HomeMy WebLinkAbout17- Task Order 4 - Sanderson Stewart - Architectural and Engineering Services for Midtown Task Order Number 04
Issued under the authority of Professional Services Agreement with Sanderson Stewart for
Architectural and Engineering Services in the Bozeman Midtown Urban Renewal District Term
Contract 2015-2018.
This Task Order is dated 20between City of Bozeman
(City) and Sanderson Stewart (Contractor).
The following representatives have been designated for the work performed under this Task
Order:
City: David Fine, Economic Development Specialist
Contractor: Danielle Scharf,Associate Principal
SCOPE OF WORK:
The scope for Task Order No. 1 is detailed in the attached Midtown Urban Renewal District
Scope of Work— Task Order No. 4 812512017.
COMPENSATION:
Sanderson Stewart will bill for its services on a lump sum basis with a project total of$7,900.
Sanderson Stewart shall submit invoices to the Client for work accomplished during each
calendar month. The amount of each monthly invoice shall be determined on the "percentage
of completion method" whereby Sanderson Stewart will estimate the percentage of the total
work (provided on a lump sum basis) accomplished during the invoicing period.
The provisions of the Professional Services Agreement shall govern the Work.
IN WITNESS WHEREOF, the parties authorized to commit resources of the parties have
executed this Task Order:
Citvaf Bozeman Co ractor
By: 1\ . By:
Title: �� r '~ � Title: 92 Z= LO I L7,� hl aL,&=
Date: ttlt7 Date: V7/L7'J
►-4
SANDERSON %V77
STEWART
Midtown Urban Renewal District
Scope of Work—Task Order No. 4—Oak Street& N 7th Avenue Intersection Improvements
8/25/17
Sanderson Stewart is pleased to provide this scope of work for design and construction administration services
for street improvements at the intersection of Oak Street and North 7th Avenue in Bozeman,Montana.This
work is to be done as a part of the Midtown Urban Renewal District term contract for architectural and
engineering services.
We understand the project generally includes restriping the east leg of the intersection to provide three approach
lanes for westbound traffic and associated signal modifications. The project does not include any roadway
widening. Construction will take place during the fall 2017. A detailed list of assumptions and scope of services
for the project are outlined below.
Scope of Work:
Phase 1-Project Initiation
This phase of the project will include project initiation and planning tasks, including scoping, contract
preparation,and meetings with the City of Bozeman. All project management tasks and client meetings beyond
project initiation will be allocated to the remaining project phases.
Phase 2-Topographic Survey Pick-up and Base Mapping
A detailed topographic survey of the project area has already been completed and base drawings have been
prepared in Autocad format. It is anticipated that some quick pick-up topo will be needed to verify the exact
extents of existing striping and curb lines within the planned area for restriping. The resulting survey points
will be added to the existing base file.
i
Phase 3—Preliminary Design
Design tasks for this phase of the project will include a striping plan, signing plan and a signal plan. Detail
sheets for signal modifications will be provided as well. Sanderson Stewart will prepare special provisions and
a specifications manual including bid documents. The engineer's opinion of probable cost will also be provided
with this review submittal.
Phase 4—Final Design
Sanderson Stewart will address all review comments received from the City of Bozeman and MDT and prepare
final plans,specifications and engineer's opinion of probable cost. The final deliverable will include electronic
copies of all submittal documents,as well as up to three hard copies.
li
I
Phase 5—Construction Administration and Inspection
This phase of project will consist of limited construction bidding services, contract administration and
construction inspection tasks,including the following:
• Assist with a limited construction bidding process including a request for bids from up to three
contractors,bid review and bid tabulation
• Process contract documents
• Facilitate pre-construction meeting,prepare agenda and distribute minutes
• Shop drawing review
• Construction observation and documentation(assume 8 hours of construction inspection time)
• Respond to Contractor RFI's
• Construction testing coordination and review(if required)
• Process pay applications submitted by Contractor and any necessary change orders, verify material
quantities on all contractor pay requests
• Process the Certificate of Substantial Completion,coordinate final inspection and prepare punch list
• Prepare as-built(record) drawings
• Conduct warranty inspection and prepare punch list(if required)
Phase 6—Construction Staking
This phase of the project consists of the construction layout,anticipated to include the following:
• Striping and signage staking
Fees and Billing Arrangements:
Phase Fee
1. Project Initiation $300
2. Topographic Survey and Base Mapping $600
3. Preliminary Design $3,000
4. Final Design $700
5. Construction Administration and Inspection $2,800
6. Construction Staking $500
Total $7,900
Sanderson Stewart will bill for its services on a lump sum basis with a project total of$7,900. Sanderson
Stewart shall submit invoices to the Client for work accomplished during each calendar month. The amount
of each monthly invoice shall be determined on the"percentage of completion method"whereby Sanderson
Stewart will estimate the percentage of the total work(provided on a lump sum basis)accomplished during
die invoicing period.
Project Schedule:
The anticipated schedule for this project consists of the preliminary design deliverable widen 3 weeks of
notice to proceed.