Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer Rick Hixson, City Engineer SUBJECT: Resolution 4863 authorizing Change Order No. 2 to the 5.3 Million Gallon
(MG) Water Storage Tank Project.
MEETING DATE: November 13, 2017
AGENDA ITEM TYPE: Consent
RECOMMENDATION: Approve Resolution 4863 authorizing Change Order No. 2 to the 5.3 MG Water Storage Tank Project.
BACKGROUND: Attached is a copy of resolution 4863 and change order number 2 for the
above referenced project. This change order includes five items. Two are credits and three are additions. Pages three through ten of the change order provide a short description of each of the items involved with this change along with additional backup information. Overall this change will decrease the contract price by $36,234.06 and increase the contract time by 17 days. The final recommended change in cost and time for these items is reasonable and commensurate with the
work involved.
UNRESOLVED ISSUES: None
ALTERNATIVES: As suggested by the City Commission.
FISCAL EFFECTS: Overall this change order decreases the contract amount by $36,234.06 from $7,668,234.00 to $7,631,999.94.
Attachments: Resolution No 4863, Change Order No 2 Report compiled on: 10/31/17