HomeMy WebLinkAboutResolution 4859 Adopting the Street Impact Fee Fund Capital Improvement Plan for FY2019-2023Street Impact FeeCapital Improvement Plan Financial Summary Current YearFY18 FY19 FY20 FY21 FY22 FY23 UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 11,636,058$ 3,133,569$ 986,819$ (1,451,619)$ (2,492,178)$ 2,150,235$ Plus: Impact Fee Revenues Dedicated to CIP 4,025,000$ 4,226,250$ 4,437,563$ 4,659,441$ 4,892,413$ 5,137,033$ ‐$ Plus: Urban Funds: Less: Carryover FY17 Capital Projects (4,826,244)$ Less: Scheduled CIP Project Costs* (7,701,245)$ (6,373,000)$ (6,876,000)$ (5,700,000)$ (250,000)$ (7,250,000)$ (26,816,000)$ Projected Year‐End Cash Dedicated to CIP 3,133,569$ 986,819$ (1,451,619)$ (2,492,178)$ 2,150,235$ 37,268$ Assumptions Made for Revenue Estimates Current YearFY18FY19FY20FY21 FY22 FY23Estimated Annual Street Impact Fee Revenues** 4,025,000$ 4,025,000$ 4,226,250$ 4,437,563$ 4,659,441$ 4,892,413$ Estimated Annual Increase 0.0% 5% 5% 5% 5% 5%Total Estimated Revenues 4,025,000$ 4,226,250$ 4,437,563$ 4,659,441$ 4,892,413$ 5,137,033$ Current Revenues Dedicated to CIP % 100.0%100.0%100.0%100.0%100.0%100.0% Plus: Increase Dedicated to Street Capacity Expansion CIP0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP100.0%100.0%100.0%100.0%100.0%100.0%Total Estimated Revenues Dedicated to CIP 4,025,000$ 4,226,250$ 4,437,563$ 4,659,441$ 4,892,413$ 5,137,033$ *Note: This schedule no longer contains the portions of project coststhat will be paid by other sources, with the exception of FederalUrban Funds. See the "Funding Sources" discussion at the bottom of each project item sheet. **Using three year average for estimatesProjectedProjectedCURRENT$(6,373,000)$(6,876,000)$(5,700,000)$(250,000)$(7,250,000)$(26,816,000)FY18 FY19 FY20 FY21 FY22 FY23 UNSCHEDULEDSTREET IMPACT FEE PROJECTS
^
^
^^
^
^
^
^
^
^27thSIF128 & SIF129S 11thChurchS 3rdBridger
GriffinDavis
Main
Main
WillsonKagy HighlandRouse7th19th19th19thFowlerFergusonCottonwoodBaxter
I-90
Graf
Babcock
OakOak
Durston Peach
Main
Kagy
College
SIF123 & SIF116
SIF140 & SIF134
SIF098 SIF058
SIF136
SIF121
SIF063
SIF062
SIF137 & SIF105
SIF143 & SIF086 SIF110
SIF108
SIF111
SIF132 & SIF117SIF133 & SIF113
SIF109
Babcock
SIF009
SIF142
SIF141 & SIF138
SIF139 & SIF057
Durston
S 11thSIF076 & SIF114 & SIF127
SIF073
SIF118
A&C005 (FY20)A&C006 (FY21)Flanders MillA&C001 (Unscheduled)
A&C004 (FY19)
SIF85 (FY19)
This map was created by the City of Bozeman GIS Department on 11/7/17 and is intended for planning purposes only.
0 10.5 Mile
¯
^FY19
^FY20
^FY21
^FY22
^FY23
^Unscheduled
FY19
FY20
FY21
FY22
FY23
Unscheduled
A&C Project
FY19-23 Street Impact Fees + Arterial & Collector District
Approved Volume Increase
0 - 500
500 - 1500
1500 - 3000
3000 - 6000
6000 - 9000
Design Project
LOS - Restrictions
LOS - FY18-21 Improvements
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22Impact Fees StreetsSIF001Street Impact FANNUAL RIGHT OF WAY ACQUISITION$250,000$250,000$250,000$250,000$250,000SIF009Street Impact FeesKAGY (WILLSON TO 19TH) - CONSTRUCTION$8,000,000SIF057Street Impact FeesOAK (FLANDERS MILL TO RYUN SUN WAY) - CONSTRUCTION$1,000,000SIF058Street Impact FeesOAK & N 27TH (INTERSECTION IMPROVEMENTS) - DESIGN & CONSTRUCTION$800,000SIF062Street Impact FeesDURSTON (FOWLER TO FERGUSON) - CONSTRUCTION$760,000SIF063Street Impact FeesFOWLER & BABCOCK (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$1,600,000SIF073Street Impact FeesFOWLER & DURSTON (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$1,616,000SIF076Street Impact FeesFOWLER CONNECTION (HUFFINE TO OAK) - DESIGN (INCLUDES 3 INTERSECTIONS)$500,000SIF086Street Impact FeesBAXTER & COTTONWOOD (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$2,000,000SIF098Street Impact FeesOAK & COTTONWOOD (INTERSECTION IMPROVEMENTS) - ROUNDABOUT CONSTRUCTION$2,192,000SIF105Street Impact FeesCOTTONWOOD (DURSTON TO OAK) - CONSTRUCTION$1,250,000SIF108Street Impact FeesS 3RD AND GRAF (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$1,200,000SIF109Street Impact FeesOAK (ROUSE THROUGH CANNERY DISTRICT) - CONSTRUCTION$133,000SIF110Street Impact FeesMANLEY & GRIFFIN (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$1,600,000SIF111Street Impact FeesHIGHLAND (MAIN TO KAGY) - CONSTRUCTION & DESIGN$5,000,000SIF113Street Impact FGRIFFIN (7TH TO ROUSE) - CONSTRUCTION$3,500,000SIF114Street Impact FeesFOWLER CONNECTION (HUFFINE TO OAK) - CONSTRUCTION$3,750,000
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22SIF116Street Impact FeesBRIDGER DR & STORY MILL RD (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$1,200,000SIF117Street Impact FeesSTORY MILL (GRIFFIN TO BRIDGER) - CONSTRUCTION$250,000SIF118Street Impact FeesBABCOCK (11TH AVE TO 19TH AVE) - CONSTRUCTION$750,000SIF118Street Impact FeesBABCOCK (11TH AVE TO 19TH AVE) - DESIGN$250,000SIF121Street Impact FeesBAXTER & DAVIS (INTERSECTION IMPROVEMENTS) - ROUNDABOUT CONSTRUCTION$2,000,000SIF123Street Impact FeesBRIDGER DR & STORY MILL RD (INTERSECTION IMPROVEMENTS) - DESIGN$100,000SIF127Street Impact FFOWLER RIGHT OF WAY PURCHASE$1,000,000SIF128Street Impact FKAGY (WILLSON TO HIGHLAND) - DESIGN$500,000SIF129Street Impact FeesKAGY (WILLSON TO HIGHLAND) - CONSTRUCTION$6,000,000SIF132Street Impact FeesSTORY MILL (GRIFFIN TO BRIDGER) - DESIGN$50,000SIF133Street Impact FGRIFFIN (7TH TO ROUSE) - DESIGN$400,000SIF134Street Impact FeesOAK (COTTONWOOD TO FLANDERS MILL) - CONSTRUCTION$434,000SIF136Street Impact FeesBABCOCK WIDENING FERGUSON TO COTTONWOOD$900,000SIF137Street Impact FeesCOTTONWOOD (DURSTON TO OAK) - DESIGN$250,000SIF138Street Impact FeesCOTTONWOOD ROAD, OAK TO BAXTER - CONSTRUCTION$500,000SIF139Street Impact FeesOAK (FLANDERS MILL TO RYUN SUN WAY) - DESIGN$150,000SIF140Street Impact FeesOAK (COTTONWOOD TO FLANDERS MILL) - DESIGN$180,000SIF141Street Impact FeesCOTTONWOOD ROAD, OAK TO BAXTER - DESIGN$250,000
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY19UnscheduledFY23FY20FY21FY22SIF142Street Impact FeesDURSTON ROAD & N. 27TH (INTERSECTION IMPROVEMENTS) - CONSTRUCTION$1,200,000SIF143Street Impact FeesBAXTER & COTTONWOOD INTERSECTION - RIGHT OF WAY$750,000$7,250,000$6,373,000$6,876,000$5,700,000$250,000$26,816,000Totals by DEPARTMENTSummary for Impact Fees Streets (37 items)Totals by year:$7,250,000$6,373,000$6,876,000$26,816,000FY23FY19FY20UnscheduledFY22$250,000$5,700,000FY21
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF001
DEPARTMENT
Street Impact Fees
PROJECT NAME
Annual Right Of Way Acquisition
FY19
$250,000
FY20
$250,000
Unscheduled
DESCRIPTION OF PROJECT
Annual allocation available for right-of-way purchases as they become available. In all cases, the only reason additional R/W is
required is that the existing roadway is being expanded and capacity will be increased. Purchasing additional right-of-way may be
critical to connecting elements of the transportation network, and in doing so, conformance with the City Transportation Master
Plan can be obtained. Purchase of R/W is often a prerequisite for construction of the critical elements of the transportation
network. Other affected projects include all of the other street impact fee projects could potentially be affected by R/W
acquisition.
ALTERNATIVES CONSIDERED
Condemn property for right-of-way; pay court costs as well as appraised value of property. Time consuming for city staff and a relatively
expensive process. Wait for adjacent property owners to dedicate R/W as part of the annexation/development process.
ADVANTAGES OF APPROVAL
Provides dollars for the purchase of necessary right-of-way as it becomes available on the market. Avoids the expensive, antagonistic
condemnation process where possible or having to wait for voluntary dedications.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Street Impact Fees can not be spent on operating and maintaining facilities. There is expected to be a
very minimal, incremental cost to the Street Maintenance District from this expenditure.
FUNDING SOURCES
None
New
Replacement
Equipment
Project
FY21
$250,000
FY22
$250,000
FY23
$250,000
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF009
DEPARTMENT
Street Impact Fees
PROJECT NAME
Kagy (Willson to 19th) - Construction
FY19 FY20 Unscheduled
$8,000,000
DESCRIPTION OF PROJECT
This project consists of reconstructing Kagy Boulevard from the intersection of S 19th Ave to Willson Ave to a 4 lane urban
arterial standard. This project directly increase capacity by adding additional travel lanes, dedicated bike lanes and sidewalks and
making improvements to the intersections. Future developments which impact this intersection area may not be allowed to
proceed until improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. Kagy serves as an important element of Bozeman's perimeter street system connecting Highland Blvd.,
Willson Ave, and S. 19th. It also serves as the primary access to Montana State University and the University's major athletic
facilities. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained with
this project. Other affected projects include intersection Improvements at Kagy & 19th, Kagy & 7th, Kagy & 11th, Kagy & Willson.
ALTERNATIVES CONSIDERED
SID, Urban funds, incremental construction by adjacent development.
ADVANTAGES OF APPROVAL
Kagy is a State Urban Route and is eligible for expenditure of State urban funds designated annually for the City of Bozeman; however, the
availability of urban funds cannot match the pace of the City's transportation improvement needs. The need for this project comes from
increased traffic due to growth in the Bozeman area and the project is eligible for Impact Fee Funds. Use of Street Impact Funds enables the
community to leverage the available State Urban transportation funds to complete projects and address more of its pressing transportation
needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($8,000,000) and Urban Funds ($8,000,000). A Payback District or SID may be able to created to
leverage other stakeholders.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF057
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Flanders Mill to Ryun Sun Way) - Construction
FY19 FY20
$1,000,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Flanders Mill to Ryun Sun Way, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to proceed until these
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. This project will complete an important east-west link between Ferguson and Cottonwood, and conformance with
the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak and Ferguson, Oak
Street - New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,300,000) the Arterial & Collector District ($500.000) and local participation. The Flander's Mill
development is expected to be a partner in the construction of the segments adjacent to their development.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF058
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak & N 27th (Intersection Improvements) - Design & Construction
FY19
$800,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Oak and N 27th. This intersection is currently 2-way stop controlled.
Replacing it with a signal will greatly increase its capacity. The level of service at this intersection has degraded to unacceptable
levels. Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. Other affected projects include Oak
Street corridor projects and North 27th Street improvements project.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Secure additional financing by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF062
DEPARTMENT
Street Impact Fees
PROJECT NAME
Durston (Fowler to Ferguson) - Construction
FY19
$760,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete Durston Rd, from Cottonwood to Fowler, to a three-lane urban minor arterial standard. This project directly increase
capacity by adding additional lanes, dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to
proceed until these improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. Connectivity already exists at this location, it is capacity that is affected. With completion, conformance
with the Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders.
Other affected projects include intersection improvements at Durston & Ferguson, Durston & Fowler, Durston & Flanders Mill.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($757,421) and the Arterial & Collector District ($757,421). A payback district may be created to
reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF063
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler & Babcock (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$1,600,000
DESCRIPTION OF PROJECT
Install a traffic signal, roundabout, or other adequate traffic control device at the intersection of Fowler and Babcock. This
intersection is currently 1-way stop controlled. Replacing it with a signal or roundabout will greatly increase its capacity. East-
west connectivity already exists at this location. North-south connectivity is still lacking. Peak hour level of service for
northbound traffic is degrading due to lack of north-south connectivity in the network. The Level of Service (LOS) Standard
(BMC) and conformance with the Transportation Master Plan will be attained at completion. A Payback District or SID may be
created to leverage other stakeholders. Other affected projects include Fowler corridor improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,600,000) and the Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF073
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler & Durston (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$1,616,000
DESCRIPTION OF PROJECT
Improve the intersection control at the intersection of Fowler and Durston. This intersection is currently 1- way stop controlled.
Replacing it with a signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location.
North-south connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation
Master Plan will be attained at completion. Other affected projects include Fowler corridor street improvements.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Improves an imporant connecting element in the network.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,616,000) and the Arterial & Collector District ($404,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $404,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF076
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler Connection (Huffine to Oak) - Design (Includes 3 Intersections)
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Design Fowler from Huffine to Oak to an urban minor arterial standard, including three intersections. This project directly
increase capacity by adding additional travel lanes, dedicated bike lanes and sidewalks and making improvements to the
intersections. Future developments which impact this intersection area may not be allowed to proceed until improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. This project
completes an important north-south connection on the west side of town. With its completion, the Level of Service (LOS)
Standard (BMC) and conformance with the Transportation Master Plan will be attained. A Payback District or SID may be created
to leverage other stakeholders. Other affected projects include intersection improvements at Fowler and Durston and Fowler
and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will complete an important north-south connection, expand the capacity of our street network and improve safety for drivers and
pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($500,000) and the Arterial & Collector District ($500,000). A development payback district may
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $500,000).
New
Replacement
Equipment
Project
FY21
$500,000
FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF086
DEPARTMENT
Street Impact Fees
PROJECT NAME
Baxter & Cottonwood (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection at Baxter and Cottonwood. This intersection is currently 1-way stop controlled. Replacing it with a
signal or roundabout will greatly increase its capacity. East-west connectivity already exists at this location. North-south
connectivity is still lacking. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at completion. Other affected projects include Cottonwood corridor improvements and Baxter corridor
improvements.
ALTERNATIVES CONSIDERED
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic control device
when warrants are met.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
$2,000,000
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF098
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak & Cottonwood (Intersection Improvements) - Roundabout Construction
FY19 FY20
$2,192,000
Unscheduled
DESCRIPTION OF PROJECT
Installation of a roundabout at the intersection of Oak and Cottonwood. Capacity will be greatly increased on the network as a
whole as this intersection is currently 3-legged, rural and stop controlled on Cottonwood (Harper Puckett). This improvement
will complete an important north-south connection on Cottonwood. Functionality of the network at large is dependent on this
element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those
elements of the street network that are in place. The Level of Service (LOS) Standard (BMC) and conformance with the
Transportation Master Plan will be attained at completion. Other affected projects include Cottonwood Road Improvements and
Oak Street Improvements.
ALTERNATIVES CONSIDERED
Not installing the intersection improvement at the same time as the construction of the intersecting streets. Secure additional financing by
creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,192,000) and a local share ($548,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF105
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood (Durston to Oak) - Construction
FY19 FY20
$1,250,000
Unscheduled
DESCRIPTION OF PROJECT
Complete the construction of Cottonwood Road from Durston Road to Oak Street to a five-lane urban arterial standard. This
project increases capacity directly by adding additional lanes, dedicated bike lanes and sidewalks. Future developments which
impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at
large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Cottonwood Rd serves as an important element
in Bozeman's west side street system and serves as a primary north-south corridor on the west side of the city, and conformance
with the Transportation Master Plan will be attained with its completion. A Payback District or SID may be created to leverage
other stakeholders. Other affected projects include Cottonwood corridor street improvements, intersection improvements at
Cottonwood and Durston and Cottonwood and Oak.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
The total project cost is $2.5M. $1.5M will come from Impact Fees, the remainder is the local share which will come from either BSD 7, an SID
or Payback of some sort or some combination of these.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF108
DEPARTMENT
Street Impact Fees
PROJECT NAME
S 3rd and Graf (Intersection Improvements) - Construction
FY19
$1,200,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at S 3rd and Graf. This is currently a stop controlled intersection. Installation of a roundabout
will directly increase capacity. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) will be attained at completion.
ALTERNATIVES CONSIDERED
Accept the existing level of service, create an SID for financing.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF109
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Rouse through Cannery District) - Construction
FY19
$133,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project consists of improving Oak from Rouse through the Cannery District to include curb, gutter, sidewalks, and a turning
lane to provide a complete arterial street standard. The Cannery District will be responsible for the cost of curb, gutter, and
sidewalk along their property frontage as well as the turn lane to access two drive accesses that allow a left turn movement from
Oak Street into the Cannery District. Future developments in this area may not be allowed to proceed until these improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Left turn traffic safety will be improved upon installation of left turn lanes. Pedestrian safety will be improved. Conformance with
the Transportation Master Plan will be attained with its completion. A payback District or SID may be created to leverage other
stakeholders. Cash-in-lieu of infrastructure is anticipated to be contributed from the Cannery District developer to cover the
cost of the left turn lanes needed for their drive accesses as well as the cost of curb, gutter, and sidewalk adjacent to their
property. Other affected projects include Oak Street Corridor improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians. There will be substantial
pedestrian traffic between the Fairgrounds and the Cannery District. Additionally, the traffic impact study for the Cannery District indicated the
need for left turn lanes for their drive accesses. As the City's transportation master plan identifies the need to upgrade the Oak Street Corridor
to an arterial standard, this is an opportunity to partner with the Cannery District developer to complete a portion of the Oak Street
improvements.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($133,000), the Arterial & Collector District ($133,000), and Developer share ($133,000). A
development payback district or SID may be created to reimburse the Arterial & Collector District for the County’s (project related) costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF110
DEPARTMENT
Street Impact Fees
PROJECT NAME
Manley & Griffin (Intersection Improvements) - Construction
FY19 FY20
$1,600,000
Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Manley & Griffin. This intersection is currently 1-way stop controlled. Replacing it with a
signal will greatly increase its capacity. Future developments which impact this intersection area may not be allowed to proceed
until improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained at
completion. A Payback District or SID may be created to leverage other stakeholders. Other affected projects include Griffin
corridor improvements.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Street Impact Fees ($1,600,000) and Arterial & Collector District ($400,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF111
DEPARTMENT
Street Impact Fees
PROJECT NAME
Highland (Main to Kagy) - Construction & Design
FY19 FY20 Unscheduled
$5,000,000
DESCRIPTION OF PROJECT
Upgrade Highland, from Main to Kagy. Future developments in this area may not be allowed to proceed until these improvements
are in place. This project directly increase capacity by adding additional lanes, dedicated bike lanes and sidewalks. Connectivity
already exists at this location, it is capacity that is affected. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at the completion of
the project. A payback District or SID may be created to leverage other stakeholders. Other affected projects include
Intersection improvements at Highland and Kagy, Highland and Ellis and Highland and Main Street.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs
FUNDING SOURCES
This project is funded by Street Impact Fees ($5,000,000) and the Arterial & Collector District ($5,000,000). A payback district may be
created to reimburse both funds for any local share (project related) costs that may be allocated to future developments.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF113
DEPARTMENT
Street Impact Fees
PROJECT NAME
Griffin (7th to Rouse) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construct W Griffin corridor improvements from N. 7th to Rouse to an urban minor arterial standard. Designed improvements
will improve LOS at the key intersections and will increase capacity in the corridor as a whole. Connectivity already exists at this
location, it is capacity which is being expanded. Future developments which impact this intersection area may not be allowed to
proceed until improvements are in place. Functionality of the network at large is dependent on this element functioning as
intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street
network that are in place. The Level of Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will
be attained at the completion of this project. A Payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Griffin and 7th and Griffin and Rouse.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,500,000) and the Arterial & Collector District ($2,000,000). A development payback district or
SID may be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $2,000,000).
New
Replacement
Equipment
Project
FY21
$3,500,000
FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF114
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler Connection (Huffine to Oak) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Complete the section of Fowler from Huffine to Oak. This project allows for extension of Fowler Avenue, which will directly
increase capacity, and it extends an important north-south corridor on the west side of the city. Future developments which
impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at
large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Conformance with the Transportation Master
Plan will be attained at the completion of this project. Other affected projects include intersection improvements on Fowler at
Huffine, Babcock, Durston and Oak.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Completes an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($3,750,000) and the Arterial & Collector District ($3,750,000). A Payback District or SID may be
created to reimburse the Arterial & Collector District for any local improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$3,750,000
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF116
DEPARTMENT
Street Impact Fees
PROJECT NAME
Bridger Dr & Story Mill Rd (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve the intersection control at Bridger and Story Mill. Adding additional phases and improving geometry will increase
capacity for deficient movements at this intersection. Future developments which impact this intersection area may not be
allowed to proceed until improvements are in place. Functionality of the network at large is dependent on this element
functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary demand on those elements
of the street network that are in place. Conformance with the Transportation Master Plan will be attained at completion. Other
affected projects include Story Mill, Griffin to Bridger Drive.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,200,000) and the Arterial & Collector District ($300,000). An SID or payback district may
be created to recover the local share.
New
Replacement
Equipment
Project
FY21
$1,200,000
FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF117
DEPARTMENT
Street Impact Fees
PROJECT NAME
Story Mill (Griffin to Bridger) - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Improve Story Mill from Griffin to Bridger. This project directly increases capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback District or SID
may be created to leverage other stakeholders. Other affected projects include intersection improvements to Story Mill and
Bridger Drive.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Improves an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($250,000) and the Arterial & Collector District ($250,000). An SID or payback district may be
created to recover the local share.
New
Replacement
Equipment
Project
FY21
$250,000
FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF118
DEPARTMENT
Street Impact Fees
PROJECT NAME
Babcock (11th Ave to 19th Ave) - Construction
FY19 FY20 Unscheduled
$750,000
DESCRIPTION OF PROJECT
Construct the Babcock (11th to 19th) street upgrade. This project increases capacity directly by adding additional lanes, dedicated
bike lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback
District or SID may be created to leverage other stakeholders.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($750,000) and the Arterial & Collector District ($750,000). An SID or payback district may be
created to pay for some local share improvements.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF118
DEPARTMENT
Street Impact Fees
PROJECT NAME
Babcock (11th Ave to 19th Ave) - Design
FY19 FY20 Unscheduled
$250,000
DESCRIPTION OF PROJECT
Design the Babcock (11th to 19th) street upgrade. This project increases capacity directly by adding additional lanes, dedicated
bike lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until
improvements are in place. Functionality of the network at large is dependent on this element functioning as intended. The
incomplete transportation network in this vicinity is putting unnecessary demand on those elements of the street network that
are in place. Conformance with the Transportation Master Plan will be attained at the completion of this project. A Payback
District or SID may be created to leverage other stakeholders.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
100% Street Impact Fees. A payback district may be able to reimburse for design costs.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF121
DEPARTMENT
Street Impact Fees
PROJECT NAME
Baxter & Davis (Intersection Improvements) - Roundabout Construction
FY19
$2,000,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Install a roundabout at Baxter & Davis. This intersection is currently 4-way stop controlled. Replacing it with a roundabout will
greatly increase its capacity. Future developments in this area may not be allowed to proceed until these improvements are in
place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan and Level of Service Standard will be attained at completion. Other affected projects include
Baxter Lane Corridor Improvements.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network, improve safety for drivers and pedestrians and increase capacity at this
intersection. Facilitates development currently occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,000,000) and the Arterial & Collector District ($500,000).
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF123
DEPARTMENT
Street Impact Fees
PROJECT NAME
Bridger Dr & Story Mill Rd (Intersection Improvements) - Design
FY19 FY20
$100,000
Unscheduled
DESCRIPTION OF PROJECT
Design of Intersection improvements at the intersection of Story Mill and Bridger Drive.
ALTERNATIVES CONSIDERED
Accept the current LOS
ADVANTAGES OF APPROVAL
Increased capacity at this intersection. Facilitate development already occurring in this area
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF127
DEPARTMENT
Street Impact Fees
PROJECT NAME
Fowler Right of Way Purchase
FY19 FY20 Unscheduled
$1,000,000
DESCRIPTION OF PROJECT
Purchase the right of way on Fowler (Durston to Annie). This purchase allows for extension of Fowler Avenue, which will
directly increase capacity, and it extends an important north-south corridor on the west side of the City. Future developments
which impact this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network
at large is dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting
unnecessary demand on those elements of the street network that are in place. Other affected projects include Fowler corridor
improvements.
ALTERNATIVES CONSIDERED
Do nothing, wait for adjacent development to dedicate the R/W
ADVANTAGES OF APPROVAL
Allows for improvements to be made to the corridor at a time more favorable to the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
100% Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF128
DEPARTMENT
Street Impact Fees
PROJECT NAME
Kagy (Willson to Highland) - Design
FY19 FY20 Unscheduled
$500,000
DESCRIPTION OF PROJECT
Design Kagy, from Willson to Highland, including the intersections at Sourdough & Kagy and Highland & Kagy. This project
increases capacity directly by adding additional lanes, dedicated bike lanes and sidewalks and by improving intersection LOS.
Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. A Payback
District or SID may be created to leverage other stakeholders. Other affected projects include intersections at
Sourdough/Church and Highland.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Design is 100% impact fee eligible.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF129
DEPARTMENT
Street Impact Fees
PROJECT NAME
Kagy (Willson to Highland) - Construction
FY19 FY20 Unscheduled
$6,000,000
DESCRIPTION OF PROJECT
Complete Kagy, from Willson to Highland, including the intersections at Sourdough & Kagy and Highland & Kagy. This project
increases capacity directly by adding additional lanes, dedicated bike lanes and sidewalks and by improving intersection LOS.
Future developments which impact this intersection area may not be allowed to proceed until improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. The Level of
Service (LOS) Standard (BMC) and conformance with the Transportation Master Plan will be attained at completion. A Payback
District or SID may be created to leverage other stakeholders. Other affected projects include intersections at
Sourdough/Church and Highland.
ALTERNATIVES CONSIDERED
Wait for adjacent development to install the improvements section by section.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is eligible for Urban funds. A payback district or SID could be created to recover a portion of the local share.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF132
DEPARTMENT
Street Impact Fees
PROJECT NAME
Story Mill (Griffin to Bridger) - Design
FY19 FY20
$50,000
Unscheduled
DESCRIPTION OF PROJECT
Story Mill design from Griffin to Bridger. This project directly increases capacity by adding additional travel lanes, dedicated bike
lanes and sidewalks. Future developments which impact this intersection area may not be allowed to proceed until improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
Conformance with the Transportation Master Plan will be attained at completion. A Payback District or SID may be created to
leverage other stakeholders. Other affected projects include intersection improvements to Story Mill and Bridger Drive.
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and construct the road incrementally.
ADVANTAGES OF APPROVAL
Improves an important north-south link in the transportation network which reduces demand on other adjacent corridors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
Design is 100% impact fee eligible.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF133
DEPARTMENT
Street Impact Fees
PROJECT NAME
Griffin (7th to Rouse) - Design
FY19
$400,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design W Griffin corridor improvements from N. 7th to Rouse to an urban minor arterial standard. Designed improvements will
improve LOS at the key intersections and will increase capacity in the corridor as a whole. Future developments which impact
this intersection area may not be allowed to proceed until improvements are in place. Functionality of the network at large is
dependent on this element functioning as intended. The incomplete transportation network in this vicinity is putting unnecessary
demand on those elements of the street network that are in place. The Level of Service (LOS) Standard (BMC) and conformance
with the Transportation Master Plan will be attained at completion. A Payback District or SID may be created to leverage other
stakeholders. Other affected projects include intersection improvements at Griffin and 7th and Griffin and Rouse.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city and network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
Design is 100% impact fee eligible.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF134
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Cottonwood to Flanders Mill) - Construction
FY19 FY20
$434,000
Unscheduled
DESCRIPTION OF PROJECT
This project is the completion of the street segment of Oak St, from Cottonwood to Flanders Mill, to a five-lane urban principal
arterial standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding
additional lanes, dedicated bike lanes and sidewalks, and it completes an important east-west link between Ferguson and
Cottonwood. Future developments in this area may not be allowed to proceed until these improvements are in place.
Functionality of the network at large is dependent on this element functioning as intended. The incomplete transportation
network in this vicinity is putting unnecessary demand on those elements of the street network that are in place. Conformance
with the Transportation Master Plan will be attained at completion. A payback District or SID may be created to leverage other
stakeholders. Other affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak
and Ferguson, Oak Street New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($434,000) and $430,000 for the local share adjacent to the City park, and an additional $430,000
from School District #7.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF136
DEPARTMENT
Street Impact Fees
PROJECT NAME
Babcock Widening Ferguson to Cottonwood
FY19 FY20 Unscheduled
$900,000
DESCRIPTION OF PROJECT
Widen Babcock to a 3-lane collector standard per the section defined in the 2017 Transportation Master Plan.
ALTERNATIVES CONSIDERED
Developer funded street expansion per the former streets policy where the developers on the south side of Babcock will upgrade the street as
development proceeds.
ADVANTAGES OF APPROVAL
Coordinate upgrade of the entire street segment with development along the south side of Babcock and use a payback district to recover costs
from development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
The street already exists, and the street will be widened to add a center turn lane. Therefore additional striping and pavement maintenance will
be required for approximately 2,600 feet.
FUNDING SOURCES
Development funded improvement of the southern half of the street per the former streets policy under which the northern half of the street
improvement was constructed.
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF137
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood (Durston to Oak) - Design
FY19
$250,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design of 5 lane arterial in FY 19 to allow construction in FY20
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city as well as network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF138
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood Road, Oak to Baxter - Construction
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Construction of a 5 lane Principal Arterial Street
ALTERNATIVES CONSIDERED
SID, Payback District, TOPS, incremental construction by adjacent developers.
ADVANTAGES OF APPROVAL
The project will expand the capacity and improve the connectivity of the city street network. It will improve safety for drivers and pedestrians
and improve access to the Sports Park. It will facilitate development currently occurring in this part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
The total project cost is $2.5M. $750K will come from Impact Fees, the remainder is the local share which will come from either TOPS money,
BSD 7 an SID or Payback of some sort or some combination of these.
New
Replacement
Equipment
Project
FY21 FY22 FY23
$500,000
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF139
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Flanders Mill to Ryun Sun Way) - Design
FY19
$150,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design of 5 lane arterial in FY 19 to allow construction in FY20.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians. Facilitates development currently
occurring in this part of the city as well as network performance overall.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF140
DEPARTMENT
Street Impact Fees
PROJECT NAME
Oak (Cottonwood to Flanders Mill) - Design
FY19
$180,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
This project is to design the street segment of Oak St, from Cottonwood to Flanders Mill, to a five-lane urban principal arterial
standard. This project increases capacity directly by constructing new segments of arterial roadway and by adding additional lanes,
dedicated bike lanes and sidewalks. Future developments in this area may not be allowed to proceed until these improvements
are in place. Functionality of the network at large is dependent on this element functioning as intended. The incomplete
transportation network in this vicinity is putting unnecessary demand on those elements of the street network that are in place.
This project completes an important east-west link between Ferguson and Cottonwood, and conformance with the
Transportation Master Plan will be attained. A payback District or SID may be created to leverage other stakeholders. Other
affected projects include intersection improvements at Oak and Cottonwood, Oak and Flanders Mill, Oak and Ferguson, Oak
Street New Holland to Ferguson.
ALTERNATIVES CONSIDERED
Construct segment by segment as adjacent parcels develop.
ADVANTAGES OF APPROVAL
Increased capacity, connectivity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF141
DEPARTMENT
Street Impact Fees
PROJECT NAME
Cottonwood Road, Oak to Baxter - Design
FY19
$250,000
FY20 Unscheduled
DESCRIPTION OF PROJECT
Design a 5 lane Principal Arterial Street
ALTERNATIVES CONSIDERED
SID, Payback District, TOPS, incremental construction by adjacent developers.
ADVANTAGES OF APPROVAL
The project will expand the capacity and improve the connectivity of the city street network. It will improve safety for drivers and pedestrians
and improve access to the Sports Park. It will facilitate development currently occurring in this part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NA
FUNDING SOURCES
NA
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF142
DEPARTMENT
Street Impact Fees
PROJECT NAME
Durston Road & N. 27th (Intersection Improvements) - Construction
FY19 FY20 Unscheduled
$1,200,000
DESCRIPTION OF PROJECT
Installation of a roundabout or signal at the intersection of Durston Road and N. 27th
ALTERNATIVES CONSIDERED
Accept the current level of service
ADVANTAGES OF APPROVAL
Increased capacity at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Incremental increases in sweeping, plowing, painting and general maintenance costs
FUNDING SOURCES
Arterial and Collector funds
New
Replacement
Equipment
Project
FY21 FY22 FY23
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF143
DEPARTMENT
Street Impact Fees
PROJECT NAME
Baxter & Cottonwood Intersection - Right of Way
FY19 FY20 Unscheduled
DESCRIPTION OF PROJECT
Purchase of the right of way necessary for the construction of the Baxter & Cottonwood intersection improvments
ALTERNATIVES CONSIDERED
Do not construct intersection until ROW obtained
ADVANTAGES OF APPROVAL
This project will allow an intersection to built
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
100% Street Impact Fees
New
Replacement
Equipment
Project
FY21 FY22 FY23
$750,000
BOZEMAN, GREAT FALLS, KALISPELL & SHELBY, MT | SPOKANE, WA | LEWISTON, ID | WATFORD CITY, ND | MEDIA, PA
406.586.0277
tdhengineering.com
234 East Babcock Street
Suite 3
Bozeman, MT 59715
August 14, 2017
Rick Hixson, City Engineer
City of Bozeman Engineering Department
PO Box 1230
Bozeman, MT 59771
Email: rhixson@bozeman.net
RE: BOZEMAN SCHOOL DISTRICT, CAPITAL
IMPROVEMENTS PLAN PROJECT REQUEST
TD&H ENGINEERING JOB NO. B16-100
Dear Rick,
As you know, the Bozeman School District bond was passed earlier this year allowing for
construction of a new high school. The chosen location for the school is southeast of the
intersection between Cottonwood Road and Oak Street (Tract 1A2, COS 2554B and Tract
2A, COS 2554A). In order to facilitate access to the school, the following road
improvements are proposed with construction of the new high school.
x Construction of the east half of Cottonwood Road from its intersection with Durston
Road to Oak Street
x Construction of the full width of Oak Street from its intersection with Flanders Mill
Road to Cottonwood Road, including a pedestrian tunnel
x Construction of the Cottonwood Road and Oak Street intersection roundabout
The Bozeman School District is requesting these projects be placed on the 2019-2023
Capital Improvements Program (CIP) as scheduled projects. Currently, these projects are
on the 2018-2022 CIP as unscheduled projects.
City of Bozeman 2018-2022 CIP Summary
Project Description Arterial & Collector
District Fund Designation
Street Impact Fee
Designation
SIF 150
Cottonwood (Durston to
Oak) – Construction
$1,240,000 NA
SIF 134
Oak (Cottonwood to
Flanders Mill) – Construction
$250,000 $1,300,000
SIF 098
Oak & Cottonwood
(Intersection) – Roundabout
Construction
$548,000 $2,192,000
PAGE NO. 2
tdhengineering.com
AUGUST 14, 2017
The Bozeman School District is on an aggressive schedule to begin construction on the
above infrastructure in the spring of 2018 in order to provide access to the new high school
site, which will be adjacent to Oak Street and centered between Cottonwood Road and
Flanders Mill Road. We would appreciate the City and Impact Fee Advisory Committee
consider keeping these projects on the 2019 – 2023 CIP as well as upgrading them from
unscheduled to scheduled. Ideally, scheduling these projects for FY 2019 would be
preferred.
We believe these projects will greatly improve the flow and distribution of traffic in the
vicinity of the new high school and tie in perfectly with development of the Bozeman Sports
Park along with the other road improvement projects being constructed in the area
(Ferguson Avenue, Oak Street, Flanders Mill, Cottonwood Road). The combination of
these projects will create a safer and better functioning street network for City Residents.
We realized involvement from the School District during the CIP process and attendance at
Impact Fee Advisory meetings is critical to the success of these projects being scheduled
in the next CIP. We look forward to providing our input.
Please feel free to contact me or Todd Swinehart, Bozeman School District Facilities
Director, with any questions regarding the project and schedule.
Sincerely,
Kyle Scarr PE
Regional Manager
TD&H ENGINEERING
J:\2016\B16-100 Second Bozeman High School\DOCUMENTS\CORRESPONDENCE\8.14.17 BOZEMAN
HIGH SCHOOL CIP REQUEST.DOC
KKKKKKKKKKKKKKKKKK lllllllll S PE
$SULO
5LFN+L[VRQ3(
&LW\RI%R]HPDQ &LW\(QJLQHHU
(DVW2OLYH6WUHHW
%R]HPDQ0W
5( 2DN6WDQG
WK ,QWHUVHFWLRQ
'HDU0U+L[VRQ
:HKDYHEHHQZRUNLQJ&LW\6WDIIRQWKH%R]HPDQ:HVW$SDUWPHQWSURMHFW$SSOLFDWLRQ
WKDWLVORFDWHGRQ/RW%RI&26$7KLVSURSRVHGSURMHFW LVZLWKLQòPLOH
RIWKHDERYH UHIHUHQFHG LQWHUVHFWLRQ $V\RXDUHDZDUHWKHUHLVD/26LVVXHZLWKWKLV
LQWHUVHFWLRQ 7KHSURMHFWZDVRULJLQDOO\RQWKH&LW\¶V&,3 OLVW DQGVFKHGXOHG
IRUFRQVWUXFWLRQLQ)< 6,)VHHWKHDWWDFKHG&,33URMHFW)XQG'HVFULSWLRQDQG
WKH/26LVVXHZDVQRWJRLQJWRKROG XS WKH%R]HPDQ:HVW$SDUWPHQWSURMHFW
%HWZHHQWKHLQIRUPDOUHYLHZDQGRXUIRUPDOVLWHSODQDSSOLFDWLRQWKHSURMHFWZDVPRYHG
IURP)<WRXQVFKHGXOHGLQWKH &,3OLVW
:HDUHZULWLQJWRIRUPDOO\UHTXHVWWKHSURMHFWJHWVSXWEDFNRQWKH&LW\RI%R]HPDQ¶V
\HDU&,3OLVW7KHFRPSHOOLQJUHDVRQVWKLVSURMHFWVKRXOGEHEDFNRQWKH\HDU&,3OLVW
DUHWKHVDPHUHDVRQVWKHSURMHFWZDVSXWRQWKHOLVWRULJLQDOO\
7KHOHYHORIVHUYLFHDWWKHLQWHUVHFWLRQKDVGHJUDGHGWRXQDFFHSWDEOHOHYHOV2XU
7UDIILF,PSDFW6WXG\IRUWKH%R]HPDQ:HVW$SDUWPHQWSURMHFWVKRZWKDWWKH
H[LVWLQJSHDNKRXU6RXWKERXQG/HIWDQGWKH1RUWKERXQG/HIWPRYHPHQWVDUH
EHORZD/HYHORI6HUYLFH&
7KHSURMHFWLVFXUUHQWO\DWZRZD\VWRSFRQWUROLQWHUVHFWLRQ%\VLJQDOL]LQJWKH
LQWHUVHFWLRQLWZRXOGJUHDWO\LQFUHDVHWKHFDSDFLW\RIWKHLQWHUVHFWLRQ
7KHVLJQDOL]DWLRQRIWKH2DNDQG
WK ,QWHUVHFWLRQLV DQLQWHJUDOSDUWRIWKHRYHUDOO
2DN6WUHHW&RUULGRU,PSURYHPHQWV
7KHUHDUHVHYHUDOSURMHFWVLQWKHDUHDWKDWFDQQRWSURFHHGXQWLOWKH
LPSURYHPHQWV DUHLQSODFH
7KDQN\RXIRU\RXUFRQVLGHUDWLRQRQWKLVPDWWHU,I\RXKDYHDQ\TXHVWLRQVRUQHHGDQ\
IXUWKHULQIRUPDWLRQ SOHDVHIHHOIUHHWRFRQWDFW PHDW RUHPDLOPHDW
PHNVWURP#PPQHW
5HJDUGV
//QTTKUQP/CKGTNG+PE
BBBBBBBBBBBBBBBBBBBBBBBBBBBB
0DWW(NVWURP3(
&F &UDLJ:RRODUG3XEOLF:RUNV'LUHFWRU
&KULV6DXQGHUV&RPPXQLW\'HYHORSPHQW'LUHFWRU
1???&RUUHVSRQGHQFH?$JHQF\?&2%2DN WK&,3/,67GRF
1091 Stoneridge Drive • Bozeman, Montana • Phone (406) 587-1115 • Fax (406) 587-9768
www.chengineers.com • E-Mail: info@chengineers.com
Civil/Structural Engineering and Surveying
6HSWHPEHU
&LW\RI%R]HPDQ
&KULV6DXQGHUV
5LFKDUG+L[VRQ3(
(2OLYH
%R]HPDQ07
5( 1RUWRQ(DVW5DQFK6XEGLYLVLRQ3KDVH/DXUHO3DUNZD\5RDG:LGHQLQJ,PSDFW
)HH&UHGLW5HTXHVW
'HDU0U6DXQGHUVDQG0U+L[VRQ
,WLVUHTXHVWHGWKDWWKHIRRWVRXWKHUQH[WHQVLRQRI/DXUHO3DUNZD\&,3)061DV
SURSRVHGZLWKWKH1RUWRQ(DVW5DQFK6XEGLYLVLRQ±3KDVHSUHOLPLQDU\SODWEHDGGHGWRWKH
&DSLWDO,PSURYHPHQWV3ODQWREHHOLJLEOHIRULPSDFWIHHUHLPEXUVHPHQWLQ1RUWRQ(DVW
5DQFK6XEGLYLVLRQ3KDVHSURSRVHVWRH[WHQG/DXUHO3DUNZD\DVDQHQKDQFHGFROOHFWRUVWUHHW
ZLWKODQGVFDSHGPHGLDQDSSUR[LPDWHO\IHHWVRXWKIURPLWVFXUUHQWVRXWKHUQWHUPLQXVRQWKH
VRXWKERXQGDU\RI1RUWRQ(DVW5DQFK6XEGLYLVLRQ3KDVH$
7KLVDSSOLFDWLRQLQFOXGHVFRVWVIRUZLGHQLQJ/DXUHO3DUNZD\WRD¶ZLGHFROOHFWRUVWDQGDUG
ZLWKDODQGVFDSHGPHGLDQ7KHVXJJHVWHGORFDOVWUHHWVWDQGDUGVDUHLGHQWLILHGLQWKH*UHDWHU
%R]HPDQ$UHD7UDQVSRUWDWLRQ3ODQXSGDWHDV¶ZLGH7KH¶ZLGHORFDOVWUHHWZRXOG
DGHTXDWHO\VHUYH3KDVHEDVHGRQWKHIXWXUHWUDIILFSURMHFWLRQV1RUWRQ3URSHUWLHV//&LV
UHTXHVWLQJIXQGLQJIURPWKH5RDG,PSDFW)HH)XQGWRFRYHUWKHFRVWGLIIHUHQWLDOEHWZHHQWKH
QHHGHG¶ZLGHURDGDQGWKHUHTXLUHG¶ZLGHFROOHFWRUVWUHHWZLWKDODQGVFDSHGPHGLDQ7KH
DPRXQW RI WKLV UHTXHVW LV3OHDVH VHH WKH HQFORVHG VSUHDGVKHHW IRU WKH TXDQWLW\
WDNHRIIIRULQVWDOOLQJ/DXUHO3DUNZD\DVD¶ZLGHFROOHFWRUZLWKODQGVFDSHGPHGLDQYHUVXV
LQVWDOOLQJ/DXUHO3DUNZD\DVD¶ZLGHORFDOVWUHHW
3HU0&$³A local government may require a subdivider to pay or guarantee payment
for part of all of the costs of extending capital facilities related to public health and safety,
including but not limited to public roads, sewer lines, water supply lines, and storm drains to a
subdivision. The costs must reasonably reflect the expected impacts directly attributable to the
subdivision.”
,I\RXUHTXLUHDQ\IXUWKHULQIRUPDWLRQSOHDVHJLYHPHDFDOO7KDQN\RXYHU\PXFK
6LQFHUHO\
0DWWKHZ+DXVDXHU3(
6LQFHUHO\\
Norton East Ranch Subdivision, Phase 4 Improvements (Collector [Laurel Parkway] - 62' Wide)09/15/17PUBLIC IMPROVEMENTS QUANTITY TAKEOFF
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE COST
WATER
1-1 12" CL 51 DIP 598 LF $58.00 $34,6901-2 :$7(56(59,&(1 EA $1,500.00 $1,5001-3 12" GATE VALVE ASSEMBLY 2 EA $2,550.00 $5,100
1-4 12"x8" CROSS 1 EA $1,000.00 $1,000
1-5 12" CAP AND BLOWOFF 1 EA $2,350.00 $2,350
1-6 WATER MAIN TESTING 1 LS $2,500.00 $2,500 TOTAL $47,140
SANITARY SEWER
2-1 8" PVC SDR-35 SEWER MAIN 235 LF $48.00 $11,275
2-2 10" PVC SDR-35 SEWER MAIN 233 LF $52.00 $12,100
2-3 4" PVC SDR-26 SEWER SERVICE WITH 8" X 4" PVC WYE 3 EA $1,500.00 $4,500
2-4 12" PVC CAP 1 EA $400.00 $4002-5 48" MANHOLE 2 EA $3,500.00 $7,000
2-6 SANITARY SEWER TESTING 1 LS $2,500.00 $2,500
TOTAL $37,776
STREET IMPROVEMENTS
3-1 COMPACTED SUB-GRADE CUT VOLUME (HAUL OFF)3,252 CY $2.00 $6,5043-2 COMPACTED SUB-GRADE FILL VOLUME 0 CY $2.00 $03-3 6" MINUS PIT RUN (18" THICK COMPACTED)2,211 CY $18.00 $39,793
3-4 1 ½" MINUS CRUSHED BASE COURSE (6" THICK COMPACTED)737 CY $22.00 $16,212
3-5 HOT PLANT MIX ASPHALT CONCRETE (3" THICK COMPACTED)683 TONS $82.00 $55,991
3-6 GEOTEXTILE FABRIC 4,421 SY $2.00 $8,8433-7 CURB & GUTTER 2,329 LF $12.00 $27,9523-8 COMPACTION & TESTING OF SUBGRADE 1 LS $3,000.00 $3,000
3-9 STANDARD CONCRETE FILLETS/INTERSECTION DOUBLE GUTTER 2 EA $2,750.00 $5,500
3-10 6' WIDE CONCRETE SIDEWALK (6" THICK)6,792 SF $9.00 $61,124
3-11 ADA DOUBLE CONCRETE PEDESTRIAN RAMP 4 EA $2,500.00 $10,0003-12 SIGNAGE (STREET, NO PARKING, ETC.)8 EA $550.00 $4,4003-13 PAVEMENT MARKINGS 1 LS $5,500.00 $5,500
TOTAL $244,818
MISCELLANEOUS
4-1 MOBILIZATION 1 LS $4,500.00 $4,5004-2 EROSION CONTROL MEASURES 1 LS $2,250.00 $04-3 CONSTRUCTION TRAFFIC CONTROL 1 LS $0.00 $0
4-4 DEWATERING DURING UTILITY INSTALLATION 1 LS $3,500.00 $3,500
4-5 BACKFILL AROUND CURBS 1 LS $1,500.00 $1,500
4-6 IRRIGATE AND LANDSCAPE MEDIAN 1 LS $4,250.00 $4,2504-7 INSTALL COLLECTOR STREET LIGHTS 3 EA $8,044.00 $24,132 TOTAL $37,882
PUBLIC IMPROVEMENTS TOTAL: $367,615
127(6
1.$63+$/7$1'($57+:25.92/80(6$5(&203$&7(',13/$&(
2.$3521$1'$'$5$03&216758&7,21,1&/8'(%$6(&2856(
Norton East Ranch Subdivision, Phase 4 Improvements (Local [Laurel Parkway] - 31' Wide)09/15/17PUBLIC IMPROVEMENTS QUANTITY TAKEOFF
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE COST
WATER
1-1 8" CL 51 DIP 598 LF $50.00 $29,9051-2 :$7(56(59&(1 EA $1,500.00 $1,5001-3 8" GATE VALVE ASSEMBLY 2 EA $2,400.00 $4,800
1-4 8"x8" CROSS 1 EA $1,000.00 $1,000
1-5 8" CAP AND BLOWOFF 1 EA $2,250.00 $2,250
1-6 WATER MAIN TESTING 1 LS $2,500.00 $2,500 TOTAL $41,955
SANITARY SEWER
2-1 8" PVC SDR-35 SEWER MAIN 235 LF $48.00 $11,275
2-2 8" PVC SDR-35 SEWER MAIN (SOUTH OF FALLON)233 LF $48.00 $11,170
2-3 4" PVC SDR-26 SEWER SERVICE WITH 8" X 4" PVC WYE 3 EA $1,500.00 $4,500
2-4 12" PVC CAP 1 EA $400.00 $4002-5 48" MANHOLE 2 EA $3,500.00 $7,000
2-6 SANITARY SEWER TESTING 1 LS $2,500.00 $2,500
TOTAL $36,845
STREET IMPROVEMENTS
3-1 COMPACTED SUB-GRADE CUT VOLUME (HAUL OFF)1,626 CY $3.00 $4,8783-2 COMPACTED SUB-GRADE FILL VOLUME 0 CY $16.00 $03-3 6" MINUS PIT RUN (18" THICK COMPACTED)1,142 CY $18.00 $20,560
3-4 1 ½" MINUS CRUSHED BASE COURSE (6" THICK COMPACTED)381 CY $22.00 $8,376
3-5 HOT PLANT MIX ASPHALT CONCRETE (3" THICK COMPACTED)327 TONS $82.00 $26,791
3-6 GEOTEXTILE FABRIC 2,284 SY $2.00 $4,5693-7 CURB & GUTTER 1,213 LF $12.00 $14,5563-8 COMPACTION & TESTING OF SUBGRADE 1 LS $2,800.00 $2,800
3-9 STANDARD CONCRETE FILLETS/INTERSECTION DOUBLE GUTTER 2 EA $2,750.00 $5,500
3-10 5' WIDE CONCRETE SIDEWALK (4" THICK)5,660 SF $7.00 $39,617
3-11 ADA DOUBLE CONCRETE PEDESTRIAN RAMP 4 EA $2,500.00 $10,0003-12 SIGNAGE (STREET, NO PARKING, ETC.)5 EA $550.00 $2,750 TOTAL $140,397
MISCELLANEOUS
4-1 MOBILIZATION 1 LS $4,500.00 $4,500
4-2 EROSION CONTROL MEASURES 1 LS $2,250.00 $04-3 CONSTRUCTION TRAFFIC CONTROL 1 LS $0.00 $04-4 DEWATERING DURING UTILITY INSTALLATION 1 LS $3,500.00 $3,500
4-5 BACKFILL AROUND CURBS 1 LS $1,500.00 $1,500
4-6 INSTALL LOCALE INTERSECTION STREET LIGHT 1 EA $8,044.00 $8,044
TOTAL $17,544
PUBLIC IMPROVEMENTS TOTAL: $236,741
127(6
1.$63+$/7$1'($57+:25.92/80(6$5(&203$&7(',13/$&(
2.$3521$1'$'$5$03&216758&7,21,1&/8'(%$6(&2856(