BOZEMAN PARKING COMMISSION
Parking Program Manager's Report
Date: January 5, 2018
To: Bozeman Parking Commission
From: Ed Meece, Parking Program Manager
An update of major developments, in December, includes:
• The Parking Services Division and Finance Department held a three day on-site visit with T2 Systems to further the
data conversion efforts, plan for necessary'back office' procedures, and begin staff training/familiarity with new
systems. The PPM engages in twice weekly project management calls with T2 project staff, with other COB staff
involved on 'as needed' basis.
• The Parking Services Division dedicated considerable staff resources, in December, toward "48"
enforcement/towing in an attempt to assist the Streets Department with snow plowing and removal efforts.
• The PPM is part of an internal COB team working with Bozeman School District #7 on review of the proposed
athletic stadium redevelopment,specifically as to how this project will impact nearby on-street parking in the BHS
Residential Parking Permit District.
• The PPM met with COB staff assigned to the Stiff Professional Building to finalize a new 'parking policy' for staff
and re-design of lot signage and enforcement. Policy implementation is pending,expected by spring of 2018.
• The PPM is working with the Etha Hotel in preparation for a possible January 2018 closure of the Armory (n.
Willson lot)as a construction staging area for the project.
• The PPM developed a narrative for the Parking Services section of the Information Technology Strategic Plan,
outlining major hardware/software expenditures planned for the next three years.
• The PPM acted as'prosecutor'for one parking violation(Restricted Zone-Yellow)appealed to Bozeman Municipal
Court.The court has not issued a ruling at this time.
• The City Attorney's Office continues to review the proposed changes to the parking regulations within the
Bozeman Municipal Code (submitted to legal, 8/6/17). Upon completion of their review, an updated version will
be presented to the Bozeman Parking Commission for further consideration and action.
Financial Update
Revenues for the fiscal year are at 88.6735(w/out TIFD funds).
Expenditures for the fiscal year are at 45.8T10 (w/out TIFD funds); The Garage-Operating line item is at 61.66%, which
reflects considerable snow removal expenditures at the garage and surface lots during December.
Parking Services Fund-Operating (1/4/18)
December 2017- Revenue & Expenditures Report
o�
FY 18 FY 18 EARNED
REVENUE BUDGET ACTUAL YTD
Parking Lot Permits $25,000.00 $34,621.00 138.48%
Garage Permits $250,000.00 $329,413.00 131.77%
Garage-Transient Revenue $75,500.00 $56,622.00 75.00%
Garage Validation Coupons $3,000.00 $2,265.00 75.50%
Residential Nghbd.Permits $13,000.00 $30,370.00 233.62%
Employee Ngbad. Permits $2,000.00 $4,390.00 219.50%
Visitor Ngbad. Permits $10,500.00 $20,585.00 196.05%
Admin/Late Fees $42,000.00 $24,467.00 58.25%
Boot Fees $2,000.00 $300.00 15.00%
Citation Revenue $300,000.00 $132,453.00 44.15%
Misc. Revenue $0.00 $3,014.00 NA
Rents/Royalties/Other $2,000.00 $1,140.00 57.00%
Interest Income $750.00 $0.00 0.00%
Loan Interest $840.00 $383.00 45.60%
Refunds& Reimbursements $0.00 $25.00 0.00%
Collection Fees $6,000.00 $9,518.00 158.63%
Transfer Other Funds (TIFD) $250,000.00 $0.00 0.00%
TOTAL(w/TIFD Transfer) $982,590.00 $649,566.00 66.11%
TOTAL (w/out TIFD Transfer) $732,590.00 $649,566.00 88.67%
o�
FY 18 FY 18 SPENT
EXPENDITURE BUDGET ACTUAL YTD
Admin - Personnel $100,127.00 $46,677.00 46.62%
Admin--Operating $159,232.00 $84,661.00 53.17%
Admin--Capital $250,000.00 $28,700.00 11.48%
Enforcement-- Personnel $202,384.00 $72,277.00 35.71%
Enforcement--Operating $49,465.00 $12,359.00 24.99%
Enforcement--Capital $10,000.00 $0.00 N/A
Garage-- Personnel $40,122.00 $16,725.00 41.69%
Garage--Operating $156,900.00 $96,740.00 61.66%
Garage--Capital $0.00 $0.00 N/A
TOTAL(w/Admin Capital -TIFD) $968,230.00 $358,139.00 36.99%
TOTAL(w/out Admin Capital-TIFD) $718,230.00 $329,439.00 45.87%
NOTE:At this time, December payroll had not
posted,those expenses are not reflected in this
report.
Active Projects:Strategic Parking ManagtTwww— COMPLETED
14 PENDING
January 2018 HOLD/NOT STARTED
PROJECTED ACTUAL
STRATEGY DESCRIPTION COMPLETION COMPLETION COMMENTS
Formalize the guiding principles
as policies within the parking and Adopted by the BPC in
1 transporation system plan. Aug-16 8/2016.
Adopt the 85%rule as the
standard for measuring
performance of the parking
supply and triggering specific Adopted by the BPC in
2 management strategies. Aug-16 8/2016.
Strengthen the role of the
Parking Manager and the Parking
Services Division-to better PPM attending DRC
integrate with the Community meetings,and offering
Development and Economic data/comment as staff
3 Development planning. On-Going On-Going review.
Establish a policy for adjusting Adopted by the BPC in
4 rates(on and off-street) Oct-16 10/2016.
BPC approved Resolution
2017-03(6/2017);City
Commission approved
Establish a Capital Maintenance CC Approval Resolution#4837 on
5 Reserve Fund Jul-16 8/14/17 8/14/17.
PPM is working with the
Comm.Dev.Department;
Re-evaluate and restructure CDD has assigned this a'fall
6 current cash-in-lieu program. TBD 2018'priority status.
PPM worked with the ED
dept on changes to the
minimum parking standards
(UDC)in the 62M zone,
approved by CC 9/2017;
PPM actively attending
internal DRC meetings to
offer guidance on policy
issues and prepare for 2018
effort to modify the parking
Re-evaluate code based standards section of the
7 minimum parking requirements UDC.
Re-evaluate and clarify the
purpose and intent of the PPM is waiting on the
current code section regarding Admin./Legal Depts.For
Special Improvement District# further instruction on this
8 565. TBD isue.
PPM is completing research
for facility mgt.best
Implement a Facilities practices,starting to draft
9 Maintenance Plan. 12/30/2017 On-going Fac.Mgt.plan,8/17;
Data collection ocurred,
following the Strategic
Parking Management Plan,
Spring and Summer 2017;
WTI report(draft)submitted
9/2017,under staff review
at this time;Final comments
submitted to WTI for
modification,10/23/17;The
Develop a reasonable schedule final WTI Parking
of data collection to assess Occupancy Report was
performance,including an released on 11/14/2017,
accurate on and off street analysis is underway-
inventory(public and private) including
and an occupancy/utilization review/memorandum from
10 analysis. 5/1/17&7/1/17 On-going Rick Williams Consulting.
1st shared use agreement
negotiated and approved
with Big Sky Western Bank
Identify off-street shared use (June 2017);Completion of
opportunities based on data the WTI Parking Occupancy
from strategy 9.Establish goals Study on 11/14/17 is
for transitioning employees, expected to demonstrate
begin outreach to opportunity areas where new shared
sites,negotiate agreements,and space agreements will be
11 assign employees to facilities. On-Going most effective.
Complete the 2008 Parking
District Identification
12 Signage/Branding Plan No activity at this time.
Clarify current on-street parking
signage,particularly in areas
where unlimited parking is
allowed.Consider incorporating
the current City parking logo into
13 on-street signage. No activity at this time.
Rename all publicly owned lots
14 and garages by address. No activity at this time.
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17:
Project kick off call held
Upgrade the access/revenue 11/10/17,data conversion
control system at the Bridger and preliminary staff
15 Garage. 6/30/2017 On-going training underway;
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17;
Project kick off call held
Install a vehicle counter system 11/10/17,data conversion
at Bridger Garage and at the and preliminary staff
16 Surface lots. 6/30/2017 On-Going training underway;
Establish best practice protocols
and performance metrics for
existing enforcement personnal Court/Appeals Packet
and support enforcement with (4/17);Uniform Policy
17 appropriate technology. On-going (8/17);