Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Assistant City Manager
Kristin Donald, Finance Director
SUBJECT: Approval of the General Fund Capital Improvement Plan (CIP) for
Fiscal Years 2019-2023
AGENDA ITEM TYPE: Action
MEETING DATE: December 11, 2017
RECOMMENDATION: Adopt the General Fund Capital Improvement Plan (CIP) for
Fiscal Years 2019-2023.
BACKGROUND: Each year, the City Manager is required to prepare a multi-year Capital
Improvements Plan and submit it to the Commission by December 15th. The City’s General
Fund portion of the CIP contains, by far, the greatest number of capital items and pays for a
broad range of departmental needs. During the months of October, November, and December
numerous staff meetings have taken place to develop this recommended plan.
The plan includes capital items from eleven different departments in the General Fund. There
are over $66 million in equipment and projects recommended within the next five budget-years.
There are also an additional $11 million in projects that are “unscheduled”; they are either not
ready to schedule or their funding has not been developed within the 5 year plan.
116
Summary of Scheduled Projects:
GENERAL FUND CIP FY19 FY20 FY21 FY22 FY23
TOTAL FY19-23 CIP
SCHEDULED
Cemetery 836,859$ 166,000$ 118,000$ 18,000$ 18,000$ 1,156,859$
City Admin/Clerk 113,000$ 57,000$ 28,000$ 28,000$ 28,000$ 254,000$
Economic Dev 25,000$ 25,000$ 25,000$ 25,000$ 25,000$ 125,000$
Facilities (incl Shops)134,031$ 375,000$ 125,000$ 78,000$ 10,000$ 722,031$
Finance 35,000$ -$ -$ -$ -$ 35,000$
Fire -$ 6,500,000$ -$ -$ 4,500,000$ 11,000,000$
Human Resources 25,000$ -$ 30,000$ -$ -$ 55,000$
IT 276,186$ 110,000$ 188,000$ 180,000$ 158,000$ 912,186$
Parks 346,000$ 500,000$ 733,000$ 658,000$ 203,000$ 2,440,000$
Police (incl L&J)10,449,000$ 509,000$ 20,234,000$ 235,000$ 177,000$ 31,604,000$
Recreation 116,500$ 290,277$ 188,560$ 17,932,300$ -$ 18,527,637$
GENERAL FUND TOTAL CIP 12,356,576$ 8,532,277$ 21,669,560$ 19,154,300$ 5,119,000$ 66,831,713$
117
There are four scheduled projects in the plan that have an estimated combined cost of over $57
million, representing 85% of the total scheduled costs. We expect that each project will require
voter approval of a mill levy increase or issuance of bonds.
While our capital plans for the past 5 years have included both the Law & Justice Center (in
some form or another) and an Aquatics Facility, the replacements of Fire Station #1 and Fire
Station #2 are new this year.
Parks department scheduled capital for FY20-FY23 will be moved to a separate Parks
Maintenance District Fund CIP upon the successful creation of a District (scheduled in FY19.)
You will see in the Financial Summary were we adjust the General Fund CIP Project costs by the
amount of Parks capital in those years. We do not reduce General Fund revenues in those years;
we will need the current (and slightly increasing) revenues to continue to pay for General Fund
capital.
Summary of Unscheduled Projects:
The largest single unscheduled project is GF219 – Addition to City Hall, Consolidation of
Services estimated at $5.5 Million. This has been discussed as a project that would be needed
within the 6-10 year timeframe. Refer to the attached CIP schedule for the details of other
unscheduled projects.
GF263 - Law & Justice Center 30,000,000$
GF056 - Aquatics Facility 16,600,000
GF306 - Fire Station 1 6,500,000
GF305 - Fire Station 2 4,500,000
Total Large Scheduled Projects 57,600,000$
118
GENERAL FUND CIP
TOTAL CIP
UNSCHEDULED
Cemetery 360,000$
City Admin/Clerk 28,000$
Economic Dev 25,000$
Facilities (incl Shops)5,816,600$
Finance 333,333$
Fire -$
Human Resources -$
IT 83,000$
Parks 3,395,000$
Police (incl L&J)1,146,000$
Recreation 160,000$
GENERAL FUND TOTAL CIP 11,346,933$
119
Items of particular note this year are:
1. Timing of voter-based initiatives are highlighted in orange in the attached Financial
Summary:
a. Law & Justice Center- GF263 project is currently being examined by the City
and the County. For this plan we represented the option the County was favoring.
This is planned to be funded through bond issuance/mill levy question to city
voters in both FY19 (Law Enforcement Building) and FY21 (Justice Building.)
i. Last year, the CIP was adopted without including the Law & Justice
Center project because of the uncertainty of how we would proceed.
b. Fire Station #1 Relocation- GF306 has been recommend in the Fire Master Plan
and the current Station is in need of repairs in order to remain in service longer. It
is likely we would be selling the existing site to reduce the costs of building a new
station; however, we haven’t estimated the value of the current site that would
off-set the costs. We have also not included any amounts from the Fire
Equipment and Capital Replacement Fund for this project, which we could
consider. As we move forward with planning, those amounts could be known.
c. Aquatics Facility & Projects – GF056 and GF137 have been on the plan and
would require a voter approved levy and bond issuance in FY22.
d. Fire Station #2 Relocation – GF305 was also recommended in the Fire Master
Plan. Similar to Station #1, it is likely we would be selling the existing site to
reduce the costs of the new station. The value of the current site isn’t know, but
could be determined at a future date. We have also not included any amounts
from the Fire Equipment and Capital Replacement Fund for this project, which
we could consider. This project is planned for FY23.
e. Parks Maintenance District creation – the city has funded a Feasibility Study
that will be presented in early 2018. The creation would create a new, separate
fund for the district that would include capital items. This plan anticipates the
District being created in FY19, with its first assessments and funding in FY20.
As a result, we show the Park Department capital items “moved to their own
fund,” and would be removed from the General Fund plan in the Financial
Summary beginning in FY20
120
2. Other projects and equipment of note added to the plan this year:
a. Software and Technology enhancement and updates. Specifically the
Commission room - GF283 and Laserfiche - GF284 for records management.
SunGuard Analytics Software - GF224 is moved forward a year due to needs of
various departments.
b. Vehicle and equipment additions and replacements. Police and Parks have their
rotation of vehicle replacements with some additions. Police added an additional
patrol car and non-patrol cars. Recreation is requesting a vehicle replacement in
FY20 and a new van in FY21.
c. Facilities and Aquatics have maintenance and replacement requests to keep
buildings and equipment working and up to standards.
3. In order to continue to make the necessary improvements and equipment purchases, we
need to make increased funding available for capital projects in the General Fund.
This plan makes a 3-pronged recommendation that will make more money available for
projects.
a. Increased borrowing: The planned voter-approved bonds, as discussed above.
b. The Park Maintenance District, if created, is funded by a separate assessment
without decreasing the General Fund revenue dedicated to capital.
c. Annual General Fund Revenues available for Capital Improvements have been
increased to 3% in FY20, and to 3.5% in FY21. In order to accomplish this and
actually fund the capital projects listed, we will need to prioritize capital projects
ahead of the growth of the other portions of the General Fund budget going
forward.
UNRESOLVED ISSUES: Law and Justice Center plans with the County, timing of Fire
Station relocation and the possible creation of a Park Maintenance District.
ALTERNATIVES: As suggested by the City Commission. If the Commission does not
wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
121
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY19. Projects and equipment purchases can only be made after being included in an Approved
Budget.
Report compiled on: December 4, 2017
Attached: Draft - General Fund CIP
122
General Fund Capital Improvement PlanFinancial Summary Current YearFY18 FY19 FY20 FY21 FY22 FY23UnscheduledProjected Beginning Balance Dedicated to CIP ‐$ 236,000$ (56,664)$ (465,568)$ (262,920)$ 278,229$ Plus: General Fund Revenues Dedicated to CIP 1,284,996$ 919,412$ 1,083,374$ 1,094,207$ 1,105,149$ 1,116,201$ ‐$ Plus: GF231 ‐ Cem. Irrigation Project ‐ Reserve Used for Grant Match 200,000$ 200,000$ Plus: GF231 ‐ Cem. Irrigation Project ‐ GrantFunding DNRC and BOR 425,000$ Plus: GF286 ‐ Veterans Cemetery Project ‐ Reserve Used 88,000$ 40,000$ 45,000$ Plus: GF280 ‐ Story Mansion Sewer Repair, from Story Mansion Fund 18,000$ Plus: GF052 ‐ Police Non‐Patrol Vehicle, from Donation 18,000$ Plus: Intercap Loan ‐ GF260, GF261 Sports Complex Imps. 431,500$ Plus: Bond Issue: GF263 L&J** Court then Law Enforcement Option 10,000,000$ 20,000,000$ Plus: Bond Issue: GF305 Fire Station 1 6,500,000$ Plus: Bond Issue: GF306 Fire Station 24,500,000 Plus: Bond Issue: GF056 Indoor/Outdoor Aquatics Facility 16,500,000$ Plus: GF137 Swim Center/ GF238 Bogert Bond Issue (with Aquatics Facility question) 1,432,300$ Less: Scheduled CIP Project Costs (1,284,996)$ (12,356,576)$ (8,532,277)$ (21,669,560)$ (19,154,300)$ (5,119,000)$ (11,346,933)$ Creation of Citywide Park Maint Dist. CIP projects moved to own fundCreation 500,000$ 733,000$ 658,000$ 203,000$ 3,395,000$ Projected Year‐End Cash Dedicated to CIP236,000$ (56,664)$ (465,568)$ (262,920)$ 278,229$ 978,430$ Assumptions Made for Revenue Estimates:Current YearFY18FY19FY20FY21 FY22 FY23Estimated Annual General Fund Revenues30,343,623$ 30,343,623$ 30,647,059$ 30,953,530$ 31,263,065$ 31,575,696$ Estimated Growth in General Fund Revenues0% 1% 1% 1% 1% 1%Total Estimated General Fund Revenues30,343,623$ 30,647,059$ 30,953,530$ 31,263,065$ 31,575,696$ 31,891,453$ Current Revenues Dedicated to CIP %2.6%2.6%3.0%3.5%3.5%3.5% Plus: Increase Dedicated to Capital Improvements %0.4% 0.4% 0.5% 0.0% 0.0% 0.0% Total % Dedicated to CIP3.0% 3.0% 3.5% 3.5% 3.5% 3.5%Total Estimated Revenues Dedicated to CIP910,309$ 919,412$ 1,083,374$ 1,094,207$ 1,105,149$ 1,116,201$ ProjectedProjectedCURRENT$(12,356,576)$(8,532,277)$(21,669,560)$(19,154,300)$(5,119,000)$(11,346,933)FY18 FY19 FY20 FY21 FY22 FY23 UNSCHEDULEDGENERAL FUND PROJECTS & EQUIPMENT123
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22General FundGF010CEMETERYCEMETERY MOWER REPLACEMENTS$18,000$16,000$16,000$18,000$18,000GF083CEMETERYBACKHOE$110,000GF116CEMETERYCEMETERY VEHICLE REPLACEMENTS$50,000GF231CEMETERYCEMETERY IRRIGATION PROJECT$682,859GF252CEMETERYCEMETERY COLUMBARIUM$55,000GF268CEMETERYSOUTHWEST MONTANA VETERAN'S CEMETERY$88,000$360,000$40,000$45,000$18,000$836,859$166,000$118,000$18,000$360,000Totals by DEPARTMENTGeneral FundGF282City Admin/ Sustainability CITY HALL PLUG-IN HYBRID ELECTRIC VEHICLE$33,000$33,000Totals by DEPARTMENTGeneral FundGF283City Clerk’s Office / COMMISSION ROOM TECHNOLOGY UPGRADE$80,000GF284City Clerk’s OffiLASERFICHE SOFTWARE UPGRADE$28,000$28,000$57,000$28,000$28,000$28,000$80,000$57,000$28,000$28,000$28,000Totals by DEPARTMENTGeneral FundGF275ECONOMIC DEVFIBER OPTIC CONDUIT AND VAULTS$25,000$25,000$25,000$25,000$25,000$25,000$25,000$25,000$25,000$25,000$25,000$25,000Totals by DEPARTMENTGeneral FundGF285Facilities/LibraryLIBRARY EXTERIOR DOOR OPERATORS/CLOSURES REPLACEMENT$12,000$12,000Totals by DEPARTMENTGeneral FundGF103FACILITY - CHAMERICAN'S WITH DISABILITIES ACT (ADA) COMPLIANCE IMPROVEMENTS$10,000$10,000$10,000$10,000$10,000124
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22GF219FACILITY - CHADDITION TO CITY HALL, CONSOLIDATION OF SERVICES$5,500,000GF241FACILITY - CHREPLACEMENT OF CITY HALL AC CONDENSING UNIT – ROOF TOP$50,000GF245FACILITY - CHENERGY PROJECTS – CITY HALL$75,000GF271FACILITY - CHCITY HALL NEW PARKING LOT$250,000GF272FACILITY - CHSITE SECURITY UPGRADE - BUILDING LOCKS$15,000$15,000$15,000GF303FACILITY - CHCITY HALL EXPANSION REMODEL OF STORAGE AREAS INTO OFFICES$25,000GF304FACILITY - CHCITY HALL COMMISSION ROOM EXPANSION/REMODEL$300,000$10,000$75,000$325,000$125,000$10,000$5,750,000Totals by DEPARTMENTGeneral FundGF001FACILITY - PROFPROFESSIONAL BUILDING ELEVATOR REPLACEMENT$66,600GF199FACILITY - PROFPROFESSIONAL BUILDING RECONFIGURATION - PHASE 2$37,031$37,031$66,600Totals by DEPARTMENTGeneral FundGF157FACILITY - SCSENIOR CENTER ELEVATOR$68,000$68,000Totals by DEPARTMENTGeneral FundGF224FINANCESUNGARD ANALYTICS NOW COGNOS BI (BUSINESS INTELLIGENCE) WEB-BASED REPORTING SUITE$35,000GF227FINANCEERP REPLACEMENT / UPGRADE "SUNGARD REPLACEMENT / UPGRADE"$333,333$35,000$333,333Totals by DEPARTMENTGeneral FundGF305FireFIRE STATION 2$4,500,000GF306FireFIRE STATION 1$6,500,000125
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22$4,500,000$6,500,000Totals by DEPARTMENTGeneral FundGF287Human ResourcLEARNING MANAGEMENT SYSTEM$25,000GF288Human ResourcAPPLICANT TRACKING SYSTEM$30,000$25,000$30,000Totals by DEPARTMENTGeneral FundGF062I.T.PERSONAL COMPUTER (PC) REPLACEMENT$60,000$50,000$55,000$65,000$65,000GF080I.T.REMOTE CLOSET SWITCHES, ROUTER AND WIRELESS AP REPLACEMENT$50,000$45,000$45,000$45,000$50,000GF199I.T.PROFESSIONAL BUILDING RECONFIGURATION - PHASE 2$136,186GF229I.T.ISCSI STORAGE REPLACEMENT$45,000GF233I.T.VEHICLE REPLACEMENT$23,000$83,000GF263I.T.POLICE VIDEO EVIDENCE STORAGE AND BACKUP$40,000GF265I.T.GENERAL FUND SERVER REPLACEMENT$68,000GF289I.T.SERVER FARM SOFTWARE UPGRADES$25,000$10,000$10,000$25,000$158,000$276,186$110,000$188,000$180,000$83,000Totals by DEPARTMENTGeneral FundGF031PARKSPARK IMPROVEMENT GRANTS$150,000$150,000GF034PARKSLARGE DECK MOWER$60,000$90,000$110,000$58,000GF084PARKSPARKS RESTROOM UPGRADES$470,000$80,000GF092PARKSPLAYGROUND EQUIPMENT$120,000$95,000$95,000$120,000GF108PARKSPARK SIDEWALK REPLACEMENTS$88,000$120,000GF115PARKSPARK VEHICLE REPLACEMENTS$55,000$50,000$180,000$30,000$30,000$28,000GF148PARKSBMX PARKING LOT$85,000GF190PARKS4-WHEELER ATV REPLACEMENT$14,000$16,000GF191PARKSUPGRADE SOFTBALL COMPLEX LIGHTING$1,000,000126
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22GF195PARKSTURF SWEEPER$32,000$36,000GF205PARKSPROST PLAN UPDATE$109,000GF250PARKSSPLASH PADS$190,000$225,000$240,000GF260PARKSSPORTS COMPLEX - CONSTRUCTION OF 'PROJECT RELATED' COTTONWOOD ROAD AREA WATER & WASTEWATER IMPROVEMENTS$364,000GF270PARKSSNOW PLOWING VEHICLE$65,000$75,000GF278PARKSGRIFFIN AT STORY MILL PARK ROAD IMPROVEMENT - .26 MILE$260,000GF279PARKSSTORY MILL ROAD IMPROVEMENT - .17 MILE$170,000GF281PARKSBOZEMAN POND PARK & AASHEIM BALLFIELDS ROAD EXPANSION - .17 MILE & .09 MILE$260,000GF290PARKSIRRIGATION SYSTEM REPLACEMENTS$425,000GF291PARKSPICKLEBALL COURTS$90,000$203,000$346,000$500,000$733,000$658,000$3,395,000Totals by DEPARTMENTGeneral FundPW05/06Parks and Facility PortionPUBLIC WORKS SHOPS FACILITY PLAN AND CONSTRUCTION$10,000$50,000$10,000$50,000Totals by DEPARTMENTGeneral FundGF052POLICEPOLICE NON-PATROL VEHICLE REPLACEMENTS$30,000$15,000$377,000$15,000$15,000GF053POLICEPATROL VEHICLE REPLACEMENT$132,000$124,000$680,000$189,000$128,000$195,000GF165POLICEPATROL MOTORCYCLE REPLACEMENTS$60,000GF166POLICEPORTABLE AND MOBILE RADIO REPLACEMENTS$295,000$295,000GF262POLICEPOLICE K9$19,000$17,000GF263POLICELAW & JUSTICE CENTER$10,000,000$20,000,000GF292POLICEPATROL CAR AUXILIARY EQUIPMENT$15,000$15,000$10,000$10,000$10,000$10,000127
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22GF293POLICENON-PATROL CAR NEW VEHICLES$15,000$15,000GF294POLICEPATROL CAR - ADDITIONAL$64,000$177,000$10,449,000$509,000$20,234,000$235,000$1,146,000Totals by DEPARTMENTGeneral FundGF056RECREATIONDESIGN & CONSTRUCT INDOOR/OUTDOOR FAMILY AQUATICS CENTER$100,000$16,500,000GF137RECREATIONSWIM CENTER - FACILITY REPAIRS AND REPLACEMENTS$949,300GF140RECREATIONLINDLEY CENTER PARKING LOT RENOVATION$53,560GF209RECREATIONLINDLEY CENTER FULL UPGRADE: RESTROOMS, WINDOWS, SIDING, KITCHEN, ROOF, FLOORING$224,277GF238RECREATIONBOGERT POOL RENOVATION$483,000GF295RECREATIONSWIM CENTER UV SYSTEM REPLACEMENT$68,500GF296RECREATIONSWIM CENTER – FRONT FURNACE REPLACEMENT$36,000GF297RECREATIONSWIM CENTER ROOF REPLACEMENT$26,000GF298RECREATIONSWIM CENTER – BARRIER WALL IN PUMP ROOM$22,000GF299RECREATIONVEHICLE REPLACEMENT$30,000GF300RECREATIONSTORY MILL COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT$110,000GF301RECREATIONSTORY MANSION EXTERIOR PAINT$50,000GF302RECREATIONPASSENGER VAN$35,000$116,500$290,277$188,560$17,932,300$160,000Totals by DEPARTMENTSummary for General Fund (78 items)Totals by year:$5,119,000$12,356,576$8,532,277$11,346,933FY23FY19FY20UnscheduledFY22$19,154,300$21,669,560FY21128
CIP Project Fund
General Fund
PROJECT NUMBER
GF001
DEPARTMENT
FACILITY - PROF
PROJECT NAME
PROFESSIONAL BUILDING ELEVATOR REPLACEMENT
FY19 FY20 Unscheduled
$66,600
DESCRIPTION OF PROJECT
The elevator in the Professional Building is a three stop Otis elevator. The elevator was installed when the second floor was
added in 1972. Since the City purchased the building we have remodeled several areas on both the main floor and second floor –
the elevator remains original and is approaching 44 years of continued use. The elevator is to the point where many technological
improvements have been made in elevator technology and a change out would yield both improved service and some reductions
in energy costs. The elevator is inspected annually and is still safe although there are some inherent problems with the operation
of the elevator. Of the four elevators owned by the City, this system experiences the most downtime. One big problem is the
leveling systems and the way the rails and tracks are mounted in the building. The elevator will malfunction and require resetting if
it loaded heavy to one side. A new car and track system would solve the nuisance trips associated with this aging elevator.
ALTERNATIVES CONSIDERED
Continue to maintain and adjust the elevator operating systems throughout the year.
ADVANTAGES OF APPROVAL
Increase reliability and reduced maintenance costs. Some electrical savings associated with improved electric motors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs
FUNDING SOURCES
General Fund and Building Inspection Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
129
CIP Project Fund
General Fund
PROJECT NUMBER
GF010
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY MOWER REPLACEMENTS
FY19
$16,000
FY20
$16,000
Unscheduled
DESCRIPTION OF PROJECT
Ongoing cemetery mower replacement program. Scheduled on a five year replacement program, with the oldest cemetery mower
now being 5 years old. Proposing to go back to the three replacement cycle, due to numerous breakdowns after the three year
mark. These mowers are used to complete the mowing 53+ acres of turf inside and outside the cemetery which include mowing
of the open space, trails, and the weekly mowing through the headstones.
ALTERNATIVES CONSIDERED
Keep older mowers for extended periods of time, which has been done as we moved to a 5 year replacement program instead of a 3 year
program.
ADVANTAGES OF APPROVAL
Less down time; Decreased repair /maintenance costs; High trade –in value; Increased productivity; Less emissions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Routine maintenance, oil changes, fuel.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$18,000
FY22
$18,000
FY23
$18,000
130
CIP Project Fund
General Fund
PROJECT NUMBER
GF031
DEPARTMENT
PARKS
PROJECT NAME
PARK IMPROVEMENT GRANTS
FY19 FY20
$150,000
Unscheduled
DESCRIPTION OF PROJECT
The General Fund contributes funds every other year towards improving park infrastructure through implementation of park
master plans. This grant program is a matching funds program in which the City receives a minimum 1 to 1 match from the
recipient. The Commission has established a formal grant policy by resolution. By switching to every other year, and also
increasing the allocation, bigger projects can be accomplished, though these projects will take more time to complete.
ALTERNATIVES CONSIDERED
Handle park equipment and improvement requests on an adhoc basis, as various donors or service groups bring them forward. Allocate more or
fewer dollars to the program.
ADVANTAGES OF APPROVAL
This matching funds program provides critical infrastructure to the park system by utilizing the talents of our community members through
matching funds, donations, labor in lieu of and numerous specialized services. All of the above can be used as a match in this program
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: New infrastructure and facilities bring on increased maintenance and labor costs. The nature of each
project funded will determine the continued costs. Some projects have very low ongoing costs, others have relatively higher costs.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22
$150,000
FY23
131
CIP Project Fund
General Fund
PROJECT NUMBER
GF034
DEPARTMENT
PARKS
PROJECT NAME
LARGE DECK MOWER
FY19
$90,000
FY20 Unscheduled
$110,000
DESCRIPTION OF PROJECT
The mower request in FY19 would be an addition of a large-deck sports turf mower, anticipated to be needed for additional
parkland used for athletics, such as: Enterprise Park (formerly Lerner Park), Oak Springs Park, Adam Bronken Sports Complex,
and the eventual 80 acre Bozeman Sports Complex. The City currently mows over 150 acres of irrigated turfgrass weekly.
ALTERNATIVES CONSIDERED
Continue to repair as break downs occur, Replace mowers as they breakdown, explore a lease program.
ADVANTAGES OF APPROVAL
Proper mowing of sports fields and formal parks are imperative to safety. Regular replacement will reduce maintenance costs and decrease the
number of breakdowns we have been experiencing. Well mowed parks are an important reflection on our City and how it is perceived by
visitors and citizens. New mowers will be more reliable, safer, productive, and will reduce the workload on the vehicle maintenance shop
personnel. Well maintained sports fields have proven to be a vital component to the economic growth of our community, by attracting regional
and state tournaments to Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Improve scheduling of mowing and increase crew efficiency because of reliable equipment.
FUNDING SOURCES
100% General Fund.
New
Replacement
Equipment
Project
FY21
$58,000
FY22 FY23
$60,000
132
CIP Project Fund
General Fund
PROJECT NUMBER
GF052
DEPARTMENT
POLICE
PROJECT NAME
POLICE NON-PATROL VEHICLE REPLACEMENTS
FY19
$15,000
FY20 Unscheduled
$377,000
DESCRIPTION OF PROJECT
The police department has unmarked vehicles used by command staff, detectives and some support positions. Some of these
vehicles are used for support operations, such as animal control, community resource officer, code compliance, etc…. Command
and detective vehicles are assigned and used to respond to emergency calls for command/control or investigations. Generally
vehicle replacement of these vehicles involves buying used, lower mileage vehicles with some trade-in done by higher mileage
vehicles nearing the end of time to operate safely. Decisions on when to rotate these vehicles is usually higher mileage than a
normal police car and dependent largely on track history for maintenance concerns. In FY19 and FY21 we have 2 detective
vehicles in need of replacement. Cost estimates involve buying a lower mileage or lease return vehicle, not a new vehicle. In
FY20 and FY22 we anticipate adding two School Resource Officer Positions to cover the new Bozeman High School and increased
demand for police services at all schools. In FY22 and FY23 we have identified 3 admin vehicles that will need replacement. These
are used by command officers for daily and on-call response throughout the city.
ALTERNATIVES CONSIDERED
Each year we assess each purchase decision. At times we may be able to convert a marked police car to a detective use, when the vehicle is no
longer trustworthy to the levels of immediate emergency response, but could be used for a year or two as an unmarked support vehicle.
ADVANTAGES OF APPROVAL
2 of these vehicles are new and essential. The replacements are also essential and continue to provide safe and reliable transportation. These
unmarked cars tend to last for at least 15 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$15,000
FY22
$15,000
FY23
$30,000
133
CIP Project Fund
General Fund
PROJECT NUMBER
GF053
DEPARTMENT
POLICE
PROJECT NAME
PATROL VEHICLE REPLACEMENT
FY19
$124,000
FY20
$189,000
Unscheduled
$680,000
DESCRIPTION OF PROJECT
This plan allows for a number of patrol cars to be replaced each year, including all of the necessary vehicle equipment (top lights,
sirens, radio, mobile data terminals, video cameras, electronic reporting / ticketing systems, etc.) Costs are based on actual costs
in FY18 of $61,000 per vehicle and anticipated increases in FY19 and beyond. Patrol vehicles are an essential item in the operation
of the Bozeman Police Department, being the primary tool used for over 50,000 Response to Calls each year. Police vehicles must
be available for police patrol and emergency call response 24 hours a day, 365 days a year. These vehicles are used to respond to
both emergency and non-emergency calls for service, investigate vehicle crashes, conduct traffic enforcement and for general
patrol duties. These patrol vehicles average approximately 20,000 miles annually. Vehicles earmarked for replacement will have a
minimum estimated 110,000 miles per vehicle, which with police emergency response tends to be the rough time when police
vehicles are no longer safe for emergency response. An additional 10 patrol vehicles will need replacement after FY23. A review
of mileage and estimated staffing increases in patrol by 2-3 officers over the next few years has also led to the identified need for
an additional patrol vehicle in FY21. This won’t replace a vehicle and brings the total patrol response vehicles to 23 (1 unmarked /
2 K9 vehicles / 20 fully marked)
ALTERNATIVES CONSIDERED
None.
ADVANTAGES OF APPROVAL
This helps us plan for safe and reliable emergency response vehicles for patrol use, as well as projected lower annual maintenance costs. This
program would allow for the replacement of older, higher mileage patrol cars that become less reliable and more costly to repair. Equipment
components mounted inside the car can sometimes be transferred from the old car to the new car, depending on the condition. These
replacements continue to bring the department closer to 100% matching Ford SUV patrol vehicles.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
These are replacement vehicles. Recurring costs frequently decline as newer cars replace older ones. Maintenance costs have stabilized due to
regularly scheduled service, even though calls for service have increased and additional officers have been hired.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$128,000
FY22
$195,000
FY23
$132,000
134
CIP Project Fund
General Fund
PROJECT NUMBER
GF056
DEPARTMENT
RECREATION
PROJECT NAME
DESIGN & CONSTRUCT INDOOR/OUTDOOR FAMILY AQUATICS CENTER
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Indoor/Outdoor Aquatics Center. This item was identified as a “Top Ten Capital Facility Recommendation” in the PROST plan,
adopted October 2007. The design phase in FY18 includes the preliminary design of the Family Aquatics Center. This project will
need to be approved by the voters. It is estimated that an election would be offered in the fall of 2021.
ALTERNATIVES CONSIDERED
Do not build a community aquatics center.
ADVANTAGES OF APPROVAL
Community Benefits of an Aquatics Center: safe and healthy place for families to play, connected families, strong vital involved community, and
increased community programs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs to include additional aquatic staff: Cost undetermined at this time.
FUNDING SOURCES
Bond and General Fund.
New
Replacement
Equipment
Project
FY21
$100,000
FY22
$16,500,000
FY23
135
CIP Project Fund
General Fund
PROJECT NUMBER
GF062
DEPARTMENT
I.T.
PROJECT NAME
PERSONAL COMPUTER (PC) REPLACEMENT
FY19
$50,000
FY20
$55,000
Unscheduled
DESCRIPTION OF PROJECT
This is a general item for replacement of personal computers for General Fund related jobs and services. (Enterprise and Special
Revenue fund services pay for their own pc’s.) As of FY17, Personal Computers moved to a 5 year rotation before replacement.
PC Replacements are one of the primary drivers of Help Desk Calls (PM01 & WL01) - aging computers can have more software
and technical conflicts, and replaced PC's often require user support for newer versions of software, etc.
ALTERNATIVES CONSIDERED
Not replace computer/server hardware as frequently.
ADVANTAGES OF APPROVAL
City technology needs will be better met and the IT department will be able to more efficiently support employees and citizens.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$65,000
FY22
$65,000
FY23
$60,000
136
CIP Project Fund
General Fund
PROJECT NUMBER
GF080
DEPARTMENT
I.T.
PROJECT NAME
REMOTE CLOSET SWITCHES, ROUTER AND WIRELESS AP REPLACEMENT
FY19
$45,000
FY20
$45,000
Unscheduled
DESCRIPTION OF PROJECT
Wan Site end of life replacements for switches and router throughout City to include City Hall, Professional Building, City Shops,
Landfill, L&J, Library, WWTP, WTP, Swim Center, Beall Park, Cemetery. Smaller sites will be consolidated in one year. FY 15 -
Prof-Building, Vehicle Maint. This equipment is critical to the City's technology network, supporting all of the department's
performance measures related to system "uptime" (PM02-PM06) and workload measures related to number of hours the network
and various software is "in service" (WL02-W06).
ALTERNATIVES CONSIDERED
Maintain current switches without critical support or maintenance.
ADVANTAGES OF APPROVAL
Maintain uptime for all WAN locations throughout the City to include phone services as well as data.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund – with costs shared with Enterprise, as location warrants.
New
Replacement
Equipment
Project
FY21
$45,000
FY22
$50,000
FY23
$50,000
137
CIP Project Fund
General Fund
PROJECT NUMBER
GF083
DEPARTMENT
CEMETERY
PROJECT NAME
BACKHOE
FY19 FY20
$110,000
Unscheduled
DESCRIPTION OF PROJECT
This piece of equipment would replace the current cemetery backhoe (2001- 3119 hours) that is used for burials an average of 2
times per week. This is the main piece of equipment utilized for cemetery burials.
ALTERNATIVES CONSIDERED
Continue to utilize the older backhoe and repair and maintain as necessary. Potentially, borrow from another department.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff and the families relying on cemetery services. The old cemetery backhoe could potentially be transitioned
to the Parks Division.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Operating and repair costs are expected to be lower than the existing vehicle.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
138
CIP Project Fund
General Fund
PROJECT NUMBER
GF084
DEPARTMENT
PARKS
PROJECT NAME
PARKS RESTROOM UPGRADES
FY19 FY20 Unscheduled
$470,000
DESCRIPTION OF PROJECT
This project is the general replacement and upgrading of the City Park’s public restroom facilities. Other restrooms that need to
be replaced- and/or built are: Rose Park $80,000 (FY 21), Beall Park $40,000 and the Softball Complex $300,000 –( Large Facility
plus Concession Stand), BMX- Westlake Park $130,000 are unscheduled.
ALTERNATIVES CONSIDERED
Continue to try to maintain existing facilities. The Rose and BMX Park projects will provide restroom facilities in areas where currently none
exist. The BMX project potentially could be part of the Midtown Urban Renewal District.
ADVANTAGES OF APPROVAL
Ease and efficiency of maintaining new restrooms; increased cleanliness of public facilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Operating and repair costs are expected to be lower than the existing facilities.
FUNDING SOURCES
100% General Fund, BMX Park funding possible from TIF
New
Replacement
Equipment
Project
FY21
$80,000
FY22 FY23
139
CIP Project Fund
General Fund
PROJECT NUMBER
GF092
DEPARTMENT
PARKS
PROJECT NAME
PLAYGROUND EQUIPMENT
FY19 FY20
$95,000
Unscheduled
$120,000
DESCRIPTION OF PROJECT
The following playground equipment will eventually need to be replaced due to its age and condition: Replacement will bring
equipment up to today’s standards and reduce safety and liability concerns. Jarrett Park (FY19) and Christie Park (FY20) are
identified as the playgrounds that need replacement, in that priority. New replacements include: Lindley Park (FY22) and Kirk
Park playgrounds. The majority of the city-maintained playgrounds were installed in the early 1990’s. In general, safety
recommendations for playgrounds address: playground site elements, sight lines, equipment features and materials, surfacing
materials, hardware, paints and finishes, and any other hazards that might be present. Playground repairs require same-day
response given their critical safety implication. Currently, the Parks Division inspects and maintains 21 playgrounds city-wide and
assists with another 19 HOA- maintained playgrounds with monthly inspections and recommendations.
ALTERNATIVES CONSIDERED
Keep existing equipment in place, maintain as we go
ADVANTAGES OF APPROVAL
Increased safety for community members.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
100% General Fund.
New
Replacement
Equipment
Project
FY21
$95,000
FY22
$120,000
FY23
140
CIP Project Fund
General Fund
PROJECT NUMBER
GF103
DEPARTMENT
FACILITY - CH
PROJECT NAME
AMERICAN'S WITH DISABILITIES ACT (ADA) COMPLIANCE IMPROVEMENTS
FY19
$10,000
FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
Replace or install ADA upgrades in various city-owned buildings. Work examples include: door hardware, handrails, parking
signage and stalls, building access, etc. The Facilities Superintendent has been working with the ADA advisory committee to
provide recommendations to the City on priority order for any upgrades or improvements that may be identified to make our
facilities and programs more accessible. This money has been used, and will continue to be used to improve accessibility as
demonstrates a commitment from the City to address ADA issues. Based on the initial review of the work to be done the dollar
amount should be increased in order to complete the improvements within the needed timeframe.
ALTERNATIVES CONSIDERED
When remodels are initiated on buildings they are brought up to current ADA requirements as per regulations. There are changes to the ADA
that took effect in March 2011. We will continue to make upgrades as changes are made to buildings but this budget item would accelerate the
compliance for city buildings.
ADVANTAGES OF APPROVAL
It has been the policy of the city to meet the full spirit of the law as outlined in the ADA regulations. By taking the initiative to bring all our
buildings up to current standards we can provide a positive example to the community in meeting the needs of people with restricted or limited
mobility.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No significant costs are anticipated with these improvements.
FUNDING SOURCES
100% General Fund.
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
$10,000
141
CIP Project Fund
General Fund
PROJECT NUMBER
GF108
DEPARTMENT
PARKS
PROJECT NAME
PARK SIDEWALK REPLACEMENTS
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Sidewalks Identified for replacement due to deteriorating cement, missing sections and heaving from weather and tree roots. New
sidewalks must meet or exceed city code. Replacing the old sidewalk will result in a safer sidewalk year round and enable the
sidewalk plows to better meet the snow removal municipal code. Costs of approximately $11.75 square foot for rip and replace.
Project 1: $120,000 - Southside Park - replace 730' of sidewalk along South 5th Avenue and along West Alderson Street with new
6' (six foot) wide concrete sidewalk, and the related retaining wall. Project 2: $88,000 - Cooper Park - replace the sidewalk
around the entire block approximately 1875' total. This sidewalk serves as a main route to and from the University.
ALTERNATIVES CONSIDERED
Maintain existing sidewalks and patch and repair as needed.
ADVANTAGES OF APPROVAL
Increased safety for community members and efficiency of operation (plowing)
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: no estimate at this time
FUNDING SOURCES
General Fund.
New
Replacement
Equipment
Project
FY21 FY22
$120,000
FY23
$88,000
142
CIP Project Fund
General Fund
PROJECT NUMBER
GF115
DEPARTMENT
PARKS
PROJECT NAME
PARK VEHICLE REPLACEMENTS
FY19
$50,000
FY20
$30,000
Unscheduled
$180,000
DESCRIPTION OF PROJECT
The Parks Division utilizes vehicles for mowing, fertilization, irrigation, inspections, snow plowing and repairs of the city parks.
City parkland now has grown to over 500 acres that the Parks Division is responsible for. All vehicles are utilized until service
related down-time for equipment and staff become problematic or safety is compromised. FY19 represents a one ton pick-up
replacement. Dodge has ceased making parts for 2001 1-ton that is currently in the Parks fleet. The two current 1-tons in the
Park fleet are used for plowing parking lots, ice rinks, hauling garbage, stone, and trail fines among other duties. The addition in
FY20 of $30,000 is for a ½ ton fleet vehicle to replace the 1991 Dodge with 5 year repair costs of $32124.00.That vehicle is
currently on the auction block. An incremental approach to replacing aging fleet vehicles which includes an additional hybrid car
(FY22)- and ½ ton pickups for the increase in FTE’s within the division. (FY20 and FY21) An additional 1-ton pickup was moved
into FY23. A more detailed list of the replacement plan, along with updated vehicle mileage, has been sent to Finance- Mileage
updated October 2, 2017.
ALTERNATIVES CONSIDERED
None.
ADVANTAGES OF APPROVAL
This insures safe and reliable vehicles for park use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: These are replacements; recurring costs frequently decline as newer cars replace older ones. 5 year
average on repairs to the Parks fleet - $3,550.00 per vehicle.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$30,000
FY22
$28,000
FY23
$55,000
143
CIP Project Fund
General Fund
PROJECT NUMBER
GF116
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY VEHICLE REPLACEMENTS
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Cemetery Vehicle Replacement Plan - the Cemetery Department utilizes 1-Ton trucks for operations and maintenance of the
Sunset Hills Cemetery. Asset# 1213 - 1989 1Ton 4x4, *41,360 miles - is critical to providing prompt burial services roughly twice
a week and sanding/plowing cemetery roads. While it has relatively low miles, it has extremely low fuel economy (460 engine)
which drives our recommendation to replace this 28 year old vehicle. *Mileage as of 11/2017.
ALTERNATIVES CONSIDERED
Keep maintaining #1213 until a new replacement is funded or replacement parts are no longer available.
ADVANTAGES OF APPROVAL
This insures safe and reliable vehicles for cemetery use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: These are replacements; recurring costs frequently decline as newer cars replace older ones
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
144
CIP Project Fund
General Fund
PROJECT NUMBER
GF137
DEPARTMENT
RECREATION
PROJECT NAME
SWIM CENTER - FACILITY REPAIRS AND REPLACEMENTS
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The Swim Center requires numerous repair and equipment replacements which would be added to the Bond initiative for the
Indoor/Outdoor Aquatics Center. These items include: gutter replacement $159,000; deck tile replacement $150,000; removal of
ceiling tiles and basic cosmetic improvements $127,000; HVAC unit replacement $365,000; pool re-plaster $148,000
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
These projects will help to ensure that we are able to maintain a safe and functional facility. The pool is extremely well utilized and repairs and
replacements are necessary over time in order to continue to serve the community.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional annual operating and maintenance costs
FUNDING SOURCES
Bond
New
Replacement
Equipment
Project
FY21 FY22
$949,300
FY23
145
CIP Project Fund
General Fund
PROJECT NUMBER
GF140
DEPARTMENT
RECREATION
PROJECT NAME
LINDLEY CENTER PARKING LOT RENOVATION
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Curb and overlay the parking lot at the Lindley Center and include ADA parking stalls. Install parking lot lights and bases, a
dumpster pad and dumpster enclosure fence. This project aligns with section 10.10.1 of the PROST plan (adopted October 2007)
that recommends that City parks, recreation facilities and trails are accessible to the greatest extent possible. Includes permit fees.
ALTERNATIVES CONSIDERED
Sealing and striping lot and not installing lights
ADVANTAGES OF APPROVAL
Comply with city codes, allow for more cars to be parked in the lot at a time, more organized parking which will make the lot safer and reduced
liability, lights will help with public safety and parking lot/facility security, ADA spots will be designated which will make the lot accessible, the
dumpster would be enclosed.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs to include stripping and periodic overlays.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$53,560
FY22 FY23
146
CIP Project Fund
General Fund
PROJECT NUMBER
GF148
DEPARTMENT
PARKS
PROJECT NAME
BMX PARKING LOT
FY19 FY20 Unscheduled
$85,000
DESCRIPTION OF PROJECT
Installation of parking lot at Westlake BMX park, left as unscheduled due to this potentially could be part of the Mid-Town Urban
Renewal project- as Westlake/BMX reside in this area.
ALTERNATIVES CONSIDERED
Do not install a parking lot
ADVANTAGES OF APPROVAL
Increased access to the Children’s Memorial Park and Christmas tree drop off area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Minimal. Clean-up, possible snow plowing, painting lines every few years
FUNDING SOURCES
100% General Fund, possible funding from TIF
New
Replacement
Equipment
Project
FY21 FY22 FY23
147
CIP Project Fund
General Fund
PROJECT NUMBER
GF157
DEPARTMENT
FACILITY - SC
PROJECT NAME
SENIOR CENTER ELEVATOR
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The elevator at the Bozeman Senior Social Center is a three stop Otis elevator. The elevator was installed in early 1980 and is at
the point where many technological improvements have been made in elevator technology. A change out would yield both
improved service and some reductions in energy costs. While the elevator is inspected annually and is safe, it is used heavily by the
members of the Senior Center. Planning ahead for the replacement of the elevator will be more cost effective and avoid
unnecessary down time during the replacement process. The elevator maintenance contractor has recommended this be the first
elevator replaced by the City.
ALTERNATIVES CONSIDERED
Continue to maintain and adjust the elevator operating systems as needed. Wait to replace the elevator until it physically breaks down or
continue to monitor the operation and hold off on the replacement until the routine repair and maintenance costs exceed acceptable limits
ADVANTAGES OF APPROVAL
Improved operations and reduced maintenance for the elevator most needed by a special population. Small reduction in annual energy costs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs.
FUNDING SOURCES
General Fund -
New
Replacement
Equipment
Project
FY21 FY22
$68,000
FY23
148
CIP Project Fund
General Fund
PROJECT NUMBER
GF165
DEPARTMENT
POLICE
PROJECT NAME
PATROL MOTORCYCLE REPLACEMENTS
FY19 FY20 Unscheduled
$60,000
DESCRIPTION OF PROJECT
Currently the Police Department has two police motorcycles and one used solely for training. Patrol motorcycles are an essential
item in the traffic enforcement division, used for a portion of the over 13,000 traffic stops, crashes, and citations each year. These
motorcycles are used from March to October each year and are responsible for a portion of the response to both emergency and
non-emergency calls for service, investigate accidents, conduct traffic enforcement and general patrol duties. In FY18 we did not
deploy the motorcycles because of staffing shortages and have plans to deploy in FY19. The current motorcycles will not need
replacement during the next 5 years.
ALTERNATIVES CONSIDERED
None.
ADVANTAGES OF APPROVAL
This ensures safe and reliable emergency response vehicles for patrol use, as well as lower annual maintenance costs. For the traffic division to
be effective, this equipment must be kept in top operating condition. Police motorcycles are available for police patrol use during the day and
when the city streets are clear enough to ride.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance costs are stable due to regularly scheduled service. Officers assigned to the motorcycle division are also assigned to their own
motorcycle.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
149
CIP Project Fund
General Fund
PROJECT NUMBER
GF166
DEPARTMENT
POLICE
PROJECT NAME
PORTABLE AND MOBILE RADIO REPLACEMENTS
FY19
$295,000
FY20
$295,000
Unscheduled
DESCRIPTION OF PROJECT
In FY18 the department and City has been in conversations and planning with Gallatin County 9-1-1 to improve radio
communication that has become an operational and safety concern. Regardless of the final improvements to infrastructure, one of
the identified needs for replacement is subscriber units (portable radios used by officers and mobile radios used in emergency
response vehicles).The replacement of these subscriber units (radios) are a major stop to improving communications and
responses capabilities. These radios are an essential item in the operation of the Bozeman Police Department, being a critical
communication tool used for over to 50,000 Response to Calls each year. Police radios must be available for police use 24 hours a
day, 365 days a year. These radios are individually assigned, allowing for greater longevity, and department-wide communication in
the event of a need for major response. The City Commission approved purchasing these units, which are currently purchased
with payments in FY19 and FY21. These radios will have at least a 10 year use for emergency response. This purchase included
70 Portable (handheld) radios and 27 mobile (vehicle) radios. This amount represents just the police department share of
purchases.
ALTERNATIVES CONSIDERED
No other alternatives at this time.
ADVANTAGES OF APPROVAL
This ensures safe and reliable emergency communication and response. Program allows for a planned and predictable need for equipment
replacement. Clear and dependable communication allows for quick and efficient deployment and the required level of officer safety.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
150
CIP Project Fund
General Fund
PROJECT NUMBER
GF190
DEPARTMENT
PARKS
PROJECT NAME
4-WHEELER ATV REPLACEMENT
FY19 FY20 Unscheduled
$14,000
DESCRIPTION OF PROJECT
Replace the ATV (2000 Yamaha Grizzly) used for sidewalk snow removal and is the main piece of equipment that is used to spray
approx 300 acres with herbicides and biostimulants for the Parks Division.
ALTERNATIVES CONSIDERED
Continue to use the 2000 Yamaha Grizzly and repair as needed.
ADVANTAGES OF APPROVAL
Maximize efficiency, minimize down time, proactive replacement of aging equipment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$16,000
FY22 FY23
151
CIP Project Fund
General Fund
PROJECT NUMBER
GF191
DEPARTMENT
PARKS
PROJECT NAME
UPGRADE SOFTBALL COMPLEX LIGHTING
FY19 FY20 Unscheduled
$1,000,000
DESCRIPTION OF PROJECT
Replace the current lights at the Softball Complex with appropriate stadium lights. Estimate provided by MUSCO, would be bid at
the time of construction. Existing lights have light spillage/pollution and cannot be “retro-fitted”.
ALTERNATIVES CONSIDERED
Keep existing lights
ADVANTAGES OF APPROVAL
The new lights can offer 50% less light spillage and glare and reduce energy costs by up to 50%. Additionally, upgraded lights could help to reduce
or eliminate complaints regarding light pollution.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Reduction in electrical use.
FUNDING SOURCES
100% General Fund, or fundraising by user groups - Cost estimates range from $750,000 to $825,000 in August 2012.
New
Replacement
Equipment
Project
FY21 FY22 FY23
152
CIP Project Fund
General Fund
PROJECT NUMBER
GF195
DEPARTMENT
PARKS
PROJECT NAME
TURF SWEEPER
FY19
$32,000
FY20 Unscheduled
$36,000
DESCRIPTION OF PROJECT
This would be used to maintain the 150+ acres of turf in the park inventory. This piece of equipment would be used extensively at
the new Sports Complex and other venues on the west side of town. ( Ex. Adam Bronken Sports Complex and Oak Springs
Park.) An efficient coring aerator is productive and coincides with water conservation efforts and safe playing athletic fields.
ALTERNATIVES CONSIDERED
Continue to operate with two aerators.
ADVANTAGES OF APPROVAL
Proactively and aggressively aerate parks and sports fields within the City to create safer and healthier turf that uses less water and attract
tournaments to Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
153
CIP Project Fund
General Fund
PROJECT NUMBER
GF199
DEPARTMENT
FACILITY - PROF
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$37,031
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this growth, we need to remodel the Stiff Building. In FY16 the City Commission
approved Phase 1 of the remodel which will provide better use of existing space by relocating certain functions to the basement
and repurposing unused square footage. Approval of Phase II would allow the consolidation of Community Development
(Planning and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater)
together on another floor. This will allow better coordination of staff and better service to our public.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking
New
Replacement
Equipment
Project
FY21 FY22 FY23
154
CIP Project Fund
General Fund
PROJECT NUMBER
GF199
DEPARTMENT
I.T.
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$136,186
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this grow, we need to remodel the Stiff Building. In FY16 the City Commission
approved a Phase 1 of the remodel that will provide a better use of existing space by relocating certain functions to the basement
and reclaiming unused square footage. Approval of Phase II would allow the consolidation of Community Development (Planning
and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater) together
on another floor. This will allow better coordination of staff and better service to our public. Phase 1 is anticipated to be
completed late spring of 2016.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking
New
Replacement
Equipment
Project
FY21 FY22 FY23
155
CIP Project Fund
General Fund
PROJECT NUMBER
GF205
DEPARTMENT
PARKS
PROJECT NAME
PROST PLAN UPDATE
FY19
$109,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Update the 2007 Parks Recreation Open Space Trail (PROST) Plan. The current plan is now 10 years old. Since adoption, the city
has grown in size, new park properties have come into the system, and local demographics have changed. This project anticipates
hiring an outside party to update the Plan that will take into consideration the updated Community Plan.
ALTERNATIVES CONSIDERED
Do not update the plan.
ADVANTAGES OF APPROVAL
The update would record and reference new and accurate information that has been developing over the last 10 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
156
CIP Project Fund
General Fund
PROJECT NUMBER
GF209
DEPARTMENT
RECREATION
PROJECT NAME
LINDLEY CENTER FULL UPGRADE: RESTROOMS, WINDOWS, SIDING, KITCHEN, ROOF, FLOOR
FY19 FY20
$224,277
Unscheduled
DESCRIPTION OF PROJECT
This project is the combination of requests for upgrade of the Restrooms ($56,650), Window Replacement ($24,926), Siding
Replacement ($27,192), Kitchen Upgrade ($56,650), East Roof Insulation ($27,192), Floor support ($14,389), Roof support
($17,278) . This is a heavily used community center that could benefit from substantial improvements.
ALTERNATIVES CONSIDERED
As suggested by the Commission
ADVANTAGES OF APPROVAL
1. Brings restroom up to current ADA requirements; 2. Brings restroom up to current City of Bozeman building codes; 3. Improves sanitation in
the restrooms and kitchen facilities; 4. Rehabs and secures the building envelope for years to come; 5. Reduced energy consumption from
improved windows and insulation. 6. Addresses deficiencies that were identified in the 2014 structural analysis and 2012 facility condition
inventory.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
157
CIP Project Fund
General Fund
PROJECT NUMBER
GF219
DEPARTMENT
FACILITY - CH
PROJECT NAME
ADDITION TO CITY HALL, CONSOLIDATION OF SERVICES
FY19 FY20 Unscheduled
$5,500,000
DESCRIPTION OF PROJECT
This project would relocate the functions currently housed in the Stiff Building (Community Development/Engineering/IT/Building
Inspection) into an expansion of City Hall on Lamme Street.
ALTERNATIVES CONSIDERED
Keep operations at the Stiff Building.
ADVANTAGES OF APPROVAL
Centralizing more services in one location at City Hall will improve efficiency of staff and make it easier for citizens to conduct business with the
City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The new facility should have lower operating costs than the Stiff Building.
FUNDING SOURCES
Potential Funding Sources include: General Fund, Enterprise Fund (for public works), Building Inspection Fund (Building Inspection Division), sale
of the Stiff Building. This is a very rough estimate, based on building square footage and current construction costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
158
CIP Project Fund
General Fund
PROJECT NUMBER
GF224
DEPARTMENT
FINANCE
PROJECT NAME
SUNGARD ANALYTICS NOW COGNOS BI (BUSINESS INTELLIGENCE) WEB-BASED REPORTING
FY19
$35,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Web-based report authoring tool used to build sophisticated, multi-page, multi-query reports using data from SunGard. Seamlessly
integrates Microsoft Excel, enabling users to explore and analyze data in a familiar environment using skills they already have.
Includes enhanced e-mailing and report publishing capabilities, in addition to access by mobile devices including iPads & iPhones.
ALTERNATIVES CONSIDERED
Continue to use SunGard QREP product, which requires a higher level of training and expertise for end-users. QREP is no longer being
developed/enhanced and IBM software support is scheduled to end on April 30, 2018
ADVANTAGES OF APPROVAL
An increased ability to push more big data out to a bigger audience and to empower novice users to collect and analyze the tremendous amount
of data in SunGard.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Ongoing annual maintenance cost = $3,280
FUNDING SOURCES
General Fund, although enterprise funds would continue to be big users, especially GIS
New
Replacement
Equipment
Project
FY21 FY22 FY23
159
CIP Project Fund
General Fund
PROJECT NUMBER
GF227
DEPARTMENT
FINANCE
PROJECT NAME
ERP REPLACEMENT / UPGRADE "SUNGARD REPLACEMENT / UPGRADE"
FY19 FY20 Unscheduled
$333,333
DESCRIPTION OF PROJECT
Replacing/upgrading the current system installed in 1999. This is the system that runs all the financial, community development,
land records, utility and business license applications. Although it is unscheduled we are currently looking into this with a
possibility of FY20.
ALTERNATIVES CONSIDERED
Continue running current SunGard package. Use SunGard.net (NaviLine EDGE) as an improvement to the current system, but not a full
replacement.
ADVANTAGES OF APPROVAL
Simplified package. Easier to integrate the various applications/programs. Easier to pull out information for end users. Easier compilation of
Commission reports and packets for Community Development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown. Dependent on the option chosen.
FUNDING SOURCES
General Fund 33%; Water Fund 33%; Wastewater Fund 33%
New
Replacement
Equipment
Project
FY21 FY22 FY23
160
CIP Project Fund
General Fund
PROJECT NUMBER
GF229
DEPARTMENT
I.T.
PROJECT NAME
ISCSI STORAGE REPLACEMENT
FY19
$45,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
All of the virtual servers that reside at these two buildings use these devices as their storage device. These are critical pieces of
infrastructure.
ALTERNATIVES CONSIDERED
Don't replace for one more year.
ADVANTAGES OF APPROVAL
Allows us to keep our critical pieces of infrastructure running well and under warranty.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
161
CIP Project Fund
General Fund
PROJECT NUMBER
GF231
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY IRRIGATION PROJECT
FY19
$682,859
FY20 Unscheduled
DESCRIPTION OF PROJECT
Phased Project to move irrigation of cemetery and park lands off treated municipal supply onto raw surface supply previously
decreed to irrigate cemetery lands from the Story Mill Ditch .The planned improvements dramatically reduces the amount of man
hours required to monitor watering during season. Improved irrigation system reduces/eliminates water loss and water is applied
in the most efficient manner maximizing the use of the resource. FY 17: Phase II Design for Irrigation of Cemetery Lands • Inlet
structure and piping • Pump house • Main and laterals • Electrical • Irrigation System Components. FY 18:* Phase III Installation of
Diversion Works Project to Cemetery Lands. FY 19:* Phase IV Extension to Haggerty Fields •Design •Installation.
ALTERNATIVES CONSIDERED
Continue to use treated water for cemetery land irrigation.
ADVANTAGES OF APPROVAL
The Parks & Rec Department would no longer pay for large quantities of treated water for irrigation. It protects and preserves the City’s most
valuable decreed surface water right and makes available for sale treated water that would otherwise have irrigated the cemetery. The treated
water that is no longer applied to the cemetery and parks irrigation would be available for sale to new water customers enabling future growth
and/or improving the reliability of the City’s water supplies for use in times of drought. Makes available approximately 258 AF of treated water,
valued at $1,548,000.00 available for retail sale for approximately 1,121 SF homes or 2,080 MF homes. increases the reliability of domestic water
supplies in times of drought.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Pump replacement. It is yet to be determined what additional operations and maintenance costs would be associated with the project during FY
19-21 at this time. This is due to the fact that the feasibility study that will be completed in FY 17 and will identify various alternatives and costs
of each alternative will inform future operations and maintenance costs during FY 19-21. Upon completion of the feasibility study, an alternative
will be selected and projected operations and maintenance costs can be included into the CIP for FY 19-21.
FUNDING SOURCES
General Fund. This project started in Fy18 with 200K. *If awarded, grant funding through the Bureau of Reclamation’s WaterSMART Program
would offset total project costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
162
CIP Project Fund
General Fund
PROJECT NUMBER
GF233
DEPARTMENT
I.T.
PROJECT NAME
VEHICLE REPLACEMENT
FY19 FY20 Unscheduled
$83,000
DESCRIPTION OF PROJECT
Replacement of IT Vehicles. If our current vehicle is still running well and maintenance costs are not high, we would keep them
beyond what is shown here. 2005 Chevy Colorado with 38K 1999 Dodge Truck with 107K 1999 Jeep Cherokee with 74K 1995
Dodge Truck with 67K
ALTERNATIVES CONSIDERED
Buy new or Do nothing.
ADVANTAGES OF APPROVAL
Provide functional transportation with reduced maintenance costs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
$23,000
163
CIP Project Fund
General Fund
PROJECT NUMBER
GF238
DEPARTMENT
RECREATION
PROJECT NAME
BOGERT POOL RENOVATION
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Bogert Pool is beginning to show its wear faster every year. This project would replace the coping around the pool that is
cracked in several areas and the pool gutters that are cracking, crumbling, and/or lifting from the pool edge. All of the leaks that
could be patched without digging up the bottom of the pool have been patched. There is minimal leaking in the return pipes to
the pool but we recommend repairing the leaks in the returning piping that were identified in May of 2015, before the pool is
blasted with sand or high pressure water, prepped, and resurfaced. The retaining wall is going to be replaced with a wrought iron
fence to allow more visibility to the facility at night and provide more structure, as the current wall is weakening. The sections of
the decking in front of the locker rooms have sunken over the years and will also be replaced. The Bogert Pool renovation or
replacement with an alternate water feature would be added to the Bond Initiative for the Indoor/Outdoor Aquatic Center.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
A new gutter system would mitigate entrapment issues caused by the current gutter system. The current gutters are disintegrating between the
gutter and the ledge of the pool where there gutter sits. Several gutter tiles need to be re-adhered to the pool ledge every spring and often
during the pool season. If a tile is still attached but loose, it can easily be pulled from the wall. Several of the gutter tiles have been replaced
through the years. In many places, a space was not left between the tiles. This doesn’t allow the water to flow into the gutter system for optimal
water circulation. The surface of the pool is currently being patched with hydraulic cement in areas where the plaster is coming up. A new
surface would work to protect the structure of the pool. Making these repairs to Bogert would extend the life of the pool for many years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional costs would be associated with these repairs.
FUNDING SOURCES
Bond
New
Replacement
Equipment
Project
FY21 FY22
$483,000
FY23
164
CIP Project Fund
General Fund
PROJECT NUMBER
GF241
DEPARTMENT
FACILITY - CH
PROJECT NAME
Replacement of City Hall AC Condensing Unit – Roof Top
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The roof-top air conditioning condensing unit at City Hall is original to the building (1980) and is reaching the end of its useful
service life. This unit is critical to the temperature control for all office and public areas at City Hall.
ALTERNATIVES CONSIDERED
Continue to maintain the current unit until parts and refrigerant are no longer available.
ADVANTAGES OF APPROVAL
Reduced maintenance, increased efficiency and improved operation.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
165
CIP Project Fund
General Fund
PROJECT NUMBER
GF245
DEPARTMENT
FACILITY - CH
PROJECT NAME
Energy Projects – City Hall
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
City Hall is a LEED-Silver certified building and is currently underperforming. A recent Energy Star Portfolio Manager review found
that City Hall scored a 30 on a scale of 1 to 100, indicating that the energy performance of the building has declined as equipment
has aged or been replaced, and spaces modified. Retro-commissioning improves efficiency of a building’s equipment and systems;
often resolving problems that occurred during design or construction, or those that develop over time. It is a system-wide
evaluation of opportunities to improve energy performance and occupant comfort. City Hall was first commissioned in 2008
following the remodel. Many issues were addressed at that time, but certain problems related to the heating hot water system
balance were not due to budget constraints. The commissioning report recommended replacement of 24 fin tube balancing valves
and control valves on unit heaters. These components are negatively impacting the operation and efficiency of heating and cooling
systems. Building Commissioning was again identified as a need in the 2014 McKinstry Investment Grade Audit. This project
addresses the mechanical upgrades first identified in the commissioning report from 2008 allowing for a retro-commission for the
building following the mechanical upgrades and AC Condensing Unit replacement.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Improved HVAC system operations and reduced utility costs, based on the known conditions, McKinstry estimates that commissioning would
save at least $2,400 per year. The occupants of the building should experience more even temperatures and improved building airflow and
ventilation. Additional savings may be possible, but not fully understood until all the recommended improvements are identified.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$75,000
FY22 FY23
166
CIP Project Fund
General Fund
PROJECT NUMBER
GF250
DEPARTMENT
PARKS
PROJECT NAME
Splash Pads
FY19 FY20
$225,000
Unscheduled
$190,000
DESCRIPTION OF PROJECT
There are two proposed Splash Pad Projects: 1, The installation Interactive Water Feature at the Story Mill Community Park 2.
The installation of a splash pad at the new sports complex.This plan will give the community two larger Splash Pads / Water
Features located in large Community Parks at different ends of the City. Story Mill Community Park in the East and Sports Park in
the West.
ALTERNATIVES CONSIDERED
Do not install splash pads.
ADVANTAGES OF APPROVAL
Can help reduce children’s fear of water. Adds community water features that have no admittance fee allowing people of all socio economic
status to enjoy a public aquatics amenity. Geographically separates two installations to best serve the entire community.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Some additional water costs and maintenance will be required. Additional maintenance is estimated at 0.2 FTE
FUNDING SOURCES
Numerous funding options include TOP Bond money, General Fund cash reserves, Park Improvement Grant money, or combining into an
Aquatics Bond vote.
New
Replacement
Equipment
Project
FY21 FY22
$240,000
FY23
167
CIP Project Fund
General Fund
PROJECT NUMBER
GF252
DEPARTMENT
CEMETERY
PROJECT NAME
CEMETERY COLUMBARIUM
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Adding an additional eighty niche each columbarium to the Sunset Hills Cemetery with the first one scheduled FY18. These two
additional columbariums would be installed within the same area as the existing columbariums. Currently, the second
columbarium is approximately 96% sold.
ALTERNATIVES CONSIDERED
Do not add any columbariums to the cemetery and cease or put on hold the program once the second columbarium is full.
ADVANTAGES OF APPROVAL
Continuation on a long standing cemetery service, along with ease and minimal maintenance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal if any.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$55,000
FY22 FY23
168
CIP Project Fund
General Fund
PROJECT NUMBER
GF260
DEPARTMENT
PARKS
PROJECT NAME
SPORTS COMPLEX - CONSTRUCTION OF 'PROJECT RELATED' COTTONWOOD ROAD AREA
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
As owner of the Sports Park property, the City is required to construct a number of street, water, and sewer improvements. In
approval of the Sports Park purchase, $1,778,000 was approved in TOP Bond funding for these infrastructure improvements:
Baxter Lane, Cottonwood Road, Durston/Cottonwood Intersection, Flanders Mill Road (including ditch), and Oak Street. We
estimate that the Bond Funding will not be sufficient to cover the Cottonwood Road (or Oak Street) improvements. We
anticipate needing to build the project-related portions of the Cottonwood Road street-related improvements with Arterial
& Collector District dollars. The related water and sewer-line improvements will need to come from the General Fund. Our
original cost estimates from the Spring of 2014 have been increased by 15% to estimate construction inflation costs.
ALTERNATIVES CONSIDERED
Delay the improvements.
ADVANTAGES OF APPROVAL
Proper construction of the adjacent street, water, and sewer improvements, in concert with our development regulations. Better access and
amenities for the Sports Park.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The City's Street Maintenance Funds will maintain the street surface, once constructed. The utilities will maintain the pipes once installed.
FUNDING SOURCES
GENERAL FUND.
New
Replacement
Equipment
Project
FY21
$364,000
FY22 FY23
169
CIP Project Fund
General Fund
PROJECT NUMBER
GF262
DEPARTMENT
POLICE
PROJECT NAME
POLICE K9
FY19 FY20 Unscheduled
$19,000
DESCRIPTION OF PROJECT
Police K9 (Canine dogs) are an integral tool for police operations. The department has two trained K9teams (handler and dog) for
operations that provide assistance with drug interdiction, search ability for suspects committing crimes in buildings or helping
locate and identify suspects that have left or fled a crime-scene. A trained K9 generally has a maximum of 7-8years where the dog
is healthy and capable of serving. One of two dogs deployed is likely have reached its operational timeline by FY21, while the
remaining K9 has another 7 years+ of operational capability. This cost includes full purchase, training of the new K9
handler(officer) and shipping/transport of the K9 to Bozeman.
ALTERNATIVES CONSIDERED
Not purchasing or training a K9 dog/team is an option, but not recommended.
ADVANTAGES OF APPROVAL
Continued ability to have K9 on-duty or available to investigate and secure prosecution of criminal activity in Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The operational costs of a K9 each year are part of existing budget considerations.
FUNDING SOURCES
Other funding sources may be available as FY23 gets closer.
New
Replacement
Equipment
Project
FY21
$17,000
FY22 FY23
170
CIP Project Fund
General Fund
PROJECT NUMBER
GF263
DEPARTMENT
POLICE
PROJECT NAME
LAW & JUSTICE CENTER
FY19
$10,000,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
GF050 for City only Justice Center did not pass and the original GF263 joint City and County Justice Center did not pass. This
project is still needed and the project is being placed in the plan as options are explored.
ALTERNATIVES CONSIDERED
Non-joint project with county but other City Department joint projects could be planned
ADVANTAGES OF APPROVAL
This has been a priority since 2008 and the issues noted in the past are still present and have increased.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance of an additional building
FUNDING SOURCES
Voter approved general obligation bond and other fundig will be explored
New
Replacement
Equipment
Project
FY21
$20,000,000
FY22 FY23
171
CIP Project Fund
General Fund
PROJECT NUMBER
GF263
DEPARTMENT
I.T.
PROJECT NAME
Police Video Evidence Storage and Backup
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
We are currently generating around 1 Terabyte of data per month with the in car video systems and will be out of space for
storage in the next 12-18 months. It is critical information that grows rapidly. We are trying to get ahead of the growth by
purchasing a 5 year solution out of the gate that can be expanded as needed into the future for growth and the possibility of body
cameras. The FY 22 amount relates to the increased storage needed related to body camera files.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Will allow us to continue to safely store, access and backup crucial evidentiary data without concern of running out of storage space.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund or Grant Money
New
Replacement
Equipment
Project
FY21 FY22
$40,000
FY23
172
CIP Project Fund
General Fund
PROJECT NUMBER
GF265
DEPARTMENT
I.T.
PROJECT NAME
GENERAL FUND SERVER REPLACEMENT
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Replacement of physical servers.
ALTERNATIVES CONSIDERED
Virtualize if possible instead of buying physical servers
ADVANTAGES OF APPROVAL
Keep our server infrastructure under warranty and in good working condition for required performance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$68,000
FY22 FY23
173
CIP Project Fund
General Fund
PROJECT NUMBER
GF268
DEPARTMENT
CEMETERY
PROJECT NAME
Southwest Montana Veteran's Cemetery
FY19
$88,000
FY20
$40,000
Unscheduled
$360,000
DESCRIPTION OF PROJECT
First phase of the Southwest Montana Veteran's Cemetery which includes design, earth work, sidewalks and retaining walls to
form the 'backbone' for the Veteran group to start fundraising. Phase two potentially could be the 5500 square foot stamped
concrete plaza and phase three could be the installation of the first columbarium. Phases 2 and 3 potentially be funded with a 50%
match from the veteran's groups for the concrete and the first columbarium.
ALTERNATIVES CONSIDERED
Reduce the City's capital input and rely on the various Veteran groups for the funding.
ADVANTAGES OF APPROVAL
A true veteran's cemetery will help the veteran's realize their benefits upon their death. Currently, there are over 70,000 veterans in southwest
Montana, who upon their death, would have to be interred in Helena or Laurel to realize the benefit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Future phasing might be required, depending on the fundraising capabilities of the various veteran group in southwest Montana.
FUNDING SOURCES
50% General Fund and funds from various veteran's groups.
New
Replacement
Equipment
Project
FY21
$45,000
FY22 FY23
174
CIP Project Fund
General Fund
PROJECT NUMBER
GF270
DEPARTMENT
PARKS
PROJECT NAME
Snow Plowing Vehicle
FY19
$65,000
FY20 Unscheduled
$75,000
DESCRIPTION OF PROJECT
The eventual replacement of the 1992 MT articulating tractor, which does the bulk of the sidewalk snow removal for the Parks
Division, encompassing over 20 miles of sidewalks and four routes to plow. The newest cost saving measure is to share the cost
of a vehicle with Streets. The advantage of the co-op is that Parks needs the vehicle in the winter for plowing and Streets in the
summer for right of way mowing. The Parks and Cemetery divisions are responsible for snow removal on the majority of
sidewalks, paths, accesses and trails that the City is responsible for. The addition of Oak Spring Park, Adam Bronken sidewalk and
the Bozeman Pond expansion has necessitated moving up the request for an additional snow removal vehicle into FY19 instead of
FY20.
ALTERNATIVES CONSIDERED
Repair and maintain the 1992 MT as needed.
ADVANTAGES OF APPROVAL
Less down time and maintenance/repair costs. A new MT tractor will be able to support more implements, less emissions and better fuel
economy, faster more efficient use of time which will be a factor with the expanding sidewalk and trail snow removal routes as more parks come
on board such as Bozeman Pond expansion, sports Complex and Story Mill Community Park.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs: better fuel economy and less emissions = less maintenance and operating costs.
FUNDING SOURCES
100% General Fund for Parks but cost share with Street Maintenance District
New
Replacement
Equipment
Project
FY21 FY22 FY23
175
CIP Project Fund
General Fund
PROJECT NUMBER
GF271
DEPARTMENT
FACILITY - CH
PROJECT NAME
City Hall New Parking Lot
FY19 FY20 Unscheduled
$250,000
DESCRIPTION OF PROJECT
Convert existing lot west of City Hall into a new parking lot.
ALTERNATIVES CONSIDERED
Continue to use the underutilized lot West of City Hall as a community garden.
ADVANTAGES OF APPROVAL
Parking at City Hall is very limited due to space constraints, this has an impact on City staff, the general public, and visiting guests. Additional
parking spaces in the West lot should take pressure off of street parking around City Hall as well as allow staff to parking in the same lot. This
will free up the East side parking lot for general public during normal business hours. A new lot will also provide a safer parking environment to
the public during large meetings that take place at City Hall after hours.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General annual cost for items such as: lamp replacement, line stripping, asphalt reseal, snow removal, and landscaping.
FUNDING SOURCES
General Fund or Downtown TIF District Funding
New
Replacement
Equipment
Project
FY21 FY22 FY23
176
CIP Project Fund
General Fund
PROJECT NUMBER
GF272
DEPARTMENT
FACILITY - CH
PROJECT NAME
Site Security upgrade - Building Locks
FY19
$15,000
FY20
$15,000
Unscheduled
DESCRIPTION OF PROJECT
Currently the City has approximately 64 Trilogy keyless access locks. Of the 64 units, 18 are wireless units. The remaining 46
hardwired units require physical access with a cable & laptop to make updates for staffing access changes. This project will upgrade
the hardwire units to wireless over a period of time.
ALTERNATIVES CONSIDERED
Continue as we currently operate.
ADVANTAGES OF APPROVAL
Moving to a wireless system means all updates can be performed using the City wide network. The advantages to this system is the better
utilization of staff hours by reducing the required man hours per access update. Depending on the access level required for a staff member, it
could mean accessing 50 individual locks for a single access change.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General maintenance cost, battery change-outs.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$15,000
FY22 FY23
177
CIP Project Fund
General Fund
PROJECT NUMBER
GF275
DEPARTMENT
ECONOMIC DEVELOPMENT
PROJECT NAME
Fiber Optic Conduit and Vaults
FY19
$25,000
FY20
$25,000
Unscheduled
$25,000
DESCRIPTION OF PROJECT
Future City conduit policy will drive the future investment in city owned conduit.
ALTERNATIVES CONSIDERED
Do nothing, reduce or increase CIP investment.
ADVANTAGES OF APPROVAL
Provides funding for the purchase of fiber conduit and vaults in furtherance of a future conduit policy
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Cost of design and installation
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$25,000
FY22
$25,000
FY23
$25,000
178
CIP Project Fund
General Fund
PROJECT NUMBER
GF278
DEPARTMENT
PARKS
PROJECT NAME
Griffin at Story Mill Park road improvement - .26 mile
FY19 FY20 Unscheduled
$260,000
DESCRIPTION OF PROJECT
This represents funding the City's 1/2 portion of the East Griffin Road construction as it abuts to Story Mill Community Park.
ALTERNATIVES CONSIDERED
Construction of a woonerf type road section (or alternative park type road). More accomodating to pedestrian traffic depending on future
development by the property owners adjacent south side E Griffin.
ADVANTAGES OF APPROVAL
Safe vehiclular an dpedestrian access to municpal facilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
179
CIP Project Fund
General Fund
PROJECT NUMBER
GF279
DEPARTMENT
PARKS
PROJECT NAME
Story Mill Road Improvement - .17 mile
FY19 FY20 Unscheduled
$170,000
DESCRIPTION OF PROJECT
This represents funding the City's 1/2 portion of the Story Mill Road construction as it abuts to Story Mill Community Park.
ALTERNATIVES CONSIDERED
No alternatives considered.
ADVANTAGES OF APPROVAL
Safe vehicular and pedestrian access to municipal facilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
180
CIP Project Fund
General Fund
PROJECT NUMBER
GF281
DEPARTMENT
PARKS
PROJECT NAME
Bozeman Pond Park & Aasheim ballfields road expansion - .17 mile & .09 mile
FY19 FY20 Unscheduled
$260,000
DESCRIPTION OF PROJECT
This represents funding the City's required portion of 1/2 necessary to build Fowler Road adjacent to Bozeman Pond Park
Expansion and Aasheim ballfields.
ALTERNATIVES CONSIDERED
Waiting to acquire the ROW at the intersection of Fowler and Babcock before constructing these road sections.
ADVANTAGES OF APPROVAL
Safe vehicular and pedestrian access to municipal parks.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
181
CIP Project Fund
General Fund
PROJECT NUMBER
GF282
DEPARTMENT
City Admin/ Sustainability
PROJECT NAME
City Hall Plug-in Hybrid Electric Vehicle
FY19
$33,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Bozeman City Hall is in need of an efficient vehicle for staff to conduct daily errands and to attend local and regional meetings. As
part of City Hall’s LEED certification, the building is equipped with a 120v outlet adjacent to the west parking lot for the purpose
of charging an electric vehicle. To demonstrate our commitment to efficiency and to lead by example, we would like to
incorporate Plug-in Hybrid Electric Vehicle (PHEV) technology into our fleet. PHEVs combine a gasoline with an electric motor
and a rechargeable battery. Unlike conventional hybrids, PHEVs can be plugged-in and recharged from an outlet, allowing them to
drive extended distances using just electricity before transitioning to gasoline. PHEVs offer an exceptional range and offer
enhanced reliability by operating on either electricity or gasoline. Currently, City Hall has a Chevy Tahoe with 124,658 and gets 15
MPG compared to an estimated 133 MPGe for a PHEV and a 640 mile driving range. City Hall staff generally borrow a hybrid
vehicle from Public Works for long distance travel, however, this has become increasingly challenging as our staff grows and the
hybrids are often unavailable. The budget includes $2,000 to designate a parking space at City Hall for EV charging.
ALTERNATIVES CONSIDERED
Leasing for $300 to $380 per month for three years instead of purchasing.
ADVANTAGES OF APPROVAL
Improved operational efficiency. Most days the vehicle would operate on electricity only, but offers the flexibility to travel long distances.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Periodic tire replacements and maintenance.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
182
CIP Project Fund
General Fund
PROJECT NUMBER
GF283
DEPARTMENT
City Clerk’s Office / Informational Technology
PROJECT NAME
Commission Room Technology Upgrade
FY19
$80,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This request is to replace the majority of outdated/broken/breaking technology and structurally-related elements including but not
limited to built-in microphones, live-streaming equipment, computer display equipment, audio/amps, equipment housing, City-
responsibility audio/visual room technology/equipment, etc.
ALTERNATIVES CONSIDERED
This will require substantial in-room activity and a number of elements depend on room/dais layout, if a larger remodel of the room is planned,
this should happen concurrently.
ADVANTAGES OF APPROVAL
The Commission Room is already outdated and many elements already do not work. This will increase technological options for both meetings
and general use, as well as prevent more significant issues are larger elements inherently break over time.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No substantial operating costs, only small changes/fixes when necessary.
FUNDING SOURCES
General Fund capital?
New
Replacement
Equipment
Project
FY21 FY22 FY23
183
CIP Project Fund
General Fund
PROJECT NUMBER
GF284
DEPARTMENT
City Clerk’s Office / Informational Technology
PROJECT NAME
Laserfiche Software Upgrade
FY19 FY20
$57,000
Unscheduled
$28,000
DESCRIPTION OF PROJECT
The FY19 request is to replace the majority of outdated/broken/breaking technology and structural-related elements including but
not limited to built-in microphones, live-streaming equipment, computer display equipment, audio/amps, equipment housing, City-
responsibility audio/visual room technology/equipment, etc. | The FY20 request is an upgrade to Laserfiche Avante, which is
needed to bring our digital records software to a more recent version, as well as incorporate in functionality including workflow
and forms, which can increase efficiencies across departments. The following years request is the estimated annual fee for the
software.
ALTERNATIVES CONSIDERED
The FY19 Commission Room technology upgrade will require substantial in-room activity and a number of elements depend on room/dais
layout, if a larger remodel of the room is planned, this should happen concurrently. | The FY20 Laserfiche upgrade could potentially happen a
year prior or later, depending on workload and City priorities and staff resources. A number of departments are anxious for the increased use
of the product.
ADVANTAGES OF APPROVAL
Regarding the FY19 tech upgrade, the Commission Room is already outdated and many elements already do not work. This will increase
technological options for both meetings and general use, as well as prevent more significant issues are larger elements inherently break over
time. | The FY20+ Laserfiche upgrade is a needed improvement, and while it will be a process to bring departments on board, it will both
increase staff efficiencies in record management (across all departments) but also citizen ease of access for public information.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No substantial operating costs for the FY19 Commission Room upgrade, only small changes/fixes when necessary. | The FY20+ Laserfiche
upgrade will require an annual software fee, estimated at $28,000 (incorporated in the above schedule).
FUNDING SOURCES
General Fund capital
New
Replacement
Equipment
Project
FY21
$28,000
FY22
$28,000
FY23
$28,000
184
CIP Project Fund
General Fund
PROJECT NUMBER
GF285
DEPARTMENT
Facilities/Library
PROJECT NAME
Library Exterior Door Operators/Closures Replacement
FY19
$12,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The automatic door operators at the library have been in operation for over ten years, due to the heavy traffic load on these door
they are showing wear. Issues with the operators can impact ADA performance and also not close fully when seals are in place.
Normal door closure will also be replaced at the same time.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increases the reliability of the building system
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$1200 per year, preventative maintenance cost General Fund
FUNDING SOURCES
Library has stated they have funds in Library depreciation fund that can be used for this project
New
Replacement
Equipment
Project
FY21 FY22 FY23
185
CIP Project Fund
General Fund
PROJECT NUMBER
GF287
DEPARTMENT
Human Resources
PROJECT NAME
Learning Management System
FY19
$25,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Enterprise solution for housing and administering employee training
ALTERNATIVES CONSIDERED
none
ADVANTAGES OF APPROVAL
Efficient and manageable training for employees in a variety of formats, improved training records
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$5,000 annual maintenance estimate
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
186
CIP Project Fund
General Fund
PROJECT NUMBER
GF288
DEPARTMENT
Human Resources
PROJECT NAME
Applicant Tracking System
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
System to electronically manage the recruitment process – from application to hire.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increased efficiency, accuracy, and applicant experience
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$5,000 estimate
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$30,000
FY22 FY23
187
CIP Project Fund
General Fund
PROJECT NUMBER
GF289
DEPARTMENT
I.T.
PROJECT NAME
Server Farm Software Upgrades
FY19 FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
Upgrading our VM farm and SQL Cluster to the newest versions for current and future compatibility
ALTERNATIVES CONSIDERED
Stay on our current versions until forced to upgrade
ADVANTAGES OF APPROVAL
Will keep the City current with supported versions of the operating systems and will allow us to support software that requires the newer
versions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund-Perhaps some enterprise funds to cover their use.
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$25,000
FY23
$25,000
188
CIP Project Fund
General Fund
PROJECT NUMBER
GF290
DEPARTMENT
Parks
PROJECT NAME
Irrigation System Replacements
FY19 FY20 Unscheduled
$425,000
DESCRIPTION OF PROJECT
Replacement of irrigation systems that are past their life cycle estimates. 40 years is the average life cycle of an irrigation system.
ALTERNATIVES CONSIDERED
Not replace the systems and fix on an “as needed” basis.
ADVANTAGES OF APPROVAL
Efficient water use, lower repair costs, compatibility with the new Centralized systems. Potentially coincide with transitioning the Softball
Complex and Lindley Park off of treated water (Complex) and on to surface water.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
189
CIP Project Fund
General Fund
PROJECT NUMBER
GF291
DEPARTMENT
Parks
PROJECT NAME
Pickleball Courts
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Install Pickleball courts in one of our city parks. One potential site would be Bogert Park Tennis Courts.
ALTERNATIVES CONSIDERED
Do not install Pickleball courts and continue to utilize Southside tennis courts.
ADVANTAGES OF APPROVAL
Separate the increasing number of Pickleball players from the tennis players. Dedicated space for a fast growing sport
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Resurfacing or re-painting in future years.
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$90,000
FY22 FY23
190
CIP Project Fund
General Fund
PROJECT NUMBER
GF292
DEPARTMENT
POLICE
PROJECT NAME
PATROL CAR AUXILIARY EQUIPMENT
FY19
$15,000
FY20
$10,000
Unscheduled
$10,000
DESCRIPTION OF PROJECT
Within a patrol car is a significant amount of technology related auxiliary equipment. This includes a radar unit, Arbitrator Video
Recorder, Electronic ticketing printer, Mobile Data Computer amongst other items. Most of these items are part of a normal
replacement schedule as new patrol vehicles are purchased and old patrol vehicles retired. However, we are finding the need to
address several areas in this category separate from this rotation schedule. First, in FY19, we need to replace all electronic
ticketing printers, which were installed over 5 years ago, with full sized printers. This will allow for integration with our new
Records management system and will allow for the printing of tickets in the field that are easier to read, printing of forms or
“Marsy rights” notifications, etc… Secondly, we are finding that a Mobile Data Computer needs replacement about every 5 years,
and many of our vehicles are rotated at 6 or 7 years, meaning some additional MDC will be needed beyond what is part of a
vehicle rotation. And 3rd, we will be moving to a more portable MDC and docking stations over a 5 year period that makes the
ability for an officer to use the MDC outside of the vehicle, on calls and bringing it into buildings or our station to complete
reports. This direction will also lead to less desktop computers being purchased and increase officer efficiency.
ALTERNATIVES CONSIDERED
Alternatives are to continue to use existing MDC
ADVANTAGES OF APPROVAL
Less costs for desktop computers, less duplication of maintenance, more efficiency for officers, meaning officers more available for emergency
call response.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
$15,000
191
CIP Project Fund
General Fund
PROJECT NUMBER
GF293
DEPARTMENT
POLICE
PROJECT NAME
NON-PATROL CAR NEW VEHICLES
FY19 FY20
$15,000
Unscheduled
DESCRIPTION OF PROJECT
In FY20 and FY22 we anticipate adding two School Resource Officer Positions to cover the new Bozeman High School and
increased demand for police services at all schools.
ALTERNATIVES CONSIDERED
Alternatives may include use of older patrol cars that can’t be used for patrol response, or the use of existing marked units which will add
mileage to those vehicles and effect that rotation schedule.
ADVANTAGES OF APPROVAL
These vehicles tend to be used for more than 10 years and provide SRO ability to respond to the schools, other emergency and on-call
response after hours.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21 FY22
$15,000
FY23
192
CIP Project Fund
General Fund
PROJECT NUMBER
GF294
DEPARTMENT
POLICE
PROJECT NAME
PATROL CAR - ADDITIONAL
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
A review of mileage and estimated staffing increases in patrol by 2-3 officers over the next few years has also led to the identified
need for an additional patrol vehicle in FY21. This won’t replace a vehicle and brings the total patrol response vehicles to 23 (1
unmarked / 2 K9 vehicles / 20 fully marked)
ALTERNATIVES CONSIDERED
Continue patrol response with existing patrol cars, resulting in higher mileage/annum for each vehicle and difficulty at times to have sufficient
vehicles available for # of officers hired and deployed by FY21+)
ADVANTAGES OF APPROVAL
This is an essential vehicle for safe and reliable emergency response vehicles for patrol use, as well as projected lower annual maintenance costs.
This additional vehicle provides sufficient marked patrol cars for 24/7 response.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% General Fund
New
Replacement
Equipment
Project
FY21
$64,000
FY22 FY23
193
CIP Project Fund
General Fund
PROJECT NUMBER
GF295
DEPARTMENT
Recreation
PROJECT NAME
SWIM CENTER UV SYSTEM REPLACEMENT
FY19
$68,500
FY20 Unscheduled
DESCRIPTION OF PROJECT
A functioning UV system is critical when dealing with the high bather load that the swim center accommodates. The UV system
was installed in 2010. We are in line for a replacement considering the environment the electrical components are exposed to. If
we were able to construct a wall between the humid, corrosive environment and our electronics it is estimated that a UV unit
would last twice that long. Annually we are spending approximately four times the amount in repairs and maintenance compared
to units that are stored separately from an open water source and units that are more advanced since this unit was put it. The
Swim Center currently has such a high bather load that when the UV goes out in the winter months it is difficult and sometimes
impossible to keep our combined chlorine levels within the range outlined by the MT Health Code. It is a safety issue for the
swimmers. Parts for this unit are not readily available. Control panels have a 6 week lead time to be replaced and the electrical
components have to be shipped from Germany.
ALTERNATIVES CONSIDERED
Do not replace the current system.
ADVANTAGES OF APPROVAL
In addition to maintaining air quality, UV systems act as a secondary disinfectant to the chlorine, making the water cleaner and safer for
swimmers. A modern UV unit would be more energy efficient, and it would be easier to obtain parts for since UV systems are now standard
practice for pool sanitization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
194
CIP Project Fund
General Fund
PROJECT NUMBER
GF296
DEPARTMENT
Recreation
PROJECT NAME
SWIM CENTER – FRONT FURNACE REPLACEMENT
FY19 FY20
$36,000
Unscheduled
DESCRIPTION OF PROJECT
The front furnace supplies air to the lobby, locker rooms, and lifeguard room. The unit is deteriorating due to the humid
environment. Getting parts for the furnace is becoming increasingly difficult due to its age. The unit would be replaced with a unit
which are designed for aquatic environments or be placed outside. The current unit was installed in 2008.
ALTERNATIVES CONSIDERED
Continue to repair the unit.
ADVANTAGES OF APPROVAL
Replacing the current unit would cut down on costs to repair and service the unit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
195
CIP Project Fund
General Fund
PROJECT NUMBER
GF297
DEPARTMENT
RECREATION
PROJECT NAME
SWIM CENTER ROOF REPLACEMENT
FY19
$26,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The roof over the locker rooms/lobby area needs to be reroofed. The recommendation it to remove the existing Hypalon roof
membrane and Gypsum cover board. Replace any damaged insulation. Attach ½ inch layer of HD Polylso cover board on top of
the existing poly roof insulation on the entire surface that is being reroofed. Install a fully adhered Firestone 60 mil EPDM roof
system. Flash all walls, pipes, and penetrations with Firestone flashing material. Install new prefinished metal drip edge on the
outer perimeter and seal with a 5” flashing membrane.
ALTERNATIVES CONSIDERED
Do not replace the roof.
ADVANTAGES OF APPROVAL
Fix the roof before it becomes problematic.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
196
CIP Project Fund
General Fund
PROJECT NUMBER
GF298
DEPARTMENT
Recreation
PROJECT NAME
SWIM CENTER – BARRIER WALL IN PUMP ROOM
FY19
$22,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The pump room at the swim center contains an open filtration pit. The pump room also houses all of the equipment necessary to
operate the pool. The constant exposure to the chlorine and humidity from the open pit leads to accelerated deterioration of the
electrical and mechanical components on the boilers, UV system and programmable logic controller.
ALTERNATIVES CONSIDERED
Do not build the wall.
ADVANTAGES OF APPROVAL
Thousands of dollars are spent each year replacing parts due to rust and corrosion. It has been recommended to us by those who service our
equipment to build a barrier between the open water source and our equipment in order to help extend the life of the equipment and cut down
on money spent on parts and service.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
General Fund.
New
Replacement
Equipment
Project
FY21 FY22 FY23
197
CIP Project Fund
General Fund
PROJECT NUMBER
GF299
DEPARTMENT
RECREATION
PROJECT NAME
Vehicle Replacement
FY19 FY20
$30,000
Unscheduled
DESCRIPTION OF PROJECT
Replacement of a 1989 truck with a more dependable vehicle for Recreation Division staff.
ALTERNATIVES CONSIDERED
Not replacing the 1989 truck
ADVANTAGES OF APPROVAL
Having a reliable and safer vehicle for Recreation Division staff to utilize.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine maintenance
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
198
CIP Project Fund
General Fund
PROJECT NUMBER
GF300
DEPARTMENT
RECREATION
PROJECT NAME
Story Mill Community Center gymnasium floor replacement
FY19 FY20 Unscheduled
$110,000
DESCRIPTION OF PROJECT
Replacing the existing gymnasium floor with a wood floor that is more durable and conducive to multiple uses.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The current floor is made of brightly colored plastic tiles that include a large Boys and Girls Club logo in the middle. The former Boys and Girls
Club was used primarily for youth programs. The Story Mill Community Center will be home to Parks and Recreation Department programs for
people of all ages, large special events, and will also be utilized by community groups for sports leagues and events. There will be a significant
increase in use of the space and existing floor is not conducive to many of those uses, including pickleball, one of our most popular adult
programs. A wood gymnasium floor is the most durable and long lasting option.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Refinishing when needed
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
199
CIP Project Fund
General Fund
PROJECT NUMBER
GF301
DEPARTMENT
RECREATION
PROJECT NAME
Story Mansion Exterior Paint
FY19 FY20 Unscheduled
$50,000
DESCRIPTION OF PROJECT
Repainting the exterior of the Story Mansion
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
The exterior paint at the Story Mansion has started to fade and peel. As this continues, we risk compromising the siding which could need
replacement due to damage and would be a significantly more expensive project.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Repainting as needed
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
200
CIP Project Fund
General Fund
PROJECT NUMBER
GF302
DEPARTMENT
RECREATION
PROJECT NAME
Passenger Van
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
The purchase of a 12-15 passenger van for Parks and Recreation Department programs as well as other city departments use as
needed.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Our current passenger van can accommodate 13 children and 2 staff when used for programs. The majority of our programs have a max
capacity of 20 or more, which means multiple trips and additional staff support is required when transporting participants, or a lower max
number put on the program. Another van would better meet current needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine Maintenance
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$35,000
FY22 FY23
201
CIP Project Fund
General Fund
PROJECT NUMBER
GF303
DEPARTMENT
FACILITY - CH
PROJECT NAME
City Hall Expansion Remodel of Storage areas into Offices
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
With the additional planned FTE as the City grows City Hall's current storage areas can be remodeled into office spaces. The
space could potentially provide 2-3 offices spaces downstairs.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Any additional FTE in any of the Department in City Hall do not currently have space. This would provide space that is permenant.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine Maintenance and cleaning.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21
$25,000
FY22 FY23
202
CIP Project Fund
General Fund
PROJECT NUMBER
GF304
DEPARTMENT
FACILITY - CH
PROJECT NAME
City Hall Commission Room Expansion/Remodel
FY19 FY20
$300,000
Unscheduled
DESCRIPTION OF PROJECT
This will address security issues and provide an additional meeting room.
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Increases safety and provides the needed additional meeting room.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine Maintenance and cleaning.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY21 FY22 FY23
203
CIP Project Fund
General Fund
PROJECT NUMBER
GF305
DEPARTMENT
Fire
PROJECT NAME
Fire Station 2
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Fire Station 2, located at 410 S. 19th Ave, is a 1-story building that was constructed in 1974 to serve as the West end fire station
for the City of Bozeman. Due to growth of the city, this station now primarily serves what is the South side and Central parts of
the city. The station serves as the primary response station for all areas west of N. 7th Ave to the City limits that are South of
Durston Ave. This station is the primary response station for all of MSU campus and Bozeman High School and is the secondary
response to areas in the downtown core. General maintenance and repairs have been the majority of work completed on this
station since it’s opening. The department has continued to deal with a sewage problem on a reoccurring basis where the sewage
backs up into the living area of the station. Multiple plans have been implemented to addressed this but to date the problem still
occurs. Size and location are two factors that impede the service delivery of this station. Based on it’s location in relation to
campus and the downtown core this is the station where the fire department ladder truck should be housed, however the station
is too small to accommodate the ladder truck. In terms of location when station 2 was built N. 19th was a two lane road whereas
today it is a 4 lane major thoroughfare for the city. Leaving from and returning to the fire station can be an extremely difficult task
for fire crews during peak traffic hours. In September 2017 the Fire Master Plan update was presented with the
recommendation to relocate Fire Station 2 somewhere on MSU campus to improve response capabilities. This would require a
partnership with MSU but could have multiple benefits from an emergency planning standpoint. If a plan were to be developed
that relocated Fire Station 2 to MSU campus additional funds and planning should be evaluated for relocating the fire department
training facility to the same site, an additional recommendation from the recent Fire Master Plan.
ALTERNATIVES CONSIDERED
As recommended by Commission
ADVANTAGES OF APPROVAL
Addresses health and safety, space, and long term needs of fire station 2 for the next 25-30 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General operating cost which are currently budgeted in the fire department general fund budget.
FUNDING SOURCES
TBD
New
Replacement
Equipment
Project
FY21 FY22 FY23
$4,500,000
204
CIP Project Fund
General Fund
PROJECT NUMBER
GF306
DEPARTMENT
Fire
PROJECT NAME
Fire Station 1
FY19 FY20
$6,500,000
Unscheduled
DESCRIPTION OF PROJECT
Fire Station 1, located at 34 N. Rouse Ave, is a 2-story building with an ancillary fire tower attached to the building that was
constructed in 1965 to serve as the downtown fire station for the City of Bozeman as well as the administrative offices for the
Fire Department. The station serves as the primary response station for all areas east of N. 7th Ave to the City limits and is the
secondary response to areas primarily east of 19th Ave included all of MSU campus. Since its opening the station has been a
shared facility between police and fire with the police presences fluctuating over that period of time. Today the station houses
the support services functions of BPD which is comprised of a staff of 5 personnel and 1 Administrative Assistant. The station
also serves as an East annex for patrol officers who need to access a computer, paperwork, or restroom. A remodel was done in
1996 on the main level portions of the building currently used by the Police Department which added some exterior windows and
moved some of the interior walls. An addition to North Side of Fire Station 1 was completed in 2003, adding an additional office,
locker space for firefighter’s personal protective equipment, and a clean room were members could decontaminate themselves
and their equipment after returning from an emergency call. In 2011 a Heating Plan Replacement Assessment was conducted by
CTA Architects & Engineers to assess three different heating plant replacement options. The following is from the executive
summary of the report, the entire report can be found in Appendix A of this report. “The existing heating plant contains the
original steam boiler that currently serves the existing fire station. The boiler’s chemical treatment history has been erratic at
best. Consequently the boiler and steam piping has corroded severely over time and its overall condition can be considered as
poor. The boiler was originally sized to serve the fire station and the adjacent old City Hall building which included an intended
future addition. In 2010 the connection of the steam system to the old city hall was severed as a result of the building being sold.
With the extreme reduction of the steam load the existing steam boiler has experienced severe cycling. The continued short
cycling will inevitably lead to boiler failure”. To date now action has been taken on this study.In 2012 the Bozeman Facilities
Department partnered with Bechtle Architects to conduct a facilities condition inventory, Appendix B. In this report the
ALTERNATIVES CONSIDERED
As recommended by Commission
ADVANTAGES OF APPROVAL
Addresses structural, mechanically, health and safety, and space needs of fire station 1 for the next 25-30 years.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
General operating cost which are currently budgeting in the fire department general fund budget.
FUNDING SOURCES
TBD
New
Replacement
Equipment
Project
FY21 FY22 FY23
205
CIP Project Fund
General Fund
PROJECT NUMBER
PW05/06
DEPARTMENT
Parks and Facility Portion
PROJECT NAME
Public Works Shops Facility Plan and Construction
FY19
$10,000
FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
Develop a long term master plan for Public Works shop facilities, equipment, and personnel. This includes conducting a needs
assessment of space for existing and future employees, equipment, machinery, and rolling stock. There is a severe shortage of
enclosed storage for equipment, vehicles, and machinery, resulting in extra wear and tear, additional maintenance costs, and time
preparing the equipment on cold mornings.
ALTERNATIVES CONSIDERED
Continue using existing infrastructure.
ADVANTAGES OF APPROVAL
Provide an accurate analysis of the City of Bozeman Public Works space needs for both equipment as well as people.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Depending on the results of the plan, the likely result will be the construction of additional storage and office space.
FUNDING SOURCES
his project will be split 3 ways between Water Fund ($20,000), Wastewater Fund ($20,000), and Street Maintenance Fund ($20,000). With a
portion from the General Fund for Parks and Facility vehicle uses.
New
Replacement
Equipment
Project
FY21 FY22 FY23
206