HomeMy WebLinkAbout12-04-17 City Commission Packet Materials - C3. Parking CIP FY2019-2023
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Kristin Donald, Finance Director
SUBJECT: Adopt the Parking Fund Capital Improvement Plan (CIP) for Fiscal
Years 2019-2023.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 4, 2017
RECOMMENDATION: Adopt the Parking Fund Capital Improvement Plan (CIP) for
Fiscal Years 2019-2023.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th.
The Assistant City Manager and other city staff met in October & November to develop the
attached Capital Plan for the equipment and capital needs of the Parking Fund. The plan was
given at the Parking Commission’s meeting on November 9, 2017 where there was no quorum.
Item of Note:
P001 Willson Lot Redesign – While originally funded in FY17, we will not be
completing the project due to the timeframes related to its use as a construction staging
site. Instead, we have added the project back into the plan in FY19.
P017 Rouse Parking Lot redesign – This is planned to be funded in FY21
16
Revenue: Parking Revenues are unpredictable; a large portion of the funds (roughly
50%) comes from parking enforcement (ticket/fine) revenues. Parking operations do not
generate adequate revenues to fund capital replacement or expansion projects. The
Parking Fund must rely heavily on the Downtown Tax Increment Finance (TIF) District
to support its capital plan. The Downtown TIF is planning to contribute $1,000,000 to
Parking Capital between FY18-FY21.
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission does not
wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
Year Revenues Change
2011 427,272.00$
2012 395,914.00$ ‐7.3%
2013 431,128.00$ 8.9%
2014 619,319.00$ 43.7%
2015 584,593.00$ ‐5.6%
2016 647,708.63$ 10.8%
2017 788,713.00$ 21.8%
Average FY13‐ FY17 614,292.33$ 10.1%
640 ‐ Parking Fund Revenue history
17
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY19.
Report compiled on: November 22, 2017
Attached: Parking Fund CIP
18
Parking FundCapital Improvement PlanFinancial Summary Current YearFY18 FY19 FY20 FY21 FY22 FY23UnscheduledProjected Beginning Balance Dedicated to CIP 710,702$ 323,373$ 642,697$ 701,771$ 675,798$ 497,684$ Plus: Parking Revenues Dedicated to CIP43,835$ 46,027$ 48,329$ 50,745$ 53,282$ 55,946$ Cash In Lieu of Parking Plus: Parking Revenues Dedicated to Capital 43,835$ 48,329$ 50,745$ 53,282$ 53,604$ 53,604$ ‐$ Plus: Downtown TIF Interest Contribution 10,000$ 10,000$ 10,000$ 10,000$ 10,000$ 10,000$ Plus: TIF Contribution for parking lot redesign and improv. 250,000$ 300,000$ 280,000$ 170,000$ ‐$ ‐$ Plus: Grant funding for P024 27,000$ Less: Scheduled CIP Costs (adjusted) (735,000)$ (112,031)$ (330,000)$ (310,000)$ (295,000)$ (30,000)$ (1,900,000)$ Projected Year‐End Cash Dedicated to CIP 323,373$ 642,697$ 701,771$ 675,798$ 497,684$ 587,235$ Assumptions Made for Revenue Estimates:Current YearFY18 FY19 FY20 FY21 FY22 FY23Estimated Annual Parking Fund Revenues730,590$ 730,590$ 767,120$ 805,475$ 845,749$ 888,037$ Estimated Growth in Revenues0% 5% 5% 5% 5% 5%Total Estimated Revenues730,590$ 767,120$ 805,475$ 845,749$ 888,037$ 932,439$ Current Revenues Dedicated to CIP %0.0% 6.0% 6.0% 6.0% 6.0% 6.0% Plus: Increase Dedicated to Capital Improvements %6.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP6.0% 6.0% 6.0% 6.0% 6.0% 6.0%Total Estimated Revenues Dedicated to Capital43,835$ 46,027$ 48,329$ 50,745$ 53,282$ 55,946$ ProjectedProjectedCURRENT$(112,031)$(330,000)$(310,000)$(295,000)$(30,000)$(1,900,000)FY18 FY19 FY20 FY21 FY22 FY23 UNSCHEDULEDPARKING FUND CAPITAL PROJECTS 19
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22Parking FundGF199PARKINGPROFESSIONAL BUILDING RECONFIGURATION - PHASE 2$37,031P001PARKINGWILLSON LOT REDESIGN$300,000P004PARKINGSURFACE PARKING LOT HARDWARE & SOFTWARE SYSTEMS$15,000$15,000$15,000$15,000$15,000P012PARKINGARMORY LOT REDESIGN AND IMPROVEMENTS$250,000P014PARKINGPARKING GARAGE CRACK MAINTENANCE AND REPAIR$5,000$20,000$5,000$5,000$20,000P015PARKINGPARKING GARAGE ROOF PROJECT$400,000P016PARKINGPURCHASE OF PROPERTY FOR FUTURE PARKING FACILITIES IN THE DOWNTOWN PARKING DISTRICT.$1,500,000P017PARKINGROUSE PARKING LOT RE-DESIGN AND IMPROVEMENTS$280,000P020PARKINGPARKING VEHICLE LEASES$10,000$10,000$10,000$10,000$10,000P024PARKINGELECTRIC VEHICLE CHARGING STATION$30,000$30,000$112,031$330,000$310,000$295,000$1,900,000Totals by DEPARTMENTSummary for Parking Fund (10 items)Totals by year:$30,000$112,031$330,000$1,900,000FY23FY19FY20UnscheduledFY22$295,000$310,000FY2120
CIP Project Fund
Parking Fund
PROJECT NUMBER
GF199
DEPARTMENT
PARKING
PROJECT NAME
PROFESSIONAL BUILDING RECONFIGURATION - Phase 2
FY19
$37,031
FY20 Unscheduled
DESCRIPTION OF PROJECT
The City is responding to growth by adding staff to meet the increased demand for services in our community. We have also
reorganized divisions (Community Development) and created other divisions (Stormwater) to improve efficiency and better serve
our community. In order to accommodate this growth, we need to remodel the Stiff Building. In FY16 the City Commission
approved a Phase 1 of the remodel that will provide a better use of existing space by relocating certain functions to the basement
and reclaiming unused square footage. Approval of Phase II would allow the consolidation of Community Development (Planning
and Building) together on one floor and the consolidation of Public Works Services (Engineering, GIS and Stormwater) together
on another floor. This will allow better coordination of staff and better service to our public. Phase 1 is anticipated to be
completed late spring of 2016.
ALTERNATIVES CONSIDERED
Continue to operate as we are today
ADVANTAGES OF APPROVAL
Community Development would be able to consolidate its operations and services to allow for an integrated customer-focused service delivery
model. It will also provide Public Works with the ability to collocate its services in the Stiff Building. Finally it will help the City to take a planned
and efficient approach to building utilization and service optimization.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs anticipated for building reconfiguration.
FUNDING SOURCES
Building Inspection, Community Development, General Fund, and Parking
New
Replacement
Equipment
Project
FY21 FY22 FY23
21
CIP Project Fund
Parking Fund
PROJECT NUMBER
P001
DEPARTMENT
PARKING
PROJECT NAME
Willson Lot Redesign
FY19 FY20
$300,000
Unscheduled
DESCRIPTION OF PROJECT
Improve the parking lot layout, set-backs, landscaping, signage, lighting, required storm water treatment infrastructure
requirements and parking kiosk.
ALTERNATIVES CONSIDERED
Keep lot as is
ADVANTAGES OF APPROVAL
Improved functioning of parking lot
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
Parking Fund and TIF Contribution
New
Replacement
Equipment
Project
FY21 FY22 FY23
22
CIP Project Fund
Parking Fund
PROJECT NUMBER
P004
DEPARTMENT
PARKING
PROJECT NAME
Surface Parking Lot Hardware & Software Systems
FY19
$15,000
FY20
$15,000
Unscheduled
DESCRIPTION OF PROJECT
It is highly likely the Downtown Parking Lots will be transitioned to a fee lots. This will require the purchase and installation of
pay-and-display kiosks for each parking lot estimated to cost $60,000. The pads and vehicle protection will be installed as a part of
each surface lot’s redesign.
ALTERNATIVES CONSIDERED
Do not convert lots to pay lots; continue the current practice of permit holders and free 2-hour parking.
ADVANTAGES OF APPROVAL
Citizens using the surface lots will pay for the actual time they use the facilities. Revenue from parking charges can be used to support the
parking operations and fund additional parking assets. This equipment will improve the efficiency of parking officers monitoring parking rules in
the downtown.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minor operational costs.
FUNDING SOURCES
Parking Fund and TIF Contributions
New
Replacement
Equipment
Project
FY21
$15,000
FY22
$15,000
FY23
23
CIP Project Fund
Parking Fund
PROJECT NUMBER
P012
DEPARTMENT
PARKING
PROJECT NAME
Armory Lot Redesign and Improvements
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
This project is scheduled after the completion of the Etha Hotel construction project. Layout, set-backs, landscaping, signage,
lighting, sidewalks, and storm water treatment facilities are being planned.
ALTERNATIVES CONSIDERED
Keep the lot as is.
ADVANTAGES OF APPROVAL
Better functioning and safer parking lot layout. Will reduce a significant amount of untreated stormwater runoff. Increased revenue and parking
asset coordination through the implementation of pay kiosks.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
New asphalt will require less maintenance, but plantings and landscaping will require additional maintenance.
FUNDING SOURCES
Parking Fund and TIF Contributions - the Etha Hotel may also help fund these improvements.
New
Replacement
Equipment
Project
FY21 FY22
$250,000
FY23
24
CIP Project Fund
Parking Fund
PROJECT NUMBER
P014
DEPARTMENT
PARKING
PROJECT NAME
Parking Garage Crack Maintenance and Repair
FY19
$20,000
FY20
$5,000
Unscheduled
DESCRIPTION OF PROJECT
Includes laser measuring of deck gaps and routine repairs and patching of concrete deck surfaces. Structural gap repair is
anticipated every 3 years with routine caulking in between.
ALTERNATIVES CONSIDERED
Moving to an every other year gap maintenance or reducing the frequency of structural gap filling (not advised).
ADVANTAGES OF APPROVAL
Will extend the life of the parking garage deck surfaces.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Parking Fund
New
Replacement
Equipment
Project
FY21
$5,000
FY22
$20,000
FY23
25
CIP Project Fund
Parking Fund
PROJECT NUMBER
P015
DEPARTMENT
PARKING
PROJECT NAME
Parking Garage Roof Project
FY19 FY20 Unscheduled
$400,000
DESCRIPTION OF PROJECT
Construction in the downtown core has increased demand for parking space in the Garage. The demand for additional space is
anticipated with construction projects both planned and underway. The top floor of the garage has limited use during the winter
months as snow removal is difficult due to limited clearances. Installing a roof on the top floor would allow for maximum
utilization of the garage year around.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased utilization of the Parking Garage in all weather conditions.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Parking Fund and TIF Contributions
New
Replacement
Equipment
Project
FY21 FY22 FY23
26
CIP Project Fund
Parking Fund
PROJECT NUMBER
P016
DEPARTMENT
PARKING
PROJECT NAME
Purchase of property for future parking facilities in the Downtown Parking District.
FY19 FY20 Unscheduled
$1,500,000
DESCRIPTION OF PROJECT
The Downtown Strategic Parking Management Plan was adopted by the Parking omission and City Commission in July 2016. The
plan outlines 26 strategies to address current and future parking issue in the Downtown. Over the next year, the Parking
Commission will be working with city staff, downtown stakeholders and the community at large on next steps based on the
adopted plan. The acquisition and construction of future parking assets (surface and structured) is a fundamental component.
Costs and locations of those needed assets are not know, but our current Black (Carnegie) Parking lot was appraised at $1.5 M in
2011.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Adequate parking resources are critical for the economic health and vibrancy of the Downtown Bozeman.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Additional lot maintenance each year/season.
FUNDING SOURCES
Parking Fund, Bonds, TIF, Loans, SID
New
Replacement
Equipment
Project
FY21 FY22 FY23
27
CIP Project Fund
Parking Fund
PROJECT NUMBER
P017
DEPARTMENT
PARKING
PROJECT NAME
Rouse Parking Lot Re-design and Improvements
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Rouse Lot Improvements – Layout, set-backs, landscaping, signage, lighting, sidewalks, and stormwater treatment facilities. These
improvements are separate from any creek restoration project and will only involve the surface lot.
ALTERNATIVES CONSIDERED
Maintain current configuration.
ADVANTAGES OF APPROVAL
Better functioning and safer parking lot layout. Increased revenue and parking asset coordination through the implementation of pay kiosks.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
New asphalt will require less maintenance, but plantings and landscaping will require additional maintenance.
FUNDING SOURCES
Parking Fund, TIF contribution for lot improvements.
New
Replacement
Equipment
Project
FY21
$280,000
FY22 FY23
28
CIP Project Fund
Parking Fund
PROJECT NUMBER
P020
DEPARTMENT
PARKING
PROJECT NAME
Parking Vehicle Leases
FY19
$10,000
FY20
$10,000
Unscheduled
DESCRIPTION OF PROJECT
In the fall of 2016, the Parking Division transitioned from utilizing old Police vehicles to leased Prius hybrids. Initial indications are
that these vehicles will work exceptionally well for parking enforcement duties and will reduce the fuel consumption and
maintenance costs when compared to the retired patrol vehicles.
ALTERNATIVES CONSIDERED
Continue to use retired patrol vehicles, lease hybrid vehicles at $280/pm. 12,000 mile annual usage. Purchase new cars.
ADVANTAGES OF APPROVAL
Low cost vehicles that are suitable for the Parking Enforcement function; re-use of police vehicles once they are no longer suitable for first-
responder use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Anticipating maintenance requirements for used police vehicles is difficult at best as their age and condition were the primary reasons they were
replaced in the PD. Maintenance and operations for leased vehicles would be limited to oil changes and fuel costs and would be significantly
lower than the current fleet.
FUNDING SOURCES
Parking Fund
New
Replacement
Equipment
Project
FY21
$10,000
FY22
$10,000
FY23
29
CIP Project Fund
Parking Fund
PROJECT NUMBER
P024
DEPARTMENT
Parking
PROJECT NAME
Electric Vehicle Charging Station
FY19
$30,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
The Sustainability Coordinator is preparing a grant application to the Montana Department of Environmental Quality for federal
pass-thru grant funding, derived from the Volkswagen settlement, for the purchase and installation of one electric vehicle charging
station (EVCS) at the Bridger Park Downtown Garage. The EVCS will be positioned directly outside the parking office, inside the
parking garage, and will have the capability to charge two EV’s at once. The amount budgeted ($3,000) is a required 10% match
on the project.
ALTERNATIVES CONSIDERED
N/A
ADVANTAGES OF APPROVAL
Installation and operation of the EVCS will enhance the City of Bozeman’s ability to service multi-modal forms of transportation, and provide
additional support to local sustainability efforts.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Increased electric power costs for the parking garage, level of which is unknown at this time.
FUNDING SOURCES
Parking Services Fund (Operating). It is the intention of Majority of the funding is grant related with a 10% match. Thee parking fund will only be
required to contribute $3,000 of the $30,000 total cost.
New
Replacement
Equipment
Project
FY21 FY22 FY23
30