6
,
0
0
0
$3
6
,
0
0
0
$3
6
,
0
0
0
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
WI
F
4
0
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
SO
U
R
D
O
U
G
H
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
–
PH
A
S
E
2
(
F
I
N
A
N
C
E
W
9
0
)
$4
8
0
,
0
0
0
WI
F
4
8
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
DE
B
T
S
E
R
V
I
C
E
F
O
R
B
O
R
R
O
W
I
N
G
-
TR
A
N
S
M
I
S
S
I
O
N
M
A
I
N
(
W
8
9
)
$30,000 $380,000
$3
0
,
0
0
0
$3
0
,
0
0
0
$30,000
$4
8
0
,
0
0
0
$3
0
,
0
0
0
$3
0
,
0
0
0
$380,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
W4
7
Wa
t
e
r
Op
e
r
a
t
i
o
n
s
RE
P
L
A
C
E
#
2
6
4
7
-
1
9
9
8
1
/
2
T
O
N
C
H
E
V
Y
PI
C
K
U
P
$2
7
,
0
0
0
W4
9
Wa
t
e
r
Op
e
r
a
t
i
o
n
s
RE
P
L
A
C
E
#
3
0
7
8
-
2
0
0
2
1
/
2
T
O
N
C
H
E
V
Y
PI
C
K
U
P
$2
7
,
0
0
0
W6
8
Wa
t
e
r
O
p
e
r
a
t
i
o
WH
E
E
L
E
D
E
X
C
A
V
A
T
O
R
$151,000
W6
9
Wa
t
e
r
O
p
e
r
a
t
i
o
WA
T
E
R
S
Y
S
T
E
M
C
O
N
D
I
T
I
O
N
A
S
S
E
S
S
M
E
N
T
$1
0
0
,
0
0
0
$1
0
0
,
0
0
0
W7
0
Wa
t
e
r
O
p
e
r
a
t
i
o
RE
D
U
N
D
A
N
T
N
O
R
T
H
5
0
3
8
Z
O
N
E
F
E
E
D
$6
6
,
8
8
0
W7
1
Wa
t
e
r
Op
e
r
a
t
i
o
n
s
PR
V
P
H
A
S
E
2
-
A
U
T
O
M
A
T
I
O
N
A
N
D
IN
S
T
R
U
M
E
N
T
A
T
I
O
N
U
P
G
R
A
D
E
S
$6
,
7
1
0
,
0
0
0
36
9
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
W7
2
Wa
t
e
r
Op
e
r
a
t
i
o
n
s
PR
V
P
H
A
S
E
1
-
M
E
C
H
A
N
I
C
A
L
A
N
D
ST
R
U
C
T
U
R
A
L
U
P
G
R
A
D
E
S
$1
,
7
5
0
,
0
0
0
W7
3
Wa
t
e
r
Op
e
r
a
t
i
o
n
s
PR
V
A
B
A
N
D
O
N
M
E
N
T
S
(
A
P
P
R
O
X
I
M
A
T
E
L
Y
6
SI
T
E
S
)
$510,106
W7
5
Wa
t
e
r
O
p
e
r
a
t
i
o
LE
A
D
S
E
R
V
I
C
E
L
I
N
E
R
E
P
L
A
C
E
M
E
N
T
$2
0
0
,
0
0
0
W8
5
Wa
t
e
r
Op
e
r
a
t
i
o
n
s
SO
U
T
H
U
N
I
V
E
R
S
I
T
Y
D
I
S
T
R
I
C
T
1
2
"
W
A
T
E
R
MA
I
N
$2
9
6
,
5
0
9
$2
,
2
4
6
,
5
0
9
$1
6
6
,
8
8
0
$2
7
,
0
0
0
$6
,
8
3
7
,
0
0
0
$661,106
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Wa
t
e
r
F
u
n
d
W5
6
WT
P
WT
P
F
A
C
I
L
I
T
Y
R
&
R
$40,000
$4
0
,
0
0
0
$4
0
,
0
0
0
$4
0
,
0
0
0
$4
0
,
0
0
0
W5
7
WT
P
WT
P
F
A
C
I
L
I
T
Y
E
N
G
I
N
E
E
R
I
N
G
&
OP
T
I
M
I
Z
A
T
I
O
N
$20,000
$2
0
,
0
0
0
$2
0
,
0
0
0
$2
0
,
0
0
0
$2
0
,
0
0
0
W5
8
WT
P
MO
D
U
L
E
R
E
P
L
A
C
E
F
U
N
D
$50,000
$5
0
,
0
0
0
$5
0
,
0
0
0
$5
0
,
0
0
0
$5
0
,
0
0
0
W6
2
WT
P
RE
P
L
A
C
E
#
3
4
4
6
-
W
T
P
G
M
C
S
I
E
R
R
A
PI
C
K
U
P
$0
$4
5
,
0
0
0
W6
3
WT
P
SO
U
R
D
O
U
G
H
W
A
T
E
R
S
H
E
D
F
U
E
L
RE
D
U
C
T
I
O
N
$4
0
0
,
0
0
0
W7
8
WT
P
HI
L
L
T
O
P
T
A
N
K
I
N
S
P
E
C
T
I
O
N
A
N
D
M
I
X
I
N
G
SY
S
T
E
M
$1
3
0
,
0
0
0
W7
9
WT
P
HY
A
L
I
T
E
D
A
M
A
N
D
R
E
S
E
R
V
O
I
R
OP
T
I
M
I
Z
A
T
I
O
N
I
M
P
R
O
V
E
M
E
N
T
S
$4
,
0
0
0
,
0
0
0
W8
3
WT
P
SO
U
R
D
O
U
G
H
I
N
T
A
K
E
I
M
P
R
O
V
E
M
E
N
T
S
$2,000,000
W8
4
WT
P
SO
U
R
D
O
U
G
H
T
A
N
K
I
N
S
P
E
C
T
I
O
N
A
N
D
IM
P
R
O
V
E
M
E
N
T
S
$6
0
0
,
0
0
0
W8
6
WT
P
SO
U
R
D
O
U
G
H
D
I
V
E
R
S
I
O
N
C
L
E
A
N
O
U
T
$2
5
,
0
0
0
W8
7
WT
P
LY
M
A
N
T
A
N
K
A
N
D
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
DE
S
I
G
N
$5
0
0
,
0
0
0
W8
8
WT
P
LY
M
A
N
T
A
N
K
A
N
D
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
CO
N
S
T
R
U
C
T
I
O
N
$1
0
,
0
0
0
,
0
0
0
$110,000
$1
,
1
6
5
,
0
0
0
$7
5
5
,
0
0
0
$1
4
,
1
1
0
,
0
0
0
$1
1
0
,
0
0
0
$2,000,000
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
37
0
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Su
m
m
a
r
y
f
o
r
W
a
t
e
r
F
u
n
d
(
4
6
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$1,460,791
$4
,
8
8
2
,
5
5
7
$3
,
4
3
5
,
7
4
9
$3,479,439FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$1
0
,
4
0
4
,
7
3
1
$1
5
,
5
5
0
,
6
2
5
FY
2
1
37
1
CIP Project Fund
Water Fund
PROJECT NUMBER
GF227
DEPARTMENT
Finance
PROJECT NAME
ERP Replacement "Sungard Replacement/Upgrade"
FY19 FY20 Unscheduled
$333,333
DESCRIPTION OF PROJECT
Replacing/upgrading the current system installed in 1999. This is the system that runs all the financial, community development,
land records, utility and business license applications. Although it is unscheduled we are currently looking into this with a
possibility of FY20.
ALTERNATIVES CONSIDERED
Continue running current SunGard package. Use SunGard.net (NaviLine EDGE) as an improvement to the current system, but not a full
replacement.
ADVANTAGES OF APPROVAL
Simplified package. Easier to integrate the various applications/programs. Easier to pull out information for end users. Easier compiliation of
Commission reports and packets for Community Development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown. Dependent on the option chosen.
FUNDING SOURCES
General Fund 33%; Water Fund 33%; Wastewater Fund 33%
New
Replacement
Equipment
Project
FY21 FY22 FY23
372
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS03
DEPARTMENT
GIS
PROJECT NAME
Asset Management Software
FY19 FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
Managing infrastructure efficiently continues to be one of the top priorities and goals of the Bozeman City Commission. Assets
within the water distribution system, wastewater collection system, and the stormwater system will benefit from modern analysis.
Specialized asset management software will build upon existing datasets and systems to assist in delivering the desired level of
service for the lowest life cycle cost. Advanced applications are necessary to analyze condition information and criticality to
identify and coordinate overlaps and gaps among various assets. Asset management software will be used to better understand
opportunities for system repair and improvement across all asset categories. This technology will leverage the strengths of
coordinating and scheduling overlapping needs across all infrastructures. Current and future facility planning efforts will benefit
from a comprehensive application of asset management as it relates to coordinated infrastructure improvements throughout the
city.
ALTERNATIVES CONSIDERED
Continue managing data and workflow using manual processes with limited potential for effective analysis.
ADVANTAGES OF APPROVAL
Using technology to support long term capital planning will aid in rehabilitation/repair/replacement decisions and ultimately result in a prolonged
asset lifespan. A fully developed asset management program will assist the organization in continuing to deliver a high level of service in the most
sustainable way possible.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Maintenance (first year included) = $8,000
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
373
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS04
DEPARTMENT
GIS
PROJECT NAME
Aerial Photography
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Aerial photography is used on a daily basis in all levels of city operations to support a wide variety of decisions. Benefits to both
the organization and the community include a clear and accurate representation of current conditions in addition to serving as an
important historical record during times of high growth. Current aerial photography supports timely decisions based on accurate
information and continues to experience unprecedented user demand (i.e., staff reports, Commission presentations,
water/sewer/stormwater utilities, public requests, etc.).
ALTERNATIVES CONSIDERED
Use of lower resolution satellite imagery. Partnerships with other agencies.
ADVANTAGES OF APPROVAL
Contributes to on-going acquisition of photos at regular intervals for historical archives. Since 1987 we have not gone more than five years
without an update. Measurements and land use determinations are made on a local or regional basis without requiring extensive field time. Used
extensively in several on-line and in-house mapping applications. Provides background information for existing and future GIS & CAD datasets
and Facility Plans. Meets public demand for current and accurate aerial photography.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
There are no annual operating or maintenance costs associated with this project.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21
$85,000
FY22 FY23
374
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS06
DEPARTMENT
GIS
PROJECT NAME
GPS System Replacement
FY19
$17,500
FY20 Unscheduled
DESCRIPTION OF PROJECT
GPS data provides current and accurate information to support critical decisions. GPS is used to collect a wide variety of location
data, including all water, sewer, stormwater, parks, and transportation related assets. This is the second of two planned upgrades
to replace equipment originally purchased in 2012. Advancements in technology allow for greater efficiency along with improved
accuracy. Major departments that share in the use of this equipment include water/sewer, stormwater, engineering, community
development, streets, etc.
ALTERNATIVES CONSIDERED
Contracted data collection services. Rental equipment.
ADVANTAGES OF APPROVAL
Meets the demands of recent expansions in the scope of data collection efforts within Public Works. Maintains our most critical equipment in
the GIS Department with current technology.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
There are no annual operating or maintenance costs associated with this project.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
375
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS08
DEPARTMENT
GIS
PROJECT NAME
Large Format Plotter - Replacement
FY19
$20,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Printing large scale maps is critical for the delivery of hard-copy exhibits for both the organization as well as the public. Large
format displays facilitate efficient and effective decision making by providing visual context for surrounding infrastructure and
development. Large format prints are produced on a daily basis in support of all city departments, including public map sales. Major
departments that share in the use of this equipment include water/sewer, stormwater, engineering, community development,
streets, etc.
ALTERNATIVES CONSIDERED
Maintain current equipment beyond recommended lifespan (replacement parts become difficult to locate over time). Contracted printing
services.
ADVANTAGES OF APPROVAL
Maintains critical equipment in the GIS Department with current technology. Supports on-going printing needs for several departments
(including the public).
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
On-going expenses include printing supplies and routine maintenance (approx. $2,500.00/yr.).
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
376
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS11
DEPARTMENT
Public Works
PROJECT NAME
Computer Replacements
FY19
$49,048
FY20
$45,369
Unscheduled
DESCRIPTION OF PROJECT
Anticipated Public Works computer replacements.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$30,125
FY22
$59,231
FY23
$52,291
377
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS12
DEPARTMENT
GIS
PROJECT NAME
FME Server
FY19
$20,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Purchase upgrade to an existing database technology which effectively automates the transfer of information between a variety of
systems. Database information is used on a daily basis in all levels of our operations to support a wide variety of decisions.
Updated technology will result in a more efficient process for managing large volumes of data. Database information is used by
almost every department to support many technology systems. Deferring the purchase of this upgrade will not allow for the full
realization of potential efficiency of moving large amounts of data between systems. Upgraded FME server technology will
leverage the strengths of a wide variety of database systems throughout the organization. Several current and future projects will
benefit from automated data transformation including solid waste, stormwater, and water conservation.
ALTERNATIVES CONSIDERED
Continue transferring database information using manual processes with limited potential for increased efficiency.
ADVANTAGES OF APPROVAL
Employees and citizens will have real-time access to a wide variety of information that is typically out of date and hard to attain.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Maintenance (first year included) = $3,470
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
378
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS13
DEPARTMENT
GIS
PROJECT NAME
Vertical Asset Risk Assessment (Phase 2)
FY19 FY20 Unscheduled
$85,000
DESCRIPTION OF PROJECT
Risk assessment (i.e., likelihood vs. consequence) is currently a major factor in considering horizontal infrastructure repair &
replacements for both water distribution and wastewater collection systems. This project will exectute the implementation plan
developed in Phase 1 to expand the use of risk to vertical assets including reservoirs, groundwater sources, PRV's, booster
stations, and treatments plants. A generalized risk policy allows for the comparison of risk across various asset classes on a
comparable scale, which then allows for better allocation of CIP funding and effort to the highest risk assets across the entire
utility.
ALTERNATIVES CONSIDERED
Continue to assess risk for only horizontal infrastructure, while using separate criteria to evaluate vertical assets.
ADVANTAGES OF APPROVAL
Completes the need for considering risks for both horizontal and vertical infrastructure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Dedicated staff time will be needed to maintain the resulting risk model.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
379
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS14
DEPARTMENT
GIS
PROJECT NAME
Vertical Asset Risk Assessment (Phase 1)
FY19 FY20 Unscheduled
$20,000
DESCRIPTION OF PROJECT
Risk assessment (i.e., likelihood vs. consequence) is currently a major factor in considering horizontal infrastructure repair &
replacements for both water distribution and wastewater collection systems. This project will result in an implementation plan to
expand the use of risk to vertical assets including reservoirs, groundwater sources, PRV's, booster stations, and treatments plants.
A generalized risk policy allows for the comparison of risk across various asset classes on a comparable scale, which then allows
for better allocation of CIP funding and effort to the highest risk assets across the entire utility.
ALTERNATIVES CONSIDERED
Continue to assess risk for only horizontal infrastructure, while using separate criteria to evaluate vertical assets.
ADVANTAGES OF APPROVAL
Completes the need for considering risks for both horizontal and vertical infrastructure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Dedicated staff time will be needed to maintain the resulting risk model.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
380
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS14
DEPARTMENT
SCADA
PROJECT NAME
SCADA Upgrades & Improvements
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Install Wide Area Network infrastructure, connect PRV vaults, verify/install Pressure relief per each Pressure Zone, central site
improvements, update historian, and implement pressure management regimes to improve system pressure protection. This will
result in improved surveillance of system operation, increased control and understanding of real-time system conditions, and the
ability to implement tighter pressure management controls. Additionally, this will improve our understanding of cause/effect allows
improved overall system operation including more precise pressure control, real-time updates during abnormal events. This
project has a direct impact on our PRV vault upgrades, Reservoir mixing upgrades, new storage reservoir, Pear St. Booster Station
upgrade, and remote water quality surveillance system.
ALTERNATIVES CONSIDERED
Status Quo
ADVANTAGES OF APPROVAL
Improved surveillance of system operation, increased control and understanding of real-time system conditions, ability to implement tighter
pressure management controls.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
SCADA WAN maintenance expenses, server and hardware maintenance, software maintenance and programming libraries
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22
$2,100,000
FY23
381
CIP Project Fund
Water Fund
PROJECT NUMBER
GIS15
DEPARTMENT
GIS
PROJECT NAME
GIS Field Vehicle Replacement
FY19
$26,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The GIS Department collects data for many assets including water, wastewater, stormwater, and all transportation infrastructure.
Over 500 hours are spent each year in the field mapping and verifying location information across the city. The vehicle currently in
use is a 1998 Chevy 1500 1/2 Ton 4WD Pickup with 98,418 miles (as of 8/3/17). The vehicle replacement policy within Public
Works states 100,000 and/or 20 years, putting this vehicle within range. A fuel efficient Prius is recommended and will meet the
needs of the department for years to come.
ALTERNATIVES CONSIDERED
Leased vehicle.
ADVANTAGES OF APPROVAL
Replaces an aging, inefficient vehicle.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Standard vehicle maintenance costs.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
382
CIP Project Fund
Water Fund
PROJECT NUMBER
PW05
DEPARTMENT
Public Works
PROJECT NAME
Public Works Shops Master Plan
FY19
$20,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Develop a long term master plan for Public Works shop facilities, equipment, and personnel. This includes conducting a needs
assessment of space for existing and future employees, equipment, machinery, and rolling stock. There is a severe shortage of
enclosed storage for equipment, vehicles, and machinery, resulting in extra wear and tear, additional maintenance costs, and time
preparing the equipment on cold mornings. Additionally, there is a lack of space available for existing as well as future staff. This
will be split three ways between water ($20,000), wastewater ($20,000), and streets ($20,000).
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
Provide an accurate analysis of the City of Bozeman Public Works space needs for both equipment as well as people.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Depending on the results of the plan, the likely result will be the construction of additional storage and office space.
FUNDING SOURCES
This project will be split 3 ways between Water Fund ($20,000), Wastewater Fund ($20,000), and Street Maintenance Fund ($20,000)
New
Replacement
Equipment
Project
FY21 FY22 FY23
383
CIP Project Fund
Water Fund
PROJECT NUMBER
PW06
DEPARTMENT
Public Works
PROJECT NAME
Public Works Shops Facility Construction
FY19 FY20
$670,000
Unscheduled
DESCRIPTION OF PROJECT
Construct additional facilities recommended in the result of the Public Works Shops Master Plan. This will be split three ways
between water ($670,000), wastewater ($670,000), and streets ($670,000).
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
The construction of a new Public Works facility will provide indoor storage for millions of dollars of equipment, machinery, vehicles, etc. This
will both reduce wear and tear and maintenance costs, as well as reduce time spent on preparing equipment on cold mornings.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Normal building maintenance and utility costs.
FUNDING SOURCES
This project will be split 3 ways between Water Fund ($670,000), Wastewater Fund ($670,000), and Street Maintenance Fund ($670,000)
New
Replacement
Equipment
Project
FY21 FY22 FY23
384
CIP Project Fund
Water Fund
PROJECT NUMBER
W03
DEPARTMENT
Engineering
PROJECT NAME
Annual Water Pipe Replacement Program - Design
FY19
$22,500
FY20
$22,500
Unscheduled
DESCRIPTION OF PROJECT
This item provides for design work to be completed every year, in anticipation of the Annual Water System Upgrades.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the design of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY21
$22,500
FY22
$22,500
FY23
$22,500
385
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-19
DEPARTMENT
Engineering
PROJECT NAME
Water Pipe Replacement Program - Construction in 2019
FY19
$1,200,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The water replacement program sets aside funds to assess and replace failing water pipes. Priority will go to replace the water
pipe associated with the annual street construction (S Tracy from Babcock to College). The remaining funds will be used to
conduct water pipe condition assessments and repair identified pipes.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
386
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-20
DEPARTMENT
Engineering
PROJECT NAME
Water Pipe Replacement Program - Construction in 2020
FY19 FY20
$1,200,000
Unscheduled
DESCRIPTION OF PROJECT
The water replacement program sets aside funds to assess and replace failing water pipes. Priority will go to replace the water
pipe associated with the annual street construction (S Black from College to the Cul-De-Sac). The remaining funds will be used to
conduct water pipe condition assessments and repair identified pipes.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
387
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-21
DEPARTMENT
Engineering
PROJECT NAME
Water Pipe Replacement Program - Construction in 2021
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The water replacement program sets aside funds to assess and replace failing water pipes. Priority will go to replace the water
pipe associated with the annual street construction (N Tracy from Villard to Peach). The remaining funds will be used to conduct
water pipe condition assessments and repair identified pipes.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$1,200,000
FY22 FY23
388
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-22
DEPARTMENT
Engineering
PROJECT NAME
Water Pipe Replacement Program - Construction in 2022
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The water replacement program sets aside funds to assess and replace failing water pipes. Priority will go to replace the water
pipe associated with the annual street construction (N 17th from Durston to the End). The remaining funds will be used to
conduct water pipe condition assessments and repair identified pipes.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22
$1,200,000
FY23
389
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-23
DEPARTMENT
Engineering
PROJECT NAME
Water Pipe Replacement Program - Construction in 2023
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The water replacement program sets aside funds to assess and replace failing water pipes. Priority will go to replace the water
pipe associated with the annual street construction (West Koch Street from 8th to Tracy). The remaining funds will be used to
conduct water pipe condition assessments and repair identified pipes.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
$1,200,000
390
CIP Project Fund
Water Fund
PROJECT NUMBER
W47
DEPARTMENT
Water Operations
PROJECT NAME
Replace #2647 - 1998 1/2 Ton Chevy Pickup
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project is to replace a 1998 Chevy with 70,779 miles. As our crew grows this type of vehicle is used daily in support of the
department's mission. This truck responds to all types of calls from locating to witnessing bores to a support vehicle for
excavation jobs. Using an older vehicle becomes more unreliable, but if we had to, we could hold off a year.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
As the truck ages there will be unforeseen costs to maintain this vehicle.
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21
$27,000
FY22 FY23
391
CIP Project Fund
Water Fund
PROJECT NUMBER
W49
DEPARTMENT
Water Operations
PROJECT NAME
Replace #3078 - 2002 1/2 Ton Chevy Pickup
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project replaces a 2002 Chevy pickup with 85,816 miles. This truck is used for leak detection, locating, and fire hydrant
flushing, which are 3 critical programs for our department. This truck will be replaced with a more fuel efficient vehicle.
ALTERNATIVES CONSIDERED
Continue to use older piece of equipment which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
As the truck ages there will be unforeseen costs to maintain this vehicle.
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22
$27,000
FY23
392
CIP Project Fund
Water Fund
PROJECT NUMBER
W56
DEPARTMENT
WTP
PROJECT NAME
WTP Facility R&R
FY19
$40,000
FY20
$40,000
Unscheduled
DESCRIPTION OF PROJECT
Repair and replacement fund for the WTP. Having this item in the budget will allow for unexpected and rapid repair of equipment,
in the event of failure. This will result in shorter down time and not defer other planned projects. Without this fund, maintenance
could be deferred for up to a year.
ALTERNATIVES CONSIDERED
Not having this fund would defer other needed maintenance.
ADVANTAGES OF APPROVAL
If systems fail, they need to be repaired immediately. If the failure is unexpected, other items that have been budgeted for will need to be
postponed. Not all repairs or equipment failures can be predicted and budgeted as capital improvement projects
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Water Funds
New
Replacement
Equipment
Project
FY21
$40,000
FY22
$40,000
FY23
$40,000
393
CIP Project Fund
Water Fund
PROJECT NUMBER
W57
DEPARTMENT
WTP
PROJECT NAME
WTP Facility Engineering & Optimization
FY19
$20,000
FY20
$20,000
Unscheduled
DESCRIPTION OF PROJECT
WTP Facility Engineering & Optimization. The longer the water treatment plant is in operation, operators become familiar with
the processes and come up with ideas to optimize the process. This line item will allow for engineering studies on the operators
ideas before the expense of changing the process. In particular, the plan for this budget items is to improve the process from the
raw water intakes to the treated water reservoirs. It will allow studies to be conducted to make sure that proposed optimizations
will actually improve the process at a reasonable expense. Through the optimization of the plant with engineering studies the
process will be streamlined and will save money in the future.
ALTERNATIVES CONSIDERED
Proceed with optimization projects without knowing if the project will actually improve plant performance.
ADVANTAGES OF APPROVAL
The advantage of having funds available to do engineering studies before any project is started will make sure that the right equipment is
purchased and that it will perform properly. Optimization studies will predict actual cost/benefit over time to make sure the city is spending its
money efficiently.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Water Funds
New
Replacement
Equipment
Project
FY21
$20,000
FY22
$20,000
FY23
$20,000
394
CIP Project Fund
Water Fund
PROJECT NUMBER
W58
DEPARTMENT
WTP
PROJECT NAME
Module Replace Fund
FY19
$50,000
FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
Without the timely replacement of the membranes at the end of their useful lifespan, the whole treatment process will need to be
shut down. Because this treatment process is relatively new, we do not have a firm estimate on the lifespan of the membranes.
We expect them to last at least ten years but they could last twenty. This "savings account" will provide for rapid acquisition and
replacement of the membrane modules when the time comes, instead of waiting for the next budget cycle. The costs for these
replacements would be significant and typically need to be planned for after 10 years. This will be an on-going item for the next 20
years.
ALTERNATIVES CONSIDERED
Determine funding source at the time these replacements are needed.
ADVANTAGES OF APPROVAL
If a membrane module at the plant needs to be replaced, the cost will be significant. This will allow the city to save money over time.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Water Funds
New
Replacement
Equipment
Project
FY21
$50,000
FY22
$50,000
FY23
$50,000
395
CIP Project Fund
Water Fund
PROJECT NUMBER
W62
DEPARTMENT
WTP
PROJECT NAME
Replace #3446 - WTP GMC Sierra Pickup
FY19 FY20
$45,000
Unscheduled
DESCRIPTION OF PROJECT
This truck replaces #3446, the plant’s sampling vehicle. This truck currently has over 100,000 miles on it and is driven
approximately 35 miles per day, 365 days per year.
ALTERNATIVES CONSIDERED
Continue driving #3446 and risk break downs and increased maintenance costs.
ADVANTAGES OF APPROVAL
A new truck would be more reliable and result in lower repair and maintenance costs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal Maintenance Costs
FUNDING SOURCES
100% Water Funds
New
Replacement
Equipment
Project
FY21 FY22 FY23
$0
396
CIP Project Fund
Water Fund
PROJECT NUMBER
W63
DEPARTMENT
WTP
PROJECT NAME
Sourdough Watershed Fuel Reduction
FY19
$400,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Sourdough fuel reduction will protect investments in WTP pre-membrane sedimentation process and membrane filters by
reducing wildfire impacts on raw water quality in sourdough. This will reduce wildfire risk in sourdough drainage and increases
resiliency against catastrophic wildfire, and should lessen wear and tear on processes and components in event of wildfire
impacted source water. Additionally, it provides a safer environment for fire suppression to occur in the event of. This project
works in dovetail with USFS BMW project, and will not happen unless BMW project goes.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Provides landscape level fuel reduction that dovetails with the USFS BMW project. reduces susceptivibility of catastrophic wildfire in Sourdough
municipal watershed. Reduces impacts to public and watershed closures during work activities
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown
FUNDING SOURCES
$270,000 DNRC Special State Fire Assistance Grant
New
Replacement
Equipment
Project
FY21 FY22 FY23
397
CIP Project Fund
Water Fund
PROJECT NUMBER
W66
DEPARTMENT
SCADA
PROJECT NAME
Meters, Transducers & Communications (Replacement Scada Radio & Strap On Flow Meter)
FY19
$10,000
FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
Meters, Transducers & Communications (Replacement Scada Radio & Strap On Flow Meter) for the SCADA Technician. The
City's SCADA Technician needs funds to perform their necessary job functions. Failure of electronic devices needed to perform
the job cannot be foreseen or scheduled. This fund would allow funds for that equipment. SCADA directly impacts water
distribution, WRF, and WTP. Improved SCADA will result in cost savings through water conservation.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
This fund will allow the Technician to repair or replace important equipment in a more timely manner.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Water Funds
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
$10,000
398
CIP Project Fund
Water Fund
PROJECT NUMBER
W68
DEPARTMENT
Water Operations
PROJECT NAME
Wheeled Excavator
FY19 FY20 Unscheduled
$151,000
DESCRIPTION OF PROJECT
This would be a trackhoe excavator with wheels instead of tracks. It is a critical piece of machinery in our departments, and it is
used to maintain water, sewer, and stormwater infrastructure. The excavator will be split 50/50 with the wastewater fund
(WW86).
ALTERNATIVES CONSIDERED
Continue to use smaller equipment .
ADVANTAGES OF APPROVAL
Increased productivity with larger excavator.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
$151,000 Water Fund, $151,000 Wastewater Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
399
CIP Project Fund
Water Fund
PROJECT NUMBER
W69
DEPARTMENT
Water Operations
PROJECT NAME
Water System Condition Assessment
FY19 FY20
$100,000
Unscheduled
DESCRIPTION OF PROJECT
Prepare and evaluate condition assessment plan and execute water main condition assessments in high risk portions of the city.
These are major assets whose failure could affect a large population of end-users. Work-a round may be possible with heavy
burden on Utility resources. Additionally, these studies could produce substantial & quantifiable benefits that improves product
quality, processes, or adoption of best industry practices. Depending on the results, these studies could result in follow-up R&R.
ALTERNATIVES CONSIDERED
No inspection
ADVANTAGES OF APPROVAL
Doing planned condition assessment can provide a cost effective mechanism of identifying likely asset failures and thereby offering the
opportunity of repairing the deficiency or the whole asset if needed prior to failure. Additionally, CA often can identify assets in good working
condition, so only required repairs are completed thereby saving significant money in replacing assets in good working order.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22
$100,000
FY23
400
CIP Project Fund
Water Fund
PROJECT NUMBER
W70
DEPARTMENT
Water Operations
PROJECT NAME
Redundant North 5038 Zone Feed
FY19 FY20
$66,880
Unscheduled
DESCRIPTION OF PROJECT
Evaluate, and upgrade as required, 2nd location of redundant feed of 5130 Zone water into North (5038) Zone. This will ensure
alternative source of water exists and is sufficient to feed North Zone in time when Lyman Creek source is unavailable. This
provides a second path for water to move from South Zone to North Zone in event that Lyman source is unavailable. This
project will meet the City’s hydraulic criteria. It could be performed in conjunction with Pear St. Booster Upgrade to facilitate
testing and commissioning.
ALTERNATIVES CONSIDERED
Continue with single connection between pressure zones
ADVANTAGES OF APPROVAL
Use existing facilities and connectivity to provide redundant back up source of water
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
401
CIP Project Fund
Water Fund
PROJECT NUMBER
W71
DEPARTMENT
Water Operations
PROJECT NAME
PRV Phase 2 - Automation and Instrumentation Upgrades
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Upgrade pressure instrumentation, automate valve actuation, and provide a LAN connection and SCADA programming for real-
time monitoring and remote control of PRV settings. Without this project, system operators are without vital data on system
operating conditions. Limited real time data allows operators to anticipate, diagnose, or correct abnormal operating conditions.:
Standardized pressure control offers improved protections from surge conditions which are a likely cause of pipe failure. It will
also improve service levels to existing customers where pressure transients cause leaks in sprinkler systems or within customer
premises.
ALTERNATIVES CONSIDERED
Status quo operation
ADVANTAGES OF APPROVAL
Improve water distribution operations through increased understanding of system operating characteristics. Improve responsiveness to dynamic
operating conditions. Facilitate improved access to existing sites now requiring confined space entry procedures. Standardize and improve surge
control features throughout system.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Debt service (if any) to construct, power costs, SCADA maintenance, vault maintenance, instrument maintenance, programming libraries
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22
$6,710,000
FY23
402
CIP Project Fund
Water Fund
PROJECT NUMBER
W72
DEPARTMENT
Water Operations
PROJECT NAME
PRV Phase 1 - Mechanical and Structural Upgrades
FY19
$1,750,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Upgrade hatch/entry, valving, piping, pressure settings, sump pumps and provide power, which will provide operators with a safe
working environment, and sets PRVs at operating pressures at pressure zone interfaces consistent with the WFPU
recommendations. Additionally, it will provide necessary upgrades to equipment, piping and valving in PRV vaults to reduce
likelihood of failures. Standardized pressure controls offers improved protections from surge conditions, which are likely causes of
pipe failure. It improves service levels to existing customers where pressure transients cause leaks in sprinkler systems or within
customers’ premises.
ALTERNATIVES CONSIDERED
Status quo operation
ADVANTAGES OF APPROVAL
Improve water distribution operations through increased understanding of system operating characteristics. Improve responsiveness to dynamic
operating conditions. Facilitate improved access to existing sites now requiring confined space entry procedures. Standardize and improve surge
control features throughout system.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Debt service (if any) to construct, power costs, SCADA maintenance, vault maintenance, instrument maintenance, programming libraries
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
403
CIP Project Fund
Water Fund
PROJECT NUMBER
W73
DEPARTMENT
Water Operations
PROJECT NAME
PRV Abandonments (approximately 6 sites)
FY19 FY20 Unscheduled
$510,106
DESCRIPTION OF PROJECT
Abandon (in place) existing PRV's serving Northwest 4940 Pressure Zone, at sites to be determined through detailed hydraulic
modeling. Install looped mains to maintain connectivity. This project will be done in conjunction with other transmission main
improvements serving Northwest zones. This will reduce system complexity, and simplifies control strategy, which is critical with
additional improvements planned within service area, yet maintains sufficient connectivity between zones per Hydraulic criteria.
Additionally, it will create an opportunity for PRV's feeding zone to create undesired chattering of PRV's fighting each other via
control strategy. Chattering of valves can lead to undesired hydraulic transients in system.
ALTERNATIVES CONSIDERED
Status quo
ADVANTAGES OF APPROVAL
Avoid costs of equipping sites with SCADA and related infrastructure. Reduce future operating expenses associated with PRV vault operation
and control. Simplify zone operation by reducing number of required PRV's to feed zone.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Avoid costs of equipping sites with SCADA and related infrastructure. Reduce future operating expenses associated with PRV vault operation
and control
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
404
CIP Project Fund
Water Fund
PROJECT NUMBER
W75
DEPARTMENT
Water Operations
PROJECT NAME
Lead Service Line Replacement
FY19
$200,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This is the last year of a two year project that will be used to hire a contractor to assist water crews in replacing lead service lines.
Removing lead service lines is critical to maintaining a high level of health and safety for our customers. This line removal meets
recommendations of the National Drinking Water Advisory Council for total removal of all lead service lines. City of Bozeman
water crews are assisting with the lead service line replacements.
ALTERNATIVES CONSIDERED
Continue using just COB water crews to replace the lead service lines, extending the program by several years. We have a committment to the
community that they will all be replaced by FY19.
ADVANTAGES OF APPROVAL
The City of Bozeman will no longer have any lead service lines
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
405
CIP Project Fund
Water Fund
PROJECT NUMBER
W78
DEPARTMENT
WTP
PROJECT NAME
Hilltop Tank Inspection and Mixing System
FY19
$130,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Inspect reservoir. Furnish and Install Mixer(s), Power and Control and update Reservoir SCADA to include remote monitoring
capability of mixer(s). Without mixing of tank contents, Water Quality can be impacted, cold weather operation can create
damage to reservoir contents. Freeze protection reduces risk of ice damage to cathodic protection system, tank interior.
ALTERNATIVES CONSIDERED
Installation of separate inlet and outlet configurations per each Reservoir
ADVANTAGES OF APPROVAL
Least expensive way to effect reservoir mixing and added freeze protection
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Energy costs for mixing; SCADA maintenance, scheduled mixer maintenance,
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
406
CIP Project Fund
Water Fund
PROJECT NUMBER
W79
DEPARTMENT
WTP
PROJECT NAME
Hyalite Dam and Reservoir Optimization Improvements
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Armoring of the control tower (to enable some year-over-year storage capacity) and control upgrades to improve winter
operation. Current vulnerability of Bozeman to drought is very high, due to the lack of sources that are robust in drought (large
raw water reservoirs with year-over-year storage capacity, large rivers, or groundwater). Hyalite Reservoir is capable of providing
year-over-year storage, but is not operated in that manner due to concerns of ice damage to the control tower. This increases the
risk of an extremely dry year resulting in the inability to fill the Hyalite reservoir with enough water for the City and irrigation
uses. This project could potentially remove the 20% surcharge the City pays for Hyalite releases.
ALTERNATIVES CONSIDERED
Continue to deal with current Hyalite dam operation
ADVANTAGES OF APPROVAL
Drought mitigation, improved water use and cost efficiencies
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21
$4,000,000
FY22 FY23
407
CIP Project Fund
Water Fund
PROJECT NUMBER
W83
DEPARTMENT
WTP
PROJECT NAME
Sourdough Intake Improvements
FY19 FY20 Unscheduled
$2,000,000
DESCRIPTION OF PROJECT
Sourdough intake improvements to increase efficiency of existing diversion infrastructure. Project calls for replacement of existing
surface diversion, installation of sub-surface collection system within stream bed gravels to capture water during surface freeze-off
events, new instrumentation and controls. This will increase the resiliency of the Sourdough water supply by reducing, or
potentially eliminating, periods and frequency of surface water freeze-off.
ALTERNATIVES CONSIDERED
Keep existing diversion configuration and continue to deal with intermittent freeze-off problems of the source
ADVANTAGES OF APPROVAL
Increases efficiency of diversion operations
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
408
CIP Project Fund
Water Fund
PROJECT NUMBER
W84
DEPARTMENT
WTP
PROJECT NAME
Sourdough Tank Inspection and Improvements
FY19 FY20
$600,000
Unscheduled
DESCRIPTION OF PROJECT
This project would entail taking the Sourdough Tank offline (once the WTP'S 5.3 million gallon storage tank is online), inspecting it
and repairing it as necessary. This project may or may not include reconfiguration of the inlet/outlet configuration to provide flow-
through hydraulics. The condition of the overflow and inlet/outlet pipes is poor. The last dive inspection found concrete aggregate
from the ceiling on the floor of the tank. The hydraulics to and from the tank are suspected to be suboptimal. An installed mixer
will also need to be considered. This project is critical to ensure that the Sourdough tank is reliable and operating well.
ALTERNATIVES CONSIDERED
Wait for critical failure
ADVANTAGES OF APPROVAL
Rehabilitation of critical storage infrastructure for several decades to come.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
409
CIP Project Fund
Water Fund
PROJECT NUMBER
W85
DEPARTMENT
Water Operations
PROJECT NAME
South University District 12" Water Main
FY19
$296,509
FY20 Unscheduled
DESCRIPTION OF PROJECT
Extend the water main service to the South University District with a 12” water pipe, as described in the 2016 Water Facility Plan.
This will coincide with WWIF27, resulting in overall efficiencies and mobilization cost savings.
ALTERNATIVES CONSIDERED
No action.
ADVANTAGES OF APPROVAL
Cost savings by building coincidently with WWIF27
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs
FUNDING SOURCES
Impact Fee and possible payback district.
New
Replacement
Equipment
Project
FY21 FY22 FY23
410
CIP Project Fund
Water Fund
PROJECT NUMBER
W86
DEPARTMENT
WTP
PROJECT NAME
Sourdough Diversion cleanout
FY19
$25,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The Diversions need to be cleaned every 7 to ten years to remove accumulated sediment, rock, and debris. Last time it was done
was 2010 and the pool behind the dam has diminished in size due to the sediment and rock accumulation.
ALTERNATIVES CONSIDERED
Build a larger diversion dam. Do Nothing and let sediment build up and have no pool to insure water flow into the system.
ADVANTAGES OF APPROVAL
Will ensure less freeze off during cold weather. Deeper pool, larger ice covering for insulation. and less sediment entering the plant.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
none
FUNDING SOURCES
none
New
Replacement
Equipment
Project
FY21 FY22 FY23
411
CIP Project Fund
Water Fund
PROJECT NUMBER
W87
DEPARTMENT
WTP
PROJECT NAME
Lyman Tank and Transmission Main Design
FY19
$500,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design of new Lyman Storage (5MG), new transmission design, chlorination/fluoridation design and CA based repairs design to
existing transmission main. This is necessary for construction of Lyman tank and transmission project. Without the design the
Tank and Transmission Main Construction (WIF35) will not be able to continue.
ALTERNATIVES CONSIDERED
Status quo operation of existing Lyman system
ADVANTAGES OF APPROVAL
Provides bid plans and cost estimates for construction and obtains DEQ approvals needed for construction
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
412
CIP Project Fund
Water Fund
PROJECT NUMBER
W88
DEPARTMENT
WTP
PROJECT NAME
Lyman Tank and Transmission Main Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construct a new 5MG storage tank at Lyman, decommission existing Lyman storage tank, Condition Assessment-based repairs of
the existing Lyman transmission main, new supply main tie in to new storage tank, new transmission main tie in from new storage
tank to existing transmission main, new chlorination/fluoridation feed facility. Decommission Pear Street Booster Station if
Hydraulic Grade Line of tank raised to meet Sourdough Tank. The Lyman water supply is a critical element of the city's overall
water supply portfolio accounting for roughly 20% of annual supply volume to the city currently. The source provides supply
redundancy and resiliency as it is geographically removed from the Sourdough/Hyalite source and provides an independent
connection to the distribution system. The effective available water supply is increased since the new storage system will not leak
and will expand the number of customers able to be supplied by Lyman water. Likelihood of failure of Lyman supply system will be
dramatically reduced by replaced storage. It will also complete new transmission and Condition Assessment-based rehab to
existing transmission.
ALTERNATIVES CONSIDERED
Status quo operation of existing Lyman system
ADVANTAGES OF APPROVAL
Replaces lyman storage tank which is at the end of its useful life. Increases effective available supply as existing tank leaks at a rate exceeding 100
gpm. If new storage sited at an elevation to match HGL of Sourdough Tank then Pear Street Booster Station can be decommissioned which
reduces annual operating costs for power. CA-based rehab reduces liklihood of failure of critical tranmission infrastructure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Anticipated operating cost reduction related to pear street booster decommissioning. Operating costs for new tank and transmission
comparable to
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY21
$10,000,000
FY22 FY23
413
CIP Project Fund
Water Fund
PROJECT NUMBER
WC02
DEPARTMENT
Water Conservation
PROJECT NAME
Meter Software Subscription
FY19
$36,000
FY20
$36,000
Unscheduled
DESCRIPTION OF PROJECT
Software upgrades to provide for flow management alerts to customers and individualized water use assessments. This project is
vital to both water conservation and water and sewer operations. A mechanism must be established to alert customers of leaks
and inefficient water usage in real time. Delays in relaying this information are costly for customers and harm relations between
utility and customers. This project will provide best practice standards for empowering customers with real time information
about their water usage.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Catches leaks very early and educates customers about individual water usage to reduce water consumption.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
Water Fund
New
Replacement
Equipment
Project
FY21
$36,000
FY22
$36,000
FY23
$36,000
414
CIP Project Fund
Water Fund
PROJECT NUMBER
WC03
DEPARTMENT
Water Conservation
PROJECT NAME
Municipal Watershed Data Collection
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Installation of instrumentation for data collection to quantify and monitor Bozeman’s water supplies, including snowpack and
streamflow. Understanding municipal watersheds’ seasonal and total annual water supplies is crucial to monitoring and preparing
for drought events and planning for future water supply needs. Incorporating real-time local water supply data into the drought
monitoring tool will provide the City with the data needed to make accurate, timely, data-driven decision making in face of a
drought event. These data will also assist with planning for long range water supply needs.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
These real-time data will provide City staff with the information needed to make accurate timely data-driven decision making in face of a drought
event and for future water supply planning. These data will support the 2013 Integrated Water Resources Plan and 2017 Drought Management
Plan.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
May lead to annual costs for additional data collection (stream gaging and/or SNOTEL snowpack data)
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21 FY22 FY23
415
CIP Project Fund
Water Fund
PROJECT NUMBER
WIF40
DEPARTMENT
Water Impact Fees
PROJECT NAME
Sourdough Transmission Main – Phase 2 (Finance W90)
FY19 FY20
$480,000
Unscheduled
DESCRIPTION OF PROJECT
The project consists of constructing approximately 8,000 feet of 30-inch DIP transmission main, which will start at the end of the
Phase 1 connection point and go to the Sourdough Plant. This project is critical to overcome vulnerabilities presented by the aging
and unknown condition of the existing transmission main between the City's WTP and Sourdough Tank. This transmission main
will provide additional capacity from the WTP to the Sourdough reservoir, improving connectivity between the WTP and the City.
This will reduce the risk of not having adequate potable water and fire flow supplies to the City in the event of a failure to the
existing bar-wrapped 30" main. This project's cost and administration could be improved if combined with the new 3,000 feet of
48" bypass pipe.
ALTERNATIVES CONSIDERED
Conduct a condition assesment of the existing 30-inch concrete pipe and repair/rehabilitate as necessary.
ADVANTAGES OF APPROVAL
The condition of the existing transmission main from the WTP to the Sourdough reservoir is currently unknown. Approval of this project will
provide redundancy for this main, and mitigate the risk and consequence of its failure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
$4,320,000 Water Impact Fees. $480,000 Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
416
CIP Project Fund
Water Fund
PROJECT NUMBER
WIF48
DEPARTMENT
Water Impact Fees
PROJECT NAME
Debt Service for Borrowing - Transmission Main (W89)
FY19 FY20 Unscheduled
$380,000
DESCRIPTION OF PROJECT
These are the estimated annual amounts owned for borrowing for WIF40 - Sourdough Transmission Main project. Payments will
begin in the fiscal year following borrowing.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The project can be constructed before cash is on hand.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
Water Utility Revenue Bonds will be issued, with repayments made by the Utility (10%) and Impact Fee Fund (90%)
New
Replacement
Equipment
Project
FY21
$30,000
FY22
$30,000
FY23
$30,000
417
418
Wa
t
e
r
I
m
p
a
c
t
F
e
e
Ca
p
i
t
a
l
I
m
p
r
o
v
e
m
e
n
t
P
l
a
n
Fi
n
a
n
c
i
a
l
S
u
m
m
a
r
y
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
F
Y
2
3
Unscheduled
Pr
o
j
e
c
t
e
d
B
e
g
i
n
n
i
n
g
R
e
s
e
r
v
e
B
a
l
a
n
c
e
D
e
d
i
c
a
t
e
d
t
o
C
I
P
2,
1
0
4
,
5
2
5
$
(1
,
1
1
8
,
6
2
3
)
$
(5
7
8
,
5
6
3
)
$
(2
2
7
,
0
6
9
)
$
59
4
,
0
1
6
$
868,905 $ ‐$
P
l
u
s
:
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
7
9
3
,
4
0
0
$
1,
8
8
3
,
0
7
0
$
1,
9
7
7
,
2
2
4
$
2,
0
7
6
,
0
8
5
$
2,
1
7
9
,
8
8
9
$
2,288,883 $ ‐$
P
l
u
s
:
L
o
a
n
f
o
r
W
e
l
l
F
i
e
l
d
W
I
F
3
2
8,
0
0
0
,
0
0
0
$
P
l
u
s
:
L
o
a
n
f
o
r
S
o
u
r
d
o
u
g
h
T
r
a
n
s
m
i
s
s
i
o
n
M
a
i
n
,
P
H
2
W
I
F
4
0
4
,
3
2
0
,
0
0
0
$
L
e
s
s
:
C
a
r
r
y
o
v
e
r
F
Y
1
7
C
a
p
i
t
a
l
P
r
o
j
e
c
t
s
(
1
,
8
2
6
,
5
4
8
)
$
L
e
s
s
:
S
c
h
e
d
u
l
e
d
C
I
P
P
r
o
j
e
c
t
C
o
s
t
s
(
3
,
1
9
0
,
0
0
0
)
$
(
1
,
3
4
3
,
0
1
0
)
$
(
5
,
9
4
5
,
7
2
9
)
$
(
9
,
2
5
5
,
0
0
0
)
$
(
1
,
9
0
5
,
0
0
0
)
$
(
1
,
3
0
5
,
0
0
0
)
$ (149,060,296)$
Pr
o
j
e
c
t
e
d
Y
e
a
r
‐
E
n
d
C
a
s
h
D
e
d
i
c
a
t
e
d
t
o
C
I
P
(1
,
1
1
8
,
6
2
3
)
$
(5
7
8
,
5
6
3
)
$
(2
2
7
,
0
6
9
)
$
59
4
,
0
1
6
$
86
8
,
9
0
5
$
1,852,789 $
As
s
u
m
p
t
i
o
n
s
M
a
d
e
f
o
r
R
e
v
e
n
u
e
E
s
t
i
m
a
t
e
s
Cu
r
r
e
n
t
Y
e
a
r
FY
1
8
FY
1
9
FY
2
0
FY
2
1
FY
2
2
FY23
Es
t
i
m
a
t
e
d
A
n
n
u
a
l
W
a
t
e
r
I
m
p
a
c
t
F
e
e
R
e
v
e
n
u
e
s
1,
7
9
3
,
4
0
0
$
1
,
7
9
3
,
4
0
0
$
1,
8
8
3
,
0
7
0
$
1,
9
7
7
,
2
2
4
$
2,
0
7
6
,
0
8
5
$
2,179,889 $
E
s
t
i
m
a
t
e
d
A
n
n
u
a
l
I
n
c
r
e
a
s
e
0.
0
%
5%
5%
5%
5%5%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
1,
7
9
3
,
4
0
0
$
1
,
8
8
3
,
0
7
0
$
1,
9
7
7
,
2
2
4
$
2,
0
7
6
,
0
8
5
$
2,
1
7
9
,
8
8
9
$
2,288,883 $
Cu
r
r
e
n
t
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
%
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
P
l
u
s
:
I
n
c
r
e
a
s
e
D
e
d
i
c
a
t
e
d
t
o
W
a
t
e
r
C
a
p
a
c
i
t
y
E
x
p
a
n
s
i
o
n
C
I
P
0.
0
%
0.
0
%
0.
0
%
0.
0
%
0.0%0.0%
T
o
t
a
l
%
D
e
d
i
c
a
t
e
d
t
o
C
I
P
10
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
10
0
.
0
%
1
0
0
.
0
%
1
0
0
.
0
%
To
t
a
l
E
s
t
i
m
a
t
e
d
R
e
v
e
n
u
e
s
D
e
d
i
c
a
t
e
d
t
o
C
I
P
1,
7
9
3
,
4
0
0
$
1
,
8
8
3
,
0
7
0
$
1,
9
7
7
,
2
2
4
$
2,
0
7
6
,
0
8
5
$
2,
1
7
9
,
8
8
9
$
2,288,883 $
Pr
o
j
e
c
t
e
d
Pr
o
j
e
c
t
e
d
C
U
R
R
E
N
T
$
(
1
,
3
4
3
,
0
1
0
)
$
(
5
,
9
4
5
,
7
2
9
)
$
(
9
,
2
5
5
,
0
0
0
)
$
(
1
,
9
0
5
,
0
0
0
)
$
(
1
,
3
0
5
,
0
0
0
)
$
(
1
4
9
,
0
6
0
,
2
9
6
)
FY
1
8
F
Y
1
9
F
Y
2
0
F
Y
2
1
F
Y
2
2
F
Y
2
3
U
N
S
C
H
E
D
U
L
E
D
WA
T
E
R
I
M
P
A
C
T
F
E
E
P
R
O
J
E
C
T
S
41
9
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
Im
p
a
c
t
F
e
e
s
Wa
t
e
r
WI
F
0
5
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
WE
S
T
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
-
P
H
A
S
E
1
CO
N
S
T
R
U
C
T
I
O
N
$28,006,293
WI
F
1
4
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
LO
A
N
D
E
B
T
S
E
R
V
I
C
E
-
W
T
P
5
.
3
M
G
CO
N
C
R
E
T
E
W
A
T
E
R
S
T
O
R
A
G
E
R
E
S
E
R
V
O
I
R
$6
0
0
,
0
0
0
$6,800,000
$6
0
0
,
0
0
0
$6
0
0
,
0
0
0
$6
0
0
,
0
0
0
WI
F
2
1
Wa
t
e
r
I
m
p
a
c
t
F
S
1
1
T
H
1
2
"
W
A
T
E
R
M
A
I
N
E
X
T
E
N
S
I
O
N
$1
3
6
,
0
1
0
WI
F
2
5
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
DA
V
I
S
1
2
"
W
A
T
E
R
M
A
I
N
&
V
A
L
L
E
Y
CE
N
T
E
R
1
6
"
W
A
T
E
R
M
A
I
N
E
X
T
E
N
S
I
O
N
$7
2
5
,
7
2
9
WI
F
2
7
Wa
t
e
r
I
m
p
a
c
t
F
51
2
6
W
E
S
T
S
O
U
R
D
O
U
G
H
R
E
S
E
R
V
O
I
R
1
$9,757,500
WI
F
2
8
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
51
2
6
W
E
S
T
S
O
U
R
D
O
U
G
H
R
E
S
E
R
V
O
I
R
1
-
SI
T
I
N
G
$3
5
0
,
0
0
0
WI
F
3
0
Wa
t
e
r
I
m
p
a
c
t
F
EA
S
T
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
$7,167,372
WI
F
3
2
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
GR
O
U
N
D
W
A
T
E
R
W
E
L
L
F
I
E
L
D
A
N
D
TR
A
N
S
M
I
S
S
I
O
N
C
O
N
S
T
R
U
C
T
I
O
N
$8
,
0
0
0
,
0
0
0
WI
F
3
3
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
GR
O
U
N
D
W
A
T
E
R
W
E
L
L
F
I
E
L
D
A
N
D
TR
A
N
S
M
I
S
S
I
O
N
M
A
I
N
D
E
S
I
G
N
$5
0
0
,
0
0
0
WI
F
3
6
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
WE
S
T
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
P
L
A
N
N
I
N
G
ST
U
D
Y
$400,000
WI
F
3
7
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
SO
U
R
D
O
U
G
H
C
A
N
Y
O
N
N
A
T
U
R
A
L
ST
O
R
A
G
E
-
P
L
A
N
N
I
N
G
A
N
D
D
E
S
I
G
N
$350,000
$1
5
0
,
0
0
0
WI
F
3
8
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
SO
U
R
D
O
U
G
H
C
A
N
Y
O
N
N
A
T
U
R
A
L
ST
O
R
A
G
E
C
O
N
S
T
R
U
C
T
I
O
N
$8,000,000
WI
F
4
0
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
SO
U
R
D
O
U
G
H
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
–
PH
A
S
E
2
$4
,
3
2
0
,
0
0
0
WI
F
4
1
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
WE
S
T
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
-
P
H
A
S
E
1
DE
S
I
G
N
$2,907,235
WI
F
4
2
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
WE
S
T
T
R
A
N
S
M
I
S
S
I
O
N
M
A
I
N
-
P
H
A
S
E
S
2
-
5
DE
S
I
G
N
&
C
O
N
S
T
R
U
C
T
I
O
N
$61,669,396
WI
F
4
3
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
DE
B
T
S
E
R
V
I
C
E
F
O
R
B
O
R
R
O
W
I
N
G
-
W
E
L
L
FI
E
L
D
$1,000,000 $10,800,000
$1
,
0
0
0
,
0
0
0
WI
F
4
5
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
DE
B
T
S
E
R
V
I
C
E
F
O
R
B
O
R
R
O
W
I
N
G
-
TR
A
N
S
M
I
S
S
I
O
N
M
A
I
N
$305,000 $3,445,000
$3
0
5
,
0
0
0
$3
0
5
,
0
0
0
WI
F
4
6
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
WA
T
E
R
M
A
I
N
O
V
E
R
S
I
Z
I
N
G
,
O
A
K
S
T
A
N
D
RY
U
N
S
U
N
W
A
Y
$1
0
7
,
0
0
0
42
0
CI
P
P
R
O
J
E
C
T
F
U
PR
O
J
.
DE
P
A
R
T
M
E
N
T
PR
O
J
E
C
T
N
A
M
E
FY
1
9
Unscheduled FY23
FY
2
0
FY
2
1
FY
2
2
WI
F
4
7
Wa
t
e
r
I
m
p
a
c
t
Fe
e
s
GR
A
F
A
N
D
S
.
2
7
T
H
W
A
T
E
R
T
R
A
N
S
M
I
S
S
I
O
N
MA
I
N
O
V
E
R
S
I
Z
I
N
G
$1
5
0
,
0
0
0
WI
F
4
8
Wa
t
e
r
I
m
p
a
c
t
F
49
7
5
S
O
U
T
H
W
E
S
T
R
E
S
E
R
V
O
I
R
1
$9,757,500 $1,305,000
$1
,
3
4
3
,
0
1
0
$5
,
9
4
5
,
7
2
9
$9
,
2
5
5
,
0
0
0
$1
,
9
0
5
,
0
0
0
$149,060,296
To
t
a
l
s
b
y
D
E
P
A
R
T
M
E
N
T
Su
m
m
a
r
y
f
o
r
I
m
p
a
c
t
F
e
e
s
W
a
t
e
r
(
2
0
i
t
e
m
s
)
To
t
a
l
s
b
y
y
e
a
r
:
$1,305,000
$1
,
3
4
3
,
0
1
0
$5
,
9
4
5
,
7
2
9
$149,060,296FY23
FY
1
9
FY
2
0
Unscheduled
FY
2
2
$1
,
9
0
5
,
0
0
0
$9
,
2
5
5
,
0
0
0
FY
2
1
42
1
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF05
DEPARTMENT
Water Impact Fees
PROJECT NAME
West Transmission Main - Phase 1 Construction
FY19 FY20 Unscheduled
$28,006,293
DESCRIPTION OF PROJECT
The project consists of a constructing a new transmission main from the Sourdough water treatment plant to the southwestern
edge of the existing distribution network (S.19th and Graf St.) to serve future anticipated growth and provide water delivery
redundancy. This second transmission line from the WTP to the City's distribution system is critical to provide a second path to
get potable water from the WTP into the City, as well as to adequately serve the rapidly growing western portions of the City
with potable water and fire flows. Potable water delivery and fire flows will be improved in the southwest, west and northwest
portions of the City. This transmission line connects to the existing distribution system at a location that enables the existing
Sourdough and Hill top tanks to be filled even if the Sourdough pipeline is out of service. This project mitigates the risk of not
having enough potable water to serve the City's residents or provide fire suppression.
ALTERNATIVES CONSIDERED
Construct a parallel transmission line between the Sourdough Water Treatment Plant to Kagy Boulevard.
ADVANTAGES OF APPROVAL
Provides transmission capacity to current and growing peak day and fire flow demands on Bozeman's western flanks, generally west of 19th Ave.
All existing transmission capacity is on the eastern edge of the city's distribution system which presents hydraulic issues as the water demand
centroid moves westward. The transmission also provides redundant transmission in the event of failure of sourdough transmission mains.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
Developer contributions
New
Replacement
Equipment
Project
FY21 FY22 FY23
422
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF14
DEPARTMENT
Water Impact Fees
PROJECT NAME
Loan Debt Service - WTP 5.3MG Concrete Water Storage Reservoir
FY19
$600,000
FY20
$600,000
Unscheduled
$6,800,000
DESCRIPTION OF PROJECT
Repayment of debt used to finance construction of WIF03, a 5.3 million gallon concrete water storage reservoir.
ALTERNATIVES CONSIDERED
Payoff loan principal
ADVANTAGES OF APPROVAL
Increased water storage to meet the needs of our growth community, and the requirement of MDEQ. Increased system water pressure in the
southern part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Requires minimal operation and maintenance. Checking of valves, level sensors and vents on an annual basis and diver inspection and vacuuming
every five years. Estimated at $4,000 annually.
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
FY21
$600,000
FY22
$600,000
FY23
423
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF21
DEPARTMENT
Water Impact Fees
PROJECT NAME
S 11th 12" water main extension
FY19
$136,010
FY20 Unscheduled
DESCRIPTION OF PROJECT
Extension of 12" diameter main per AE2S WFPU in S 11th avenue from current terminus to Graf Street. It provides for future
looped water system per AE2S WFPU, and increases hydraulic capacity of system beyond minimum 8" main. This reduces severity
and consequences of water system outages due to future looping and provides for minimum fire flows. Impact Fees fund capacity
above 8" main which is minimum local share. Local share could be reimbursed to City through a "payback district" established by
City Commission. This will be completed in conjunction with the S 11th Ave road improvements.
ALTERNATIVES CONSIDERED
Forego project and don't loop water system in this area
ADVANTAGES OF APPROVAL
Provides for water main construction at time of road construction and implements WFPU update for G&D water infrastructure
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
n/a
FUNDING SOURCES
Developer contribution (Graf's) for their "local share" of main would need to be reimbursed through a "payback district" established by the City
Commission
New
Replacement
Equipment
Project
FY21 FY22 FY23
424
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF25
DEPARTMENT
Water Impact Fees
PROJECT NAME
Davis 12" Water Main & Valley Center 16" Water Main Extension
FY19 FY20
$725,729
Unscheduled
DESCRIPTION OF PROJECT
Extension of 12" water main in Davis Ln from Catamount to Valley Center & Extension of 16" diameter water main in Valley
Center from Davis to 27th. 16" main is per AE2S WFPU. 12" main extends existing 12" main in Davis. These mains needed to
support development south of East Valley Center between Davis and 27th. This provides for future looped water system per
AE2S WFP, and reduces severity and consequences of water system outages due to future looping and provides for minimum fire
flows. This will be completed in connection with development of Billings Clinic. Other affected projects include the 12" main in
Davis along the proposed alignment of Phase 5 of West Transmission Main in the AE2S WFPU. WTM diameter contemplated at
36" in Davis from Catamount to Valley Center.
ALTERNATIVES CONSIDERED
Billings Clinic may occupy this land. Fire flow demands may require large diameter mains above the minimum 8" diameter typical local share in
order to meet the Clinic's fire flow requirement, thus reducing the overall impact fee contribution
ADVANTAGES OF APPROVAL
Implements WFPU update for G&D infrastructure
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
n/a
FUNDING SOURCES
Developer contribution (Billings Clinic) for their "local share" of main
New
Replacement
Equipment
Project
FY21 FY22 FY23
425
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF27
DEPARTMENT
Water Impact Fees
PROJECT NAME
5126 West Sourdough Reservoir 1
FY19 FY20 Unscheduled
$9,757,500
DESCRIPTION OF PROJECT
The project consists of a constructing a new gravity fed ground storage reservoir to the south/southwest of the City, which
would tie into the West Water Transmission Main – Phase 1 and serve the existing City water distribution system. This reservoir
supplies water to the City’s existing distribution network, to provide necessary storage capacity for the entire system, as well as
contributes to adequate water supply capacity for future development along the City's western half. In the near term the storage
provided by this reservoir will augment storage provided by the City's existing Sourdough and Hilltop Tanks. In the long-term it
provides storage for the west and northwest areas of the City. This project mitigates the risk of not having enough potable water
and fire flow in the southwest area of the City. This project is directly tied to construction of the West Water Transmission
Main - Phase 1.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Two of the City's three existing reservoirs are located along the Sourdough Transmission main (Sourdough and Hilltop Tanks). If the Sourdough
transmission main or either of these tanks are off-line for any reason (i.e. maintenance, natural disaster, break, etc.), the City would have
inadequate storage and supply. An additional reservoir located on the West Transmission Main – Phase 1 provides storage redundancy, allowing
for routine inspection and maintenance of both water storage facilities/transmission mains, mitigates the risk of and reduces the consequence of
a failure on the existing Sourdough transmission main or Sourdough or Hilltop tanks. It also contributes to satisfying required storage capacity
for the system, as well as ensuring adequate potable water and fire flows to the City's southwest areas.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
an incremental increase in general maintenance cost. Current cost estimate of $XX.XX annually.
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
426
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF28
DEPARTMENT
Water Impact Fees
PROJECT NAME
5126 West Sourdough Reservoir 1 - Siting
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Siting study and land acquisition for 5MG ground storage reservoir to serve 5126 Pressure Zone from West Transmission Main.
The West Sourdough Reservoir will be the next necessary reservoir for the City to continue to provide adequate potable water
and fire flow. Proper siting of this reservoir will provide redundant supply to Sourdough and Hilltop Reservoirs. It will increase
water storage capacity by 5MG, and will provide greater efficiency in providing potable water and fire flows to the City's western
areas. Better ability to take Sourdough or Hilltop reservoirs offline and still provide sufficient storage. Other affected projects
include groundwater planning, engineering and construction West Transmission Main study, design, construction; reservoir
design, construction projects.
ALTERNATIVES CONSIDERED
Wait until the need for the reservoir is more imminent
ADVANTAGES OF APPROVAL
Procurement of land while it is available, and less expensive
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
FY21
$350,000
FY22 FY23
427
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF30
DEPARTMENT
Water Impact Fees
PROJECT NAME
East Transmission Main
FY19 FY20 Unscheduled
$7,167,372
DESCRIPTION OF PROJECT
The project consists of a constructing a new transmission main that would ensure adequate water supply capacity for future
developments located both east and northeast of the existing distribution system (extending approximately from East Kagy Blvd
to Kelly Canyon Rd and Story Hill Rd). Without this transmission main, potable water and fire flows will eventually become
insufficient in the east and northeast portions of the City. This main also supplies the future East Mountain Zone, which has a
substantial demand. This project better connects the east and northeast portions of the City with the supply from the City's
WTP. In conjunction with the west transmission mains, it will provide a more looped supply for the majority of the City. What
safety or risk measures are mitigated with this project: This project mitigates the risk of having inadequate potable water and fire
flows to the City's east and northeast areas. This project leverages improvements in delivery of water due to the Sourdough Main
replacement or paralleling. It will also enable siting of storage in the City's east and northeast areas.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The creation of an East Water Transmission Main is necessary to supply adequate water and fire flows to future developments in the eastern
portion of the City’s distribution system. This transmission line will also provides additional looping and redundancy to the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
Developer contributions
New
Replacement
Equipment
Project
FY21 FY22 FY23
428
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF32
DEPARTMENT
Water Impact Fees
PROJECT NAME
Groundwater Well Field and Transmission Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Water right permitting and mitigation plan; purchase of mitigation water rights; construction of aquifer recharge or other
mitigation infrastructure; acquisition of land for well field site; construction of wells, power, power backup, instrumentation and
controls, SCADA, control building and site improvements; and transmission main construction to tie GW supply into the existing
system. This is absolutely critical for meeting long-range water supply needs and enhancing overall water supply resiliency and
redundancy. It enhances connectivity by providing a redundant water supply source in the event of Sourdough WTP outage.
ALTERNATIVES CONSIDERED
Status quo operation
ADVANTAGES OF APPROVAL
Improve water distribution operations through increased understanding of system operating characteristics. Improve responsiveness to dynamic
operating conditions. Facilitate improved access to existing sites now requiring confined space entry procedures. Standardize and improve surge
control features throughout system.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Debt service (if any) to construct, power costs, SCADA maintenance, vault maintenance, instrument maintenance, programming libraries
FUNDING SOURCES
Capital funding for water right permitting and water could be augmented with cash in lieu of water rights fund, water fund
New
Replacement
Equipment
Project
FY21
$8,000,000
FY22 FY23
429
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF33
DEPARTMENT
Water Impact Fees
PROJECT NAME
Groundwater Well Field and Transmission Main Design
FY19
$500,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design of groundwater well field and transmission main including necessary appurtenances, instrumentation and controls, and
DEQ approvals. This is necessary for construction of groundwater supply source, but it will require DEQ construction approval;
amendments if needed to other DEQ documents such as Source Water Delineation and Assessment Report and Source Water
Protection Plan. This project utilizes the hydrogeologic model developed for the Groundwater Investigation and test well data.
ALTERNATIVES CONSIDERED
Don't develop a GW supply
ADVANTAGES OF APPROVAL
Provides bid plans and cost estimates for construction and obtains DEQ approvals needed for construction.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
430
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF36
DEPARTMENT
Water Impact Fees
PROJECT NAME
West Transmission Main Planning Study
FY19 FY20 Unscheduled
$400,000
DESCRIPTION OF PROJECT
Planning study to identify key design parameters for WTM, right of way, route alignment, and timing for bringing WTM online.
Eventual construction of the West Transmission Main is necessary to provide redundancy for the Sourdough Transmission Main
as well as adequate potable water and fire flow for the City's west, northwest and north areas, and it provides capacity sufficient
for UBO and delivery of 34 MGD from future WTP expansion. Conveyance of water to the City's western, northwestern and
northern areas will be more efficient that moving water through downtown and existing PRVs.
ALTERNATIVES CONSIDERED
Defer the study further out, deferring eventual construction of the West Transmission Main.
ADVANTAGES OF APPROVAL
Identify key design parameters, right-of-way, route and permitting for the West Transmission Main, so that design and construction can proceed
once funds are available.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
431
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF37
DEPARTMENT
Water Impact Fees
PROJECT NAME
Sourdough Canyon Natural Storage - Planning and Design
FY19 FY20
$150,000
Unscheduled
$350,000
DESCRIPTION OF PROJECT
Alternatives planning and design for sour dough natural storage enhancement project. This project will increase resiliency of
Sourdough watershed to drought impacts and provides augmented water supply, protects existing municipal water rights, and it
augments water supply capacity of sourdough watershed. This impacts the City's long-term water rights and helps close the
approaching water supply gap. This project could have potential FEMA involvement for flood control. Other affected projects
include final sizing of West Transmission Main. It will also inform long-term groundwater needs.
ALTERNATIVES CONSIDERED
Postpone
ADVANTAGES OF APPROVAL
Implements IWRP, augments Sourdough water supply capacity, and increases resiliency of Sourdough water supply by providing 'storage' to
reduce the susceptibility of drought impacts
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown
FUNDING SOURCES
Potential opportunity for federal drought and flood hazard mitigation grants, state RRGL funds. Cash in lieu of water rights fund.
New
Replacement
Equipment
Project
FY21 FY22 FY23
432
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF38
DEPARTMENT
Water Impact Fees
PROJECT NAME
Sourdough Canyon Natural Storage Construction
FY19 FY20 Unscheduled
$8,000,000
DESCRIPTION OF PROJECT
Construction of natural water storage infrastructure alternatives planned and designed in project WFP_53 that augment water
supply availability, reduce susceptibility to drought impacts, and maximize existing water rights. This project provides enhanced
water supply availability to support future growth and development, and reduces drought susceptibility and peak runoff impacts.
Leveraging potential exists with federal/state grants, federal/state cooperative agreements (consistent with fed initiatives to
increase drought resiliency in western states and consistent with recommendations in state water plan to increase storage in
closed basins). Project implements recommendations of the IWRP to develop storage in Sourdough.
ALTERNATIVES CONSIDERED
Project specific alternatives evaluated with project WFP_53. Water supply alternatives evaluated in IWRP.
ADVANTAGES OF APPROVAL
Augments Sourdough Creek water supply, reduces susceptibility to drought impacts and maximizes existing water rights
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown
FUNDING SOURCES
Federal hazard mitigation grants (drought hazard and flood hazard). State renewable resource grant and loan program.
New
Replacement
Equipment
Project
FY21 FY22 FY23
433
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF40
DEPARTMENT
Water Impact Fees
PROJECT NAME
Sourdough Transmission Main – Phase 2
FY19 FY20
$4,320,000
Unscheduled
DESCRIPTION OF PROJECT
The project consists of constructing approximately 8,000 feet of 30-inch DIP transmission main, which will start at the end of the
Phase 1 connection point and go to the Sourdough Plant. This project is critical to overcome vulnerabilities presented by the
aging and unknown condition of the existing transmission main between the City's WTP and Sourdough Tank, and will provide
additional capacity from the WTP to the Sourdough reservoir. This project will mitigate the risk of not having adequate potable
water and fire flow supplies to the City in the event of a failure to the existing bar-wrapped 30" main. This project's cost and
administration could be improved if combined with the new 3,000 feet of 48" bypass pipe.
ALTERNATIVES CONSIDERED
Conduct a condition assesment of the existing 30-inch concrete pipe and repair/rehabilitate as necessary.
ADVANTAGES OF APPROVAL
The condition of the existing transmission main from the WTP to the Sourdough reservoir is currently unknown. Approval of this project will
provide redundancy for this main, and mitigate the risk and consequence of its failure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
$4,320,000 Water Impact Fees. $480,000 Water Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
434
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF41
DEPARTMENT
Water Impact Fees
PROJECT NAME
West Transmission Main - Phase 1 Design
FY19 FY20 Unscheduled
$2,907,235
DESCRIPTION OF PROJECT
Design of the first phase of the West Transmission Main, the criteria for which would be developed in the West Transmission
Main Planning Study (WIF36). This project will reduce the consequence of a failure on the Sourdough Transmission Main, by
providing a second pipeline to convey water to the City from the WTP, and water delivery to the City's western side will become
more efficient. The Sourdough Transmission Main is currently a single point of failure for conveyance of water from the
Sourdough WTP. Other affected projects include subsequent phases of West Transmission Main design and construction, and
construction of storage reservoirs on the City's west side.
ALTERNATIVES CONSIDERED
Defer design and construction of West Transmission Main
ADVANTAGES OF APPROVAL
Potential to install the transmission main before significant growth and development occur along the route, reduced consequence of failure to
Sourdough Transmission Main
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
435
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF42
DEPARTMENT
Water Impact Fees
PROJECT NAME
West Transmission Main - Phases 2-5 Design & Construction
FY19 FY20 Unscheduled
$61,669,396
DESCRIPTION OF PROJECT
The project consists of remaining phases (2 thru 5) of the west Transmission Main, completing the transmission loop around the
city's western flank. Extending the West Transmission Line further north into the City's future western and northwestern
developments to ensure adequate potable water and fire flow for west and northwest Bozeman residents. The northwest portion
of the City remains the least well connected area to the distribution system. Flow to the northwest must come through the
existing PRVs from the Sourdough and Hilltop Tanks, or from the northeast Lyman source. This main will bring water from the
WTP well into the northwest portion of the City. Therefore, this project mitigates the risk of not having enough potable water
or fire flow to serve the City's west residents. This project will also provide the ability for the City to connect additional storage
reservoirs on the City's southwest and west to satisfy maximum day demand and fire flows.
ALTERNATIVES CONSIDERED
Do not complete west tranmission main loop.
ADVANTAGES OF APPROVAL
Further extending the West Water Transmission Main would provide the following: distribution redundancy, and adequate water supply and fire
flows for future development on the City's west and northwest sides.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
Developer contributions
New
Replacement
Equipment
Project
FY21 FY22 FY23
436
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF43
DEPARTMENT
Water Impact Fees
PROJECT NAME
Debt Service for Borrowing - Well Field
FY19 FY20 Unscheduled
$10,800,000
DESCRIPTION OF PROJECT
These are the estimated annual amounts owned for borrowing for WIF32 - Well Field and WIF40 - Sourdough Transmission Main
project. Payments will begin in the fiscal year following borrowing.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The project can be constructed before cash is on hand.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
Water Utility Revenue Bonds will be issued, with repayments made by the Impact Fee Fund.
New
Replacement
Equipment
Project
FY21 FY22
$1,000,000
FY23
$1,000,000
437
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF45
DEPARTMENT
Water Impact Fees
PROJECT NAME
Debt Service for Borrowing - Transmission Main
FY19 FY20 Unscheduled
$3,445,000
DESCRIPTION OF PROJECT
These are the estimated annual amounts owned for borrowing for WIF40 - Sourdough Transmission Main project. Payments will
begin in the fiscal year following borrowing.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The project can be constructed before cash is on hand.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
incremental increases in general maintenance costs.
FUNDING SOURCES
Water Utility Revenue Bonds will be issued, with repayments made by the Utility (10%) and Impact Fee Fund (90%)
New
Replacement
Equipment
Project
FY21
$305,000
FY22
$305,000
FY23
$305,000
438
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF46
DEPARTMENT
Water Impact Fees
PROJECT NAME
Water Main Oversizing, Oak St and Ryun Sun Way
FY19
$107,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of upsizing water mains from 8-inches to 12-inches per the Water Master Plan if the proposed Canvasback
Subdivision proceeds to approval. The Canvasback Subdivision will be required to install the mains, and the City would pay the
difference in cost between an 8-inch and a 12-inch pipe required by the 2017 Water Master Plan.
ALTERNATIVES CONSIDERED
Do nothing and require the developer to bear the full cost of the 12-inch transmission main.
ADVANTAGES OF APPROVAL
Supports implementation of the water transmission pipe network described in the 2017 Water Master Plan.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Incremental cost of water main operations.
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
439
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF47
DEPARTMENT
Water Impact Fees
PROJECT NAME
Graf and S. 27th Water Transmission Main Oversizing
FY19 FY20
$150,000
Unscheduled
DESCRIPTION OF PROJECT
This project consists of upsizing water mains from 8-inches to 12-inches per the Water Master Plan if the proposed Canvasback
Subdivision proceeds to approval. The Canvasback Subdivision will be required to install the mains, and the City would pay the
difference in cost between an 8-inch and a 12-inch pipe required by the 2017 Water Master Plan.
ALTERNATIVES CONSIDERED
Do nothing and require the developer to bear the full cost of the 12-inch transmission main.
ADVANTAGES OF APPROVAL
Supports implementation of the water transmission pipe network described in the 2017 Water Master Plan.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Incremental cost of water main operations.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
440
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF48
DEPARTMENT
Water Impact Fees
PROJECT NAME
4975 Southwest Reservoir 1
FY19 FY20 Unscheduled
$9,757,500
DESCRIPTION OF PROJECT
The project consists of a constructing a new ground storage reservoirsouthwest of town, which would tie into the West
Transmission Main – Phase 2 and serve the City’s future western and northern water distribution system.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
An additional reservoir located on the West Transmission Main – Phase 2 would help provide the following: promote storage redundancy within
the system, allow for routine inspection and maintenance of both water storage facilities/transmission mains, reduce the consequence of failure
of future transmission mains (i.e. mitigates risk), aids in supplying water to the City’s distribution network, and ensures adequate water supply
capacity for future development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water Utility will see
an incremental increase in general maintenance cost. Current cost estimate of $XX.XX annually.
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
441
442