Loading...
HomeMy WebLinkAboutEx3 BPC 11917 November 2017 PPM Report 1 BOZEMAN PARKING COMMISSION Parking Program Manager's Report Date: November 9, 2017 To: Bozeman Parking Commission From: Ed Meece, Parking Program Manager An update of major developments, in October, includes: • Final contracts with T2 Systems (parking equipment/software)were signed on 10/16/17;the Scope of Work was finalized and signed on 10/23/17. Project implementation launch is scheduled for 12/1/17. • The PPM and PEO Tucker participated in interviews for the vacant position, finalists are in the reference and background process with conditional offer letters expected to be issued in early November.The PPM was also a member of the Finance/Parking Clerk interviews,a conditional offer is expected by early November. • The PPM worked extensively with Rick Williams, as well as the Legal Department and BPC Executive Committee, to develop a final draft of the Parking Lease Policy and Lease Limit Calculation.These documents will be presented to the Bozeman Parking Commission at their 11/9/17 meeting for consideration and possible approval. • The PPM worked with numerous internal stakeholders, including the Legal Department, and performed considerable research to develop a Security Camera Policy for consideration and possible approval by the Bozeman Parking Commission.A final draft is expected for presentation at the 12/14/17 meeting of the Bozeman Parking Commission. • The PPM is collaborating with the Sustainability Coordinator, as they prepare a grant application for funds to purchase and install an electronic vehicle charging system (dual)at the Bridger Park Downtown Garage.The COB would be committed for a ten percent match (approximately$3,000). If approved, the remainder of the project costs would be funded from a state government pass-through resulting from the Volkswagen legal settlement. • The PPM attended in-house trainings regarding changes to the website content management system, as well as supervisory use of the city's new'Exec-u-time' payroll system. • The PPM is drafting a memorandum/staff report to the City Commission regarding the possible creation of a new Residential Parking Permit District, south of the downtown core, for discussion at their 11/20/17 meeting, It is expected this issue would then be sent to the Bozeman Parking Commission for further research and action. • The City Attorney's Office continues to review the proposed changes to the parking regulations within the Bozeman Municipal Code (submitted to legal, 8/6/17). Upon completion of their review, an updated version will be presented to the Bozeman Parking Commission for further consideration and action. • Garage: o Surveillance Cameras:The conduit installation of this project has been successfully completed,with a final walk through on 10/2/17.The IT Department will now use internal resources for final camera placement and computer updates necessary to make the system fully functional. Financial Update Revenues for the fiscal year are at 38.94% (w/out TIFD funds). Expenditures for the fiscal year are at 31%(w/out TIFD funds). Parking Services Fund-Operating October 2017-Revenue&Expenditures Report(As of 11/)(/2017) FY 18 FY 18 EARNED REVENUE BUDGET ACTUAL YTD Parking Lot Permits $ 25,000.00 $ 4,942.00 19.77% Garage Permits $250,000.00 $ 66,634.00 26.65% Garage-Transient Revenue $ 75,500.00 $ 36,172.00 47.91% Garage Validation Coupons $ 3,000.00 $ 1,075.00 35.83% Residential Nghbd.Permits $ 13,000.00 $ 28,970.00 222.85% Employee Ngbad. Permits $ 2,000.00 $ 4,290.00 214.50% Visitor Ngbad. Permits $ 10,500.00 $ 19,835.00 188.90% Admin/Late Fees $ 42,000.00 $ 16,629.00 39.59% Boot Fees $ 2,000.00 $ 300.00 15.00% Citation Revenue $300,000.00 $ 98,602.00 32.87% Misc. Revenue $ - $ - NA Rents/Royalties/Other $ 2,000.00 $ 1,170.00 58.50% Interest Income $ 750.00 $ - 0.00% Loan Interest $ 840.00 $ 258.00 30.71% Refunds& Reimbursements $ $ - 0.00% Collection Fees $ 6,000.00 $ 6,395.00 106.58% Transfer Other Funds(TIFD) $250,000.00 $ - 0.00% TOTAL(w/TIFD Transfer) $982,590.00 $285,272.00 29.03% TOTAL (w/out TIFD Transfer) $732,590.00 $285,272.00 38.94% FY 18 FY 18 SPENT EXPENDITURE BUDGET ACTUAL YTD Admin- Personnel $100,127.00 $ 38,678.00 39% Admin--Operating $159:232.00 $ 44,005.00 28% Admin--Capital $250,000.00 $ 28,700.00 11% Enforcement-- Personnel $202,384.00 $ 59,649.00 29% Enforcement--Operating $ 49,465.00 $ 7,703.00 16% Enforcement--Capital $ 10,000.00 $ - N/A Garage-- Personnel $ 40,122.00 $ 13,381.00 33% Garage--Operating $156,900.00 $ 57,986.00 37% Garage--Capital $ - $ - N/A TOTAL(w/Admin Capital -TIFD) $968,230.00 $250,102.00 26% TOTAL(w/out Admin Capital-TIFD) $718,230.00 $221,402.00 31% COMPLETED PENDING HOLD/NOT STARTED PROJECTED ACTUAL STRATEGY DESCRIPTION COMPLETION COMPLETION COMMENTS Formalize the guiding principles as policies within the parking and Adopted by the BPC in 1 transporation system plan. Aug-16 8/2016. Adopt the 85%rule as the standard for measuring performance of the parking supply and triggering specific Adopted by the BPC in 2 management strategies. Aug-16 8/2016. Strengthen the role of the Parking Manager and the Parking Services Division-to better PPM attending DRC integrate with the Community meetings,and offering Development and Economic data/comment as staff 3 Development planning. On-Going On-Going review. Establish a policy for adjusting Adopted by the BPC in 4 rates(on and off-street) Oct-16 10/2016. BPC approved Resolution 2017-03(6/2017);City Commission approved Establish a Capital Maintenance CC Approval Resolution#4837 on 5 Reserve Fund Jul-16 8/14/17 8/14/17. PPM is working with the Comm.Dev.Department; Re-evaluate and restructure CDD has assigned this a'fall 6 current cash-in-lieu program. TBD 2018'priority status. PPM worked with the ED dept on changes to the minimum parking standards (UDC)in the 132M zone, approved by CC 9/2017; PPM actively attending internal DRC meetings to offer guidance on policy issues and prepare for 2018 effort to modify the parking Re-evaluate code based standards section of the 7 minimum parking requirements UDC. Re-evaluate and clarify the PPM is waiting on the purpose and intent of the current Admin./Legal Depts.For code section regarding Special further instruction on this 8 Improvement District#565. TBD isue. PPM is completing research for facility mgt.best Implement a Facilities practices,starting to draft 9 Maintenance Plan. 12/30/2017 On-going Fac.Mgt.plan,8/17; Data collection ocurred, following the Strategic Develop a reasonable schedule Parking Management Plan, of data collection to assess Spring and Summer 2017; performance,including an WTI report(draft)submitted accurate on and off street 9/2017,under staff review inventory(public and private) at this time;Final comments and an occupancy/utilization submitted to WTI for 10 analysis. 5/1/17&7/1/17 On-going modification,10/23/17. Identify off-street shared use opportunities based on data from strategy 9.Establish goals for transitioning employees, ist shared use agreement begin outreach to opportunity negotiated and approved sites,negotiate agreements,and with Big Sky Western Bank 11 assign employees to facilities. On-Going (June 2017); Complete the 2008 Parking District Identification 12 Signage/Branding Plan No activity at this time. Clarify current on-street parking signage,particularly in areas where unlimited parking is allowed.Consider incorporating the current City parking logo into 13 on-street Signage. No activity at this time. Rename all publicly owned lots 14 and garages by address. No activity at this time. RFP Selection Committee is in final stages of award reccomendation,as of 9/7/17.Following 9/2017 bid award,staff is engaged in final contract negotiations and project planning; Contracts signed 10/16/17- Upgrade the access/revenue scope of Work signed control system at the Bridger 10/27/17;Project launch 15 Garage. 6/30/2017 On-going expected by 12/1/17. RFP Selection Committee is in final stages of award reccomendation,as of 9/7/17.Following 9/2017 bid award,staff is engaged in final contract negotiations and project planning; Contracts signed 30/16/17- Install a vehicle counter system scope of Work signed at Bridger Garage and at the 10/27/17;Project launch 16 Surface lots. 6/30/2017 On-Going expected by 12/1/17. Establish best practice protocols and performance metrics for existing enforcement personnal Court/Appeals Packet and support enforcement with (4/17);Uniform Policy 17 appropriate technology. On-going (8/17); J