BOZEMAN PARKING COMMISSION
Parking Program Manager's Relaort
Date: December 14, 2017
To: Bozeman Parking Commission
From: Ed Meece, Parking Program Manager
An update of major developments, in November, includes:
• The PPM held a project "Kick Off Call" with T2 Systems on 11/10/17. As a result, an initial 'data dump' was
performed by the current permit/citation provider,and T2 has started the data conversion process. Until 1/1/17,
most project activity will be related to the data conversion/confirmation process, as well as staff training.A'pre-
site'visit is expected with our T2 Business Analyst,on December 11th and 12th.
• The PPM attended training regarding the Employee Handbook; and Domestic Violence issues in the workplace.
• On 11/15/17,the Parking Enforcement Officers were trained on using,and disabling,the new alarm-activated Fire
Extinguisher Cabinets in the Bridger Park Downtown Garage.
• The PPM conducted preliminary research for, and attended a meeting, regarding the public service costs of
homelessness in Bozeman; hosted by the Economic Development Department.
• The PPM provided an initial response to a couple of citizen complaints regarding parking enforcement, during
student drop-off and pickup at Bozeman High School. Further meetings with interested citizens are planned, as
well as with administrative officials with the Bozeman School District.
• The PPM initiated a process for establishing a license agreement with Bozeman Fiber regarding their existing
placement of broadband/fiber equipment in the parking office space ('fishbowl') at the Bridger Park Downtown
Garage.
• The PPM attended the 11/20/17 regular meeting of the Bozeman City Commission to discuss their interest in
further research,and recommendations, regarding the creation of new Residential Parking Permit Districts on the
northern and southern boundaries of the downtown (B-3). Likewise, at that same meeting, the City Commission
considered and approved the use of$20,000 Cash-In-Lieu Parkland funding for improvements to the North Black
Pocket Park(directly contiguous to the North Black Parking Lot and Bridger Park Downtown Garage).
• The City Attorney's Office continues to review the proposed changes to the parking regulations within the
Bozeman Municipal Code (submitted to legal, 8/6/17). Upon completion of their review, an updated version will
be presented to the Bozeman Parking Commission for further consideration and action.
• Garage:
o Installation of the pedestrian safety railings was completed on each stairwell landing, at the garage
entry/exit point.
o Roof snow removal was done on Tuesday 11/21/17, to provide for safe/accessible parking over the
Thanksgiving holiday.
Financial Update
Revenues for the fiscal year are at 46.71%(w/out TIFD funds).
Expenditures for the fiscal year are at 40.47•10(w/out TIFD funds).
Parking Services Fund-Operating
November 2017-Revenue&Expenditures Report
(As of 12/5/2017)
i6
FY 18 FY 18 EARNED
REVENUE BUDGET ACTUAL YTD
Parking Lot Permits $25,000.00 $5,347.00 21.39%
Garage Permits $250,000.00 $80,496.00 32.20%
Garage-Transient Revenue $75,500.00 $45,513.00 60.28%
Garage Validation Coupons $3,000.00 $1,825.00 60.83%
Residential Nghbd.Permits $13,000.00 $29,807.00 229.28%
Employee Ngbad. Permits $2,000.00 $4,290.00 214.50%
Visitor Ngbad. Permits $10,500.00 $20,335.00 193.67%
Admin/Late Fees $42,000.00 $21,384.00 50.91%
Boot Fees $2,000.00 $300.00 15.00%
Citation Revenue $300,000.00 $119,973.00 39.99%
Misc. Revenue $0.00 $3,014.00 NA
Rents/Royalties/Other $2,000.00 $1,170.00 58.50%
Interest Income $750.00 $0.00 0.00%
Loan Interest $840.00 $321.00 38.21%
Refunds& Reimbursements $0.00 $25.00 0.00%
Collection Fees $6,000.00 $8,363.00 139.38%
Transfer Other Funds(TIFD) $250,000.00 $0.00 0.00%
TOTAL(w/TIFD Transfer) $982,590.00 $342,163.00 34.82%
TOTAL (w/out TIFD Transfer) $732,590.00 $342,163.00 46.71%
FY 18 FY 18 SPENT
EXPENDITURE BUDGET ACTUAL YTD
Admin- Personnel $100,127.00 $46,677.00 46.62%
Admin--Operating $159,232.00 $79,425.00 49.88%
Admin--Capital $250,000.00 $28,700.00 11.48%
Enforcement-- Personnel $202,384.00 $72,277.00 35.71%
Enforcement--Operating $49,465.00 $9,651.00 19.51%
Enforcement--Capital $10,000.00 $0.00 N/A
Garage--Personnel $40,122.00 $16,725.00 41.69%
Garage--Operating $156,900.00 $65,887.00 41.99%
Garage--Capital $0.00 $0.00 N/A
TOTAL(w/Admin Capital-TIFD) $968,230.00 $319,342.00 32.98%
TOTAL(w/out Admin Capital-TIFD) $718,230.00 $290,642.00 40.47%
Active Projects:Strategic Parking Management Plan COMPLETED
PENDING
December 2' HOLDMOT STARTED
PROJECTED ACTUAL
STRATEGY DESCRIPTION COMPLETION COMPLETION COMMENTS
Formalize the guiding principles
as policies within the parking and Adopted by the BPC in
1 transporation system plan. Aug-16 8/2016.
Adopt the 85%rule as the
standard for measuring
performance of the parking
supply and triggering specific Adopted by the BPC in
2 management strategies. Aug-16 8/2016.
Strengthen the role of the
Parking Manager and the Parking
Services Division-to better PPM attending DRC
integrate with the Community meetings,and offering
Development and Economic data/comment as staff
3 Development planning. On-Going On-Going review.
Establish a policy for adjusting Adopted by the BPC in
4 rates(on and off-street) Oct-16 10/2016.
BPC approved Resolution
2017-03(6/2017);City
Commission approved
Establish a Capital Maintenance CC Approval Resolution#4837 on
5 Reserve Fund Jul-16 8/14/17 8/14/17.
PPM is working with the
Comm.Dev.Department;
Re-evaluate and restructure CDD has assigned this a'fall
6 current cash-in-lieu program. TBD 2018'priority status.
PPM worked with the ED
dept on changes to the
minimum parking standards
(UDC)in the 62M zone,
approved by CC 9/2017;
PPM actively attending
internal DRC meetings to
offer guidance on policy
issues and prepare for 2018
effort to modify the parking
Re-evaluate code based standards section of the
7 minimum parking requirements UDC.
Re-evaluate and clarify the PPM is waiting on the
purpose and intent of the current Admin./Legal Depts.For
code section regarding Special further instruction on this
8 Improvement District#565. TBD isue.
PPM is completing research
for facility mgt.best
Implement a Facilities practices,starting to draft
9 Maintenance Plan. 12/30/2017 On-going Fac.Mgt.plan,8/17;
Data collection ocurred,
following the Strategic
Parking Management Plan,
Spring and Summer 2017;
WTI report(draft)submitted
9/2017,under staff review
at this time;Final comments
submitted to WTI for
modification,10/23/17;The
Develop a reasonable schedule final WTI Parking
of data collection to assess Occupancy Report was
performance,including an released on 11/14/2017,
accurate on and off street analysis is underway-
inventory(public and private) including
and an occupancy/utilization review/memorandum from
10 analysis. 5/1/17&7/1/17 On-going Rick Williams Consulting.
1st shared use agreement
negotiated and approved
with Big Sky Western Bank
Identify off-street shared use (June 2017);Completion of
opportunities based on data the WTI Parking Occupancy
from strategy 9.Establish goals Study on 11/14/17 is
for transitioning employees, expected to demonstrate
begin outreach to opportunity areas where new shared
sites,negotiate agreements,and space agreements will be
11 assign employees to facilities. On-Going most effective.
Complete the 2008 Parking
District Identification
12 Signage/Branding Plan No activity at this time.
Clarify current on-street parking
signage,particularly in areas
where unlimited parking is
allowed.Consider incorporating
the current City parking logo into
13 on-street signage. No activity at this time.
Rename all publicly owned lots
14 and garages by address. No activity at this time,
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17:
Project kick off call held
Upgrade the access/revenue 11/10/17,data conversion
control system at the Bridger and preliminary staff
15 Garage. 6/30/2017 On-going training underway;
RFP Selection Committee is
in final stages of award
reccomendation,as of
9/7/17.Following 9/2017
bid award,staff is engaged
in final contract negotiations
and project planning;
Contracts signed 10/16/17-
Scope of Work signed
10/27/17;Project launch
expected by 12/1/17;
Project kick off call held
Install a vehicle counter system 11/10/17,data conversion
at Bridger Garage and at the and preliminary staff
16 Surface lots. 6/30/2017 On-Going training underway;
Establish best practice protocols
and performance metrics for
existing enforcement personnal Court/Appeals Packet
and support enforcement with (4/17);Uniform Policy
17 appropriate technology. On-going (8/17);