Loading...
HomeMy WebLinkAbout11-13-17 City Commission Packet Materials - A1. Law & Justice Center Feasibility Study - ONLINE ONLY LINK                                    May 2017 Gallatin County Law and Justice Center - ASCE 41-13 - Tier 3 Systematic Evaluation and Retrofit Alternatives Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 1 of 25 Job Number: 0939-03817 Tier 3 Systematic Evaluation and Retrofit Alternatives Report Prepared For: Gallatin County 311 West Main Street Bozeman, MT 59715 May 2017 Prepared By: Stahly Engineering & Associates 851 Bridger Dr., Suite #1 Bozeman, MT 59715 Phone: (406) 522-8594 Written By: Theron Thompson, P.E. Senior Engineer Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 2 of 25 Job Number: 0939-03817 1 Facility/Structure Description The current Law and Justice Center was originally built in 1962 as the Holy Rosary Parish High School. The original facility was remodeled in 1979 to renovate it into the Gallatin County Law and Justice Center. The facility was again remodeled in 1993 to revamp the existing gym into court rooms and office space for the Bozeman Police Department and the Gallatin County Sherriff’s Department. The facility is composed of three main areas which were used to develop the study (See Figure 1). Area A is the northern portion of the original main building consisting of offices and a court room. Area B is the south portion of the original main building and contains the main entry, office space, locker rooms and restrooms. Area C is comprised of the original gym which was renovated to add court rooms and office space for the Police and Sheriff’s Departments. Figure 1 – Building Areas Area A is constructed of a three-story concrete frame structure with concrete joists, beams and slabs. The lateral system is a combination of concrete moment frames and concrete frames with masonry infill panels. The original lateral structural system was concrete frames with masonry infill panels, but the later renovations removed a majority of the infill panels, leaving a concrete frame structure. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 3 of 25 Job Number: 0939-03817 Area B is much like Area A, with the exception that fewer of the masonry infill panels were removed and a concrete shear wall was added in the 1993 renovation. See Appendix A for drawings indicating the alterations to the original structure. Area C is comprised of numerous lateral systems. The majority of the original masonry shear wall system in the north and south walls was removed during the 1993 renovation. It was replaced with concrete shear walls at the eastern corners of the building. The renovation also included adding an upper floor which is laterally supported by light gage steel stud walls with plywood sheathing. These walls are supported on a rigid concrete deck which is laterally supported by the concrete shear walls and two steel braced frames. Again, see Appendix A for drawings indicating the alterations to the original structure. The lateral system for Area C in the north-south direction is comprised of glulam arch moment frames. The frames were repaired and strengthened during the 1993 renovation. 2 Performance Objectives and Seismic Hazards For an ASCE 41-13 evaluation the Basic Performance Objective can be selected as either the Basic Performance Objective for Existing Buildings (BPOE) or the Basic Performance Objective Equivalent to New Building Standards (BPON). The BPOE performance objective accepts performance less than what the current ASCE 7 requires, but considers the shorter remaining life span than a new building. It also recognizes the increased cost of achieving the higher level of performance. Although a reduced cost may be realized with the BPOE performance level, for a Risk Category III or IV such as an essential facility, the BPOE is not appropriate. Therefore the BPON performance objective was selected for this evaluation. This requires that the existing structure be evaluated for the Basic Safety Earthquake (BSE) 1 for use with the BPON performance objective (BSE-1N). This is equivalent to the design, 5% damped, spectral response accelerations required by ASCE 7 for new buildings. The target building performance levels evaluated were the Immediate Occupancy (S-1) and the Life Safety (S-3). The Immediate Occupancy performance level is defined as the post-earthquake damage state in which a structure remains safe to occupy and essentially retains its pre-earthquake strength and stiffness. The Immediate Occupancy level is similar to a new building designed with current codes as an essential facility. A Life Safety performance level is defined as the post-earthquake damage state in which a structure has damaged components but retains a margin against the onset of partial or total collapse. The Level of Seismicity for the geographical location is classified as “High Seismicity”. See Appendix B for the seismic information for this Tier 3 evaluation. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 4 of 25 Job Number: 0939-03817 3 ASCE 41-13 Tier 3 Systematic Evaluation The purpose of this study is to complete an ASCE 41-13, “Seismic Evaluation and Retrofit of Existing Buildings”, Tier 3 Systematic Evaluation which includes an analysis of the entire building. Analysis procedures were selected per ASCE 41-13 requirements and the building components were evaluated per the defined acceptance criteria for capacities and behavior. Retrofit alternatives were analyzed to determine recommended retrofit methods to bring the structure into compliance with the selected Performance Objective. An Opinion of Probable Cost was included to provide the expected cost range for the selected retrofit methods. Tier 1 Potential Deficiencies 3.1 The potential deficiencies identified in the previous Tier 1 Structural Screening are addressed in this evaluation and are as follows: Area A:  Concrete Moment Frames: o Possible weak story and soft story o The shear capacity of the frame members not able to develop the moment capacity at the ends of the members o Potential that a strong-beam weak-column exists at the frames o Shear stress demand in the frame columns exceeds the capacity o Column axial stress demand exceeds the capacity o Concrete columns are not adequately doweled into the foundation o Beam reinforcing is detailed inadequately o Column tie spacing is inadequate o Original drawings do not show adequate beam stirrup spacing o Beam-column joints are not adequately reinforced o Secondary components within the system do not have the shear capacity to develop the flexural strength of the components  Masonry Infill Panels: o Shear stress demand in the infill panel walls exceeds the capacity of the walls o Concrete columns are not adequately doweled into the foundation o Secondary components within the system do not have the shear capacity to develop the flexural strength of the components o Wall openings are not adequately reinforced o Infill wall panels do not meet the aspect ratio requirements Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 5 of 25 Job Number: 0939-03817 Area B: Area B is very similar to Area A and has the same possible deficiencies, except that less of the masonry infill panels have been removed. Also, the concrete shear walls that were added create a condition with the concrete frames in which the frames do not have the shear capacity to develop the flexural capacity, similar to the infill panels. As well, the coupling beams do not have adequate reinforcing over means of egress. Area C:  Concrete shear walls are possibly stressed at a level that exceeds their capacity.  Due to the main floor being a concrete diaphragm, a rigid diaphragm analysis should be completed to determine the loads that are resisted by the concrete shear walls, remaining masonry shear walls, and the steel braced frames.  Diaphragm connections may not be adequate to transfer the load to the shear walls.  Secondary components within the system do not have the shear capacity to develop the flexural strength of the components.  Steel braced frames may be over capacity.  Glued laminated timber arch members and their connections in three- hinge arch systems will need further analysis to determine if there are any possible deficiencies. Seismic Structural Analysis 3.2 The entire structure was analyzed per the procedures outlined in Chapter 6 and 7 of ASCE 41-13, including the material specific requirements of Chapters 8 through 12. Multiple methods were utilized to evaluate the various structural seismic lateral systems within the facility. The analysis methods utilized within the specific areas are defined below. Area A and B: Area A was analyzed using Linear Static Procedure 2-D models, a Linear Static Procedure 3-D model and a Linear Dynamic 3-D model. The 2-D models included the lateral systems in the transverse and longitudinal directions and the 3-D models encompassed the entire Area A structure. The structure of Area A is similar to Area B; therefore the findings from Area A will be similar to those of Area B. Because of this, the analysis findings and retrofit analysis for Area A will be utilized for Area B as well. Figure 2 shows a representative 2-D longitudinal frame with the expected deflected shape shown in Figure 3. Figure 4 shows the 3-D model with the expected deflected shape in Figure 5. Additional models and calculations can be found in Appendix C. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 6 of 25 Job Number: 0939-03817 Figure 2 – Longitudinal Concrete Frame 2-D Model Figure 3 – 2-D Model Deflected Shape Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 7 of 25 Job Number: 0939-03817 Figure 4 – Area A 3-D Model Figure 5 – Area A Deflected Shape Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 8 of 25 Job Number: 0939-03817 Figure 6 – Area A Member Unity Check The Linear Static Procedures used the Equivalent Lateral Force method, whereas the Linear Dynamic Procedure used a modal response method based on the previously identified BSE-1N spectral response acceleration parameters. The models were assessed to determine the probable capacity and behavior of the entire system. The overall findings and recommendations were developed from the comparative results of the three modeling techniques. See Appendix C for calculations and results. Figure 7 - BSE-1N Response Spectrum Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 9 of 25 Job Number: 0939-03817 Area C: Area C was analyzed using a rigid diaphragm analysis to determine load distribution to the primary lateral load resisting systems with Linear Static 2-D models for the primary lateral load system. The system included the CMU masonry shear walls, the steel braced frames and the wood shear walls added during the 1993 retrofit. See Figures 8 through 11 for the braced frame and arch models. See Appendix C for calculations and results. Figure 8 – Braced Frame Unity Check Figure 9 – Braced Frame Deflected Shape Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 10 of 25 Job Number: 0939-03817 Figure 10 – Glulam Arch Model Figure 11 – Glulam Arch Deflected Shape 4 Tier 3 Systematic Evaluation Findings The capacities for the building structural system and individual members were computed using the methods described above. These results were then compared to the seismic demands using the Acceptance Criteria as defined in ASCE 41-13. The acceptance criterion includes variables for the Knowledge factor and a modification factor to account for the expected ductility at the selected Performance Level. The Knowledge factor accounts for the uncertainty in the properties of the building members. The Knowledge factor for this evaluation was 0.9, due to gathering material properties from the design drawings only and not conducting tests to verify the in situ properties. See Appendix C for calculations and results. Area A and B 4.1 The overall condition of Area A is generally good. The building was inspected and shows little sign of settlement or deterioration. Although the condition of the building is good, Area A has numerous seismic deficiencies. The lateral seismic Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 11 of 25 Job Number: 0939-03817 force resisting system was found to be highly deficient and with the past renovations has been compromised with the removal of the masonry infill panels. The analysis of the different systems generally shows that the members will be overstressed due to the seismic loads. The structural members were not detailed in a manner that is acceptable under current design methodology to be earthquake-resistant and therefore will not behave in a ductile inelastic manner during an extreme event. Improper dowel lengths, hook lengths and lap splice lengths can also cause a sudden pull-out failure. Due to the lack of ductility provided by the lateral force resisting system, the structure has a high risk of failing in a sudden brittle manner which can cause collapse. The current design philosophy per ACI 318 is for cast-in-place concrete structures to act in the nonlinear range with decreased stiffness and greater energy dissipation, without significant loss of strength. Therefore the system will retain a substantial portion of its strength into the inelastic range under load and displacement reversals. This is accomplished by utilizing confining reinforcing steel such as hoops, ties and stirrups. Lap splices must be of adequate length and also located in specific locations. The existing structure has inadequate reinforcing to provide the required concrete confinement and will likely have a brittle failure. The specific deficiencies for Area A and B area as follows: Concrete Moment Frames  Concrete column shear strength is inadequate for columns in tension  The shear capacity of the beams is unable to develop the required moment capacity. Therefore a brittle failure may occur.  Weak Column-Strong Beam – The moment capacity of many of the beams is greater than the capacity of the columns.  The column reinforcing is doweled into the foundation but is inadequate to develop the tensile capacity required. A pull out failure could occur.  The beam top longitudinal reinforcing is not continuous throughout the frame.  The column tie spacing exceeds d/4.  The majority of the frame beams do not have stirrup reinforcing.  Beam-column joints do not have ties spaced at d/2.  Many of the beams do not have ties at the joint locations.  The secondary components do not meet the reinforcing requirements as well. Concrete Shear Walls  The secondary components do not have the shear capacity to develop the flexural strength and do not meet the reinforcing requirements. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 12 of 25 Job Number: 0939-03817  The coupling beams do not have stirrup reinforcing spaced at d/2. Concrete Frames with Masonry Infill Panels  The shear stress in the unreinforced masonry infill panels exceeds the capacity.  The concrete column reinforcing is doweled into the foundation but is inadequate to develop the tensile capacity required.  The openings in the infill panels do not have trim reinforcing on all sides.  The unreinforced panels do not have the required capacity for out-of-plane loading. Area C 4.2 The overall condition of Area C is also generally good. Although the condition of the building is good, Area C also has numerous deficiencies. The main deficiency with the differing systems is inadequate strength for the required loads causing overstressed members. The specific deficiencies for Area C area as follows: Concrete Shear Walls  The shear stress in the concrete shear walls exceeds the capacity.  The chord connections to transfer the seismic load to the concrete shear walls do not meet the required capacity. Steel Braced Frames  For the Immediate Occupancy performance level, the brace effective area is less than the brace gross area. Wood and Light Gauge Steel Shear Walls  The shear stress in the shear walls exceeds the capacity. Glulam Arches  The glulam arches are overstressed due to the combination of axial load and bending. The upper level which was added in 1993 is supported with wood sheathing on light gauge studs in the north-south direction. Shear walls were not added in the east-west direction, and it is consequently not adequately supported for lateral loads in that direction. Shear walls, moment frames or braced frames need to be constructed to accommodate the loads in that orthogonal direction. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 13 of 25 Job Number: 0939-03817 5 Retrofit Alternatives and Recommendations Area A and B 5.1 There are numerous retrofit options for the deficiencies of Area A and B. FEMA 547 “Techniques for the Seismic Rehabilitation of Existing Buildings” discusses the alternatives available for retrofitting common structural systems. It provides common techniques to mitigate specific deficiencies in various model building types. Chapters 12 and 15 of the FEMA publication have been included in Appendix D for the concrete moment frame and infill panel systems. Rehabilitation can be completed by strengthening the existing elements, adding new elements such as shear walls and bracing, or a combination of both. The retrofit method will also be designed to increase the ductility of the structure and ensure that the connection strength of the diaphragms to the vertical lateral force resisting systems is adequate. The strengthening of the concrete elements and masonry infill panels can be completed by reinforced concrete jacketing, steel plate bonding and jacketing or Fiber Reinforced Polymer (FRP) jacketing (See Figures 12 - 16). Figure 12 – Jacketing of Concrete Column Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 14 of 25 Job Number: 0939-03817 Figure 13 – Jacketing of Concrete Beam and Column Figure 14 – Steel Jacketing Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 15 of 25 Job Number: 0939-03817 Figure 15 – FRP Jacketing of Column Figure 16 – FRP Jacketing of Beam Elements can be added to the structure such as new concrete shear walls, moment frames or braced frames (See Photos 17 – 20). These elements are integrated into the structure to increase the strength and ductility. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 16 of 25 Job Number: 0939-03817 Figure 17 – Retrofit Concrete Shear Wall Figure 18 – Steel Moment Frame Retrofit Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 17 of 25 Job Number: 0939-03817 Figure 19 – Retrofit Braced Frame – Exterior Figure 20 – Retrofit Braced Frame - Interior Jacketing is the least intrusive manner of retrofitting the structure, as it uses the existing elements and only increases their size. The approach of adding lateral elements can be more intrusive and affect the overall use of the building. The added shear walls, moment frames, or braced frames can interfere with the existing use of the facility. The current use of the facility requires open areas for Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 18 of 25 Job Number: 0939-03817 court rooms and offices and thus adding structural elements may compromise the usage of the facility. Area C 5.2 The main deficiencies in the gym area would require adding additional concrete shear walls, strengthening the glulam arches, strengthening the existing wood shear walls and adding shear walls, moment frames or braced frames in the east-west direction. These retrofits would be less invasive then those of Areas A and B, but will still require significant rehabilitation. Recommendations 5.3 It is recommended that the lateral force resisting system of Area A and B be retrofitted with a reinforced concrete jacketing or reinforced shotcrete jacketing. This has generally been proven to be an adequate repair at a lesser cost than other alternatives. The masonry infill panels are also recommended to be strengthened with reinforced concrete jacketing or reinforced shotcrete. The FRP jacketing is also a potential retrofit option, but should be researched further to determine the cost efficiency. The FRP option is superior in the aspect that it will not increase the mass and weight of the structure. It is recommended that Area C be retrofitted by adding additional concrete shear walls to the exterior and strengthening the diaphragm chord connections to the concrete shear walls. The glulam arches should be strengthened using steel members and additional moment frames should be added to support the upper level in the east-west direction. The wood shear walls will also require strengthening by additional nailing and revised holdowns. 6 Opinion of Probable Cost An Opinion of Probable Cost was completed to determine the cost range for the required structural retrofitting of the facility. This was completed based on a square foot cost. Costs were developed using FEMA-156 and data from past evaluations completed in Portland, Oregon and California. It should be noted that these costs are for the structural portion of the retrofit only and do not include any costs for mechanical, electrical, plumbing or other miscellaneous items. FEMA-156 “Typical Costs for Seismic Rehabilitation of Existing Buildings” provides structural rehabilitation costs compiled from data collected from a total of 2088 retrofit projects. The square foot costs were normalized to 1993 dollars for the State of Missouri to represent a national average. The square foot costs were developed based on the FEMA Building Type, level of seismicity and size of Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 19 of 25 Job Number: 0939-03817 project for the Life Safety performance objective. The 1993 cost values for this report were normalized to 2017 dollars. The FEMA-156 cost values were then compared to recent studies completed in Portland, Oregon and California. The FEMA Life Safety level costs were as follows: Level of Seismicity 1993 S.F. Cost 2017 S.F. Cost Very High Seismicity $25.04 $31.83 High Seismicity $18.89 $42.19 “Portland’s Unreinforced Masonry Seismic Retrofit Project” report by Walt McMonies and Lane Powell was also reviewed for cost data on similar projects. There findings for hard costs were $35 to $40 per square foot for Life Safety and $63 to $74 for Immediate Occupancy. They also recommended adding $30 per square foot for soft costs. A report was also completed by David Bell of PJHM Architects, Inc. on “How to Evaluate Buildings and Determine Retrofit Costs”. In the report the California Division of the State Architect recommends $60 per square foot for retrofit. FEMA’s normalized costs adjusted to the Immediate Occupancy level align with the recommendations of the other reports, therefore $60 per square foot plus $30 per square foot for soft costs were used. The cost of $40/SF and $30/SF were used for the Life Safety level to align with the normalized FEMA values. The level of retrofit required for Area C will be less than Areas A and B, thus a decreased cost was used in that area. With the use of the above values, overall project costs were developed for the Life Safety and Immediate Occupancy levels. The Opinion of Probable Costs can be seen in Figures 21 and 22. Although the cost estimates indicate a specific cost, at this level of the evaluation they should be viewed as approximate ranges. Thus, the cost estimate for the Life Safety retrofit should be considered in the range of $5.5M and $7M and the Immediate Occupancy would be in the range of $7m and $8.5M. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 20 of 25 Job Number: 0939-03817 Figure – 21 – Life Safety Retrofit Opinion of Probable Cost Figure 22 – Immediate Occupancy Opinion of Probable Cost Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 21 of 25 Job Number: 0939-03817 7 Tier 3 Evaluation Summary The ASCE 41-13 Tier 3 Systematic Evaluation for the Law and Justice Building clearly identified numerous seismic deficiencies for the structure. Many of the deficiencies were related to inadequate strength and lack of ductility due to insufficient reinforcing details. This applied to the concrete moment frames, concrete moment frames with masonry infill panels, concrete shear walls, light gauge steel shear walls and glulam arches. There were also deficiencies identified with diaphragm connections and steel braced frame net areas. It is recommended that the lateral force resisting system of Area A and B be retrofitted with a reinforced concrete jacketing or reinforced shotcrete jacketing. The masonry infill panels are also recommended to be strengthened with reinforced concrete jacketing or reinforced shotcrete. FRP jacketing is also a potential retrofit option, but should be researched further to determine the cost efficiency. It is recommended that Area C be retrofitted by adding additional concrete shear walls to the exterior and strengthening the diaphragm chord connections to the concrete shear walls. The glulam arches should be strengthened using steel members and additional moment frames should be added to support the upper level in the east-west direction. The wood shear walls will also require strengthening by additional nailing and revised holdowns. With the use of the previously defined retrofit values, overall project costs were developed for the Life Safety and Immediate Occupancy levels. The cost estimate for the Life Safety retrofit should be considered in the range of $5.5M and $7M and the Immediate Occupancy would be in the range of $7m and $8.5M. Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 22 of 25 Job Number: 0939-03817 Appendix A – Building Structural Alterations Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 23 of 25 Job Number: 0939-03817 Appendix B – Tier 3 Seismic Information   www.seaeng.com Engineers and Land Surveyors 851 Bridger Drive, Suite 1, Bozeman, MT 59715 | phone: 406-522-8594 | fax: 406-522-9528      L:\0901-0950\0939-Gallatin County\-03817 L&J Structural Study\Phase 2\Study and Report\L&J - Tier 3 - Systematic Evalaution Phase.docx 3 May 2017 Law and Justice Center – Tier 3 – Systematic Evaluation Phase ASCE-41-13 Risk Category: IV – Essential Facility Performance Objective (Section 2.2): Immediate Occupancy Performance Level (1-B) Building Performance Level: S-1, N-A Seismic Hazard: BSE-1N Level of Seismicity: High – SDC D Building Type:  Area A (north half of the west wing): C1, C3 and C3a  Area B (south half of the west wing): C1, C2, C3, and C3a  Area C (east wing – original gymnasium): C2, C2a, C3, C3a, S2, S2a and W2 Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 24 of 25 Job Number: 0939-03817 Appendix C – ASCE 41 Tier 3 Evaluation Calculations Tier 3 Systematic Evaluation and Retrofit Alternatives Report 5/5/2017 Page 25 of 25 Job Number: 0939-03817 Appendix D – FEMA 547 Information