HomeMy WebLinkAboutResolution 4858 Adopting the Arterial & Collector Fund Capital Improvement Plan for FY2019-2023Arterial & Collector District Fund Capital Improvement Plan Financial Summary Current YearFY18 FY19 FY20 FY21 FY22 FY23UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 1,474,917$ 2,425,321$ 1,286,543$ 3,779,884$ 1,247,710$ 3,216,926$ Plus: Assessment Revenues Dedicated to CIP 1,806,513$ 1,128,643$ 1,151,216$ 1,208,777$ 1,269,216$ 1,345,369$ ‐$ Plus: Payback Revenue 221,891$ 600,579$ 591,792$ 361,049$ Plus: New Gas Tax dollars 200,000$ 700,000$ 700,000$ 700,000$ 700,000$ 700,000$ Plus: Developer contribution SIF105 and SIF 134 1,683,333$ Less: Scheduled CIP Project Costs (1,278,000)$ (3,568,000)$ (1,633,000)$ (4,802,000)$ ‐$ (5,250,000)$ (7,454,000)$ Projected Year‐End Cash Dedicated to CIP 2,425,321$ 1,286,543$ 3,779,884$ 1,247,710$ 3,216,926$ 12,294$ Beginning Balance of Payback Improvements: (2,544,666)$ (2,322,775)$ (1,855,196)$ (1,263,405)$ (1,402,356)$ (1,402,356)$ (1,402,356)$ SIF036 ‐ Payback DistrictSIF046 ‐ Gallatin County SIDSIF073 ‐ Payback District(404,000)$ SIF076 ‐ Payback District(500,000)$ SIF080 ‐ Gallatin County SID 378,688$ 369,901$ 361,049$ SIF080‐ Flanders Payback221,891$ 221,891$ 221,891$ SIF109 ‐ Gallatin County Payback/SID(133,000)$ SIF113 ‐ Payback District(666,667)$ SIF117 ‐ Payback District(83,333)$ SIF118 ‐ Payback District(750,000)$ SIF138‐ Payback District(333,333)$ Ending Balance of Payback Improvements: (2,322,775)$ (1,855,196)$ (1,263,405)$ (1,402,356)$ (1,402,356)$ (1,402,356)$ (1,806,356)$ Assumptions Made for Revenue Estimates Current YearFY18FY19FY20FY21 FY22 FY23Estimated Annual Assessment Revenues* 1,095,000$ 1,106,513$ 1,128,643$ 1,151,216$ 1,208,777$ 1,269,216$ Estimated Annual Increase 65.0%2% 2% 5% 5% 6%Total Estimated Revenues 1,806,513$ 1,128,643$ 1,151,216$ 1,208,777$ 1,269,216$ 1,345,369$ Current Revenues Dedicated to CIP % 100.0%100.0%100.0%100.0%100.0%100.0% Plus: Increase Dedicated to CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 100.0%100.0%100.0%100.0%100.0%100.0%Total Estimated Revenues Dedicated to CIP 1,806,513$ 1,128,643$ 1,151,216$ 1,208,777$ 1,269,216$ 1,345,369$ * Assessment will decrease with increased Gas Tax FundingProjectedProjectedCURRENT$(1,633,000)$(4,802,000)$‐$(5,250,000)$(7,454,000)FY19 FY20 FY21 FY22FY23 UNSCHEDULEDARTERIAL & COLLECTOR PROJECTS
^
^
^^
^
^
^
^
^
^27thSIF128 & SIF129S 11thChurchS 3rdBridger
GriffinDavis
Main
Main
WillsonKagy HighlandRouse7th19th19th19thFowlerFergusonCottonwoodBaxter
I-90
Graf
Babcock
OakOak
Durston Peach
Main
Kagy
College
SIF123 & SIF116
SIF140 & SIF134
SIF098 SIF058
SIF136
SIF121
SIF063
SIF062
SIF137 & SIF105
SIF143 & SIF086 SIF110
SIF108
SIF111
SIF132 & SIF117SIF133 & SIF113
SIF109
Babcock
SIF009
SIF142
SIF141 & SIF138
SIF139 & SIF057
Durston
S 11thSIF076 & SIF114 & SIF127
SIF073
SIF118
A&C005 (FY20)A&C006 (FY21)Flanders MillA&C001 (Unscheduled)
A&C004 (FY19)
SIF85 (FY19)
This map was created by the City of Bozeman GIS Department on 11/7/17 and is intended for planning purposes only.
0 10.5 Mile
¯
^FY19
^FY20
^FY21
^FY22
^FY23
^Unscheduled
FY19
FY20
FY21
FY22
FY23
Unscheduled
A&C Project
FY19-23 Street Impact Fees + Arterial & Collector District
Approved Volume Increase
0 - 500
500 - 1500
1500 - 3000
3000 - 6000
6000 - 9000
Design Project
LOS - Restrictions
LOS - FY18-21 Improvements
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22Arterial & Collector StreetsSIF057Arterial & CollectorOAK (FLANDERS MILL TO RYUN SUN WAY) - CONSTRUCTION$500,000SIF058Arterial & CollectorOAK & N 27TH (INTERSECTION IMPROVEMENTS) - DESIGN & CONSTRUCTION$200,000SIF062Arterial & CollectorDURSTON (FOWLER TO FERGUSON) - CONSTRUCTION$760,000SIF063Arterial & CollectorFOWLER & BABCOCK (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$400,000SIF073Arterial & CollectorFOWLER & DURSTON (INTERSECTION IMPROVEMENTS) - CONSTRUCTION*$404,000SIF076Arterial & CollectorFOWLER CONNECTION (HUFFINE TO OAK) - DESIGN (INCLUDES 3 INTERSECTIONS)*$500,000SIF085Arterial & CollecBAXTER (7TH TO 19TH) - CONSTRUCTION$1,500,000SIF086Arterial & CollectorBAXTER & COTTONWOOD (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$500,000SIF106Arterial & CollectorTRANSPORTATION DEMAND MANAGEMENT CONTRACT$50,000SIF108Arterial & CollectorS 3RD AND GRAF (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$300,000SIF109Arterial & CollectorOAK (ROUSE THROUGH CANNERY DISTRICT) - CONSTRUCTION*$133,000SIF110Arterial & CollectorMANLEY & GRIFFIN (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$400,000SIF111Arterial & CollectorHIGHLAND (MAIN TO KAGY) - CONSTRUCTION & DESIGN$5,000,000SIF113Arterial & CollectorGRIFFIN (7TH TO ROUSE) - CONSTRUCTION*$2,000,000SIF114Arterial & CollectorFOWLER CONNECTION (HUFFINE TO OAK) - CONSTRUCTION$3,750,000SIF116Arterial & CollectorBRIDGER DR & STORY MILL RD (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$300,000
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22SIF117Arterial & CollectorSTORY MILL (GRIFFIN TO BRIDGER) - CONSTRUCTION*$250,000SIF118Arterial & CollectorBABCOCK (11TH AVE TO 19TH AVE) - CONSTRUCTION*$750,000SIF121Arterial & CollectorBAXTER & DAVIS (INTERSECTION IMPROVEMENTS) - ROUNDABOUT CONSTRUCTION$500,000SIF134Arterial & CollectorOAK (COTTONWOOD TO FLANDERS MILL) - CONSTRUCTION$433,000SIF138Arterial & CollectorCOTTONWOOD ROAD, OAK TO BAXTER - CONSTRUCTION*$1,000,000SIF142Arterial & CollectorDURSTON ROAD & N. 27TH (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$300,000$5,250,000$3,443,000$1,333,000$3,050,000$6,854,000Totals by DEPARTMENTArterial & Collector StreetsA&C001Arterial & Collector OAK MEDIAN CONSTRUCTION (7TH TO 19TH)$600,000A&C002Arterial & CollecMIOVISION TRAFFIC DATA SYSTEM$50,000A&C003Arterial & CollecTRAFFIC MODELING SOFTWARE$15,000A&C004Arterial & CollecOAK & 7TH RESTRIPING$60,000A&C005Arterial & Collector COLLEGE (8TH TO 19TH) - DESIGN RECONSTRUCTION$300,000A&C006Arterial & Collector COLLEGE (8TH TO 19TH) - RECONSTRUCTION$1,752,000$125,000$300,000$1,752,000$600,000Totals by DEPARTMENTSummary for Arterial & Collector Streets (28 items)Totals by year:$5,250,000$3,568,000$1,633,000$7,454,000FY23FY19FY20UnscheduledFY22$4,802,000FY21
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C001
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Oak Median Construction (7th to 19th)
FY19 FY20 Unscheduled
$600,000
DESCRIPTION OF PROJECT
Replace the two way left turn lane with a landscaped median on Oak St between 7th and 19th. This project will also add street
lights along the corridor.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
This project may be used to limit access for some of th eprivate driveways, but is primarily an aesthetic improvement.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C002
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Miovision Traffic data system
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Purchase of modern traffic counting devices to provide current data for the City's new Transportation Model
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Allows us to populate our new transportation model with best available data resulting in best possible information
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
na
FUNDING SOURCES
na
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C003
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Traffic Modeling Software
FY19
$15,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Traffic modeling guides many important decisions resulting in improved performance of the transportation network. This
software purchase will leverage considerable investments already in place (e.g., WTI & MDT modeling efforts). The model will
run alongside existing water and wastewater modeling packages to provide advanced understanding of current conditions,
including the impacts of future development.
ALTERNATIVES CONSIDERED
Use professional contracted services for modeling analysis.
ADVANTAGES OF APPROVAL
This software leverages previous investments in transportation modeling efforts while bringing maintenance responsibilities in-house.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual software maintenance costs are estimated to be under $2,500.
FUNDING SOURCES
N/A
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C004
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
Oak & 7th Restriping
FY19
$60,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Restripe the intersection of Oak and 7th.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C005
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
College (8th to 19th) - Design Reconstruction
FY19 FY20
$300,000
Unscheduled
DESCRIPTION OF PROJECT
RDesign College, from 19th to 8th, to an urban minor arterial standard. The street is already in a failing condition and continues
to function; however, eventually the street will become deteriorated to a point where it is unfeasible to maintain and keep open
to public use. This project will provide the design for a city standard street section, with ADA compliant pedestrian ramps,
pavement markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will eliminate
potholes and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion.
ALTERNATIVES CONSIDERED
Accept the current failing configuration
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Arterial & Collector 100%
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
A&C006
DEPARTMENT
Arterial & Collector Streets
PROJECT NAME
College (8th to 19th) - Reconstruction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Reconstruct College, from 19th to 8th, to an urban minor arterial standard. The street is already in a failing condition and
continues to function; however, eventually the street will become deteriorated to a point where it is unfeasible to maintain and
keep open to public use. This project will provide a city standard street section, with ADA compliant pedestrian ramps, pavement
markings, and signage which will improve pedestrian safety. Also, new asphalt and drainage improvements will eliminate potholes
and minimize ice buildup. ADA compliance and MS4 permit compliance will be met at completion.
ALTERNATIVES CONSIDERED
Accept the current failing configuration
ADVANTAGES OF APPROVAL
Enhances safety and drainage, preserves pavement
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Arterial & Collector 100%
New
Replacement
Equipment
Project
FY21
$1,752,000
FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF057
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak (Flanders Mill to Ryun Sun Way) - Construction
FY19 FY20
$500,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Flanders Mill to Ryun Sun Way, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to proceed until these
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. This project will complete an important east-west link between Ferguson and Cottonwood, and conformance with
the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak and Ferguson, Oak
Street - New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,300,000) the Arterial & Collector District ($500.000) and local participation. The Flander's Mill
development is expected to be a partner in the construction of the segments adjacent to their development.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF058
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak & N 27th (Intersection Improvements) - Design & Construction
FY19
$200,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Oak and N 27th. This intersection is currently 2-way stop controlled.
Replacing it with a signal will greatly increase its capacity. The level of service at this intersection has degraded to unacceptable
levels. Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. Other affected projects include Oak
Street corridor projects and North 27th Street improvements project.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Secure additional financing by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF062
DEPARTMENT
Arterial & Collector
PROJECT NAME
Durston (Fowler to Ferguson) - Construction
FY19
$760,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete Durston Rd, from Cottonwood to Fowler, to a three-lane urban minor arterial standard. This project directly increase
capacity by adding additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. Connectivity already exists at this location, it is capacity that is affected. With completion, conformance
with the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders.
Other affected projects include intersection improvements at Durston & Ferguson, Durston & Fowler, Durston & Flanders Mill.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($757,421) and the Arterial & Collector District ($757,421). A payback district may be created to
reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF063
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler & Babcock (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$400,000
DESCRIPTION OF PROJECT
Install a traffic signal, roundabout, or other adequate traffic control device at the intersection of Fowler and Babcock. This
intersection is currently 1-way stop controlled. Replacing it with a signal or roundabout will greatly increase its capacity. East-
west connectivity already exists at this location. North-south connectivity is still lacking. Peak hour level of service for
northbound traffic is degrading due to lack of north-south connectivity in the network. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. A Payback District or SID may be
created to leverage other stakeholders. Other affected projects include Fowler corridor improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,600,000) and the Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF073
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler & Durston (Intersection Improvements) - Construction*
FY19 FY20 Unscheduled
$404,000
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Fowler and Durston. This intersection is currently 1- way stop controlled.
Replacing it with a signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location.
North-south connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation
Master Plan will be attained at completion. Other affected projects include Fowler corridor street improvements.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Improves an imporant connecting element in the network.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,616,000) and the Arterial & Collector District ($404,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $404,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF076
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler Connection (Huffine to Oak) - Design (Includes 3 Intersections)*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Design Fowler from Huffine to Oak to an urban minor arterial standard, including three intersections. This project directly
increase capacity by adding additional travel lanes, dedicated bike lanes and sidewalks and making improvements to the
intersections. Future developments which impact this intersection area may not be allowed to proceed until improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. This project
completes an important north-south connection on the west side of town. With its completion, the Level of Service (LOS)
Standard (BMC) and conformance with the Transportation Master Plan will be attained. A Payback District or SID may be created
to leverage other stakeholders. Other affected projects include intersection improvements at Fowler and Durston and Fowler
and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will complete an important north-south connection, expand the capacity of our street network and improve safety for drivers and
pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($500,000) and the Arterial & Collector District ($500,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $500,000).
New
Replacement
Equipment
Project
FY21
$500,000
FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF085
DEPARTMENT
Arterial & Collector
PROJECT NAME
Baxter (7th to 19th) - Construction
FY19
$1,500,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Street Reconstruction
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded 100% by Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF086
DEPARTMENT
Arterial & Collector
PROJECT NAME
Baxter & Cottonwood (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection at Baxter and Cottonwood. This intersection is currently 1-way stop controlled. Replacing it with a
signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location. North-south
connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at completion. Other affected projects include Cottonwood corridor improvements and Baxter corridor
improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
$500,000
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF106
DEPARTMENT
Arterial & Collector
PROJECT NAME
Transportation Demand Management Contract
FY19
$50,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Explore the potential for reducing vehicle demand on the network at peak hours by flexible start times, work from home
incentives etc. This project is important because the funding available to increase capacity by building physical improvements to
the network is unlikely to ever be sufficient. This project supplements that effort by reducing overall demand on the network.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
May improve peak hour LOS in many locations by directly reducing demand
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Three-year commitment with Western Transportation Institute and MSU. FY17 was the first year of funding. FY18 & FY19 are the remaining
years. 33% Impact Fee, 33% Montana State University, 33% Western Transportation Institute
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF108
DEPARTMENT
Arterial & Collector
PROJECT NAME
S 3rd and Graf (Intersection Improvements) - Construction
FY19
$300,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at S 3rd and Graf. This is currently a stop controlled intersection. Installation of a roundabout
will directly increase capacity. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) will be attained at completion.
ALTERNATIVES CONSIDERED
Accept the existing level of service, create an SID for financing.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF109
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak (Rouse through Cannery District) - Construction*
FY19
$133,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of improving Oak from Rouse through the Cannery District to include curb, gutter, sidewalks, and a turning
lane to provide a complete arterial street standard. The Cannery District will be responsible for the cost of curb, gutter, and
sidewalk along their property frontage as well as the turn lane to access two drive accesses that allow a left turn movement from
Oak Street into the Cannery District. Future developments in this area may not be allowed to proceed until these improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Left turn traffic safety will be improved upon installation of left turn lanes. Pedestrian safety will be improved. Conformance with
the Transportation Master Plan will be attained with its completion. A payback District or SID may be created to leverage other
stakeholders. Cash-in-lieu of infrastructure is anticipated to be contributed from the Cannery District developer to cover the
cost of the left turn lanes needed for their drive accesses as well as the cost of curb, gutter, and sidewalk adjacent to their
property. Other affected projects include Oak Street Corridor improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians. There will be substantial
pedestrian traffic between the Fairgrounds and the Cannery District. Additionally, the traffic impact study for the Cannery District indicated the
need for left turn lanes for their drive accesses. As the City's transportation master plan identifies the need to upgrade the Oak Street Corridor
to an arterial standard, this is an opportunity to partner with the Cannery District developer to complete a portion of the Oak Street
improvements.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($133,000), the Arterial & Collector District ($133,000), and Developer share ($133,000). A
development payback district or SID may be created to reimburse the Arterial & Collector District for the County’s (project related) costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF110
DEPARTMENT
Arterial & Collector
PROJECT NAME
Manley & Griffin (Intersection Improvements) - Construction
FY19 FY20
$400,000
Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Manley & Griffin. This intersection is currently 1-way stop controlled. Replacing it with a
signal will greatly increase its capacity. Future developments which impact this intersection area may not be allowed to proceed
until improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained at
completion. A Payback District or SID may be created to leverage other stakeholders. Other affected projects include Griffin
corridor improvements.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Street Impact Fees ($1,600,000) and Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF111
DEPARTMENT
Arterial & Collector
PROJECT NAME
Highland (Main to Kagy) - Construction & Design
FY19 FY20 Unscheduled
$5,000,000
DESCRIPTION OF PROJECT
Upgrade Highland, from Main to Kagy. Future developments in this area may not be allowed to proceed until these improvements
are in place. This project directly increase capacity by adding additional lanes, dedicated bike lanes and sidewalks. Connectivity
already exists at this location, it is capacity that is affected. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at the completion of
the project. A payback District or SID may be created to leverage other stakeholders. Other affected projects include
Intersection improvements at Highland and Kagy, Highland and Ellis and Highland and Main Street.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs
FUNDING SOURCES
This project is funded by Street Impact Fees ($5,000,000) and the Arterial & Collector District ($5,000,000). A payback district may be
created to reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF113
DEPARTMENT
Arterial & Collector
PROJECT NAME
Griffin (7th to Rouse) - Construction*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construct W Griffin corridor improvements from N. 7th to Rouse to an urban minor arterial standard. Designed improvements
will improve LOS at the key intersections and will increase capacity in the corridor as a whole. Connectivity already exists at this
location, it is capacity which is being expanded. Future developments which impact this intersection area may not be allowed to
proceed until improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at the completion of this project. A Payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Griffin and 7th and Griffin and Rouse.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,500,000) and the Arterial & Collector District ($2,000,000). A development payback district or
SID may be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $2,000,000).
New
Replacement
Equipment
Project
FY21
$2,000,000
FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF114
DEPARTMENT
Arterial & Collector
PROJECT NAME
Fowler Connection (Huffine to Oak) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete the section of Fowler from Huffine to Oak. This project allows for extension of Fowler Avenue, which will directly
increase capacity, and it extends an important north-south corridor on the west side of the city. Future developments which
impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at
large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Conformance with the Transportation Master
Plan will be attained at the completion of this project. Other affected projects include intersection improvements on Fowler at
Huffine, Babcock, Durston and Oak.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Completes an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,750,000) and the Arterial & Collector District ($3,750,000). A Payback District or SID may be
created to reimburse the Arterial & Collector District for any local improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$3,750,000
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF116
DEPARTMENT
Arterial & Collector
PROJECT NAME
Bridger Dr & Story Mill Rd (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Bridger and Story Mill. Adding additional phases and improving geometry will increase
capacity for deficient movements at this intersection. Future developments which impact this intersection area may not be
allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at completion. Other
affected projects include Story Mill, Griffin to Bridger Drive.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000). An SID or payback district may
be created to recover the local share.
New
Replacement
Equipment
Project
FY21
$300,000
FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF117
DEPARTMENT
Arterial & Collector
PROJECT NAME
Story Mill (Griffin to Bridger) - Construction*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve Story Mill from Griffin to Bridger. This project directly increases capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback District or SID
may be created to leverage other stakeholders. Other affected projects include intersection improvements to Story Mill and
Bridger Drive.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Improves an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($250,000) and the Arterial & Collector District ($250,000). An SID or payback district may be
created to recover the local share.
New
Replacement
Equipment
Project
FY21
$250,000
FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF118
DEPARTMENT
Arterial & Collector
PROJECT NAME
Babcock (11th Ave to 19th Ave) - Construction*
FY19 FY20 Unscheduled
$750,000
DESCRIPTION OF PROJECT
Construct the Babcock (11th to 19th) street upgrade. This project increases capacity directly by adding additional lanes, dedicated
bike lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback
District or SID may be created to leverage other stakeholders.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($750,000) and the Arterial & Collector District ($750,000). An SID or payback district may be
created to pay for some local share improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF121
DEPARTMENT
Arterial & Collector
PROJECT NAME
Baxter & Davis (Intersection Improvements) - Roundabout Construction
FY19
$500,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Install a roundabout at Baxter & Davis. This intersection is currently 4-way stop controlled. Replacing it with a roundabout will
greatly increase its capacity. Future developments in this area may not be allowed to proceed until these improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan and Level of Service Standard will be attained at completion. Other affected projects include
Baxter Lane Corridor Improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network, improve safety for drivers and pedestrians and increase capacity at this
intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF134
DEPARTMENT
Arterial & Collector
PROJECT NAME
Oak (Cottonwood to Flanders Mill) - Construction
FY19 FY20
$433,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Cottonwood to Flanders Mill, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks, and it completes an important east-west link between Ferguson and
Cottonwood. Future developments in this area may not be allowed to proceed until these improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan will be attained at completion. A payback District or SID may be created to leverage other
stakeholders. Other affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak
and Ferguson, Oak Street New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($434,000) and $430,000 for the local share adjacent to the City park, and an additional $430,000
from School District #7.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF138
DEPARTMENT
Arterial & Collector
PROJECT NAME
Cottonwood Road, Oak to Baxter - Construction*
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construction of a 5 lane Principal Arterial Street
ALTERNATIVES CONSIDERED
SID, Payback District, TOPS, incremental construction by adjacent developers.
ADVANTAGES OF APPROVAL
The project will expand the capacity and improve the connectivity of the city street network. It will improve safety for drivers and pedestrians
and improve access to the Sports Park. It will facilitate development currently occurring in this part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
The total project cost is $2.5M. $750k will come from Impact Fees, the remainder is the local share which will come from either TOPS money,
BSD 7 an SID or Payback of some sort or some combination of these.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$1,000,000
CIP Project Fund
Arterial & Collector Streets
PROJECT NUMBER
SIF142
DEPARTMENT
Arterial & Collector
PROJECT NAME
Durston Road & N. 27th (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$300,000
DESCRIPTION OF PROJECT
Installation of a roundabout or signal at the intersection of Durston Road and North 27th Avenue
ALTERNATIVES CONSIDERED
Accept the current level of service
ADVANTAGES OF APPROVAL
Increased capacity at this intersection
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Incremental increase in sweeping, plowing, painting and general maintenance
FUNDING SOURCES
Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23