BOZEMAN PARKING COMMISSION
Parking Program Manager's Report
Date: September 14, 2017
To: Bozeman Parking Commission
From: Ed Meece, Parking Program Manager
An update of major developments, in August, includes:
• Parking Enforcement Officer Ryan Tucker celebrated his one year service anniversary with the Parking Services
Division,and City of Bozeman, on August 71n.Job Well Done, Ryan!
• The Parking Program Manager, Treasurer, IT Director, and Senior Parking Enforcement Officer engaged an
intensive "scoping" process with T2 Systems for the purpose of refining the equipment,software, and services to
be purchased under their submission to the recent Request for Proposal process.This effort required a review of
current business and enforcement practices,as well as numerous multi-partner phone conferences,and will result
in a more accurate cost projection and statement of work for consideration by the Bozeman Parking Commission.
• The City Attorney's Office continues to review the proposed changes to the parking regulations within the
Bozeman Municipal Code. Upon completion of their review,an updated version will be presented to the Bozeman
Parking Commission for further consideration and action; possibly at the regular October 2017 meeting.
• The Parking Program Manager met with two contractors to review this year's needs related to concrete crack
repair at the Bridger Downtown Parking Garage.Their recommendations are being evaluated, and a decision on
the pending scope of work is pending.
• Homebase LLC is completing final punch list items for restoration of the North Willson surface lot, as required by
the 2015 lease agreement with the Bozeman Parking Commission.The Parking Program Manager hopes to have
this process complete by September 15tn
• The Parking Program Manager began a project working with the Human Resources Department and Montana
Municipal Inter-local Authority to develop,and implement,the first written safety and safety training program for
Parking Services Division employees.
• Stairwells
• The Parking Services Division and Bozeman Police Department planned for, and executed,joint parking/student
pickup safety and enforcement activities for the first weeks of school.
• The Parking Services Division is working with the Streets Division (Public Works) to plan and implement a "48
Hour/Abandoned Vehicle" sweep, and community education effort, in early November; in preparation for winter
snow removal.
• The Parking Services Division developed new 'Information Cards' — briefly explaining the rolling rule and MSU
Residential Permit District. The cards have been professionally printed, and are being used in daily enforcement
efforts.Thanks to PEO Gallagher for her graphic design skills on this project.
• Garage:
o Fire Extinguisher Cabinets:A partial installation was completed on September 7tn.The contractor will need
to return to finish, however, unexpected issues with removal of the old cabinets hampered their progress.
The new cabinets were successfully outfitted with a graffiti resistant wrap prior to installation.
2
o Surveillance Cameras:The project for installation of the conduit necessary for completing Phase II of this
project has begun,and the final order of camera equipment has been made. Project completion deadline
has been moved to 9/30/17.
Financial Update
Revenues for the fiscal year are at 21%(w/out TIFD funds).
Expenditures for the fiscal year are at 19%(w/out TIFD funds).
New Developments(land use)
The City of Bozeman is currently under the limitations of judicial order that restrains us from giving formal consideration,
and or approval, to development projects with the B-3 zone (downtown core). However, the Parking Program Manager
continues to attend the Development Review Committee,to provide any meaningful assistance regarding projects not in
the B-3.
Further Information:
htips;/fgisweb.bgzeman.ne /Html5Vlewerl?viewer alannine.
Parking Services Fund-Operating
Auaust 2017-Revenue&Expenditures Report(As of 9/7/17)
o�
FY 18 FY 18 EARNED
REVENUE BUDGET ACTUAL YTD
Parking Lot Permits $25,000.00 $1,879.00 8%
Garage Permits $250,000.00 $28,602.00 11%
Garage-Transient Revenue $75,500.00 $19,860.00 26%
Garage Validation Coupons $3,000.00 $1,075.00 36%
Residential Nghbd.Permits $13,000.00 $21,395.00 165%
Employee Ngbad. Permits $2,000.00 $2,190.00 110%
Visitor Ngbad. Permits $10,500.00 $14,160.00 135%
Admin/Late Fees $42,000.00 $8,592.00 20%
Boot Fees $2,000.00 $150.00 8%
Citation Revenue $300,000.00 $48,117.00 16%
Misc. Revenue $0.00 $5,878.00 N/A
Rents/Royalties/Other $2,000.00 $670.00 34%
Interest Income $750.00 $0.00 N/A
Loan Interest $840.00 $188.00 N/A
Refunds& Reimbursements $0.00 $0.00 N/A
Collection Fees $6,000.00 $3,669.00 61%
Transfer Other Funds (TIFD) $250,000.00 $0.00 N/A
TOTAL(w/TIFD Transfer) $982,590.00 $156,425.00 16%
TOTAL (w/out TIFD Transfer) $732,590.00 $156,425.00 21%
FY 18 FY 18 SPENT
EXPENDITURE BUDGET ACTUAL YTD
Admin - Personnel $ 100,127.00 $ 18,009.00 18%
Admin --Operating $ 159,232.00 $ 31,326.00 20%
Admin --Capital $ 250,000.00 $ - 0%
Enforcement-- Personnel $ 202,384.00 $ 35,979.00 18%
Enforcement--Operating $ 49,465.00 $ 5,115.00 10%
Enforcement--Capital $ 10,000.00 $ - N/A
Garage-- Personnel $ 40,122.00 $ 6,693.00 17%
Garage--Operating $ 156,900.00 $ 39,299.00 25%
Garage--Capital $ - N/A
TOTAL(w/Admin Capital-TIFD) $ 968,230.00 $ 136,421.00 14%
TOTAL(w/out Admin Capital-TIFD) $ 718,230.00 $ 136,421.00 19%
COMPLETED
September 2011 VIA PENDING
HOLD/NOT STARTED
PROJECTED ACTUAL
STRATEGY DESCRIPTION COMPLETION COMPLETION COMMENTS
Formalize the guiding principles
as policies within the parking and Adopted by the BPC in
1 transporation system plan. Aug-16 8/2016.
Adopt the 85%rule as the
standard for measuring
performance of the parking
supply and triggering specific Adopted by the BPC in
2 management strategies. Aug-16 8/2016.
Strengthen the role of the
Parking Manager and the Parking
Services Division-to better PPM attending DRC
integrate with the Community meetings,and offering
Development and Economic data/comment as staff
3 Development planning. On-Going On-Going review.
Establish a policy for adjusting Adopted by the BPC in
4 rates(on and off-street) Oct-16 10/2016.
BPC approved Resolution
2017-03(6/2017);City
Commission approved
Establish a Capital Maintenance CC Approval Resolution#4837 on
5 Reserve Fund Jul-16 8/14/17 8/14/17.
PPM is working with the
Comm.Dev.Department;
Re-evaluate and restructure CDD has assigned this a'fall
6 current cash-in-lieu program. TBD 2018'priority status.
PPM is working with the ED
dept on changes to the
minimum parking standards
(UDC)in the 621VI zone;
PPM atively attending
internal DRC meetings to
offer guidance on policy
issues and prepare for 2018
effort to modify the parking
Re-evaluate code based standards section of the
7 minimum parking requirements UDC.
Re-evaluate and clarify the PPM is waiting on the
purpose and intent of the current Admin./Legal Depts.For
code section regarding Special further instruction on this
8 Improvement District#565. TBD isue.
PPM is completing research
for facility mgt.best
Implement a Facilities practices,starting to draft
9 Maintenance Plan. 12/30/2017 On-going Fac.Mgt.plan,8/17;
Develop a reasonable schedule
of data collection to assess
performance,including an
accurate on and off street Data collection ocurred,
inventory(public and private) following the Strategic
and an occupancy/utilization Parking Management Plan,
10 analysis. 5/1/17&7/1/17 On-going Spring and Summer 2017.
Identify off-street shared use
opportunities based on data
from strategy 9.Establish goals
for transitioning employees, 1st shared use agreement
begin outreach to opportunity negotiated and approved
sites,negotiate agreements,and with Big Sky Western Bank
11 assign employees to facilities. On-Going (June 2017);
Complete the 2008 Parking
District Identification
12 Signage/Branding Plan No activity at this time.
Clarify current on-street parking
signage,particularly in areas
where unlimited parking is
allowed.Consider incorporating
the current City parking logo into
13 on-street signage. No activity at this time.
Rename all publicly owned lots
14 and garages by address. No activity at this time.
RFP Selection Committee is
Upgrade the access/revenue in final stages of award
control system at the Bridger reccomendation,as of
15 Garage. 6/30/2017 On-going 9/7/17.
RFP Selection Committee is
Install a vehicle counter system in final stages of award
at Bridger Garage and at the reccomendation,as of
16 Surface lots. 6/30/2017 On-Going 9/7/17.
Court/Appeals Packet
Establish best practice protocols (4/17);Uniform Policy
and performance metrics for (8/17);RFP Selection
existing enforcement personnal Committee is in final stages
and support enforcement with of award reccomendation,
17 appropriate technology. On-going as of 8/7/17;